CN106351362B - Superelevation lightgage steel joist Thistle board partition wall and its construction method - Google Patents

Superelevation lightgage steel joist Thistle board partition wall and its construction method Download PDF

Info

Publication number
CN106351362B
CN106351362B CN201610748467.3A CN201610748467A CN106351362B CN 106351362 B CN106351362 B CN 106351362B CN 201610748467 A CN201610748467 A CN 201610748467A CN 106351362 B CN106351362 B CN 106351362B
Authority
CN
China
Prior art keywords
keel
wall
thin
wall tube
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610748467.3A
Other languages
Chinese (zh)
Other versions
CN106351362A (en
Inventor
邵枫
张瑜
高良
代东华
谈建明
丁伯圣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jia Yang Hualian Building Decoration Ltd By Share Ltd
Original Assignee
Jiangsu Jia Yang Hualian Building Decoration Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Jia Yang Hualian Building Decoration Ltd By Share Ltd filed Critical Jiangsu Jia Yang Hualian Building Decoration Ltd By Share Ltd
Priority to CN201610748467.3A priority Critical patent/CN106351362B/en
Publication of CN106351362A publication Critical patent/CN106351362A/en
Application granted granted Critical
Publication of CN106351362B publication Critical patent/CN106351362B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/74Removable non-load-bearing partitions; Partitions with a free upper edge
    • E04B2/76Removable non-load-bearing partitions; Partitions with a free upper edge with framework or posts of metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Supports For Pipes And Cables (AREA)
  • Building Environments (AREA)

Abstract

The invention discloses a kind of superelevation lightgage steel joist Thistle board partition walls, it include: the concrete slab of top and bottom, furred ceiling face, a day keel A is provided on the downside of top concrete plate, ground joist has been set on the upside of lower concrete plate, keelson and vertical keel are provided between its keel A and ground joist, perpendicular to vertical keel direction, punching keel are provided on the downside of furred ceiling face, several vertical thin-wall tubes are also evenly arranged between top layer and bottom concrete plate, the distance between adjacent two vertical thin-wall tubes H1 is set as 6 ~ 8 meters, hanging top face, the horizontal thin-wall tube of horizontal direction is provided between vertical thin-wall tube, the horizontal thin-wall tube is set as 80 ~ 100mm apart from the distance between furred ceiling face, it is fixed between the vertical thin-wall tube and concrete slab by expansion bolt.By the above-mentioned means, the present invention can control partition wall thickness, meet superelevation partition wall intensity requirement, and guarantees that partition wall is stable and secured.

