CN106345821A - Steel rolling water-penetrating system water tank control method and device - Google Patents

Steel rolling water-penetrating system water tank control method and device Download PDF

Info

Publication number
CN106345821A
CN106345821A CN201610755141.3A CN201610755141A CN106345821A CN 106345821 A CN106345821 A CN 106345821A CN 201610755141 A CN201610755141 A CN 201610755141A CN 106345821 A CN106345821 A CN 106345821A
Authority
CN
China
Prior art keywords
water tank
water
default
steel
steel rolling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610755141.3A
Other languages
Chinese (zh)
Inventor
王长毅
王洪权
刘光武
饶斌
唐春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dazhou Iron and Steel Group Co Ltd
Original Assignee
Dazhou Iron and Steel Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dazhou Iron and Steel Group Co Ltd filed Critical Dazhou Iron and Steel Group Co Ltd
Priority to CN201610755141.3A priority Critical patent/CN106345821A/en
Publication of CN106345821A publication Critical patent/CN106345821A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B37/00Control devices or methods specially adapted for metal-rolling mills or the work produced thereby
    • B21B37/74Temperature control, e.g. by cooling or heating the rolls or the product
    • B21B37/76Cooling control on the run-out table

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Control Of Metal Rolling (AREA)

Abstract

The invention discloses a steel rolling water-penetrating system water tank control method and device. The method includes: detecting real-time current signals of a finishing mill; judging whether the finishing mill is in a steel biting state or a tail shedding state or not according to the real-time current signals; if yes, controlling water valves of water tanks to be sequentially opened or closed according to a preset water tank sequence. By applying the steel rolling water-penetrating system water tank control method and device, signals controlling the water tanks are changed from original hot metal detector signals to real-time current information of the finishing mill, the problem of steel heaping caused by impact on rolled pieces due to the fact that water penetrating valves are frequently opened and closed or not closed because of unstable signals originally is avoided, and the water tanks can be controlled to be accurately closed; memory temperature control is performed on heads and tails of the rolled pieces, so that the problem that the heads and the tails of the rolled pieces are unqualified in physical performance is avoided, production cost is lowered, and rolling yield is increased.

