CN106407505A - Method and apparatus for performing wiring on bridge frames based on Revit platform - Google Patents

Method and apparatus for performing wiring on bridge frames based on Revit platform Download PDF

Info

Publication number
CN106407505A
CN106407505A CN201610717204.6A CN201610717204A CN106407505A CN 106407505 A CN106407505 A CN 106407505A CN 201610717204 A CN201610717204 A CN 201610717204A CN 106407505 A CN106407505 A CN 106407505A
Authority
CN
China
Prior art keywords
path
crane span
span structure
wiring
spool
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610717204.6A
Other languages
Chinese (zh)
Other versions
CN106407505B (en
Inventor
张向龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guotai Epoint Software Co Ltd
Original Assignee
Jiangsu Guotai Epoint Software Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Guotai Epoint Software Co Ltd filed Critical Jiangsu Guotai Epoint Software Co Ltd
Priority to CN201610717204.6A priority Critical patent/CN106407505B/en
Publication of CN106407505A publication Critical patent/CN106407505A/en
Application granted granted Critical
Publication of CN106407505B publication Critical patent/CN106407505B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Abstract

Embodiments of the invention provide a method and an apparatus for performing wiring on bridge frames based on a Revit platform. The method comprises the steps of determining M first bridge frames corresponding to path leading-in ends according to the path leading-in ends; determining N second bridge frames corresponding to path leading-out ends according to the path leading-out ends, wherein the path leading-in ends are start devices for wiring, and the path leading-out ends are stop devices for wiring; generating K wiring paths according to the path leading-in ends, the path leading-out ends, the M first bridge frames, the N second bridge frames and a preset wiring distance rule, and performing display, wherein the wiring paths are paths from the path leading-in ends to the path leading-out ends through a first bridge frame and a second bridge frame in sequence; obtaining a first wiring path from the displayed K wiring paths according to a path selection operation instruction of a user; and arranging a wire pipe along the first wiring path. Therefore, the bridge frames can be wired on the Revit platform, and an entity model after wiring can be visually seen on the bridge frames on the Revit platform.

