- CN106351174A CN106351174A CN201610745377.9A CN201610745377A CN106351174A CN 106351174 A CN106351174 A CN 106351174A CN 201610745377 A CN201610745377 A CN 201610745377A CN 106351174 A CN106351174 A CN 106351174A
- Authority
- CN
- China
- Prior art keywords
- riser
- water
- risers
- conservancy construction
- water conservancy
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/10—Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
The invention discloses a combined water retaining device for water conservancy construction, comprising a group of device bases; left risers, right risers and middle risers which are arranged on the device bases; a group of positioning drill rods respectively penetrates through two ends of the device bases; slide tracks are arranged on the left sides of the left vertical slab and slide rails are arranged on the right sides of the right risers; the upper parts of the right risers, the middle risers and the middle risers are connected with extension risers; the tops of the extension risers are respectively connected with top cover plates; middle water retaining plates are respectively arranged among the left risers, the middle risers and the right risers; gap water retaining plates are arranged between the left risers and the right risers adjacent to the left risers. The combined water retaining device is simplified in structure and convenient to disassemble and assemble; water flow is step by step cut off through combined installation, and thus the water retaining device has the good cut-off effect; after construction completion, the entire device can be withdrawn and reused, and thus the water conservancy construction cost is reduced.
Description
Technical field
The present invention relates to water conservancy construction apparatus field, specially a kind of water conservancy construction combination baffle device for water.
Background technology
When carrying out water conservancy construction work, current are blocked the work being to be frequently necessary to complete, and carries out current at present and block
When cutting, typically to complete by the way of landfill or using the device of similar cofferdam equipment, by the way of landfill, to intercept water
During stream, need to use the landfill materials such as a large amount of sandbag rubbles, and fill nothing and be easily flushed away, complete to block job demand consuming greatly
The time of amount, and block that effect is poor, later stage cleaning work is also extremely difficult, because by current when being intercepted using cofferdam equipment
Powerful impulsive force, is also not easy to carry out construction working, now needs a kind of new to dam what work brought convenience to dash
Baffle device for water is solving the above problems.
Content of the invention
It is an object of the invention to provide a kind of water conservancy construction combination baffle device for water, to solve to carry in above-mentioned background technology
The problem going out.
In order to solve above-mentioned technical problem, the present invention proposes technical scheme below: water conservancy construction combination baffle device for water, it
Including device pedestal, described device base top two ends are separately installed with left riser and right riser, the middle part of described device base
It is provided with middle riser, the rear and front end of described device base is all coated with positioning pricker, and the left side of described left riser is provided with cunning
Road, the right side of described right riser is provided with slide rail, and described slideway is matched with slide rail.
The top of described left riser, right riser and middle riser is all connected with extension riser, described extension by connector
The top of riser is all connected with top blind flange by screw rod, in being provided between described left riser, middle riser and right riser
Portion's water fender, is provided with gap water fender between described left riser and adjacent right riser.
It is provided with back support muscle between one end of described left riser, right riser and middle riser and device pedestal;Institute
State and be provided with front support muscle between the other end of left riser, right riser and middle riser and device pedestal.
One group of through hole, described through hole and positioning pricker cooperation are offered on described device base, described positioning pricker is installed on logical
Kong Zhong, described device base offers locating slot, and described left riser, right riser and middle riser are all adapted to locating slot.
The upper and lower two ends of the both upper ends thereof of described left riser, right riser and middle riser and extension riser are all pacified
Equipped with connecting seat, described connecting seat and connector coordinate, described extension riser pass through connecting seat and left riser or right riser or in
Between riser be detachably connected.
It is provided with limiting plate on top one side position of described middle part water fender.
The top of described left riser, right riser and middle riser and extension riser is all machined with lifting hole(eyelet).
The described top extending riser offers screw, and described screw and screw flight are connected.
Described left riser and right riser all offer gap dash board slot, and described gap dash board slot and gap water fender are slided
Dynamic cooperation, the both sides of the opposite side of described left riser and right riser and described middle riser all offer middle part dash board slot,
Described middle part dash board slot and middle part water fender are slidably matched, and described gap dash board slot and middle part dash board slot inwall all paste
It is provided with rubber cushion.
Compared with prior art, the invention has the beneficial effects as follows: this water conservancy construction with combination baffle device for water use when, first
Device pedestal is tiled on the ground, then the locating slot on left riser, right riser and middle riser and device pedestal is joined
Close, complete the connection of left riser, right riser, middle riser and device pedestal by way of welding, by back support muscle with
Front support muscle is welded between device pedestal and each riser, strengthens the intensity of whole device, determines to install additional according to the depth of water and prolongs
Stretch the group number of riser, extend riser and pass through connecting seat and connector and left riser or right riser or middle riser connection, if water
Depth is deeper, then can select to install additional two groups or three groups extension risers according to practical situation, vertical in left riser, right riser, centre
In plate, the assembly work of extension riser, the lifting hole(eyelet) of each riser, the carrying out of work convenient for assembly can be hung by suspender, complete
After the assembling of riser, put in water by the device pedestal that hanging device will be equipped with riser, because water can lead between riser
Cross, so at this moment whole device is little by the impulsive force of water, device steadily can drop to the bottom, after being put into the bottom, then
Positioning pricker is pounded into riverbed depths, the fixation of finishing device base through through hole, now by fixture, middle part water fender is clamped
And be sequentially inserted between riser, limiting plate can prevent middle part water fender deflect with fixture under the resistance of water it is ensured that
The smooth decline of middle part water fender, completes the thorough blocking-up of current, middle part water fender is slidably matched with middle part dash board slot, glue
Pad can provide good frictional force, also strengthens sealing effectiveness, can mitigate infiltration situation, completes the assembling of middle part water fender
Afterwards, then by top blind flange lid it is located at the top extending riser, and top blind flange is completed by screw rod and extends the connection of riser, top
Portion's cover plate is in above the water surface, can walk above or add other equipment, and this device can use in groups, adjacent left riser and
Right riser passes through slideway and slide rail connects, and is provided with gap water fender between adjacent left riser and right riser, and gap keeps off
Water plate is installed using with middle part water fender identical mounting means;This apparatus structure is simple, easy accessibility, provides to transport
Great convenience, by the way of combination is installed incremental complete current block work, effect of damming is good, simultaneously work
After the completion of journey, whole device can also be fetched and reuse, reduce the cost of water conservancy construction.
Brief description
The invention will be further described with reference to the accompanying drawings and examples.
Fig. 1 is present configuration schematic diagram.
Fig. 2 is the left view of the present invention.
Fig. 3 pulls down the top view after top blind flange for the present invention.
Fig. 4 is the close-up schematic view irising out part in Fig. 3.
In figure: 1, device pedestal, 2, left riser, 3, right riser, 4, middle riser, 5, positioning pricker, 6, slideway, 7, slide rail,
8th, connector, 9, extend riser, 10, screw rod, 11, top blind flange, 12, middle part water fender, 13, gap water fender, 14, rear portion props up
Support muscle, 15, front support muscle, 16, through hole, 17, locating slot, 18, connecting seat, 19, limiting plate, 20, lifting hole(eyelet), 21, screw, 22,
Gap dash board slot, 23, middle part dash board slot, 24, rubber cushion.
Specific embodiment
Below in conjunction with the accompanying drawings embodiments of the present invention are described further.
As Fig. 1-4, water conservancy construction combination baffle device for water, it includes device pedestal 1, described device base 1 top two ends
It is separately installed with left riser 2 and right riser 3, the middle part of described device base 1 is provided with middle riser 4, described device base 1
Rear and front end is all coated with positioning pricker 5, and the left side of described left riser 2 is provided with slideway 6, and the right side of described right riser 3 is provided with
Slide rail 7, described slideway 6 is matched with slide rail 7.
Further, the top of described left riser 2, right riser 3 and middle riser 4 is all connected with extension by connector 8
Riser 9, the described top extending riser 9 is all connected with top blind flange 11 by screw rod 10, described left riser 2, middle riser 4 and
It is provided with middle part water fender 12 between right riser 3, between described left riser 2 and adjacent right riser 3, be provided with gap dash
Plate 13.
Further, it is provided between one end of described left riser 2, right riser 3 and middle riser 4 and device pedestal 1
Back support muscle 14;Before being provided between the other end of described left riser 2, right riser 3 and middle riser 4 and device pedestal 1
Portion's brace rod 15.
Further, described device base 1 offers one group of through hole 16, described through hole 16 is coordinated with positioning pricker 5, described
Positioning pricker 5 is installed in through hole 16, and described device base 1 offers locating slot 17, described left riser 2, right riser 3 and centre
Riser 4 is all adapted to locating slot 17.
Further, the both upper ends thereof of described left riser 2, right riser 3 and middle riser 4 and the top extending riser 9
It is mounted on connecting seat 18 with bottom two ends, described connecting seat 18 and connector 8 coordinate, described extension riser 9 passes through connecting seat
18 are detachably connected with left riser 2 or right riser 3 or middle riser 4.
Further, top one side position of described middle part water fender 12 is provided with limiting plate 19.
Further, the top of described left riser 2, right riser 3 and middle riser 4 and extension riser 9 is all machined with and hangs
Hole 20.
Further, the described top extending riser 9 offers screw 21, and described screw 21 is with the cooperation of screw rod 10 screw thread even
Connect.
Further, described left riser 2 and right riser 3 all offer gap dash board slot 22, described gap dash board slot
22 and gap water fender 13 be slidably matched, the opposite side of described left riser 2 and right riser 3 and the both sides of described middle riser 4
All offer middle part dash board slot 23, described middle part dash board slot 23 and middle part water fender 12 are slidably matched, described gap dash
All being sticked on board slot 22 and middle part dash board slot 23 inwall has rubber cushion 24.
The work process of the present invention and operation principle are:
When using this water conservancy construction with combination baffle device for water, first device pedestal 1 is tiled on the ground, then by left riser
2nd, right riser 3 and middle riser 4 coordinate with the locating slot 17 on device pedestal 1, completed by way of welding left riser 2,
Right riser 3, middle riser 4 and the connection of device pedestal 1, back support muscle 14 and front support muscle 15 are being welded on device bottom
Between seat 1 and each riser, strengthen the intensity of whole device, determined according to the depth of water and install the group number extending riser 9 additional, extend riser
9 pass through connecting seat 18 and connector 8 is connected with left riser 2 or right riser 3 or middle riser 4, if the depth of water is deeper, can root
Select to install two groups or three groups extension risers 9 additional according to practical situation, in left riser 2, right riser 3, middle riser 4, extend riser 9
Assembly work in, the lifting hole(eyelet) 20 of each riser, the carrying out of work convenient for assembly can be hung by suspender, complete the assembling of riser
Afterwards, put in water by the device pedestal that hanging device will be equipped with riser, because water can pass through between riser, at this moment
Whole device is subject to the impulsive force of water less, and device steadily can drop to the bottom, after being put into the bottom, then wears positioning pricker 5
Cross through hole 16 to pound into riverbed depths, the fixation of finishing device base 1, now by fixture, middle part water fender 12 is clamped and successively
Be inserted between riser, limiting plate 19 can prevent middle part water fender 12 deflect with fixture under the resistance of water it is ensured that
The smooth decline of middle part water fender 12, completes the thorough blocking-up of current, and middle part water fender 12 is slided with middle part dash board slot 23 and joins
Close, rubber cushion 24 can provide good frictional force, also strengthen sealing effectiveness, can mitigate infiltration situation, complete middle part dash
After the assembling of plate 12, then top blind flange 11 lid is located at the top extending riser 9, and by screw rod 10 complete top blind flange 11 and
Extend the connection of riser 9, top blind flange 11 is in above the water surface, can walk above or add other equipment, and this device can become
Group uses, and adjacent left riser 2 and right riser 3 are connected by slideway 6 and slide rail 7, and adjacent left riser 2 and right riser 3
Between be provided with gap water fender 13, gap water fender 13 is installed using with middle part water fender 12 identical mounting means.
By above-mentioned description, those skilled in the art completely can be in the model without departing from this invention technological thought
In enclosing, carry out various change and modification all within protection scope of the present invention.The unaccomplished matter of the present invention, belongs to ability
The common knowledge of field technique personnel.
Claims (8)
1. water conservancy construction combination baffle device for water it is characterised in that: it includes device pedestal (1), described device base (1) top
Two ends are separately installed with left riser (2) and right riser (3), and the middle part of described device base (1) is provided with middle riser (4), institute
The rear and front end stating device pedestal (1) is all coated with positioning pricker (5), and the left side of described left riser (2) is provided with slideway (6), institute
The right side stating right riser (3) is provided with slide rail (7), and described slideway (6) is matched with slide rail (7);
The top of described left riser (2), right riser (3) and middle riser (4) is all connected with extension riser by connector (8)
(9), the described top extending riser (9) is all connected with top blind flange (11) by screw rod (10), described left riser (2), centre
Be provided between riser (4) and right riser (3) middle part water fender (12), described left riser (2) and adjacent right riser (3) it
Between be provided with gap water fender (13).
2. water conservancy construction according to claim 1 with combination baffle device for water it is characterised in that: described left riser (2), right vertical
It is provided with back support muscle (14) between one end of plate (3) and middle riser (4) and device pedestal (1);Described left riser
(2), it is provided with front support muscle (15) between the other end of right riser (3) and middle riser (4) and device pedestal (1).
3. water conservancy construction according to claim 1 with combination baffle device for water it is characterised in that: on described device base (1)
Offer one group of through hole (16), described through hole (16) and positioning pricker (5) cooperation, described positioning pricker (5) is installed in through hole (16),
Locating slot (17) offered on described device base (1), described left riser (2), right riser (3) and middle riser (4) all with calmly
Position groove (17) adaptation.
4. water conservancy construction according to claim 1 with combination baffle device for water it is characterised in that: described left riser (2), right vertical
The upper and lower two ends of the both upper ends thereof of plate (3) and middle riser (4) and extension riser (9) are mounted on connecting seat
(18), described connecting seat (18) and connector (8) coordinate, described extension riser (9) pass through connecting seat (18) and left riser (2) or
Right riser (3) or middle riser (4) are detachably connected.
5. water conservancy construction according to claim 1 with combination baffle device for water it is characterised in that: described middle part water fender (12)
Top one side position on be provided with limiting plate (19).
6. water conservancy construction according to claim 1 with combination baffle device for water it is characterised in that: described left riser (2), right vertical
The top of plate (3) and middle riser (4) and extension riser (9) is all machined with lifting hole(eyelet) (20).
7. water conservancy construction according to claim 1 with combination baffle device for water it is characterised in that: the described riser (9) that extends
Top offers screw (21), and described screw (21) and screw rod (10) screw thread are connected.
8. water conservancy construction according to claim 1 with combination baffle device for water it is characterised in that: described left riser (2) and the right side
Riser (3) all offers gap dash board slot (22), and described gap dash board slot (22) and gap water fender (13) are slidably matched,
The both sides of the opposite side of described left riser (2) and right riser (3) and described middle riser (4) all offer middle part dash board slot
(23), described middle part dash board slot (23) and middle part water fender (12) are slidably matched, described gap dash board slot (22) and middle part
All being sticked on dash board slot (23) inwall has rubber cushion (24).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610745377.9A CN106351174A (en) | 2016-08-29 | 2016-08-29 | Combined water retaining device for water conservancy construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610745377.9A CN106351174A (en) | 2016-08-29 | 2016-08-29 | Combined water retaining device for water conservancy construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106351174A true CN106351174A (en) | 2017-01-25 |
Family
ID=57854680
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610745377.9A Pending CN106351174A (en) | 2016-08-29 | 2016-08-29 | Combined water retaining device for water conservancy construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106351174A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107386203A (en) * | 2017-07-14 | 2017-11-24 | 王如代 | A kind of water conservancy construction combination dash system |
CN107762260A (en) * | 2017-11-22 | 2018-03-06 | 韩玲 | A kind of water conservancy construction enclosure device |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2396099Y (en) * | 1999-08-09 | 2000-09-13 | 高云龙 | Combined checkdyke |
CN1473994A (en) * | 2003-07-31 | 2004-02-11 | 辉 黄 | Movable combined flood cut-off dam |
KR20040094136A (en) * | 2003-05-02 | 2004-11-09 | 주식회사 준별에프알피산업 | Bulkhead construct to prevent from flood and assembling nethod thereof |
CN201665852U (en) * | 2010-04-22 | 2010-12-08 | 金志刚 | Detachable inserting plate water barrier |
CN201665855U (en) * | 2010-01-26 | 2010-12-08 | 刘景裕 | Water-stopping gate |
CN201952779U (en) * | 2011-01-18 | 2011-08-31 | 黄顺仁 | Flood prevention water retaining gate structure |
CN203256702U (en) * | 2013-05-24 | 2013-10-30 | 海盐亚威工业物资有限公司 | Flood-preventing water stop board |
CN104631894A (en) * | 2013-11-12 | 2015-05-20 | 成都凯裕电子电器有限公司 | Waterproof device of underground garage |
CN205276208U (en) * | 2016-01-08 | 2016-06-01 | 福州轨道交通设计院有限公司 | Prevent flooding breakwater |
-
2016
- 2016-08-29 CN CN201610745377.9A patent/CN106351174A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2396099Y (en) * | 1999-08-09 | 2000-09-13 | 高云龙 | Combined checkdyke |
KR20040094136A (en) * | 2003-05-02 | 2004-11-09 | 주식회사 준별에프알피산업 | Bulkhead construct to prevent from flood and assembling nethod thereof |
CN1473994A (en) * | 2003-07-31 | 2004-02-11 | 辉 黄 | Movable combined flood cut-off dam |
CN201665855U (en) * | 2010-01-26 | 2010-12-08 | 刘景裕 | Water-stopping gate |
CN201665852U (en) * | 2010-04-22 | 2010-12-08 | 金志刚 | Detachable inserting plate water barrier |
CN201952779U (en) * | 2011-01-18 | 2011-08-31 | 黄顺仁 | Flood prevention water retaining gate structure |
CN203256702U (en) * | 2013-05-24 | 2013-10-30 | 海盐亚威工业物资有限公司 | Flood-preventing water stop board |
CN104631894A (en) * | 2013-11-12 | 2015-05-20 | 成都凯裕电子电器有限公司 | Waterproof device of underground garage |
CN205276208U (en) * | 2016-01-08 | 2016-06-01 | 福州轨道交通设计院有限公司 | Prevent flooding breakwater |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107386203A (en) * | 2017-07-14 | 2017-11-24 | 王如代 | A kind of water conservancy construction combination dash system |
CN107762260A (en) * | 2017-11-22 | 2018-03-06 | 韩玲 | A kind of water conservancy construction enclosure device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106351174A (en) | Combined water retaining device for water conservancy construction | |
CN205967986U (en) | Device is used in adjustable straightness's of hanging down corundum wear -resistant pipeline flange welding | |
CN204139407U (en) | A kind of unit type back bolt stone curtain wall system | |
CN204251997U (en) | Suspension type sub-base grader reference line thread-laying device | |
CN206326315U (en) | A kind of automobile bottom diskware weld jig | |
CN206476128U (en) | A kind of helicopter blade auxiliary mounting jig | |
CN214557012U (en) | Civil engineering job site reinforcing bar processingequipment | |
CN215252954U (en) | Side slope supporting device for foundation engineering construction | |
CN206174869U (en) | Coal mine tunnel bores U type anchor rope hole device | |
CN105109049A (en) | Mounting structure for replaceable net plate | |
CN205206749U (en) | Well bores machine bit lift mast | |
CN201606995U (en) | High-efficient air filter seal installation system equipped with flume | |
CN206490988U (en) | A kind of ditching machine with adjustable type chain guide rail | |
CN209011781U (en) | A kind of core drilling rig | |
CN207761127U (en) | A kind of connection structure for the curtain wall being easily installed | |
CN206551309U (en) | A kind of segmented mold drive device of tyre vulcanizer to middle regulator | |
CN206010315U (en) | Compressor crank shaft and the noise reduction head feeding unit material of noise reduction pullover assembly machine | |
CN207274845U (en) | A kind of motorcycle and its side box bracket | |
CN204867952U (en) | Load lift arm machine of shifting | |
CN205703220U (en) | The sealing ring feeding unit material of water heater water valve parts assembly machine | |
CN205970831U (en) | Mounting structure of engine exhaust system and sub vehicle frame | |
CN205634473U (en) | Material returned device for packagine machine | |
CN205476585U (en) | Steel structure support frame | |
CN205858252U (en) | A kind of coring boring blowout prevention aperture apparatus | |
CN104627913A (en) | Basket straddling hanging mechanism |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170125 |