CN106401591A - Small-angle bottom-penetrating construction method of highway grid tunnel - Google Patents

Small-angle bottom-penetrating construction method of highway grid tunnel Download PDF

Info

Publication number
CN106401591A
CN106401591A CN201611116630.0A CN201611116630A CN106401591A CN 106401591 A CN106401591 A CN 106401591A CN 201611116630 A CN201611116630 A CN 201611116630A CN 106401591 A CN106401591 A CN 106401591A
Authority
CN
China
Prior art keywords
tunnel
construction
region
high speed
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611116630.0A
Other languages
Chinese (zh)
Other versions
CN106401591B (en
Inventor
赵辉
张杨
连小涛
邓能伟
魏兆雷
吴鑫
刘利国
李胡爽
陈永宏
卢鹏程
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201611116630.0A priority Critical patent/CN106401591B/en
Publication of CN106401591A publication Critical patent/CN106401591A/en
Application granted granted Critical
Publication of CN106401591B publication Critical patent/CN106401591B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention relates to a small-angle bottom-penetrating construction method of a highway grid tunnel. The cross section of a tunnel is separated into a left upper area, a left lower area, a middle upper area, a middle lower area, a right upper area, and a right lower area in the vertical and horizontal directions. The construction method comprises the following steps of when the areas are excavated, excavating the middle area of the tunnel, and arranging an advance pre-support around the contour of the cross section of the tunnel before the middle area is excavated; after the middle area of the tunnel is excavated for a section of distance, excavating the areas at both sides of the tunnel from top to bottom, wherein when the area is excavated, the staggering distance is 3-5m at a working surface in the excavation process of a tunnel chamber, and the circulation excavation progress is 0.5m each time. The construction method has the advantages that the small-angle bottom-penetrating construction of the highway tunnel is realized, the normal passing of highways is guaranteed, the settlement of road pavements meets the design requirements, the site construction safety, quality and construction period goals are controllable, and the construction method can be applied to busy roads, such as airport highways.