Description

Based on Revit platform bridge rack wiring method and apparatus
Technical field
The present embodiments relate to Revit stage+module modeling technique field, more particularly, to one kind are existed based on Revit platform The method and apparatus of bridge rack wiring.
Background technology
The existing mode arranging cable on crane span structure, is by CAD (Computer Aided Design, referred to as:CAD) software electric wire arrangement or cable on crane span structure, but this method can not intuitively be found out on crane span structure Physical model after electric wire arrangement or cable.
Content of the invention
The embodiment of the present invention provide a kind of based on Revit platform bridge rack wiring method and apparatus, for realize exist Revit platform connects up to crane span structure, the physical model after intuitively finding out wiring on crane span structure on Revit platform.
In a first aspect, the embodiment of the present invention provide a kind of based on Revit platform bridge rack wiring method, including:
According to path leading-in end, determine M corresponding with described path leading-in end the first crane span structure;And drawn according to path End, determines N number of second crane span structure corresponding with described path exit, and described path leading-in end is the initiating terminal of wiring, described road Footpath exit is the clearing end of wiring;Described M, described N are the integer more than or equal to 1;
According to described path leading-in end, described path exit, described M the first crane span structure, described N number of second crane span structure and Default wiring distance rule, generates K bar routing path and shows, described routing path is to sequentially pass through from described path leading-in end One described first crane span structure, described second crane span structure are to the path of described path exit;Described K is more than or equal to 1 Integer;
According to the Path selection operational order of user, from the described K bar routing path of display, obtain the first routing path;
Along described first routing path arrangement spool.
Second aspect, the embodiment of the present invention provide a kind of based on Revit platform bridge rack wiring device, including:
Determining module, for according to path leading-in end, determining M corresponding with described path leading-in end the first crane span structure;With And according to path exit, determining N number of second crane span structure corresponding with described path exit, described path leading-in end is wiring Initiating terminal, described path exit is the clearing end of wiring;Described M, described N are the integer more than or equal to 1;
Path-generating module, for according to described path leading-in end, described path exit, described M the first crane span structure, institute State N number of second crane span structure and default wiring distance rule, generate K bar routing path;Described routing path is to draw from described path Enter end and sequentially pass through described first crane span structure, the path of described second crane span structure to described path exit;Described K is big In or be equal to 1 integer;
Display module, for showing described K bar routing path;
Acquisition module, for the Path selection operational order according to user, obtains from the described K bar routing path of display First routing path;
Interconnection module, for along described first routing path arrangement spool.
Provided in an embodiment of the present invention based on Revit platform bridge rack wiring method and apparatus, by according to path Leading-in end, determines M corresponding with described path leading-in end the first crane span structure;And according to described path exit, determine and institute State corresponding N number of second crane span structure of path exit;According to described path leading-in end, described path exit, described M the first bridge Frame, described N number of second crane span structure and default wiring distance rule, generate K bar routing path and show;Path choosing according to user Select operational order, from the described K bar routing path of display, determine the first routing path;Along described first routing path deployment line Pipe;It is achieved thereby that connecting up to crane span structure in Revit platform, wiring intuitively can be found out on crane span structure on Revit platform Physical model afterwards.
Brief description
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing Have technology description in required use accompanying drawing be briefly described it should be apparent that, drawings in the following description are these Some bright embodiments, for those of ordinary skill in the art, on the premise of not paying creative work, can also root Obtain other accompanying drawings according to these accompanying drawings.
Fig. 1 is the flow chart of present invention embodiment of the method one in bridge rack wiring based on Revit platform;
Fig. 2 is the flow chart of present invention embodiment of the method two in bridge rack wiring based on Revit platform;
Fig. 3 is the flow chart of present invention embodiment of the method three in bridge rack wiring based on Revit platform;
Fig. 4 is the structural representation of present invention device embodiment one in bridge rack wiring based on Revit platform;
Fig. 5 is the structural representation of present invention device embodiment two in bridge rack wiring based on Revit platform;
Fig. 6 is the structural representation of present invention device embodiment three in bridge rack wiring based on Revit platform.
Specific embodiment
Purpose, technical scheme and advantage for making the embodiment of the present invention are clearer, below in conjunction with the embodiment of the present invention In accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described it is clear that described embodiment is The a part of embodiment of the present invention, rather than whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art The every other embodiment being obtained under the premise of not making creative work, broadly falls into the scope of protection of the invention.
Revit:It is to aim at BIM (English:Building Information Modeling, referred to as:BIM) Build, building designers' design can be helped, build and maintenance quality is more preferable, a set of groupware of the more preferable building of efficiency.
Fig. 1 is the flow chart of present invention embodiment of the method one in bridge rack wiring based on Revit platform, as shown in figure 1, The method of the present embodiment can include:
S101, according to path leading-in end, determine individual first crane span structure of M corresponding with described path leading-in end;And according to road Footpath exit, determines N number of second crane span structure corresponding with described path exit.
Wherein, described path leading-in end is the initiating terminal of wiring, and described path exit is the clearing end of wiring;Path is drawn Entering end is to be determined according to the selection of user with path exit, e.g.:Equipment, spool, airduct annex, conduit fittings Deng.Need to be connected up with path exit in path leading-in end, it needs to be determined that routing path before connecting up, and path is drawn Enter, between end and path exit, there are multiple crane span structures, need therefrom to determine the crane span structure for generating routing path.
Alternatively, above-mentioned M the first crane span structure can be the crane span structure corresponding with path leading-in end pre-setting, above-mentioned N number of second crane span structure can also be the crane span structure corresponding with path exit pre-setting, and described M, described N are more than or equal to 1 Integer.For example:Above-mentioned M the first crane span structure can user be arranged by interface with above-mentioned N number of second crane span structure.