Description

Superelevation lightgage steel joist Thistle board partition wall and its construction method
Technical field
The present invention relates to building fields, more particularly to a kind of superelevation lightgage steel joist Thistle board partition wall and its construction party Method.
Background technique
Some large-scale commercial buildings, because the pipelines such as ventilation, fire-fighting are more, layer height is often as high as 3.9 meters or more, in space Every the light steel keel partition to top surface, we term it the light high keel partition walls of superelevation.
It is general that superelevation partition wall is then selected using 75 serial small dimension keel when partition wall height is lower than 3.9 meters The big specification series keel of C100, C150.
Big specification series keel are selected to do partition backbone, partition wall thickness necessarily increases, and causes to build workable area It reduces, for commercial building, rent and sale valence is often corresponding with usable floor area, and investor controls partition wall thickness tighter.If but selecting Separated with small dimension series keel, then partition wall intensity is inadequate, and stability is poor.
The pipelines such as HVAC, fire-fighting, intelligence are numerous in large scale business public building room, local floor slab tops certain area model Have a large amount of thickly dotted pipeline in enclosing, centre keel be difficult to across, day keel can only disconnect here to be set to below pipeline, It is vacantly withstood by centre keel, causes partition wall planar stability poor.
Summary of the invention
The invention mainly solves the technical problem of providing a kind of superelevation lightgage steel joist Thistle board partition wall and its constructions Method can control partition wall thickness, meet superelevation partition wall intensity requirement, and guarantee that partition wall is stable and secured.
In order to solve the above technical problems, one technical scheme adopted by the invention is that: a kind of superelevation lightgage steel joist paper is provided Surface gypsum board partition wall, comprising: the concrete slab of top and bottom, furred ceiling face are provided with a day keel on the downside of top concrete plate A is provided with ground joist on the upside of lower concrete plate, is provided with keelson and vertical keel between day keel A and ground joist, Perpendicular to punching keel are provided on the downside of vertical keel direction, furred ceiling face, also uniformly set between top layer and bottom concrete plate Be equipped with several vertical thin-wall tubes, the distance between adjacent two vertical thin-wall tubes H1 is set as 6~8 meters, hang top face, The horizontal thin-wall tube of horizontal direction is provided between vertical thin-wall tube, the horizontal thin-wall tube is set apart from the distance between furred ceiling face It is set to 80~100mm, is fixed between the vertical thin-wall tube and concrete slab by expansion bolt.
Preferably, it is additionally provided with galvanized steel plain sheet between the vertical thin-wall tube and concrete slab, the galvanized steel plain sheet and perpendicular It is welded and fixed between thin-wall tube, is fixed between galvanized steel plain sheet and concrete slab by expansion bolt.
Preferably, it is additionally provided with bearing diagonal between the horizontal thin-wall tube and top layer concrete slab, the bearing diagonal and perpendicular 30~60 ° are set as to the angle between thin-wall tube.
Preferably, it is connected between the bearing diagonal and top layer concrete slab by galvanized steel plain sheet and expansion bolt, bearing diagonal It is welded to connect between horizontal thin-wall tube.
Preferably, it is provided with pipeline below the top layer concrete slab, the pipeline is arranged on suspension and support, the branch By hanging bar connection between hanger and top layer concrete slab, the lower end surface of the suspension and support is provided with a day keel B.
In order to solve the above technical problems, another technical solution used in the present invention is: providing a kind of superelevation lightgage steel joist The construction method of Thistle board partition wall, which is characterized in that mainly include the following steps:
One, field lofting, positioning:
One) live 1.0 meters of elevation lines and the pop-up minimum elevation line of furred ceiling, are ferreted out;
Two) partition wall is popped up in ground, top surface, metope, cylinder in, the superelevation light steel keel partition position determining according to design The position line marks door and window, openings position;
Three), when partition wall length is greater than 8 meters and when without lateral wall support, then the position or at interval of 6 meters of left sides among partition wall A piece vertical thin-wall tube of right setting reinforces wall, then corresponds to and mark each vertical thin-wall tube position on partition wall position on ground, top It sets, in wall, cylinder, at furred ceiling absolute altitude 100-150mm on the upper side, the side of the partition wall position line of abutting mark, mark is horizontal Thin-wall tube position;
Two, reinforce thin-walled control peace
One), thin-wall tube rod piece makes, post-install installation: the vertical thin-wall tube and horizontal thin-walled at each position in actual measurement scene The site dimension of pipe, blanking carry out cutting processing;It is installed in the concrete structure at each mark with the expansion bolt of φ 10 simultaneously The rear billboard of 200*200*10;
Two), thin-wall tube is installed: by the rear billboard firm welding of vertical thin-wall tube and ground, top;By horizontal thin-wall tube with Wall, cylinder or vertical thin-wall pipe welding are secured;
Three, suspension and support system is pacified
One), suspension and support size and sling point position determine: the broad-ruler of the densely covered pipeline of measurement suspension and support position It is very little, determine the length of the horizon bar of suspension and support;Two hangings of suspension and support are found out within the scope of length of boom, in pipeline gap Bar installation site is simultaneously identified in top surface;
Two), suspension and support is installed: according to the hanging bar of actual measurement size production suspension and support and horizon bar and being completed;Simultaneously In concrete structure at home position, with the rear billboard of the expansion bolt installation 200*200*8 of φ 10;Hanging suspension and support again Hanging rod and anchor slab firm welding, when suspension and support sunpender is installed, it is necessary to draw logical line traffic control, it is ensured that suspension and support center line and top surface partition wall Place-centric line is on one wire;
Four, lightgage steel joist skeleton is installed
One), world keel installation: world keel installation is in ground, top position line or on suspension and support;
Two), vertical keel install: vertical keel clipping room away from be 300-400mm, fixed with day ground joist, level it is thin Wall pipe infall, with self-tapping screw by the two fixation;
Three), in vertical thin-wall tube side self-tapping screw by the lateral keel fixation of lightgage steel joist;
Four), punching keel, stull keel are connect with vertical keel, lateral keel;
Five, sealing plate: the sealing plate of lightgage steel joist side is first completed;After the completion of intraskeletal electric wire, pipeline construction, it is built-in every Sound cotton, and concealment acceptance is carried out, after qualified, remaining plasterboard installation;
Six, it checks and accepts.
The beneficial effects of the present invention are: the present invention 1, using conventional inline keel, reinforced with thin-wall tube, not will increase Partition wall thickness can but reach superelevation light steel keel partition intensity requirement, guarantee partition wall stability and firmness, commercial building inch of land Very little gold, partition wall thickness are reduced, and building usable floor area increases, and economic benefit can increase accordingly;2, rigid suspension and support is added, is improved Frame strength increases partition wall stability, it is ensured that superelevation lightgage steel joist Thistle board partition wall total quality reaches requirement.
Detailed description of the invention
Fig. 1 is a kind of one preferred embodiment of superelevation lightgage steel joist Thistle board partition wall of the present invention
Structural schematic diagram;
Fig. 2 is Section A-A schematic diagram in shown Fig. 1;
Fig. 3 is the structural schematic diagram of the suspension and support part;
The components in the drawings are labeled as follows: 1, concrete slab, 2, day keel A, 3, ground joist, 4, vertical keel, 5, side Keel, 6, furred ceiling face, 7, punching keel, 8, vertical thin-wall tube, 9, horizontal thin-wall tube, 10, expansion bolt, 11, galvanized steel plain sheet, 12, bar, 13, suspension and support, 14, pipeline, 15, day keel B, 16, bearing diagonal are hung.
Specific embodiment
The preferred embodiments of the present invention will be described in detail with reference to the accompanying drawing, so that advantages and features of the invention energy It is easier to be readily appreciated by one skilled in the art, so as to make a clearer definition of the protection scope of the present invention.
Fig. 1, Fig. 2 are please referred to, the embodiment of the present invention includes:
A kind of superelevation lightgage steel joist Thistle board partition wall, comprising: the concrete slab 1 of top and bottom, furred ceiling face 6, It is provided with a day keel A2 on the downside of top concrete plate 1, ground joist 3, day keel A2 and ground are provided on the upside of lower concrete plate 1 It is provided with keelson 5 and vertical keel 4 between keel 3, is provided with punching on the downside of perpendicular to 4 direction of vertical keel, furred ceiling face 6 Keel 7 are also evenly arranged with several vertical thin-wall tubes 8, adjacent two vertical thin-walleds between top layer and bottom concrete plate 1 The distance between pipe 8 H1 is set as 6 meters, and the level that horizontal direction is provided with above furred ceiling face 6, between vertical thin-wall tube 8 is thin Wall pipe 9, the horizontal thin-wall tube 9 are set as 100mm, the vertical thin-wall tube 8 and concrete apart from the distance between furred ceiling face 6 It is fixed by expansion bolt 10 between plate 1.