Description

High Speed Grid method for tunnel construction is worn under low-angle
Technical field
The present invention relates to technical field of tunnel construction is and in particular to wear High Speed Grid constructing tunnel side under a kind of low-angle Method.
Background technology
With the fast development of Chinese national economy, the construction scale in city expands rapidly, in recent years with bored tunnel shape The engineering of formula underpass of freeways and railway gradually increases.Run busy highway, railway and have the structures such as building When building the underground engineerings such as tunnel or underpass below thing, how to be constructed using shallow burial hidden digging.Shallow-depth-excavation tunnel is applied During work, not only the acting on of stratum to be subject to and itself permanent load, but also train (automobile) Under Dynamic Load can be subject to.Tunnel When closely wearing down existing road or other structures, because the reasons such as working measure is improper, geological hydrology disaster cause road surface big Amount sedimentation is even caved in, and will result in interruption of communication, leads to huge economic loss and social influence.When tunnel with highway is in During existing low-angle angle, tunnel now is larger with the face ratio that overlaps of highway, such as according to traditional shallow-depth-excavation tunnel Form of construction work, the substantial amounts of sedimentation in road surface may be produced and even cave in, and when requiring the face in tunnel apart from ground When distance is less, the possibility that above-mentioned construction method produces roadbed subsidence greatly increases.
Content of the invention
It is an object of the invention to provide wearing High Speed Grid method for tunnel construction under a kind of low-angle it is ensured that in work progress High speed normal pass, roadbed subsidence meet design requirement.
For achieving the above object, the technical solution used in the present invention is:
Velocity tunnel construction method is worn, construction method comprises the steps under a kind of low-angle,
A, the section to tunnel carry out subregion, according to upper and lower to and left and right direction be divided into top left region, lower left region, In upper region, in lower region, right regions and lower right area;
When B, the excavation construction in above-mentioned 6 regions, the zone line in tunnel is carried out excavating construction, in zone line first Before excavating construction, cross section profile periphery in tunnel setting gate-type and radial direction leading pre-supporting, the digging of the zone line in tunnel Pick construction is from top to bottom carried out;
After C, the zone line in tunnel carry out excavating construction one segment distance, start the two side areas of tunneling, tunnel The excavation construction of 10 two side areas is from top to bottom carried out;
When D, the excavation construction in above-mentioned 6 regions, the face in each cavern's mining process staggers distance for 3~5m, Drilling depth is excavated in circulation every time is 0.5m.
Also there is following technical characteristic in present method invention:
In described step B, in upper region when excavating the lower section entering highway, in upper region and in lower region spacing Control in 2.5~3m, in lower region setting preliminary bracing so that in lower region form closed-loop.
In described step C, when top left region is excavated at 3m position below highway, stop to top left region, a left side The excavation construction in lower region, and the face pneumatically placed concrete closing to top left region, lower left region.
Whne in lower region excavate be more than at 5m position apart from distance below highway when, start to proceed upper left area Domain, the excavation construction of lower left region.
In described, upper region, top left region, right regions are excavated construction and are sequentially entered below highway.
During the cross section profile leading pre-supporting in tunnel, using the booth pipe of a diameter of 180mm, the conduit of a diameter of 42mm and The slip casting of full section face carries out leading pre-supporting;Wherein upper left, lower-left, upper right and lower right area advance support adopt radial grouting mode Constructed.
During the excavation construction in above-mentioned 6 regions, in upper region, top left region, right regions applied using manually carrying out excavation Work, lower left region, in lower region, lower right area constructed using hand fit's development machine, in preliminary bracing work progress, In the range of arch, the steel floral tube of pre-buried a diameter of 42mm is as Grouting Pipe, after preliminary bracing closure ring length is more than 5m, to first Carry out slip casting after supporting back.
On in distance, soil outlet is reserved in region face 3m position, in lower region face reserve and slip native groove.
Compared with prior art, the technique effect that the present invention possesses is:" latticed " disconnected by being divided into tunnel cross-section Face pattern, is realized bored tunnel sectional form " changing greatly little " purpose, is applied by each region of continuous adjustment during constructing tunnel Work order, realizes shallow-depth-excavation tunnel to wear at a high speed simultaneously smooth insertion purpose under low-angle, carries out shallow buried covered excavation using this method Construction at a high speed is worn it can be ensured that high speed normal pass and roadbed subsidence meet design requirement under rectangle large cross-section tunnel low-angle, existing Field construction safety, quality and constructing aims are controlled, and this construction method can be applicable to the busy section such as Airport Expwy.
Brief description