Alternatively, described M the first crane span structure include following at least one:First level crane span structure and the first vertical crane span structure;Institute The distance between stating first level crane span structure is apart from the nearest horizontal crane span structure of described path leading-in end, and with described path leading-in end Less than the first predeterminable range;Described first vertical crane span structure is apart from the nearest vertical crane span structure of described path leading-in end, and with institute State the distance between path leading-in end and be less than described first predeterminable range.It is, in the distance apart from path leading-in end being The interior horizontal crane span structure nearest from path leading-in end of first predeterminable range is referred to as first level crane span structure;Apart from path leading-in end away from It is referred to as the first vertical crane span structure from the nearest vertical crane span structure of path leading-in end in for the first predeterminable range, above-mentioned M the first crane span structure For two the first crane span structures, and using first level crane span structure and the first vertical crane span structure as the first crane span structure;If drawing apart from path The distance entering end is that the interior horizontal crane span structure nearest from path leading-in end of the first predeterminable range is referred to as first level crane span structure, and in distance The distance of path leading-in end is to there is not vertical crane span structure in the first predeterminable range, then above-mentioned M the first crane span structure is first bridge Frame, and using first level crane span structure as the first crane span structure;If being the first predeterminable range Nei Li road in the distance apart from path leading-in end Leading-in end nearest vertical crane span structure in footpath is referred to as the first vertical crane span structure, and is the first predeterminable range in the distance apart from path leading-in end Inside there is not horizontal crane span structure, then above-mentioned M the first crane span structure is first crane span structure, and using the first vertical crane span structure as the first bridge Frame.
Alternatively, described N number of second crane span structure include following at least one:Second horizontal crane span structure and the second vertical crane span structure;Institute The distance between stating the second horizontal crane span structure is apart from the nearest horizontal crane span structure of described path exit, and with described path exit Less than the second predeterminable range;Described second vertical crane span structure is apart from the nearest vertical crane span structure of described path exit, and with institute State the distance between path exit and be less than described second predeterminable range.It is, in the distance apart from path exit being The interior horizontal crane span structure nearest from path exit of second predeterminable range is referred to as the second horizontal crane span structure;Apart from path exit away from It is referred to as the second vertical crane span structure, above-mentioned N number of second crane span structure from the nearest vertical crane span structure of path exit in for the second predeterminable range For two the second crane span structures, and using the second horizontal crane span structure and the second vertical crane span structure as the second crane span structure;If drawing apart from path The distance going out end is that the interior horizontal crane span structure nearest from path exit of the second predeterminable range is referred to as the second horizontal crane span structure, and in distance The distance of path exit is to there is not vertical crane span structure in the second predeterminable range, then above-mentioned N number of second crane span structure is second bridge Frame, and using the second horizontal crane span structure as the second crane span structure;If being the second predeterminable range Nei Li road in the distance apart from path exit Exit nearest vertical crane span structure in footpath is referred to as the second vertical crane span structure, and is the second predeterminable range in the distance apart from path exit Inside there is not horizontal crane span structure, then above-mentioned N number of second crane span structure is second crane span structure, and using the second vertical crane span structure as the second bridge Frame.
Alternatively, on Revit platform, the specific code of S101 is for example as follows:
S102, according to described path leading-in end, described path exit, described M the first crane span structure, described N number of second bridge Frame and default wiring distance rule, generate K bar routing path and show.
In the present embodiment, after determining M the first crane span structure and N number of second crane span structure, according to described path leading-in end, Individual first crane span structure of described path exit, described M, described N number of second crane span structure and default wiring distance rule, generate K bar cloth Thread path, and display to the user that this K bar routing path, routing path is to sequentially pass through one described from described path leading-in end One crane span structure, described second crane span structure are to the path of described path exit;Described K is the integer more than or equal to 1.
Alternatively, default wiring distance rule can be the path that user is arranged by interface, i.e. user setup first Each crane span structure that crane span structure is passed through between the second crane span structure.
Alternatively, default wiring distance rule can be the shortest path between the first crane span structure and the second crane span structure, at this Under kind default wiring distance rule, above-mentioned K is less than or equal to the product of M and N, and the routing path generating the first crane span structure with Spacing distance between each crane span structure between second crane span structure or accessory is less than predetermined interval distance, and this predetermined interval distance is, for example, 170mm.
Alternatively, default wiring distance rule can not disconnect for the path of described first crane span structure to described second crane span structure, Spacing distance under a kind of this default wiring distance rule, between each crane span structure between the first crane span structure to the second crane span structure or accessory For example, 0, the path between same first crane span structure to same second crane span structure can have a plurality of.
S103, the Path selection operational order according to user, determine the first wiring from the described K bar routing path of display Path.
After displaying to the user that the K bar routing path of generation, user can select one as it from K bar routing path The required routing path being connected up, therefore, the present embodiment according to the Path selection operational order of user input, from the institute of display State one routing path of determination in K bar routing path, this routing path is referred to as the first routing path.
S104, along described first routing path arrangement spool.
In the present embodiment, after determining the first routing path, arrange spool along the first routing path, the spool of arrangement be from Path leading-in end starts, and through first crane span structure and second crane span structure, reaches path exit, the path of spool and first Routing path is identical.
The present embodiment, by according to path leading-in end, determining M corresponding with described path leading-in end the first crane span structure;With And according to described path exit, determine N number of second crane span structure corresponding with described path exit;Introduced according to described path End, described path exit, described M the first crane span structure, described N number of second crane span structure and default wiring distance rule, generate K bar Routing path simultaneously shows;According to the Path selection operational order of user, from the described K bar routing path of display, determine the first cloth Thread path;Along described first routing path arrangement spool;It is achieved thereby that connecting up to crane span structure in Revit platform, in Revit Physical model after intuitively wiring being found out on crane span structure on platform.
Fig. 2 is the flow chart of present invention embodiment of the method two in bridge rack wiring based on Revit platform, as shown in Fig. 2 The method of the present embodiment can include:
S201, according to path leading-in end, determine individual first crane span structure of M corresponding with described path leading-in end;And according to road Footpath exit, determines N number of second crane span structure corresponding with described path exit.
S202, according to described path leading-in end, described path exit, described M the first crane span structure, described N number of second bridge Frame and default wiring distance rule, generate K bar routing path and show.
Wherein, S201 and S202 implement the associated description that process can be joined in embodiment of the method shown in Fig. 1, herein Repeat no more.
S203, the path adjustment operational order according to user, are adjusted to described K bar routing path processing, obtain and adjust K bar routing path after whole, described path adjusts operational order and is used for indicating the company of the wiring of path leading-in end and the first crane span structure Connect the connected mode of the wiring of mode and path exit and the second crane span structure.