In order to reinforce the stability between vertical thin-wall tube 8 and concrete slab 1, vertical thin-wall tube 8 and concrete slab 1 it Between be additionally provided with galvanized steel plain sheet 11, be welded and fixed between the galvanized steel plain sheet 11 and vertical thin-wall tube 8, galvanized steel plain sheet 11 and coagulation It is fixed by expansion bolt 10 between native plate 1.
In order to reinforce the stability between horizontal thin-wall tube 9, vertical thin-wall tube 8 and top layer concrete slab 1, horizontal thin Bearing diagonal 16, the angle between the bearing diagonal 16 and vertical thin-wall tube 8 are additionally provided between wall pipe 9 and top layer concrete slab 1 45 ° are set as, is connected between the bearing diagonal 16 and top layer concrete slab 1 by galvanized steel plain sheet 11 and expansion bolt 10, is tiltedly propped up It is welded to connect between support 16 and horizontal thin-wall tube 8.
The pipelines such as HVAC, fire-fighting, intelligence are numerous in large scale business public building room, local floor slab tops certain area model Have a large amount of thickly dotted pipeline in enclosing, centre keel be difficult to across, day keel can only disconnect here to be set to below pipeline, It is vacantly withstood by centre keel, causes partition wall planar stability poor.In order to solve this problem, it is set in the lower section of top layer concrete slab 1 It is equipped with pipeline 14, the pipeline 14 is arranged on suspension and support 13, passes through hanging between the suspension and support 13 and top layer concrete slab 1 Bar 12 connects, and the lower end surface of the suspension and support 13 is provided with a day keel B15.
The embodiment of the invention also discloses a kind of construction method of superelevation lightgage steel joist Thistle board partition wall, feature exists In mainly including the following steps:
One, field lofting, positioning:
One) live 1.0 meters of elevation lines and the pop-up minimum elevation line of furred ceiling, are ferreted out;
Two) partition wall is popped up in ground, top surface, metope, cylinder in, the superelevation light steel keel partition position determining according to design The position line marks door and window, openings position;
Three), when partition wall length is greater than 8 meters and when without lateral wall support, then the position or at interval of 6 meters of left sides among partition wall A piece vertical thin-wall tube 8 of right setting reinforces wall, then corresponds to and mark each vertical thin-wall tube position on partition wall position on ground, top It sets, in wall, cylinder, at furred ceiling absolute altitude 100-150mm on the upper side, the side of the partition wall position line of abutting mark, mark is horizontal Thin-wall tube position;
Two, reinforce thin-walled control peace
One), thin-wall tube rod piece makes, post-install installation: the vertical thin-wall tube 8 and horizontal thin-walled at each position in actual measurement scene The site dimension of pipe 9, blanking carry out cutting processing;It is installed in the concrete structure at each mark with the expansion bolt of φ 10 simultaneously The rear billboard of 200*200*10;
Two), thin-wall tube is installed: by the rear billboard firm welding of vertical thin-wall tube 8 and ground, top;By horizontal thin-wall tube 9 with Wall, cylinder or vertical thin-wall pipe welding are secured;
Three, suspension and support system is pacified
One), 13 size of suspension and support and sling point position determine: the width of the densely covered pipeline 14 of measurement 13 position of suspension and support Size is spent, determines the length of the horizon bar of suspension and support 13;Suspension and support 13 is found out within the scope of length of boom, in 14 gap of pipeline Two 12 installation sites of hanging bar and be identified in top surface;
Two), suspension and support is installed: according to the hanging bar 12 of actual measurement size production suspension and support 13 and horizon bar and being completed; Simultaneously in the concrete structure at home position, with the rear billboard of the expansion bolt installation 200*200*8 of φ 10;Again by suspension and support 13 hanging bar 12 and anchor slab firm welding, when installing suspension and support sunpender, it is necessary to draw logical line traffic control, it is ensured that 13 center line of suspension and support On one wire with top surface partition wall place-centric line;
Four, lightgage steel joist skeleton is installed
One), world keel installation: world keel installation is in ground, top position line or on suspension and support;
Two), vertical keel install: 4 clipping room of vertical keel away from be 300-400mm, fixed with day ground joist, level it is thin 9 infall of wall pipe, with self-tapping screw by the two fixation;
Three), in vertical 8 side self-tapping screw of thin-wall tube by the lateral keel fixation of lightgage steel joist;
Four), punching keel, stull keel are connect with vertical keel, lateral keel;
Five, sealing plate: the sealing plate of lightgage steel joist side is first completed;After the completion of intraskeletal electric wire, pipeline construction, it is built-in every Sound cotton, and concealment acceptance is carried out, after qualified, remaining plasterboard installation;
Six, it checks and accepts.
The above description is only an embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant skills Art field, is included within the scope of the present invention.

Claims (2)

1. a kind of superelevation lightgage steel joist Thistle board partition wall, comprising: the concrete slab of top and bottom, furred ceiling face, at top It is provided with a day keel A on the downside of concrete slab, ground joist is provided on the upside of lower concrete plate, between day keel A and ground joist It is provided with keelson and vertical keel, is provided with punching keel on the downside of perpendicular to vertical keel direction, furred ceiling face, feature exists In, be also evenly arranged with several vertical thin-wall tubes between top layer and bottom concrete plate, adjacent two vertical thin-wall tubes it Between distance H1 be set as 6~8 meters, hanging the horizontal thin-wall tube that horizontal direction is provided between top face, vertical thin-wall tube, The horizontal thin-wall tube is set as 80~100mm apart from the distance between furred ceiling face, the vertical thin-wall tube and concrete slab it Between fixed by expansion bolt, galvanized steel plain sheet, the galvanized steel plain sheet are additionally provided between the vertical thin-wall tube and concrete slab It is welded and fixed between vertical thin-wall tube, is fixed between galvanized steel plain sheet and concrete slab by expansion bolt, the horizontal thin-walled Bearing diagonal is additionally provided between pipe and top layer concrete slab, the angle between the bearing diagonal and vertical thin-wall tube is set as 30~ It 60 °, is connected between the bearing diagonal and top layer concrete slab by galvanized steel plain sheet and expansion bolt, bearing diagonal and horizontal thin-wall tube Between be welded to connect, pipeline is provided with below the top layer concrete slab, the pipeline is arranged on suspension and support, and the branch is hung By hanging bar connection between frame and top layer concrete slab, the lower end surface of the suspension and support is provided with a day keel B.
2. it is a kind of for a kind of construction method of superelevation lightgage steel joist Thistle board partition wall as described in claim 1, it is special Sign is, mainly includes the following steps:
One, field lofting, positioning:
One) live 1.0 meters of elevation lines and the pop-up minimum elevation line of furred ceiling, are ferreted out;
Two) partition wall position is popped up in ground, top surface, metope, cylinder in, the superelevation light steel keel partition position determining according to design Line marks door and window, openings position;
Three) it, when partition wall length is greater than 8 meters and when without lateral wall support, then position or is set at interval of 6 meters or so among partition wall It sets a vertical thin-wall tube to reinforce wall, then corresponds to and mark each vertical thin-wall tube position on partition wall position on ground, top, Wall, cylinder mark horizontal thin-wall tube at furred ceiling absolute altitude 100-150mm on the upper side, the side of the partition wall position line of abutting mark Position;
Two, reinforce thin-walled control peace
One), thin-wall tube rod piece makes, post-install installation: the vertical thin-wall tube at each position in actual measurement scene and horizontal thin-wall tube Site dimension, blanking carry out cutting processing;200* is installed with the expansion bolt of φ 10 in the concrete structure at each mark simultaneously The rear billboard of 200*10;
Two), thin-wall tube is installed: by the rear billboard firm welding of vertical thin-wall tube and ground, top;By horizontal thin-wall tube and wall, column Face or vertical thin-wall pipe welding are secured;
Three, suspension and support system is pacified
One), suspension and support size and sling point position determine: the width dimensions of the densely covered pipeline of measurement suspension and support position, really Determine the length of the horizon bar of suspension and support;Two hanging bars peace of suspension and support is found out within the scope of length of boom, in pipeline gap Holding position is simultaneously identified in top surface;
Two), suspension and support is installed: according to the hanging bar of actual measurement size production suspension and support and horizon bar and being completed;It is marking simultaneously Know in the concrete structure at position, with the rear billboard of the expansion bolt installation 200*200*8 of φ 10;Again by the hanging bar of suspension and support With anchor slab firm welding, when suspension and support sunpender is installed, it is necessary to draw logical line traffic control, it is ensured that suspension and support center line and top surface partition wall position Center line is on one wire;
Four, lightgage steel joist skeleton is installed
One), world keel installation: world keel installation is in ground, top position line or on suspension and support;
Two), vertical keel is installed: vertical keel clipping room is fixed, in horizontal thin-wall tube away from for 300-400mm with day ground joist Infall, with self-tapping screw by the two fixation;
Three), in vertical thin-wall tube side self-tapping screw by the lateral keel fixation of lightgage steel joist;
Four), punching keel, stull keel are connect with vertical keel, lateral keel;
Five, sealing plate: the sealing plate of lightgage steel joist side is first completed;After the completion of intraskeletal electric wire, pipeline construction, built-in sound insulation Cotton, and concealment acceptance is carried out, after qualified, remaining plasterboard installation;
Six, it checks and accepts.
CN201610748467.3A 2016-08-30 2016-08-30 Superelevation lightgage steel joist Thistle board partition wall and its construction method Active CN106351362B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610748467.3A CN106351362B (en) 2016-08-30 2016-08-30 Superelevation lightgage steel joist Thistle board partition wall and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610748467.3A CN106351362B (en) 2016-08-30 2016-08-30 Superelevation lightgage steel joist Thistle board partition wall and its construction method