Fig. 1 is this method " latticed " tunnel cross section figure and schematic three dimensional views;
Fig. 2 is that each pilot tunnel of this method enters Airport Expwy sequence of construction schematic diagram;
Fig. 3 is upper region excavation, supporting construction schematic diagram in this method;
Fig. 4 is lower region excavation, supporting construction schematic diagram in this method;
Fig. 5 is the top left region excavation of this method, supporting construction schematic diagram;
Fig. 6 is the lower left region excavation of this method, supporting construction schematic diagram;
Fig. 7 is the right regions excavation of this method, supporting construction schematic diagram;
Fig. 8 is the lower right area excavation of this method, supporting construction schematic diagram;
Fig. 9 is the soil outlet of this method and slips the reserved skiagraph of native groove;
Figure 10 is this method soil outlet and slips the reserved plan of native groove.
Specific embodiment
In conjunction with Fig. 1 to Figure 10, the present invention is further described:
Velocity tunnel construction method is worn, construction method comprises the steps under a kind of low-angle,
A, the section to tunnel 10 carry out subregion, according to upper and lower to and left and right direction be divided into top left region 13, lower-left Region 14, in upper region 11, in lower region 12, right regions 15 and lower right area 16;
When B, the excavation construction in above-mentioned 6 regions, the zone line in tunnel 10 is carried out excavating construction, in mesozone first Before construction is excavated in domain, the cross section profile periphery in tunnel 10 arranges leading pre-supporting, and the excavation of the zone line in tunnel 10 is applied Work is from top to bottom carried out;
After C, the zone line in tunnel 10 carry out excavating construction one segment distance, start the two side areas of tunneling 10, The excavation construction of the two side areas in tunnel 10 is from top to bottom carried out;
When D, the excavation construction in above-mentioned 6 regions, the face in each cavern's mining process staggers distance for 3~5m, Drilling depth is excavated in circulation every time is 0.5m.
By tunnel 10 section is divided into " latticed " sectional form, realizes bored tunnel 10 sectional form and " change greatly Little " purpose, pass through continuous adjustment each region sequence of construction in tunnel 10 work progress, realize shallow-depth-excavation tunnel with low-angle Wear high speed smooth insertion purpose, carry out wearing under shallow buried covered excavation rectangle large cross-section tunnel 10 low-angle using this method and apply at a high speed , it can be ensured that high speed normal pass and roadbed subsidence meet design requirement, site operation safety, quality and constructing aims are controlled for work, This construction method can be applicable to the busy section such as Airport Expwy.
In described step B, in upper region 11 when excavating the lower section entering highway, in upper region 11 and in lower region 12 Spacing control in 2.5~3m, in lower region 12 setting preliminary bracing so that in lower region 12 formation closed-loop, wherein Preliminary bracing adopts I20 I-steel and the construction of C25 in-network processing, lining thickness 30cm.
In described step C, when top left region 13 is excavated at 3m position below highway, stop to top left region 13rd, the excavation construction of lower left region 14, and the face pneumatically placed concrete closing to top left region 13, lower left region 14, spray coagulation Soil thickness is 8cm, arranges reinforced mesh if necessary.
Whne in lower region 12 excavate be more than at 5m position apart from distance below highway when, start to proceed upper left area Domain 13, the excavation construction of lower left region 14.
In described, upper region 11, top left region 13, right regions 15 are excavated construction and are sequentially entered below highway, adopt This mode is constructed, and settlement of highway is less than design controlling value 30mm.
For guaranteeing front of tunnel heading and periphery soil stabilization before the construction of bored tunnel excavation supporting, the cross section profile in tunnel 10 During leading pre-supporting, paid in advance in advance using the booth pipe of a diameter of 180mm, the conduit of a diameter of 42mm and the slip casting of full section face Shield it is ensured that before the construction of bored tunnel excavation supporting face and front soil stabilization it is ensured that construction safety, wherein a diameter of Overlength booth tube pitch 0.3m of 180mm, single construction length 85m;Every construction length 3m of the conduit of a diameter of 42mm, longitudinally Spacing 2.0m, circumferential distance 0.3m;Full-face pouring adopts a diameter of 45mm conduit to construct, conduit 1*1m quincuncial arrangement, often Secondary construction length 20m, overlaps 5m.
During the excavation construction in above-mentioned 6 regions, in upper region 11, top left region 13, right regions 15 using manually carrying out Excavate construction, lower left region 12, in lower region 14, lower right area 16 constructed using artificial and development machine cooperation, the initial stage props up In shield work progress, in the range of arch the steel floral tube of pre-buried a diameter of 42mm as Grouting Pipe, when preliminary bracing closure ring is long Degree more than after 5m, to carrying out slip casting after first supporting back it is ensured that just no empty behind.
For guaranteeing that the upper pilot tunnel earthwork is quickly transported to lower pilot tunnel, in distance on region 13 face 3m position reserve soil outlet 131, in lower region 14 face reserve and slip native groove 141, slip pilot tunnel arch springing side in native groove 141 back gauge at least retain 1m away from From it is ensured that upper pilot tunnel bow member safety.