In the present embodiment, after obtaining above-mentioned K bar routing path, user can also be adjusted to K bar routing path.Its In, packet information containing the first crane span structure information, the second crane span structure information, path, path type etc. of every paths.This enforcement Example can also obtain the path adjustment operational order of user input, adjust operational order according to path and every routing path is carried out Adjustment is processed, and obtains the K bar routing path after adjustment.Wherein, path adjusts the K bar wiring after operational order is used for indicating adjustment In path the connected mode of the wiring of path leading-in end and the first crane span structure and path exit and the second crane span structure be first level or Person is first vertically, and for instruction when path leading-in end is in the prolongation of the first crane span structure (can be horizontal crane span structure or vertical crane span structure) During direction scope, the wiring between path leading-in end and the first crane span structure is walk by smooth vertical and horizontal trend or by minimum distance To when path exit is in the extending direction scope of the second crane span structure (can be horizontal crane span structure or vertical crane span structure), path is drawn End and the second crane span structure between wiring can be by smooth vertical and horizontal walk or by minimum distance trend.
It should be noted that path leading-in end refers in the extending direction scope of the first crane span structure, using path leading-in end as A bit, the first crane span structure, as a line, starts to do vertical line toward this line from this point, this vertical line is non-intersect with this line, and with The extended line of this line intersects, and is now properly termed as the extending direction scope in the first crane span structure for the path leading-in end, path exit Similar in the extending direction scope of the second crane span structure.
Wherein, the wiring between path leading-in end and the first crane span structure press minimum distance trend, refer to from path leading-in end with The line (this line is straight line) of one end of the first crane span structure as the wiring of path leading-in end to the first crane span structure, draw by path Wiring between end and the second crane span structure moves towards similar by minimum distance.
Wherein, smooth vertical and horizontal trend is pressed in the wiring between path leading-in end and the first crane span structure, refers to from the first crane span structure to road Connected up at footpath leading-in end and the perpendicular intersection of the extending direction of the first crane span structure, then to path leading-in end at perpendicular intersection Connected up;Or, carry out cloth at the perpendicular intersection of the extending direction to path leading-in end to the first crane span structure for the path leading-in end Line, is then connected up to the first crane span structure at perpendicular intersection.Wiring between path exit and the second crane span structure is pressed horizontal flat perpendicular Directly move towards similar.
Alternatively, the specific code on the Revit platform of S202 and S203 is for example as follows:
S204, the Path selection operational order according to user, determine from the described K bar routing path after the adjustment of display Described first routing path.
Wherein, S204 implement the associated description that process can be joined in embodiment of the method shown in Fig. 1, no longer superfluous herein State.
S205, the default electric wire information of basis or default cable information, generate spool.
S206, along described first routing path, arrange described spool.
In the present embodiment, spool can be generated according to default electric wire information or default cable information, then along the first wiring Path, arranges this spool, it is achieved thereby that to simulate electric wire using spool, cable is arranged.Wherein, above-mentioned default electric wire letter Breath or default cable information include:Specifications and models, radical, many types, system type, loop numbering.
Alternatively, in a kind of feasible implementation of S205, can include:According to default pipe arrangement information and described Default electric wire information or described default cable information, generate described spool.Wherein, default pipe arrangement reason information include specifications and models, System of laying etc..The spool generating in the present embodiment represents the electric wire or cable being enclosed within pipe arrangement.
Alternatively, the specific code on Revit platform of S205 and S206 is for example as follows:
1) data is obtained by Dictionary data dictionary mode
A) define the entity class of data source
B) set up data dictionary using Dictionary, when arranging spool, the number that introducing (going out) is held is filtered out by key According in that context it may be convenient to obtain data
EndDatas=new Dictionary<EndType,EndData>();
EndData endData=isImport?EndDatas[EndType.Import]:EndDatas [EndType.Outport];
2) arrangement spool direction is obtained by vector product
XYZ rankVector=upDirection* ((MaxConduitDiameter+FeetOfOneMm) * RankUpNumber);
ITransform rankTransform=CreationApplication.NewTransformTranslatio n (rankVector);
Line=line.CreateTransformed (rankTransform) as ILine;
In the present embodiment, by such scheme, it is possible to achieve in Revit platform, electric wire or cable are arranged to crane span structure, Physical model after intuitively electric wire arrangement or cable being found out on crane span structure on Revit platform.
Fig. 3 is the flow chart of present invention embodiment of the method three in bridge rack wiring based on Revit platform, as shown in figure 3, The method of the present embodiment can include:
S301, according to path leading-in end, determine individual first crane span structure of M corresponding with described path leading-in end;And according to road Footpath exit, determines N number of second crane span structure corresponding with described path exit.
S302, according to described path leading-in end, described path exit, described M the first crane span structure, described N number of second bridge Frame and default wiring distance rule, generate K bar routing path and show.
S303, the Path selection operational order according to user, determine the first wiring from the described K bar routing path of display Path.
Wherein, S301-S303 implement the associated description that process can be joined in embodiment of the method shown in Fig. 1 or Fig. 2, Here is omitted.
S304, according to described first routing path, in the fluting bottom foundation of described first crane span structure and described second crane span structure Default wiring rule, arranges described spool, and described default wiring rule is:Towards in described first crane span structure and described second crane span structure The side of heart line is sequentially arranged at least one described spool;After being covered with described spool in described side, towards described first crane span structure It is sequentially arranged at least one described spool with the opposite side of the center line of described second crane span structure.
S305, after described fluting bottom is covered with described spool, according to described first routing path, towards described first crane span structure Arrange described spool with the otch direction of described second crane span structure according to described default wiring rule.
In the present embodiment, when needing to arrange many pipelines along the first routing path, for example, need to arrange X root pipeline.One The mode of kind:Side towards the center line of the fluting bottom of described first crane span structure and described second crane span structure is sequentially arranged X root spool, and It is not covered with, illustrate to need the X root pipeline of arrangement to be all arranged in the fluting bottom towards described first crane span structure and described second crane span structure Center line side.A kind of mode:Side towards the center line of the fluting bottom of described first crane span structure and described second crane span structure It is sequentially arranged X1 root spool, and is covered with, towards the side of the center line of the fluting bottom of described first crane span structure and described second crane span structure It is sequentially arranged X2 root spool, and is not covered with, illustrate that X1 is equal to X with X2 sum.A kind of mode:Towards described first crane span structure and described The side of the center line of fluting bottom of two crane span structures is sequentially arranged at least single line pipe, and is covered with;Again towards described first crane span structure and The side of the center line of fluting bottom of described second crane span structure is sequentially arranged at least single line pipe, and is covered with;Then towards described Spool is arranged in the otch direction of one crane span structure and described second crane span structure, is also first to be sequentially arranged spool towards the side of central point, so Be sequentially arranged spool towards opposite side more afterwards, the like, until by the spool of arrangement in need deploy.
