CN106351122A - Steel structure suspension cable decoration foot bridge construction method - Google Patents

Steel structure suspension cable decoration foot bridge construction method Download PDF

Info

Publication number
CN106351122A
CN106351122A CN201610762895.1A CN201610762895A CN106351122A CN 106351122 A CN106351122 A CN 106351122A CN 201610762895 A CN201610762895 A CN 201610762895A CN 106351122 A CN106351122 A CN 106351122A
Authority
CN
China
Prior art keywords
connecting plate
hanging stick
main arch
bridge
bridge floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610762895.1A
Other languages
Chinese (zh)
Inventor
王永博
刘泽
王琭
韩思铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kocel Steel Structure Co Ltd
Original Assignee
Kocel Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kocel Steel Structure Co Ltd filed Critical Kocel Steel Structure Co Ltd
Priority to CN201610762895.1A priority Critical patent/CN106351122A/en
Publication of CN106351122A publication Critical patent/CN106351122A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/02Suspension bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a steel structure suspension cable decoration foot bridge construction method, and relates to the technical field of bridge construction. The construction method includes the steps: sequentially mounting suspension cable beams, suspension rods and a main arch to form a bridge body; determining mounting positions for mounting connecting plates on the main arch and the suspension rods; mounting the connecting plates at the connecting plate mounting positions of the main arch and the suspension rods. By the method, the technical problem of inaccuracy of positions of connecting plates during construction in the prior art is solved.