Claims (8)

1. wear High Speed Grid method for tunnel construction under a kind of low-angle it is characterised in that:Construction method comprises the steps,
A, the section to tunnel (10) carry out subregion, according to upper and lower to and left and right direction be divided into top left region (13), lower-left Region (14), in upper region (11), in lower region (12), right regions (15) and lower right area (16);
When B, the excavation construction in above-mentioned 6 regions, the zone line of tunnel (10) is carried out excavating construction, in zone line first Before excavating construction, the cross section profile periphery in tunnel (10) arranges leading pre-supporting, the excavation of the zone line of tunnel (10) Construction is from top to bottom carried out;
C, tunnel (10) zone line carry out excavate construction one segment distance after, start tunneling (10) two side areas, The excavation construction of the two side areas in tunnel (10) is from top to bottom carried out;
When wearing high speed under D, tunnel low-angle, first suspend tunnel (13), (14), (15) and (16) portion and excavate, face is sprayed Concrete enclosing, enters after main stem 5m after tunnel (12), then row tunneling (13), (14), (15) and (16) portion.
When E, the excavation construction in above-mentioned 6 regions, the face in each cavern's mining process staggers distance for 3~5m, every time It is 0.5m that drilling depth is excavated in circulation.
2. wear High Speed Grid method for tunnel construction under low-angle according to claim 1 it is characterised in that:Described step B In, in upper region (11) when excavating the lower section entering highway, in upper region (11) and in lower region (12) spacing control In 2.5~3m, in lower region (12) setting preliminary bracing so that in lower region (12) formation closed-loop.
3. wear High Speed Grid method for tunnel construction under low-angle according to claim 2 it is characterised in that:Described step C In, when top left region (13) is excavated at 3m position below highway, stop to top left region (13), lower left region (14) Excavation construction, and to the closing of the face pneumatically placed concrete of top left region (13), lower left region (14).
4. wear High Speed Grid method for tunnel construction under low-angle according to claim 3 it is characterised in that:Lower region in treating (12) excavate distance below entrance highway, more than when at 5m position, to start to proceed top left region (13), lower left region (14) excavation construction.
5. wear High Speed Grid method for tunnel construction under low-angle according to claim 3 it is characterised in that:Described Zhong Shang area Domain (11), top left region (13), right regions (15) are excavated construction and are sequentially entered below highway.
6. wear High Speed Grid method for tunnel construction under the low-angle according to 1 to 4 any one claim, its feature exists In:During the cross section profile leading pre-supporting in tunnel (10), using the steel tube shed of a diameter of 180mm, the conduit of a diameter of 42mm and The slip casting of full section face carries out leading pre-supporting.
7. wear High Speed Grid method for tunnel construction under low-angle according to claim 6 it is characterised in that:Above-mentioned 6 areas During the excavation construction in domain, in upper region (11), top left region (13), right regions (15) using manually carrying out excavating construction, left Lower region (14), in lower region (12), lower right area (16) constructed using hand fit's development machine, preliminary bracing was constructed Cheng Zhong, in the range of arch, the steel floral tube of pre-buried a diameter of 42mm, as Grouting Pipe, is more than 5m when preliminary bracing closes ring length Afterwards, carry out slip casting to after first supporting back.
8. wear High Speed Grid method for tunnel construction under low-angle according to claim 6 it is characterised in that:On in distance Soil outlet (111) is reserved in region (11) face 3m position, in lower region (12) face reserve and slip native groove (121).
CN201611116630.0A 2016-12-07 2016-12-07 High Speed Grid method for tunnel construction is worn under low-angle Active CN106401591B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611116630.0A CN106401591B (en) 2016-12-07 2016-12-07 High Speed Grid method for tunnel construction is worn under low-angle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611116630.0A CN106401591B (en) 2016-12-07 2016-12-07 High Speed Grid method for tunnel construction is worn under low-angle

Publications (2)

Publication Number Publication Date
CN106401591A true CN106401591A (en) 2017-02-15
CN106401591B CN106401591B (en) 2018-07-06

Family

ID=58083754

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611116630.0A Active CN106401591B (en) 2016-12-07 2016-12-07 High Speed Grid method for tunnel construction is worn under low-angle

Country Status (1)

Country Link
CN (1) CN106401591B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108397210A (en) * 2018-01-31 2018-08-14 山东大学 A kind of supporting construction and method for tunnel reconstruction and extension project
CN111878083A (en) * 2020-07-10 2020-11-03 中铁五局集团有限公司 Advanced grouting construction method for underground excavated tunnel
CN112195698A (en) * 2020-09-28 2021-01-08 中国一冶集团有限公司 Construction method for road crossing under road section with heavy traffic pressure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07127374A (en) * 1993-11-05 1995-05-16 Maeda Corp Method for constructing tunnel
JP2005090176A (en) * 2003-09-19 2005-04-07 Shimizu Corp Tunnel excavating method
CN101666232A (en) * 2009-09-27 2010-03-10 中铁四局集团有限公司 Construction method of six-zone digging of super cross section tunnel
CN102562076A (en) * 2011-12-23 2012-07-11 中铁十九局集团第五工程有限公司 Underground excavation construction technology for large cross-section subway station under geological condition of soft upper layer and hard lower layer
CN105888696A (en) * 2016-06-30 2016-08-24 中铁四局集团第四工程有限公司 Construction method of large-section tunnel
CN106014449A (en) * 2016-07-05 2016-10-12 重庆建工市政交通工程有限责任公司 Construction method of double-track small-clear distance large-section jointed rock mass subway tunnel

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07127374A (en) * 1993-11-05 1995-05-16 Maeda Corp Method for constructing tunnel
JP2005090176A (en) * 2003-09-19 2005-04-07 Shimizu Corp Tunnel excavating method
CN101666232A (en) * 2009-09-27 2010-03-10 中铁四局集团有限公司 Construction method of six-zone digging of super cross section tunnel
CN102562076A (en) * 2011-12-23 2012-07-11 中铁十九局集团第五工程有限公司 Underground excavation construction technology for large cross-section subway station under geological condition of soft upper layer and hard lower layer
CN105888696A (en) * 2016-06-30 2016-08-24 中铁四局集团第四工程有限公司 Construction method of large-section tunnel
CN106014449A (en) * 2016-07-05 2016-10-12 重庆建工市政交通工程有限责任公司 Construction method of double-track small-clear distance large-section jointed rock mass subway tunnel

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108397210A (en) * 2018-01-31 2018-08-14 山东大学 A kind of supporting construction and method for tunnel reconstruction and extension project
CN108397210B (en) * 2018-01-31 2024-02-27 山东大学 Supporting structure and method for tunnel reconstruction and expansion engineering
CN111878083A (en) * 2020-07-10 2020-11-03 中铁五局集团有限公司 Advanced grouting construction method for underground excavated tunnel
CN112195698A (en) * 2020-09-28 2021-01-08 中国一冶集团有限公司 Construction method for road crossing under road section with heavy traffic pressure

Also Published As

Publication number Publication date
CN106401591B (en) 2018-07-06

Similar Documents

Publication Publication Date Title
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN104500077B (en) A kind of shallow-depth-excavation tunnel passes through cottage area construction method
CN101864960B (en) Carst region double-arch road tunnel construction method
CN104265307B (en) Non-uniform-hardness stratum earth pressure balance shield tunnel underpassing railway existing line construction method
CN107542470B (en) Existing railway Business Line construction method is worn under the shallow tunnel of karst broken region
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN104612698A (en) Method for constructing upper step middle partition wall of shallow-buried excavation tunnel
CN108005660A (en) A kind of Optimization of Expressway Tunnel Construction method
CN103883328B (en) The dark construction method of half lid half of high steep V-type coombe biased segment is worn under separate tunnel
CN102518470B (en) Method for preventing and controlling water by using freezing pipes in annular water intercepting tunnel
CN102251777A (en) Large-scale karst cavity treatment method for karst tunnel
CN108412502B (en) A kind of deep tunnel passes through upper-soft lower-hard ground construction method
CN103899323A (en) Construction method of shield passing through railway yard
CN105697033A (en) Construction method for treating rock mass cavity without formworks in tunneling
WO2022247176A1 (en) Filling caving mining method
CN106014449A (en) Construction method of double-track small-clear distance large-section jointed rock mass subway tunnel
CN105909263A (en) Eolian sand stratum highway tunnel structure and construction method thereof
CN106285715A (en) The construction method of a just bored tunnel is worn in balancing earth-pressure shielding machine closely side
CN106907177B (en) A kind of girdle gob side entry retaining roadside packing method for protecting support
CN106401591B (en) High Speed Grid method for tunnel construction is worn under low-angle
CN108979659A (en) The ruggedized construction and method of structures are worn under weak soil rich water large cross-section tunnel group
CN108678753B (en) Reverse-slope tunnel construction method
CN107965325A (en) Just branch bow member replaces construction method to a kind of small interval shallow tunnel
CN106121659A (en) The narrow-bore tunnel excavation method of major urban arterial highway upper-soft lower-hard ground is worn under one

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant