CN106400810A - Foundation pit support structure and construction method thereof - Google Patents

Foundation pit support structure and construction method thereof Download PDF

Info

Publication number
CN106400810A
CN106400810A CN201610240442.2A CN201610240442A CN106400810A CN 106400810 A CN106400810 A CN 106400810A CN 201610240442 A CN201610240442 A CN 201610240442A CN 106400810 A CN106400810 A CN 106400810A
Authority
CN
China
Prior art keywords
foundation pit
construction
pit supporting
stake
smw
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610240442.2A
Other languages
Chinese (zh)
Inventor
方怡
刘健
陈坤亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Publication of CN106400810A publication Critical patent/CN106400810A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention provides a foundation pit support structure and a construction method thereof. The foundation pit support structure is used in a building project of the coastal backfill area. The foundation pit support structure comprises at least one SMW construction method pile, a pre-stressed anchor cable and an enclosure ring beam. The enclosure ring beam is built on the multiple SMW construction method piles in the horizontal direction in a closed manner. The pre-stressed anchor cable anchors the SMW construction method piles and the enclosure ring beam. According to the geological condition characteristics of coastal areas, the foundation pit support safety is ensured, the foundation pit support effect is guaranteed, and meanwhile the construction efficiency is improved.

Description

Foundation pit supporting construction and its construction method
Technical field
The application is related to mechanical field, the foundation pit supporting construction of architectural engineering in more particularly, to a kind of coastal backfill region and Its construction method.
Background technology
In coastal backfill region construction, one kind of foundation pit supporting project goes along with sb. to guard him gear earthwork formula, domestic in the past on edge In the Foundation Pit Construction in sea backfill region, frequently with Punching Borehole Cast-in-place Concrete Pile or using SMW engineering method stake (Soil Mixing Wall) mode with reference to internal support of foundation pit makees pattern foundation pit supporting structure.
When in the past pattern foundation pit supporting structure being made using Punching Borehole Cast-in-place Concrete Pile, building enclosure more firm it is difficult to cut, for also needing in the future There is larger adverse effect at the position excavated, and which need to separately add high pressure rotary churning pile or cement mixing method makees sealing, also Substantial amounts of reinforcing bar and concrete need to be expended, cost is higher;And when adopting the support pattern of SMW engineering method stake+internal support of foundation pit, foundation ditch Inside often have the structure such as a large amount of lattice columns and the support of steel concrete, have impact on earth excavation engineering and underground engineering to a certain extent The working face of each machinery in construction.
Content of the invention
The application technical problem to be solved is, according to coastal area geological condition feature, provides a kind of pattern foundation pit supporting structure knot Structure and its construction method, while to guarantee pattern foundation pit supporting structure safety, to ensure pattern foundation pit supporting structure effect, improve efficiency of construction.
For achieving the above object, a kind of foundation pit supporting construction on the one hand being provided according to the application, described pattern foundation pit supporting structure knot Structure be used for coastal backfill region architectural engineering, described foundation pit supporting construction include at least one SMW engineering method stake, prestress anchorage cable and Go along with sb. to guard him collar tie beam;Wherein,
Described go along with sb. to guard him collar tie beam and close in the horizontal direction build by laying bricks or stones in some described SMW engineering method stakes, described prestress anchorage cable pair Described SMW engineering method stake and described collar tie beam of going along with sb. to guard him are anchored.
Further, described prestress anchorage cable includes anchoring section and free segment;Wherein, described anchoring section be fixed on described in build Build in the rock mass stability of engineering underground, free segment one end of described prestress anchorage cable is connected with described anchoring section, the other end and company Be connected to SMW engineering method stake described in one and described go along with sb. to guard him collar tie beam build junction by laying bricks or stones.
Further, described prestress anchorage cable is Recyclable anchor rope.
Further, described SMW engineering method stake includes cement mixing method and is inserted in the H profile steel in cement mixing method.
Further, described foundation pit supporting construction also includes:Plain concrete load transfering strip, described plain concrete load transfering strip setting Between described SMW engineering method stake and the base plate of described architectural engineering.
Further, described plain concrete load transfering strip along described SMW engineering method stake to the transverse width in described base plate direction is 400 millimeters~600 millimeters.
A kind of construction method of the foundation pit supporting construction on the other hand being provided according to the application, described foundation pit supporting construction is used In the architectural engineering in coastal backfill region, described construction method includes:
Construct some SMW engineering method stakes;
Construction forms and does not apply prestressed anchor cable;
Collar tie beam is gone along with sb. to guard him in construction formation, described go along with sb. to guard him collar tie beam and close in the horizontal direction build by laying bricks or stones in some described SMW engineering method stakes;
Apply prestressing force to not applying prestressed anchor cable, to be formed for described SMW engineering method stake with described go along with sb. to guard him collar tie beam The prestress anchorage cable being anchored.
Further, described prestress anchorage cable includes anchoring section and free segment;Wherein, described anchoring section be fixed on described in build Build in the rock mass stability of engineering underground, free segment one end of described prestress anchorage cable is connected with described anchoring section, the other end and company Be connected to SMW engineering method stake described in one and described go along with sb. to guard him collar tie beam build junction by laying bricks or stones.
Further, described SMW engineering method stake includes cement mixing method and is inserted in H profile steel in cement mixing method, Described construction method also includes:After the completion of the basement engineering of described architectural engineering, reclaim described prestress anchorage cable and described H Shaped steel.
Further, described construction method also includes:Apply between described SMW engineering method stake and the base plate of described architectural engineering Work forms plain concrete load transfering strip.
Compared with prior art, herein described foundation pit supporting construction and its construction method have the advantage that:
1st, combine the support pattern of prestress anchorage cable due to employing SMW engineering method stake, evaded and having been made using Punching Borehole Cast-in-place Concrete Pile During supporting, the later stage is difficult to situation about cutting, and for the engineering of Develop by stages, the underground structure beneficial to different exploitation periods is carried out even Logical;
2nd, to SMW engineering method stake and go along with sb. to guard him collar tie beam and anchor using prestress anchorage cable, it is to avoid arrange using in foundation ditch When lattice column and steel concrete support, the working faces of all kinds of machineries are had a negative impact so that in earth excavation and follow-up underground engineering Vehicle during construction and all kinds of construction machinery have more flexible operating space;
3rd, adopt SMW engineering method stake, wherein, H profile steel can be recycled after the completion of basement structure construction, prestressing force Anchor cable may also be employed Recyclable anchor rope, improves the utilization rate of resource, reduces cost.
Brief description
By reading the detailed description that non-limiting example is made made with reference to the following drawings, other of the application Feature, objects and advantages will become more apparent upon:
Fig. 1 illustrates a kind of foundation pit supporting construction schematic diagram on the one hand providing according to the application;
Fig. 2 illustrates a kind of construction method of the foundation pit supporting construction according to the application another aspect offer.
In accompanying drawing, same or analogous reference represents same or analogous part.
Specific embodiment
Below in conjunction with the accompanying drawings the application is described in further detail.
The application be intended in line with according to coastal area geological condition feature it is ensured that pattern foundation pit supporting structure safety is it is ensured that pattern foundation pit supporting structure Effect, improves efficiency of construction, it is proposed that " SMW engineering method stake with together with prestress anchorage cable " in foundation pit supporting project work progress Foundation pit supporting construction and construction method.
Fig. 1 illustrates a kind of foundation pit supporting construction on the one hand providing according to the application, and described foundation pit supporting construction is used for edge The architectural engineering in sea backfill region, described foundation pit supporting construction includes at least one SMW engineering method stake 100, prestress anchorage cable 200 and encloses Guard ring beam 300;Wherein,
Described go along with sb. to guard him collar tie beam 300 and close in the horizontal direction build by laying bricks or stones in some described SMW engineering method stakes 100, described prestressing force Anchor cable 200 anchors to described SMW engineering method stake 100 and described collar tie beam 100 of going along with sb. to guard him.
Preferably, described foundation pit supporting construction is located at below nature terrace.
Further, described prestress anchorage cable 200 includes anchoring section 200a and free segment 200b;Wherein, described anchoring section 200a is fixed in the rock mass stability of described architectural engineering underground, described free segment 200b one end and described anchoring section 200a phase Even, the other end be connected to SMW engineering method stake 100 described in one and described go along with sb. to guard him collar tie beam 300 build junction by laying bricks or stones.
Preferably, described prestress anchorage cable 200 is Recyclable anchor rope.
Preferably, described SMW engineering method stake 100 includes cement mixing method 100b and is inserted in the H in cement mixing method Shaped steel 100a.Preferably, described SMW engineering method stake is to carry out drilling to certain depth at the scene with fountain type drilling mixer, with When at drill bit spray cement system hardening agent and with foundation soil mix and blend repeatedly, then take overlap to take between each construction cell Connect construction, then do not tie firmly front insertion H profile steel or steel plate as its stress reinforcing material in soil cement mixture, hard to cement knot, Just formed and include cement mixing method 100b together and be inserted in H profile steel 100a in cement mixing method, have necessarily strong Degree and rigidity, continuous whole, jointless underground wall body stake.
Additionally, described collar tie beam more than 300 of going along with sb. to guard him adopts cast-in-situ steel reinforced concrete, in order to improve the overall empty of foundation pit supporting construction Between rigidity, increase globality, building is played with the effect of waist hoop, improves shearing resistance, tensile strength, and prevent due to ground uneven Sedimentation, earthquake or other cracking destructions to house for larger vibration load, its effect is main also have adjust it may happen that inequality Even sedimentation, strengthens the globality on basis, also makes subgrade reaction evenly point, also has circle beam action and waterproof and dampproof simultaneously Effect.
Further, described foundation pit supporting construction also includes:Plain concrete load transfering strip 600, described plain concrete load transfering strip 600 are arranged between described SMW engineering method stake 100 and the base plate 500 of described architectural engineering.
Further, described plain concrete load transfering strip 600 is along described SMW engineering method stake 100 to the horizontal stroke in described base plate 500 direction It is 400 millimeters~600 millimeters to width.Preferably 500 millimeters.The effect of described plain concrete load transfering strip 600 is in H profile steel Transfer the load on the concrete of basement base plate that can stablize bearing load when reclaiming with the prestress anchorage cable playing anchorage effect, To form new mechanical balance.
Fig. 2 illustrates a kind of construction method of the foundation pit supporting construction according to the application another aspect offer, and described foundation ditch props up Protection structure is used for the architectural engineering in coastal backfill region, and described construction method includes:
Step S01:Construct some SMW engineering method stakes;
Step S02:Construction forms and does not apply prestressed anchor cable;
Step S03:Collar tie beam is gone along with sb. to guard him in construction formation, described go along with sb. to guard him collar tie beam and close in the horizontal direction build by laying bricks or stones in some described SMW In engineering method stake;
Step S04:Apply prestressing force to not applying prestressed anchor cable, to be formed for described SMW engineering method stake and described Go along with sb. to guard him the prestress anchorage cable that collar tie beam is anchored.
Further, described prestress anchorage cable includes anchoring section and free segment;Wherein, described anchoring section be fixed on described in build Build in the rock mass stability of engineering underground, free segment one end of described prestress anchorage cable is connected with described anchoring section, the other end and company Be connected to SMW engineering method stake described in one and described go along with sb. to guard him collar tie beam build junction by laying bricks or stones.
Further, described SMW engineering method stake includes cement mixing method and is inserted in H profile steel in cement mixing method, Described construction method also includes:After the completion of the basement engineering of described architectural engineering, reclaim described prestress anchorage cable and described H Shaped steel.
Further, described construction method also includes:Step S05 (does not indicate), in described SMW engineering method stake and described building Between the base plate of engineering, construction forms plain concrete load transfering strip.Further, described plain concrete load transfering strip is along described SMW engineering method Stake is 400 millimeters~600 millimeters to the transverse width in described base plate direction, that is, between described SMW engineering method stake and described base plate Distance.Preferably 500 millimeters.The effect of plain concrete load transfering strip is to recover with the prestressed anchor playing anchorage effect in H profile steel Time receiving transfers the load on the concrete of basement base plate that can stablize bearing load, to form new mechanical balance.
Compared with prior art, herein described foundation pit supporting construction and its construction method have the advantage that:
1st, combine the support pattern of prestress anchorage cable due to employing SMW engineering method stake, evaded and having been made using Punching Borehole Cast-in-place Concrete Pile During supporting, the later stage is difficult to situation about cutting, and for the engineering of Develop by stages, the underground structure beneficial to different exploitation periods is carried out even Logical;
2nd, to SMW engineering method stake and go along with sb. to guard him collar tie beam and anchor using prestress anchorage cable, it is to avoid arrange using in foundation ditch When lattice column and steel concrete support, the working faces of all kinds of machineries are had a negative impact so that in earth excavation and follow-up underground engineering Vehicle during construction and all kinds of construction machinery have more flexible operating space;
3rd, adopt SMW engineering method stake, wherein, H profile steel can be recycled after the completion of basement structure construction, prestressing force Anchor cable may also be employed Recyclable anchor rope, improves the utilization rate of resource, reduces cost.
It is obvious to a person skilled in the art that the application is not limited to the details of above-mentioned one exemplary embodiment, Er Qie In the case of spirit herein or essential characteristic, the application can be realized in other specific forms.Therefore, no matter From the point of view of which point, embodiment all should be regarded as exemplary, and be nonrestrictive, scope of the present application is by appended power Profit requires rather than described above limits, it is intended that all in the implication and scope of the equivalency of claim by falling Change is included in the application.Any reference in claim should not be considered as limiting involved claim.
Obviously, those skilled in the art can carry out the various changes and deformation essence without deviating from the present invention to the present invention God and scope.So, if these modifications to the present invention and modification belong to the model of the claims in the present invention and its equivalent technologies Within enclosing, then the present invention is also intended to comprise these variations and modification.

Claims (10)

1. a kind of foundation pit supporting construction it is characterised in that described foundation pit supporting construction be used for coastal backfill region architectural engineering, Described foundation pit supporting construction includes at least one SMW engineering method stake, prestress anchorage cable and goes along with sb. to guard him collar tie beam;Wherein,
Described go along with sb. to guard him collar tie beam and close in the horizontal direction build by laying bricks or stones in some described SMW engineering method stakes, described prestress anchorage cable is to described SMW engineering method stake and described collar tie beam of going along with sb. to guard him are anchored.
2. foundation pit supporting construction according to claim 1 it is characterised in that described prestress anchorage cable include anchoring section and from By section;Wherein,
Described anchoring section is fixed in the rock mass stability of described architectural engineering underground, free segment one end of described prestress anchorage cable with Described anchoring section is connected, the other end be connected to SMW engineering method stake described in one and described go along with sb. to guard him collar tie beam build junction by laying bricks or stones.
3. foundation pit supporting construction according to claim 1 and 2 is it is characterised in that described prestress anchorage cable is recyclable anchor Rope.
4. foundation pit supporting construction according to claim 1 is it is characterised in that described SMW engineering method stake includes Soil-cement Stake and be inserted in the H profile steel in cement mixing method.
5. foundation pit supporting construction according to claim 1 is it is characterised in that described foundation pit supporting construction also includes:
Plain concrete load transfering strip, described plain concrete load transfering strip is arranged at the base plate of described SMW engineering method stake and described architectural engineering Between.
6. foundation pit supporting construction according to claim 4 is it is characterised in that described plain concrete load transfering strip is along described SMW Engineering method stake is 400 millimeters~600 millimeters to the transverse width in described base plate direction.
7. a kind of construction method of foundation pit supporting construction is it is characterised in that described foundation pit supporting construction is used for coastal backfill region Architectural engineering, described construction method includes:
Construct some SMW engineering method stakes;
Construction forms and does not apply prestressed anchor cable;
Collar tie beam is gone along with sb. to guard him in construction formation, described go along with sb. to guard him collar tie beam and close in the horizontal direction build by laying bricks or stones in some described SMW engineering method stakes;
Apply prestressing force to not applying prestressed anchor cable, to be formed for carrying out to described SMW engineering method stake and described collar tie beam of going along with sb. to guard him The prestress anchorage cable of anchoring.
8. construction method according to claim 7 is it is characterised in that described prestress anchorage cable includes anchoring section and freedom Section;Wherein,
Described anchoring section is fixed in the rock mass stability of described architectural engineering underground, free segment one end of described prestress anchorage cable with Described anchoring section is connected, the other end be connected to SMW engineering method stake described in one and described go along with sb. to guard him collar tie beam build junction by laying bricks or stones.
9. the construction method according to claim 7 or 8 is it is characterised in that described SMW engineering method stake includes cement mixing method And it is inserted in H profile steel in cement mixing method,
Described construction method also includes:
After the completion of the basement engineering of described architectural engineering, reclaim described prestress anchorage cable and described H profile steel.
10. construction method according to claim 7 is it is characterised in that described construction method also includes:
Between described SMW engineering method stake and the base plate of described architectural engineering, construction forms plain concrete load transfering strip.
CN201610240442.2A 2015-12-29 2016-04-18 Foundation pit support structure and construction method thereof Pending CN106400810A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2015110183319 2015-12-29
CN201511018331 2015-12-29

Publications (1)

Publication Number Publication Date
CN106400810A true CN106400810A (en) 2017-02-15

Family

ID=58005407

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610240442.2A Pending CN106400810A (en) 2015-12-29 2016-04-18 Foundation pit support structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN106400810A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101775814A (en) * 2009-02-20 2010-07-14 上海强劲基础工程有限公司 Anti-slip cement soil pile soil blocking structure and construction method thereof
CN103195085A (en) * 2013-04-02 2013-07-10 东南大学 Downward story-adding basement and construction method thereof
CN103603359A (en) * 2013-11-14 2014-02-26 明业建设集团有限公司 Deep foundation pit diagonal bracing support structure demolition method
CN104131566A (en) * 2014-05-27 2014-11-05 中国建筑第四工程局有限公司 Method for constructing basement foundation pit without horizontal braces
CN205712121U (en) * 2015-12-29 2016-11-23 上海建工五建集团有限公司 Foundation pit supporting construction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101775814A (en) * 2009-02-20 2010-07-14 上海强劲基础工程有限公司 Anti-slip cement soil pile soil blocking structure and construction method thereof
CN103195085A (en) * 2013-04-02 2013-07-10 东南大学 Downward story-adding basement and construction method thereof
CN103603359A (en) * 2013-11-14 2014-02-26 明业建设集团有限公司 Deep foundation pit diagonal bracing support structure demolition method
CN104131566A (en) * 2014-05-27 2014-11-05 中国建筑第四工程局有限公司 Method for constructing basement foundation pit without horizontal braces
CN205712121U (en) * 2015-12-29 2016-11-23 上海建工五建集团有限公司 Foundation pit supporting construction

Similar Documents

Publication Publication Date Title
Bruce et al. Soil nailing: application and practice-part 1
US8898996B2 (en) Method for forming a retaining wall, and corresponding retaining wall
CN102518135A (en) Foundation pit support construction method combining horizontal rotary jet-grouting soil bolting and bore concrete piles
CN102444142A (en) Pile group column replacement expanded basement and construction method of same
CN106245927B (en) A kind of method and building suitable for frame structure building underground increasing layer
CN206070508U (en) Device for reinforcing foundation
CN205712121U (en) Foundation pit supporting construction
Ergun Deep excavations
CN106400810A (en) Foundation pit support structure and construction method thereof
CN104153356B (en) The constructing device of concrete-pile and construction method thereof
Barley Soil nailing case histories and developments
Dellaria et al. Combining multiple techniques to complete an urban deep excavation
Aziz et al. Cost and schedule savings from directly-driven soil nail and innovative fascia systems
JP2006336228A (en) Construction method of underground space
Mollahasani Application of submerged grouted anchors in sheet pile quay walls
CN114482072B (en) Soft soil close-connection double-foundation-pit combined anchor design method, supporting structure and construction method
Robison Excavation support and micropile underpinning in Vail, Colorado
Hon et al. Design and construction of an underpinning and earth-retaining system for Lehigh Valley Hospital building
Tan et al. Special design considerations for underpinning systems of existing structures due to tunnelling
Marte et al. Panels made by the deep mixing method for a building pit support in a slope
Myers et al. Aerial Siphon in Winter Park
Jardaneh Assessment of Local Excavation Support Systems: A Case Study of‎ Nablus City, Palestine
Kwong et al. Stabilizing landslides using rammed aggregate piers
Lee et al. Geotechnical design and construction of Chandler Highway upgrade project in Melbourne
Alexandru RESEARCH REGARDING EXPANDING MECHANIZATION IN THE FIELD OF CONSOLIDATION OF THE EMBANKMENT AND SLOPES

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Li Yan

Inventor after: Liu Jian

Inventor after: Chen Kunliang

Inventor before: Fang Yi

Inventor before: Liu Jian

Inventor before: Chen Kunliang

CB03 Change of inventor or designer information
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170215

WD01 Invention patent application deemed withdrawn after publication