Description

The construction method of foot bridge decorated by steel construction suspension cable
Technical field
The present invention relates to the technical field of bridge construction, especially relate to the construction that foot bridge decorated by a kind of steel construction suspension cable Method.
Background technology
In modern architecture, the embodiment that foot bridge is modern science and technology and advanced production level decorated by steel construction suspension cable, it It is the structures being coupled together by steel tension member, steel load-bearing arch and concrete bridge deck three, be used for meeting architectural image And the requirement using function.
Steel construction decoration suspension cable foot bridge span has tens meters long, also has hundreds of rice long, suspension cable decorated by existing steel construction The way of the connection plate weld of foot bridge is that the point position first being provided by design is welded, and will tie after plate positioning to be connected again Structure integral hoisting, but the welding of large-span arch structure, all can there is inevitable error in the lifting of arch, lead to connecting plate to deviate Predetermined point position, impact structure stress and overall appearance.
Therefore, problem of the prior art is the not accurate enough technical problem in position of connecting plate during construction.
Content of the invention
It is an object of the invention to provide the construction method of foot bridge decorated by a kind of steel construction suspension cable, to alleviate prior art Present in when constructing connecting plate the not accurate enough technical problem in position.
The construction method of foot bridge decorated by a kind of steel construction suspension cable that the present invention provides, comprising:
Cantilever beams, hanging stick, main arch are installed successively, to form the main body of bridge;
Determine and be used on main arch and hanging stick the installation site of connecting plate is installed;
Connecting plate is installed on each connecting plate installation site on main arch and hanging stick.
Further, the installation steps of cantilever beams are:
Cantilever beams are layed in the both sides of bridge floor, are parallel to each other between each cantilever beams of every side, every side Cantilever beams between constitute plane parallel with bridge floor;
One end of cantilever beams is welded on the two side of bridge floor.
Further, the installation steps of each hanging stick are:
The split part of hanging stick is first assembled into hanging stick on ground overall;
The assembled hanging stick terminating is lifted in cantilever beams, the two ends of hanging stick pre-fix the two ends in bridge floor respectively, hangs The main body of bar is pre-fixed away from one end of bridge floor with the cantilever beams setting gradually;
Whether the plane that the hanging stick of detection bridge floor both sides is constituted is parallel with bridge floor;
When the plane that the hanging stick of bridge floor both sides is constituted is parallel with bridge floor, by the two ends of hanging stick and bridge floor, cantilever beams The one end away from bridge floor be welded and fixed.
Further, the installation steps of main arch are:
Main arch is completed in installation on ground;
Main arch is sling, adjustment determines the installation site of main arch;
The two ends of main arch and bridge floor are pre-fixed;
Whether the angle between the vertical projecting line of detection main arch and road design center line meets design requirement;
If the angle between the vertical projecting line of main arch and road design center line meets design requirement, by main arch and bridge floor It is welded and fixed.
Further, hanging stick is provided with multiple lower connecting plates, main arch is provided with one-to-one with lower connecting plate Connecting plate, the installation steps of every a pair mutually corresponding connecting plate are:
Requirement according to design determines first time connection on the one end being located at hanging stick by three-dimensional coordinate system The position of plate;
By three-dimensional coordinate system, the direction of the first lower connecting plate is determined;
First lower connecting plate is pre-fixed on hanging stick;
Determine by three-dimensional coordinate system to be located on main arch and connect with the first lower connecting plate corresponding first on hanging stick The position of fishplate bar;
The direction of the first upper junction plate is adjusted in opposite direction with the first connecting plate;
First upper junction plate is pre-fixed on main arch;
Then pass through line connection the first lower connecting plate in kind and the first upper junction plate is simulated two connecting plates and passed through drag-line State after connection;
After the first pair of connecting plate is installed and met the requirements, determine second successively to connecting plate according to above-mentioned step ... n-th To connection Board position.
Further, after the position of plate to be connected all meets the requirements through line in kind detection, connecting plate is welded and fixed;
Line in kind is changed into cable wire.
Further, on hanging stick, often the distance between adjacent connecting plate is identical.
Further, on main arch, often the distance between adjacent connecting plate is identical.
Further, the thickness positioned at the connecting plate on main arch is more than the thickness of the connecting plate on hanging stick.
Further, connecting plate and cable wire latch connect.
The present invention provide steel construction suspension cable decorate foot bridge construction method, first by main arch, cantilever beams, hanging stick peace Dress, forms the main body of bridge, is then attached the installation of plate again according to the design of construction, and the lifting due to main arch all can There is inevitable error, lead to connecting plate to deviate predetermined point position, and be to carry out after the lifting of main arch terminates in the present invention Connecting plate installation, it is to avoid the impact that the dislocation of main arch is installed for connecting plate, alleviate the position of connecting plate during construction Not accurate enough technical problem.
Brief description
In order to be illustrated more clearly that the specific embodiment of the invention or technical scheme of the prior art, below will be to concrete In embodiment or description of the prior art the accompanying drawing of required use be briefly described it should be apparent that, below describe in Accompanying drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not paying creative work Put, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the top view that foot bridge decorated by steel construction suspension cable provided in an embodiment of the present invention;
Fig. 2 is the structural representation that foot bridge upper junction plate decorated by steel construction suspension cable provided in an embodiment of the present invention;
Fig. 3 is the sectional drawing that cable wire on foot bridge decorated by steel construction suspension cable provided in an embodiment of the present invention.
Reference:
100- cantilever beams;200- hanging stick;300- main arch;
400- connecting plate;500- cable wire;600- road axis;
410- lower connecting plate;420- upper junction plate;510- pitches ear;
520- latch;530- regulating sleeve.
Specific embodiment
Below in conjunction with accompanying drawing, technical scheme is clearly and completely described with the enforcement it is clear that described Example is a part of embodiment of the present invention, rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill The every other embodiment that personnel are obtained under the premise of not making creative work, broadly falls into the scope of protection of the invention.
In describing the invention, it should be noted that term " " center ", " on ", D score, "left", "right", " vertical ", The orientation of instruction such as " level ", " interior ", " outward " or position relationship are based on orientation shown in the drawings or position relationship, merely to Be easy to describe the present invention and simplify description, rather than instruction or the hint device of indication or element must have specific orientation, With specific azimuth configuration and operation, therefore it is not considered as limiting the invention.Additionally, term " first ", " second ", " the 3rd " is only used for describing purpose, and it is not intended that indicating or hint relative importance.
In describing the invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or is integrally connected;Can To be to be mechanically connected or electrical connection;Can be to be joined directly together it is also possible to be indirectly connected to by intermediary, Ke Yishi The connection of two element internals.For the ordinary skill in the art, above-mentioned term can be understood at this with concrete condition Concrete meaning in invention.
The central idea of the present invention is the construction method providing a kind of steel construction suspension cable to decorate foot bridge, is mainly used in bridge The technical field of beam construction, after first being installed by the main body of bridge, fixed connecting plate again on main arch and hanging stick, alleviate existing The not accurate enough technical problem in the position of connecting plate when having construction in technology.
The present embodiment provides a kind of steel construction suspension cable to decorate the construction method of foot bridge, and step includes:
S100, cantilever beams 100, hanging stick 200, main arch 300 is installed successively, to form the main body of bridge;
S200, determines and is used on main arch 300 and hanging stick 200 installing the installation site of connecting plate 400;
S300, installs connecting plate 400 in each connecting plate 400 installation site on main arch 200 and hanging stick 200.
The construction method of foot bridge decorated by steel construction suspension cable provided in an embodiment of the present invention, first by main arch 300, cantilever beams 100th, the installation of hanging stick 200, forms the main body of bridge, is then attached the installation of plate 400 again according to the design of construction, All can there is inevitable error in the lifting due to main arch 300, lead to connecting plate 400 to deviate predetermined point position, and in the present invention It is the installation of the connecting plate 400 carrying out after the lifting of main arch 300 terminates, it is to avoid the dislocation of main arch 300 is for connecting plate 400 The impact installed, alleviates the not accurate enough technical problem in the position of connecting plate 400 during construction.
In specific practice, installation steps s110 of cantilever beams 100 are:
S111, cantilever beams 100 is layed in the both sides of bridge floor, between each cantilever beams 100 of every side mutually Parallel, the plane constituting between the cantilever beams 100 of every side is parallel with bridge floor;
S112, one end of cantilever beams 100 is welded on the two side of bridge floor.
In the above-described embodiment, cantilever beams 100 are t shape, and the t head of t shape is connected with bridge floor, the t tail of each t shape it Between be set parallel to each other.
When above-mentioned cantilever beams 100 are installed, plane and bridge floor due to constituting between the cantilever beams 100 of every side are put down OK, provide plane base for the installation of follow-up cross bar 200, increased the accuracy of subsequent installation.
In specific practice, installation steps s120 of each hanging stick 200 are:
S121, the split part of hanging stick 200 is first assembled into hanging stick on ground overall;
S122, the assembled hanging stick 200 terminating is lifted in cantilever beams 100, the two ends of hanging stick 200 pre-fix respectively The two ends of bridge floor, the main body of hanging stick 200 is pre-fixed with the one end away from bridge floor of the cantilever beams 100 setting gradually;
S123, whether the plane that the hanging stick 200 of detection bridge floor both sides is constituted is parallel with bridge floor;
S124, when the plane that the hanging stick of bridge floor both sides is constituted is parallel with bridge floor, by the two ends of hanging stick 200 and bridge floor, One end away from bridge floor of cantilever beams 100 is welded and fixed.
When cantilever beams 100 are t shape, hanging stick 200 is connected with the tail end of t shape.
When above-mentioned hanging stick 200 is installed, when the plane that the hanging stick of bridge floor both sides is constituted is parallel with bridge floor, then pacify follow-up During load fishplate bar, three-dimensional localization is more accurate, and more steady after main arch lifting.
S125, above-mentioned hanging stick 200 lifting during, need to carry out three-dimensional localization it is ensured that height and position and design Scheme is coincide.
After lifting terminates, the plane that the hanging stick 200 of bridge floor both sides is constituted should be parallel with bridge floor.
In specific practice, installation steps s130 of main arch 300 are:
S131, main arch 300 is completed in installation on ground;
S132, main arch 300 is sling, and adjustment determines the installation site of main arch 300;
S133, the two ends of main arch 300 and bridge floor are pre-fixed;
S134, whether the angle between the vertical projecting line of detection main arch 300 and road design center line 600 meets design will Ask;
S135, if the angle between the vertical projecting line of main arch 300 and road design center line 600 meets design requirement, Main arch 300 and bridge floor are welded and fixed.
S136, above-mentioned main arch 300 lifting during, need to carry out three-dimensional localization it is ensured that height and position and design Scheme is coincide.
After lifting terminates, the vertical projecting line of main arch 300 needs to become 10 degree 8 points of angle with road axis 600.
Determine the vertical projecting line of main arch 300 and road axis 600 becomes 10 degree 8 points of the effect of angle to be to ensure that main arch Center of gravity be located on road axis, do not occur both sides skew and cause main arch 300 installation unstable.
In specific practice, as shown in Fig. 2 multiple lower connecting plates 410 are provided with hanging stick 200, main arch 300 is arranged There are the one-to-one upper junction plate 420 with lower connecting plate 410, installation steps s210 of every a pair mutually corresponding connecting plate 400 For:
S211, the requirement according to design determines on the one end being located at hanging stick 200 the by three-dimensional coordinate system The position of one lower connecting plate;
The direction of the first lower connecting plate is determined by s212 by three-dimensional coordinate system;
S213, the first lower connecting plate is pre-fixed on hanging stick;
S214, is determined corresponding with the first lower connecting plate on hanging stick 200 on main arch 300 by three-dimensional coordinate system The first upper junction plate position;
S215, the direction of the first upper junction plate is adjusted in opposite direction with the first connecting plate;
S216, the first upper junction plate is pre-fixed on main arch;
S217, then passes through line connection the first lower connecting plate in kind and the first upper junction plate is simulated two connecting plates and passed through State after cable wire connection;
S218, after first pair of connecting plate is installed and met the requirements, determines second to connection successively according to above-mentioned step Plate ... n-th is to connection Board position.
On hanging stick 200, the distance between often adjacent connecting plate 400 is identical.
On main arch 300, the distance between often adjacent connecting plate 400 is identical.
Above-mentioned determination connects the method for Board position it is achieved that first determining position, then line in kind detects that the position of connecting plate is true Whether determine accurately it is achieved that connecting the more accurate of Board position determination.
In specific practice, after the position of plate 400 to be connected all meets the requirements through line in kind detection, operating procedure s310 For:
S311, connecting plate 400 is welded and fixed;
S312, line in kind is changed into cable wire 500.
In the above-described embodiment, the thickness positioned at the connecting plate 400 on main arch 300 is more than the company on hanging stick 200 The thickness of fishplate bar 400.
As shown in figure 3, the two ends of cable wire 500 are respectively provided with fork ear 510, connecting plate 400 is inserted in fork ear 510, connecting plate 400 Connected by latch 520 with cable wire 510.
Regulating sleeve 530 is also set up on cable wire 500, for adjusting the length of cable wire, prevents main arch 300 from tilting.
Finally it is noted that various embodiments above, only in order to technical scheme to be described, is not intended to limit;To the greatest extent Pipe has been described in detail to the present invention with reference to foregoing embodiments, it will be understood by those within the art that: its according to So the technical scheme described in foregoing embodiments can be modified, or wherein some or all of technical characteristic is entered Row equivalent;And these modifications or replacement, do not make the essence of appropriate technical solution depart from various embodiments of the present invention technology The scope of scheme.

Claims (10)

1. a kind of steel construction suspension cable decorates the construction method of foot bridge it is characterised in that including:
Cantilever beams, hanging stick, main arch are installed successively, to form the main body of bridge;
Determine and be used on main arch and hanging stick the installation site of connecting plate is installed;
Connecting plate is installed on each connecting plate installation site on main arch and hanging stick.
2. steel construction suspension cable according to claim 1 decorates the construction method of foot bridge it is characterised in that described cantilever is horizontal The installation steps of beam are:
Cantilever beams are layed in the both sides of bridge floor, are parallel to each other between each cantilever beams of every side, every side outstanding The plane constituting between arm crossbeam is parallel with bridge floor;
One end of cantilever beams is welded on the two side of bridge floor.
3. steel construction suspension cable according to claim 1 decorates the construction method of foot bridge it is characterised in that described in each The installation steps of hanging stick are:
The split part of hanging stick is first assembled into hanging stick on ground overall;
The assembled hanging stick terminating is lifted in cantilever beams, the two ends of hanging stick pre-fix the two ends in bridge floor respectively, hanging stick Main body is pre-fixed away from one end of bridge floor with the cantilever beams setting gradually;
Whether the plane that the hanging stick of detection bridge floor both sides is constituted is parallel with bridge floor;
When the plane that the hanging stick of bridge floor both sides is constituted is parallel with bridge floor, by the two ends of hanging stick and bridge floor, cantilever beams remote One end from bridge floor is welded and fixed.
4. steel construction suspension cable according to claim 1 decorates the construction method of foot bridge it is characterised in that described main arch Installation steps are:
Main arch is completed in installation on ground;
Main arch is sling, adjustment determines the installation site of main arch;
The two ends of main arch and bridge floor are pre-fixed;
Whether the angle between the vertical projecting line of detection main arch and road design center line meets design requirement;
If the angle between the vertical projecting line of main arch and road design center line meets design requirement, main arch is welded with bridge floor Fixing.
5. steel construction suspension cable according to claim 1 decorates the construction method of foot bridge it is characterised in that on described hanging stick It is provided with multiple lower connecting plates, described main arch is provided with the one-to-one upper junction plate with described lower connecting plate, every a pair of phase Mutually the installation steps of corresponding connecting plate are:
Requirement according to design determines the first lower connecting plate being located on one end of hanging stick by three-dimensional coordinate system Position;
By three-dimensional coordinate system, the direction of the first lower connecting plate is determined;
First lower connecting plate is pre-fixed on hanging stick;
Determine by three-dimensional coordinate system to be located on main arch and connect with the first lower connecting plate corresponding first on described hanging stick The position of fishplate bar;
The direction of the first upper junction plate is adjusted in opposite direction with the first connecting plate;
First upper junction plate is pre-fixed on main arch;
Then pass through line connection the first lower connecting plate in kind and the first upper junction plate is simulated two connecting plates and connected by drag-line State afterwards;
After the first pair of connecting plate is installed and met the requirements, determine second successively to connecting plate according to above-mentioned step ... n-th to even Fishplate bar position.
6. steel construction suspension cable according to claim 5 decorates the construction method of foot bridge it is characterised in that plate to be connected After position all meets the requirements through line in kind detection, connecting plate is welded and fixed;
Line in kind is changed into cable wire.
7. steel construction suspension cable according to claim 6 decorates the construction method of foot bridge it is characterised in that on hanging stick, Often the distance between adjacent connecting plate is identical.
8. steel construction suspension cable according to claim 6 decorates the construction method of foot bridge it is characterised in that on main arch, Often the distance between adjacent connecting plate is identical.
9. steel construction suspension cable according to claim 8 decorates the construction method of foot bridge it is characterised in that being located at described master The thickness of the connecting plate on arch is more than the thickness of the connecting plate on described hanging stick.
10. steel construction suspension cable according to claim 9 decorates the construction method of foot bridge it is characterised in that described connection Plate and described cable wire latch connect.
CN201610762895.1A 2016-08-29 2016-08-29 Steel structure suspension cable decoration foot bridge construction method Pending CN106351122A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610762895.1A CN106351122A (en) 2016-08-29 2016-08-29 Steel structure suspension cable decoration foot bridge construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610762895.1A CN106351122A (en) 2016-08-29 2016-08-29 Steel structure suspension cable decoration foot bridge construction method

Publications (1)

Publication Number Publication Date
CN106351122A true CN106351122A (en) 2017-01-25

Family

ID=57857974

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610762895.1A Pending CN106351122A (en) 2016-08-29 2016-08-29 Steel structure suspension cable decoration foot bridge construction method

Country Status (1)

Country Link
CN (1) CN106351122A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110656569A (en) * 2019-09-04 2020-01-07 重庆交通大学 Ring jib and welded hollow ball node stiffening beam glass suspension bridge

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090087195A (en) * 2008-02-12 2009-08-17 케이블텍 주식회사 The erection method for cable bridges using pre-fabricated ms cable
JP2012122305A (en) * 2010-12-10 2012-06-28 Ihi Infrastructure Systems Co Ltd Arched bridge cross-linking method
CN104264789A (en) * 2014-05-23 2015-01-07 浙江东南网架股份有限公司 Novel connecting node of cross grid structure, special molding bed and preparation method thereof
CN105586826A (en) * 2015-11-30 2016-05-18 湖州交通规划设计院 Connecting structure of anchorage ends of booms of concrete tied arch bridge and construction method of connecting structure
CN105755957A (en) * 2016-03-01 2016-07-13 共享钢构有限责任公司 Rapid hoisting method for large-span pedestrian overcrossing striding over rail

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090087195A (en) * 2008-02-12 2009-08-17 케이블텍 주식회사 The erection method for cable bridges using pre-fabricated ms cable
JP2012122305A (en) * 2010-12-10 2012-06-28 Ihi Infrastructure Systems Co Ltd Arched bridge cross-linking method
CN104264789A (en) * 2014-05-23 2015-01-07 浙江东南网架股份有限公司 Novel connecting node of cross grid structure, special molding bed and preparation method thereof
CN105586826A (en) * 2015-11-30 2016-05-18 湖州交通规划设计院 Connecting structure of anchorage ends of booms of concrete tied arch bridge and construction method of connecting structure
CN105755957A (en) * 2016-03-01 2016-07-13 共享钢构有限责任公司 Rapid hoisting method for large-span pedestrian overcrossing striding over rail

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
刘子祥等: "上海新国际博览中心钢结构安装技术", 《建筑钢结构进展》 *
本书编写委员会编: "《模拟导游》", 31 August 2014, 中国旅游出版社 *
谭慧等: "人行斜跨拱桥的设计和分析", 《城市道桥与防洪》 *
金立新等: "国内外对角斜跨拱桥的设计与施工", 《公路》 *
陆新征主编: "《第25届全国结构工程学术会议论文集 第Ⅱ册》", 14 August 2016, 《工程力学》杂志社出版 *
陈娟: "住宅小区人行组合拱桥结构设计", 《中国市政工程》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110656569A (en) * 2019-09-04 2020-01-07 重庆交通大学 Ring jib and welded hollow ball node stiffening beam glass suspension bridge

Similar Documents

Publication Publication Date Title
CN101117795A (en) Mounting method for steel case basket arch single-frame segment
CN103924520B (en) Construction method and device of suspension bridge main cable anchorage prestressed pipes
CN106480823B (en) Vaulted beam device and its localization method
CN205907604U (en) Steel bridge segmental hoisting counterpoint fixing device
CN109184225B (en) Assembling method of four-chord prismatic bending-twisting circular tube truss structure system
CN111350121B (en) Modular assembling method for steel box girder bridge
CN103243649A (en) System and method for quickly installing and positioning cable saddle
CN109779007A (en) Vestibule installation method and vestibule
CN106351122A (en) Steel structure suspension cable decoration foot bridge construction method
CN214939323U (en) Suspension arm hoisting matching system for steel box girder of cable-stayed bridge
CN114134990A (en) Installation and uninstallation method of large-span overhanging corridor
CN109702387A (en) A kind of stayed bridge pylon cable inner lining steel construction manufacturing method
CN105887686A (en) Inward-tilting triangular arch-bridge steel arch rib closing method
CN210507144U (en) Stiff skeleton for positioning cable saddle of cable-branching pipe of short-tower cable-stayed bridge
CN110145159A (en) A kind of hard crossbeam of the contact net of welded connecting and its construction method
CN202393382U (en) Hanging center aligning and leveling device for composite furnace shell
CN111648258B (en) Ultrahigh single-column pier reinforcing and maintaining method
CN209323691U (en) A kind of huge diagonal brace of overlength superelevation
CN106320186A (en) Positioning system for pre-embedded anchor bar of arch support and construction method
CN208167491U (en) A kind of trapezoidal bending component of gradual change of internal anchoringwire
CN103572870A (en) Ultra-long high-inclination curtain wall oblique post and installation method thereof
CN206554273U (en) A kind of pre-assembled Anchor Bolts in Steel Column Bases structure
CN113774864B (en) Hoisting method for reverse insertion component installation
CN203640099U (en) Overlong and steep-slope curtain wall oblique post
CN104818675A (en) Assembling method of rebar segments

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170125

RJ01 Rejection of invention patent application after publication