In the present embodiment, by such scheme, the display problem of spool when the present invention solves multitube wiring.
Fig. 4 is the structural representation of present invention device embodiment one in bridge rack wiring based on Revit platform, such as Fig. 4 Shown, the device of the present embodiment can include:Determining module 11, path-generating module 12, display module 13, acquisition module 14 and Interconnection module 15.
Determining module 11, for according to path leading-in end, determining M corresponding with described path leading-in end the first crane span structure; And according to described path exit, determining N number of second crane span structure corresponding with described path exit, described path leading-in end is The initial plant of wiring, described path exit is the termination device of wiring;Described M, described N are the integer more than or equal to 1;
Path-generating module 12, for according to described path leading-in end, described path exit, described M the first crane span structure, Described N number of second crane span structure and default wiring distance rule, generate K bar routing path;Described routing path is from described path Leading-in end sequentially passes through described first crane span structure, the path of described second crane span structure to described path exit;Described K is Integer more than or equal to 1;
Display module 13, for showing described K bar routing path;
Acquisition module 14, for the Path selection operational order according to user, obtains from the described K bar routing path of display Take the first routing path;
Interconnection module 15, for along described first routing path arrangement spool.
The device of the present embodiment, can be used for executing the technical scheme of the present invention above-mentioned each method embodiment, it realizes former Reason is similar with technique effect, and here is omitted.
Fig. 5 is the structural representation of present invention device embodiment two in bridge rack wiring based on Revit platform, such as Fig. 5 Shown, the device of the present embodiment, on the basis of Fig. 4 shown device structure, further, can also include:Adjusting module 16, This adjusting module 16, in described acquisition module 14 according to the Path selection operational order of user, from the described K bar cloth of display Before obtaining the first routing path in thread path, the path according to user adjusts operational order, and described K bar routing path is carried out Adjustment is processed, and obtains the K bar routing path after adjustment, and described path adjustment operational order is used for indicating path leading-in end and first The connected mode of the wiring of the connected mode of the wiring of crane span structure and path exit and the second crane span structure;
Described acquisition module 14, specifically for:According to the Path selection operational order of user, the institute after the adjustment of display State and in K bar routing path, determine described first routing path.
Alternatively, when being many along the spool of described first routing path arrangement, described interconnection module 15, concrete use In:
According to described first routing path, in the fluting bottom of described first crane span structure and described second crane span structure according to default cloth Line rule, arranges described spool, and described default wiring rule is:Center line towards described first crane span structure and described second crane span structure Side is sequentially arranged at least one described spool;After being covered with described spool in described side, towards described first crane span structure and described The opposite side of the center line of the second crane span structure is sequentially arranged at least one described spool;
After described fluting bottom is covered with described spool, towards the otch direction of described first crane span structure and described second crane span structure Arrange described spool according to described default wiring rule.
The device of the present embodiment, can be used for executing the technical scheme of the present invention above-mentioned each method embodiment, it realizes former Reason is similar with technique effect, and here is omitted.
Fig. 6 is the structural representation of present invention device embodiment three in bridge rack wiring based on Revit platform, such as Fig. 6 Shown, the device of the present embodiment, on the basis of Fig. 4 or Fig. 5 shown device structure, further, can also include:Spool is given birth to Become module 17;
Spool generation module 17, before described interconnection module 15 is along described first routing path arrangement spool, also includes: According to default electric wire information or default cable information, generate spool.
Alternatively, spool generation module 17, specifically for:According to default pipe arrangement information, and described default electric wire information Or described default cable information, generate described spool.
Alternatively, described M the first crane span structure include following at least one:First level crane span structure and the first vertical crane span structure;Institute The distance between stating first level crane span structure is apart from the nearest horizontal crane span structure of described path leading-in end, and with described path leading-in end Less than the first predeterminable range;Described first vertical crane span structure is apart from the nearest vertical crane span structure of described path leading-in end, and with institute State the distance between path leading-in end and be less than described first predeterminable range;
Described N number of second crane span structure include following at least one:Second horizontal crane span structure and the second vertical crane span structure;Described second water Level bridge frame is apart from the nearest horizontal crane span structure of described path exit, and with the distance between described path exit less than the Two predeterminable ranges;Described second vertical crane span structure is apart from the nearest vertical crane span structure of described path exit, and draws with described path Go out the distance between end and be less than described second predeterminable range.
Alternatively, described default wiring distance rule is:The shortest path of described first crane span structure extremely described second crane span structure, or Person, the path of described first crane span structure to described second crane span structure does not disconnect.
It should be noted that the embodiment shown in Fig. 6 can also include the adjusting module 16 shown in Fig. 5, simply in Fig. 6 not Illustrate.
The device of the present embodiment, can be used for executing the technical scheme of the present invention above-mentioned each method embodiment, it realizes former Reason is similar with technique effect, and here is omitted.
One of ordinary skill in the art will appreciate that:The all or part of step realizing above-mentioned each method embodiment can be led to Cross the related hardware of programmed instruction to complete.Aforesaid program can be stored in a computer read/write memory medium.This journey Sequence upon execution, executes the step including above-mentioned each method embodiment;And aforesaid storage medium includes:Read-only memory (English: Read-Only Memory, referred to as:ROM), random access memory (English:Random Access Memory, referred to as: RAM), magnetic disc or CD etc. are various can be with the medium of store program codes.
Finally it should be noted that:Various embodiments above only in order to technical scheme to be described, is not intended to limit;To the greatest extent Pipe has been described in detail to the present invention with reference to foregoing embodiments, it will be understood by those within the art that:Its according to So the technical scheme described in foregoing embodiments can be modified, or wherein some or all of technical characteristic is entered Row equivalent;And these modifications or replacement, do not make the essence of appropriate technical solution depart from various embodiments of the present invention technology The scope of scheme.

Claims (10)

1. a kind of based on Revit platform in the method for bridge rack wiring it is characterised in that include:
According to path leading-in end, determine M corresponding with described path leading-in end the first crane span structure;And according to path exit, Determine N number of second crane span structure corresponding with described path exit, described path leading-in end is the initiating terminal of wiring, and described path is drawn Go out the clearing end for wiring for the end;Described M, described N are the integer more than or equal to 1;
According to described path leading-in end, described path exit, described M the first crane span structure, described N number of second crane span structure and default Wiring distance rule, generates K bar routing path and shows, described routing path is to sequentially pass through one from described path leading-in end Described first crane span structure, described second crane span structure are to the path of described path exit;Described K is the integer more than or equal to 1;
According to the Path selection operational order of user, from the described K bar routing path of display, obtain the first routing path;
Along described first routing path arrangement spool.
2. method according to claim 1 is it is characterised in that the described Path selection operational order according to user, from aobvious Before determining the first routing path in the described K bar routing path showing, also include:
Path according to user adjusts operational order, described K bar routing path is adjusted process, obtains the K bar after adjustment Routing path, described path adjust operational order be used for indicating path leading-in end and the first crane span structure the connected mode of wiring and The connected mode of the wiring of path exit and the second crane span structure;
The described Path selection operational order according to user, determines the first routing path from the described K bar routing path of display, Including:According to the Path selection operational order of user, from the described K bar routing path after the adjustment of display, determine described first Routing path.
3. method according to claim 1 it is characterised in that described along described first routing path arrangement spool before, Also include:
According to default electric wire information or default cable information, generate spool.
4. method according to claim 3 is it is characterised in that described basis presets electric wire information or default cable information, Generate spool, including:
According to default pipe arrangement information, and described default electric wire information or described default cable information, generate described spool.
5. the method according to claim 1-4 any one is it is characterised in that work as along described first routing path arrangement Spool be many when, described along described first routing path arrangement spool, including:
According to described first routing path, in the fluting bottom of described first crane span structure and described second crane span structure according to default cloth line gauge Then, arrange described spool, described default wiring rule is:Side towards described first crane span structure and the center line of described second crane span structure It is sequentially arranged at least one described spool;After being covered with described spool in described side, towards described first crane span structure and described second The opposite side of the center line of crane span structure is sequentially arranged at least one described spool;
After described fluting bottom is covered with described spool, according to described first routing path, towards described first crane span structure and described the Described spool is arranged according to described default wiring rule in the otch direction of two crane span structures.
6. the method according to claim 1-4 any one it is characterised in that described M the first crane span structure include with down to Few one:First level crane span structure and the first vertical crane span structure;Described first level crane span structure is nearest apart from described path leading-in end Horizontal crane span structure, and it is less than the first predeterminable range with the distance between described path leading-in end;Described first vertical crane span structure be away from From the nearest vertical crane span structure of described path leading-in end, and preset less than described first with the distance between described path leading-in end Distance;
Described N number of second crane span structure include following at least one:Second horizontal crane span structure and the second vertical crane span structure;Described second horizontal bridge Frame is apart from the nearest horizontal crane span structure of described path exit, and pre- less than second with the distance between described path exit If distance;Described second vertical crane span structure is apart from the nearest vertical crane span structure of described path exit, and with described path exit The distance between be less than described second predeterminable range.
7. the method according to claim 1-4 any one is it is characterised in that described default wiring distance rule is:Institute State the first crane span structure to the shortest path of described second crane span structure, or, do not break in the path of described first crane span structure to described second crane span structure Open.
8. a kind of based on Revit platform in the device of bridge rack wiring it is characterised in that include:
Determining module, for according to path leading-in end, determining M corresponding with described path leading-in end the first crane span structure;And root According to path exit, determine N number of second crane span structure corresponding with described path exit, described path leading-in end is the initial of wiring End, described path exit is the clearing end of wiring;Described M, described N are the integer more than or equal to 1;
Path-generating module, for according to described path leading-in end, described path exit, described M the first crane span structure, described N Individual second crane span structure and default wiring distance rule, generate K bar routing path;Described routing path is from described path leading-in end Sequentially pass through described first crane span structure, the path of described second crane span structure to described path exit;Described K be more than or Integer equal to 1;
Display module, for showing described K bar routing path;
Acquisition module, for the Path selection operational order according to user, obtains first from the described K bar routing path of display Routing path;
Interconnection module, for along described first routing path arrangement spool.
9. device according to claim 8 is it is characterised in that also include:
Adjusting module, connects up from the described K bar of display according to the Path selection operational order of user in described acquisition module Before obtaining the first routing path in path, the path according to user adjusts operational order, and described K bar routing path is adjusted Whole process, obtains the K bar routing path after adjustment, and described path adjustment operational order is used for indicating path leading-in end and the first bridge The connected mode of the wiring of the connected mode of the wiring of frame and path exit and the second crane span structure;
Described acquisition module, specifically for:According to the Path selection operational order of user, the described K bar after the adjustment of display Described first routing path is determined in routing path.
10. device according to claim 8 or claim 9 is it is characterised in that along the spool of described first routing path arrangement ought be When many, described interconnection module, specifically for:
According to described first routing path, in the fluting bottom of described first crane span structure and described second crane span structure according to default cloth line gauge Then, arrange described spool, described default wiring rule is:Side towards described first crane span structure and the center line of described second crane span structure It is sequentially arranged at least one described spool;After being covered with described spool in described side, towards described first crane span structure and described second The opposite side of the center line of crane span structure is sequentially arranged at least one described spool;
After described fluting bottom is covered with described spool, towards the otch direction foundation of described first crane span structure and described second crane span structure Described default wiring rule arranges described spool.
CN201610717204.6A 2016-08-24 2016-08-24 Based on Revit platform bridge rack wiring method and apparatus Active CN106407505B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610717204.6A CN106407505B (en) 2016-08-24 2016-08-24 Based on Revit platform bridge rack wiring method and apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610717204.6A CN106407505B (en) 2016-08-24 2016-08-24 Based on Revit platform bridge rack wiring method and apparatus

Publications (2)

Publication Number Publication Date
CN106407505A true CN106407505A (en) 2017-02-15
CN106407505B CN106407505B (en) 2019-11-19

Family

ID=58004336

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610717204.6A Active CN106407505B (en) 2016-08-24 2016-08-24 Based on Revit platform bridge rack wiring method and apparatus

Country Status (1)

Country Link
CN (1) CN106407505B (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101424361A (en) * 2008-11-28 2009-05-06 大连船舶重工集团有限公司 Automatic design method for cable bridge
US20100223032A1 (en) * 2007-05-01 2010-09-02 M.E.P. CAD Inc. Methods and Apparatuses for Proposing Resolutions to Conflicts in a CAD Drawing with Reflections
CN102254056A (en) * 2011-04-08 2011-11-23 中国核电工程有限公司 Method for designing cable path of nuclear power station
CN102156776B (en) * 2011-04-08 2013-01-02 中国核电工程有限公司 Method for establishing cable bridge network by using relational database
CN104715117A (en) * 2015-03-24 2015-06-17 陕西铁路工程职业技术学院 Method for locating continuous box girder prestressed pipeline based on BIM
CN105005659A (en) * 2015-07-16 2015-10-28 中国能源建设集团广东省电力设计研究院有限公司 Cable laying method and system
CN105138757A (en) * 2015-08-17 2015-12-09 上海电力设计院有限公司 Establishment method of visual model for power cable engineering based on Autodesk Revit
CN105260541A (en) * 2015-10-13 2016-01-20 中国十七冶集团有限公司 Pipeline deepening method based on BIM model
CN105488283A (en) * 2015-11-30 2016-04-13 中国能源建设集团广东省电力设计研究院有限公司 Modeling method and system for machine room data transmission cable
CN105808835A (en) * 2016-03-04 2016-07-27 上海宝冶集团有限公司 Method for assembling pipelines of electromechanical system based on BIM (Building Information Modeling)

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100223032A1 (en) * 2007-05-01 2010-09-02 M.E.P. CAD Inc. Methods and Apparatuses for Proposing Resolutions to Conflicts in a CAD Drawing with Reflections
CN101424361A (en) * 2008-11-28 2009-05-06 大连船舶重工集团有限公司 Automatic design method for cable bridge
CN102254056A (en) * 2011-04-08 2011-11-23 中国核电工程有限公司 Method for designing cable path of nuclear power station
CN102156776B (en) * 2011-04-08 2013-01-02 中国核电工程有限公司 Method for establishing cable bridge network by using relational database
CN104715117A (en) * 2015-03-24 2015-06-17 陕西铁路工程职业技术学院 Method for locating continuous box girder prestressed pipeline based on BIM
CN105005659A (en) * 2015-07-16 2015-10-28 中国能源建设集团广东省电力设计研究院有限公司 Cable laying method and system
CN105138757A (en) * 2015-08-17 2015-12-09 上海电力设计院有限公司 Establishment method of visual model for power cable engineering based on Autodesk Revit
CN105260541A (en) * 2015-10-13 2016-01-20 中国十七冶集团有限公司 Pipeline deepening method based on BIM model
CN105488283A (en) * 2015-11-30 2016-04-13 中国能源建设集团广东省电力设计研究院有限公司 Modeling method and system for machine room data transmission cable
CN105808835A (en) * 2016-03-04 2016-07-27 上海宝冶集团有限公司 Method for assembling pipelines of electromechanical system based on BIM (Building Information Modeling)

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
符聪: ""基于BIM平台的Revit工具集的设计实现"", 《万方数据》 *
魏毅: ""电缆敷设数据库辅助系统设计"", 《石油化工自动化》 *

Also Published As

Publication number Publication date
CN106407505B (en) 2019-11-19

Similar Documents

Publication Publication Date Title
CN102103650B (en) Three-dimensional simulation arrangement-along construction method for power transmission line
CN102663180B (en) Method for drawing network distribution single line diagram
CN102360398B (en) IEC61850-based CAD electric power graphic generation analysis method
CN109583060B (en) Lighting design method for electrical three-dimensional system
JP4825887B2 (en) 3D layout adjustment CAD data creation device for cable housing parts, control method thereof, and control program
CN108804770A (en) One kind being based on BIM technology steel structure bridge model parameterization modeling method and system
CN105487858B (en) A kind of online form design system based on HTML5
CN109101710A (en) A kind of computing device and method tilting suspension tubular busbar mechanics parameter
CN107239617A (en) Compact wiring method based on track in a kind of special-shaped domain
CN107230956A (en) A kind of construction method of arc cable trunking structure
CN108897913A (en) A method of plant stand figure is automatically generated by SCD model file
CN105098566B (en) A kind of cable wire stripping, tangent line processing unit (plant)
CN106407505A (en) Method and apparatus for performing wiring on bridge frames based on Revit platform
CN110567410B (en) Method and system for calculating length of cable in cabinet equipment in segmented manner
US7962881B2 (en) Via structure to improve routing of wires within an integrated circuit
CN104239615B (en) A kind of cylinder door frame automated analysis method
CN112906117A (en) Indoor equipment layout generating method and device, electronic equipment and storage medium
CN105140835A (en) Six-line cable fixation device of IDC machine room
US20140136161A1 (en) Precise simulation of progeny derived from recombining parents
CN109344418A (en) LED automatic wiring method, automatic routing system and storage medium
CN111324998B (en) Route search-based connecting wire routing layout method
CN109388889B (en) Method for establishing parameterized prestressed pipe bundle group
FAVRIN Escalating fire scenarios: a comprehensive approach to the use of CFD tools
JP5244709B2 (en) Optical cable core wire automatic connection program and core wire automatic connection system
CN114239243A (en) Method and system for continuously calculating tension paying-off process of power transmission line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: Suzhou City, Jiangsu province 215600 Zhangjiagang Economic Development Zone (Changxin road yangshe)

Patentee after: Guotai Xindian Software Co., Ltd

Address before: Suzhou City, Jiangsu province 215600 Zhangjiagang Jiangfan Road No. 8

Patentee before: JIANGSU GUOTAI XINDIAN SOFTWARE Co.,Ltd.