Description

Water system water tank control method and device are worn in a kind of steel rolling
Technical field
The present invention relates to Rolling production control technology field, more particularly, it relates to water system water tank control is worn in a kind of steel rolling Method and device processed.
Background technology
Fine-grained steel is that metal material makes its inherent grain size reach 5 to 8 grades by some heat treatment method crystal grain thinnings, Thus improving the steel of its mechanical performance.In the middle of the trial production process of fine grain variety steel exploitation, one side Chang Yin wears water system System causes impact in boiled water moment to the rolled piece in guide groove, leads to rolled piece to bent in guide groove or in finishing mill, reducing sizing mill Break and cause piling of steel;On the other hand it is the thermometal detector jitter because wearing water system, lead to wear water valve frequently switching on Water or do not close, causes the impact to rolled piece to cause piling of steel.
Existing using four thermometal detectors to judge rolling line whether have rolled piece to pass through and to water tank work control, essence Milling train enters, export each install one and control 1#2# water tank simultaneously, reducing sizing mill enters, export and each install a control 3#4# water simultaneously Case.Because in-situ production environment water smoke is big, often cause thermometal detector signal to flash, cause water tank to pass through period in rolled piece frequent Switch water valve and when rolling line no rolled piece water valve cannot close, open, cause next rolled piece to roll by steel stifled during water tank, whole piece Part performance is unqualified.Keep wearing water system long period steady operation, it is necessary to assure four thermometal detector signals are reliable, letter Number unstable water tank logic control program will be caused to malfunction.And thermometal detector signal is easily subject to external environmental interference, body Also fragile.
Content of the invention
In view of this, it is an object of the invention to provide water system water tank control method and device are worn in steel rolling, to solve to wear Water valve frequently switches on water or does not cut out, and causes the impact to rolled piece to cause the problem of piling of steel.
In order to achieve the above object, the following technical scheme of present invention offer:
Water system water tank control method is worn in a kind of steel rolling, comprising:
The real-time current signal of detection finishing mill;
Judge whether finishing mill is according to described real-time current signal and sting steel state or de- shape of tail state;
If so, then opened or closed successively according to the water valve of default water tank sequential control water tank.
Preferably, before the described water valve according to default water tank sequential control water tank opens or closes successively, also include:
After the default time interval of time delay, the water valve further according to default water tank sequential control water tank is beaten successively and is opened or closed Close.
Preferably, before after the default time interval of described time delay, also include:
According to the water valve action delay time itself, described default time interval is modified.
Preferably, described default time interval is between 100ms to 200ms.
Water system cistern controller is worn in a kind of steel rolling, comprising:
Detection module, for detecting the real-time current signal of finishing mill;
Judge module, for judging whether finishing mill stings steel or de- tail, if so, then triggers water tank control module;
Described water tank control module, for opening or closing successively according to the water valve of default water tank sequential control water tank.
Preferably, also include:
Time-delayed trigger module, after the default time interval of time delay, further according to default water tank sequential control water tank Water valve opens or closes successively.
Preferably, also include:
Correcting module, for being modified to described default time interval according to the water valve action delay time itself.
Preferably, described default time interval is between 100ms to 200ms.
Water system water tank control method is worn in the steel rolling that the present invention provides, and the real-time current signal of finishing mill is monitored, Judge whether finishing mill is according to real-time current signal and sting steel state or de- shape of tail state, the root when finishing mill is in and stings steel state Water valve according to default water tank sequential control water tank is opened successively;It is suitable according to default water tank when finishing mill is in de- shape of tail state Sequence controls the water valve of water tank to close successively, and the signal controlling water tank is substituted for finishing mill by original thermometal detector signal Real-time current information, it is to avoid originally jitter and the water valve of wearing that leads to frequently switch on water or do not close and cause to rolled piece Impact causes the problem of piling of steel, and water tank can be controlled accurately to close, and avoids result in finished product to rolled piece head-tail memory temperature control and rolls The part underproof problem of physical property end to end, reduces production cost, improves lumber recovery simultaneously.
Brief description
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing Have technology description in required use accompanying drawing be briefly described it should be apparent that, drawings in the following description be only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, acceptable Other accompanying drawings are obtained according to these accompanying drawings.
Fig. 1 is the schematic flow sheet that water system water tank control method is worn in steel rolling provided in an embodiment of the present invention;
Fig. 2 is the structural representation that water system cistern controller is worn in steel rolling provided in an embodiment of the present invention.
Specific embodiment
The embodiment of the invention discloses water system water tank control method and device are worn in a kind of steel rolling, water valve is worn with solution frequent Switch water or do not close, cause the impact to rolled piece to cause the problem of piling of steel.
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation description is it is clear that described embodiment is only a part of embodiment of the present invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of not making creative work Embodiment, broadly falls into the scope of protection of the invention.
Water system water tank control method is worn in a kind of steel rolling that the present invention provides, and wherein, finishing mill and water tank communicate to connect, its In, it may include multiple water tanks are connected with finishing mill.
Refer to shown in Fig. 1, be the flow process signal that water system water tank control method is worn in steel rolling provided in an embodiment of the present invention Figure, the method comprises the following steps:
S11: the real-time current signal of detection finishing mill;
S12: judge whether finishing mill is according to described real-time current signal and sting steel state or de- shape of tail state;
General, when finishing mill is in and stings steel state, electric current produces rising edge pulse signal, when finishing mill is in de- tail During state, electric current produces trailing edge pulse signal, by detecting the real-time current signal of finishing mill, judges whether finishing mill is in Sting steel state or de- shape of tail state, execute next step s13.
S13: if so, then opened or closed successively according to the water valve of default water tank sequential control water tank.
If finishing mill is in steel state of stinging, controls the water valve of water tank to open successively, rolled piece is processed, if at finishing mill In de- shape of tail state, then the water valve of water tank is controlled to close successively.Specifically, water tank may generally be 4, the first water tank and the second water tank Can be separately mounted to the entrance and exit of finishing mill, three-tank and the 4th water tank can be separately mounted to reducing sizing mill entrance and Outlet, certainly, in other embodiments it is also possible to the water tank of setting other quantity, may be provided at corresponding position as needed, The quantity and set location of specific water tank is not construed as limiting, as long as identical technical purpose can be reached.
Water system water tank control method is worn in the steel rolling that the present invention provides, and the real-time current signal of finishing mill is monitored, Judge whether finishing mill is according to real-time current signal and sting steel state or de- shape of tail state, the root when finishing mill is in and stings steel state Water valve according to default water tank sequential control water tank is opened successively;It is suitable according to default water tank when finishing mill is in de- shape of tail state Sequence controls the water valve of water tank to close successively, and the signal controlling water tank is substituted for finishing mill by original thermometal detector signal Real-time current information, it is to avoid originally jitter and the water valve of wearing that leads to frequently switch on water or do not close and cause to rolled piece Impact causes the problem of piling of steel, and water tank can be controlled accurately to close, and avoids result in finished product to rolled piece head-tail memory temperature control and rolls The part underproof problem of physical property end to end, reduces production cost, improves lumber recovery simultaneously.
Specifically, before being opened or closed successively according to the water valve of default water tank sequential control water tank, also include:
After the default time interval of time delay, the water valve further according to default water tank sequential control water tank is beaten successively and is opened or closed Close.
Wear the impact that water system caused to the rolled piece in guide groove in boiled water moment in order to reduce, can be by arranging time delay come right The water valve of water tank is opened or closed, and time interval can be set according to the position relationship between finishing mill and water tank and rolled piece Fixed, cause piling of steel to avoid rolled piece to bent in guide groove or break in finishing mill, reducing sizing mill.
Further, before after the default time interval of time delay, also include:
According to the water valve action delay time itself, default time interval is modified.
Because water valve itself also has action delay, according to the action delay time, default time interval can be modified, To ensure the accurate opening and closing of water tank, prevent from causing piling of steel to the impact of rolled piece, and head-tail physical property occurs not Qualified phenomenon.
Further, default time interval is between 100ms to 200ms.
Certainly, in other embodiments it is also possible to be set to other times interval, as long as identical technology effect can be reached Fruit, above are only more preferred embodiment, all within the scope of the present invention.
Compared to the embodiment of said method, present invention also offers water system cistern controller is worn in a kind of steel rolling, please Refering to Fig. 2, it is the structural representation that water system cistern controller is worn in steel rolling provided in an embodiment of the present invention, this device includes:
Detection module 110, for detecting the real-time current signal of finishing mill;
Judge module 120, for judging whether finishing mill stings steel or de- tail, if so, then triggers water tank control module 130;
Water tank control module 130, for opening or closing successively according to the water valve of default water tank sequential control water tank.
Water system water tank control method and device are worn in the steel rolling that the present invention provides, and the real-time current signal of finishing mill is carried out According to real-time current signal, monitoring, judges whether finishing mill is in and stings steel state or de- shape of tail state, sting steel shape when finishing mill is in Opened successively according to the water valve of default water tank sequential control water tank during state;When finishing mill is in de- shape of tail state according to default The water valve of water tank sequential control water tank cuts out successively, and the signal controlling water tank is substituted for by original thermometal detector signal The real-time current information of finishing mill, it is to avoid originally jitter and lead to wear water valve frequently switch on water or do not close cause right The impact of rolled piece causes the problem of piling of steel, and water tank can be controlled accurately to close, and rolled piece head-tail memory temperature control is avoided result in The finished product rolled piece underproof problem of physical property end to end, reduces production cost, improves lumber recovery simultaneously.
Specifically, also include:
Time-delayed trigger module, after the default time interval of time delay, further according to default water tank sequential control water tank Water valve opens or closes successively.
Further, also include:
Correcting module, for being modified to default time interval according to the water valve action delay time itself.
Further, default time interval is between 100ms to 200ms.
In this specification, each embodiment is described by the way of going forward one by one, and what each embodiment stressed is and other The difference of embodiment, between each embodiment same or similar partly mutually referring to.Fill for disclosed in embodiment For putting, because it corresponds to the method disclosed in Example, so description is fairly simple, referring to method part in place of correlation Illustrate.
Professional further appreciates that, in conjunction with the unit of each example of the embodiments described herein description And algorithm steps, can with electronic hardware, computer software or the two be implemented in combination in, in order to clearly demonstrate hardware and The interchangeability of software, generally describes composition and the step of each example in the above description according to function.These Function to be executed with hardware or software mode actually, the application-specific depending on technical scheme and design constraint.Specialty Technical staff can use different methods to each specific application realize described function, but this realization should Think beyond the scope of this invention.
The step of the method in conjunction with the embodiments described herein description or algorithm can directly be held with hardware, processor The software module of row, or the combination of the two is implementing.Software module can be placed in random access memory (ram), internal memory, read-only deposit Reservoir (rom), electrically programmable rom, electrically erasable rom, depositor, hard disk, moveable magnetic disc, cd-rom or technology In known any other form of storage medium in field.
Above water system water tank control method and device are worn to a kind of steel rolling provided by the present invention, carried out detailed Jie Continue.Specific case used herein is set forth to the principle of the present invention and embodiment, and the explanation of above example is only It is to be used to help understand the method for the present invention and its core concept.It should be pointed out that for those skilled in the art For, under the premise without departing from the principles of the invention, the present invention can also be carried out with some improvement and modify, these improve and repair Decorations also fall in the protection domain of the claims in the present invention.

Claims (8)

1. a kind of steel rolling wears water system water tank control method it is characterised in that including:
The real-time current signal of detection finishing mill;
Judge whether finishing mill is according to described real-time current signal and sting steel state or de- shape of tail state;
If so, then opened or closed successively according to the water valve of default water tank sequential control water tank.
2. steel rolling according to claim 1 wear water system water tank control method it is characterised in that described according to default water Before the water valve of case sequential control water tank opens or closes successively, also include:
After the default time interval of time delay, the water valve further according to default water tank sequential control water tank opens or closes successively.
3. steel rolling according to claim 2 wears water system water tank control method it is characterised in that when described time delay is default Between be spaced after before, also include:
According to the water valve action delay time itself, described default time interval is modified.
4. steel rolling according to claim 3 wears water system water tank control method it is characterised in that between the described default time It is divided between 100ms to 200ms.
5. a kind of steel rolling wears water system cistern controller it is characterised in that including:
Detection module, for detecting the real-time current signal of finishing mill;
Judge module, for judging whether finishing mill stings steel or de- tail, if so, then triggers water tank control module;
Described water tank control module, for opening or closing successively according to the water valve of default water tank sequential control water tank.
6. steel rolling according to claim 5 wears water system cistern controller it is characterised in that also including:
Time-delayed trigger module, after the default time interval of time delay, further according to the water valve of default water tank sequential control water tank Open or close successively.
7. steel rolling according to claim 6 wears water system cistern controller it is characterised in that also including:
Correcting module, for being modified to described default time interval according to the water valve action delay time itself.
8. steel rolling according to claim 7 wears water system cistern controller it is characterised in that between the described default time It is divided between 100ms to 200ms.
CN201610755141.3A 2016-08-29 2016-08-29 Steel rolling water-penetrating system water tank control method and device Pending CN106345821A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610755141.3A CN106345821A (en) 2016-08-29 2016-08-29 Steel rolling water-penetrating system water tank control method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610755141.3A CN106345821A (en) 2016-08-29 2016-08-29 Steel rolling water-penetrating system water tank control method and device

Publications (1)

Publication Number Publication Date
CN106345821A true CN106345821A (en) 2017-01-25

Family

ID=57857090

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610755141.3A Pending CN106345821A (en) 2016-08-29 2016-08-29 Steel rolling water-penetrating system water tank control method and device

Country Status (1)

Country Link
CN (1) CN106345821A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110496863A (en) * 2018-05-17 2019-11-26 宝山钢铁股份有限公司 A kind of rolled piece conveyor roller cooling control system and its method
CN113976634A (en) * 2021-09-23 2022-01-28 阳春新钢铁有限责任公司 Control system and method for preventing damage of thick-section middle-section variable piece rolling tool
CN117399438A (en) * 2023-11-03 2024-01-16 中天钢铁集团(南通)有限公司 Method for stabilizing head and tail performance in English standard rolling process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101912885A (en) * 2010-08-11 2010-12-15 马鞍山钢铁股份有限公司 Section mill rolled piece end bending monitoring device and method
CN102199711A (en) * 2011-04-15 2011-09-28 中天合金技术有限公司 Production method of high-precision ultralong oxygen-free copper strip
CN202860997U (en) * 2012-09-07 2013-04-10 西林钢铁集团有限公司 Water-through cooling automatic control device
CN104998912A (en) * 2015-06-25 2015-10-28 四川省达州钢铁集团有限责任公司 Automatic control method for high-line temperature control system
CN105521996A (en) * 2016-02-04 2016-04-27 东北大学 Hot roller heating and rolling device and method for magnesium alloy strips

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101912885A (en) * 2010-08-11 2010-12-15 马鞍山钢铁股份有限公司 Section mill rolled piece end bending monitoring device and method
CN102199711A (en) * 2011-04-15 2011-09-28 中天合金技术有限公司 Production method of high-precision ultralong oxygen-free copper strip
CN202860997U (en) * 2012-09-07 2013-04-10 西林钢铁集团有限公司 Water-through cooling automatic control device
CN104998912A (en) * 2015-06-25 2015-10-28 四川省达州钢铁集团有限责任公司 Automatic control method for high-line temperature control system
CN105521996A (en) * 2016-02-04 2016-04-27 东北大学 Hot roller heating and rolling device and method for magnesium alloy strips

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110496863A (en) * 2018-05-17 2019-11-26 宝山钢铁股份有限公司 A kind of rolled piece conveyor roller cooling control system and its method
CN113976634A (en) * 2021-09-23 2022-01-28 阳春新钢铁有限责任公司 Control system and method for preventing damage of thick-section middle-section variable piece rolling tool
CN117399438A (en) * 2023-11-03 2024-01-16 中天钢铁集团(南通)有限公司 Method for stabilizing head and tail performance in English standard rolling process

Similar Documents

Publication Publication Date Title
CN106345821A (en) Steel rolling water-penetrating system water tank control method and device
CN104998912A (en) Automatic control method for high-line temperature control system
CN101952059B (en) Operating method for a cooling section having centralized detection of valve characteristics and objects corresponding thereto
CN101733290B (en) Anti-tail out automatic control system of hot continuous rolling thin strip steel
CN103223420A (en) Method for controlling inner ring indentations of hot-rolled steel coil, and system
CN105573290A (en) Cigarette factory superspeed carton packaging machine multi-condition process online monitoring and fault diagnosis method
CN107345706A (en) The control method of the initial opening angle of wind guide strip when air conditioner is started shooting
CN1605669B (en) Filling insertion controlling device of jet loom
CN109550810A (en) A kind of method for aligning improving the cold steel-plate shape of thin gauge control
CN103990652A (en) Movable sleeve control method for pipeline steel
CN105598169A (en) Control method of actual speed for cutting tail end of band steel by flying shear of 2250-mm rolling mill
CN108856303A (en) Reliable hot-rolling finishing mill frame stings steel signal control method
CN106903174A (en) A kind of method of base head temperature drop in the middle of reduction
CN106325776A (en) Method and device for real-time adjustment of cache elimination strategy
CN103240276A (en) Method for protecting edge heaters during hot rolling of stainless steel
CN110273405A (en) Double-cylinder hydraulic gate oil cylinder journey error compensation method based on PID control
CN204273364U (en) A kind of feeding distribution mechanism and be applied to this feeding distribution mechanism make button machine
CN204060419U (en) Fire resistance steel door
CN108115002A (en) The method for improving tail part of band steel scroll quality
CN110548767A (en) control method for head-tail shearing of rod wire
MX2017011943A (en) Titanium nickel niobium alloy barrier for low-emissivity coatings.
CN113231478B (en) Device for accurately positioning bar rolling line and control method
CN101852599A (en) Loop strip break on-line detection method of acid pickling-rolling mill integral unit
CN204981059U (en) A send stopper device for filling machine of pluging
CN202962907U (en) Automatic elimination device of disqualified cut rolled stem at outlet of fluidized bed

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170125