Publications (2)

Publication Number Publication Date
CN106351362A CN106351362A (en) 2017-01-25
CN106351362B true CN106351362B (en) 2019-06-07

Family

ID=57855685

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610748467.3A Active CN106351362B (en) 2016-08-30 2016-08-30 Superelevation lightgage steel joist Thistle board partition wall and its construction method

Country Status (1)

Country Link
CN (1) CN106351362B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222326B (en) * 2018-01-11 2019-12-10 马鞍山十七冶工程科技有限责任公司 Foam concrete light steel keel composite ultrahigh wall and construction method thereof
CN111561074B (en) * 2020-04-29 2021-06-22 北京建院装饰工程设计有限公司 Light ultrahigh sound-insulation fireproof steel partition wall and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW486535B (en) * 2001-02-20 2002-05-11 Kuen-Da Li A building wall construction method
CN1970914A (en) * 2006-12-13 2007-05-30 北京城建集团有限责任公司 Steel structure assisted layered installation and construction method for superhigh PRC partition plate
CN202390961U (en) * 2012-04-28 2012-08-22 沈阳中辰钢结构工程有限公司 EPS (Expandable Polystyrene) foamed concrete grouted internal partition wall
CN103234080A (en) * 2013-05-08 2013-08-07 内蒙古兴泰建筑有限责任公司 Construction method for shared supporting and hanging frame for comprehensive arrangement of pipes

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW486535B (en) * 2001-02-20 2002-05-11 Kuen-Da Li A building wall construction method
CN1970914A (en) * 2006-12-13 2007-05-30 北京城建集团有限责任公司 Steel structure assisted layered installation and construction method for superhigh PRC partition plate
CN202390961U (en) * 2012-04-28 2012-08-22 沈阳中辰钢结构工程有限公司 EPS (Expandable Polystyrene) foamed concrete grouted internal partition wall
CN103234080A (en) * 2013-05-08 2013-08-07 内蒙古兴泰建筑有限责任公司 Construction method for shared supporting and hanging frame for comprehensive arrangement of pipes

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"超高轻质隔墙施工技术";刘振永等;《建筑技术》;20141031;第45卷(第10期);第912-913页,1 工程概况—3 施工工艺流程

Also Published As

Publication number Publication date
CN106351362A (en) 2017-01-25

Similar Documents

Publication Publication Date Title
CN207079724U (en) A kind of steel construction primary and secondary beam connecting node
CN106351362B (en) Superelevation lightgage steel joist Thistle board partition wall and its construction method
CN204781452U (en) Section bar and possess framework of this section bar
CN212743107U (en) Indoor metal plate ceiling close joint splicing device
CN108978978B (en) Closed profiled steel sheet cast-in-situ floor elevator device, suspended ceiling structure and construction method
CN104234289B (en) A kind of construction method of big discrepancy in elevation on-plane surface moulding ceiling structure
CN205024928U (en) Furred ceiling expansion joint structure
CN204590361U (en) A kind of large span assembled integral hollow sandwich panel ceiling for storied building
CN210067191U (en) Assembled aluminum plate wall
CN211899202U (en) Suspended ceiling conversion layer system
CN205206120U (en) Furred ceiling suspended structure
CN204960073U (en) There is not horizontal fossil fragments curtain
CN209339431U (en) A kind of furred ceiling sunpender fixed structure based on side wall bracket
CN207934346U (en) A kind of super large profiled metal roof decorations aluminium sheet fixed installation system
CN207729049U (en) Construction building site antidetonation anti-shake shaped steel fixing bracket
CN205636936U (en) Structure of making an uproar falls in pipeline sound insulation
CN208202303U (en) A kind of Integral ceiling
CN112482555A (en) Shear wall structure and construction method of shear wall
CN213418200U (en) Assembled jib reinforced structure
JP5303722B2 (en) Ceiling panel fixing device
CN111810823B (en) Hanging piece of steel structure roofing lower installation equipment
CN206987271U (en) The compound board mounting structure of columnar cement
JP6038710B2 (en) Piping or rack support
CN211396615U (en) Air conditioner board template strutting arrangement that steadiness is good
CN215106400U (en) Stone curtain wall corner connection structure and stone curtain wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant