CN106339815A - Concrete construction process structured data realization method - Google Patents

Concrete construction process structured data realization method Download PDF

Info

Publication number
CN106339815A
CN106339815A CN201610751195.2A CN201610751195A CN106339815A CN 106339815 A CN106339815 A CN 106339815A CN 201610751195 A CN201610751195 A CN 201610751195A CN 106339815 A CN106339815 A CN 106339815A
Authority
CN
China
Prior art keywords
quality
quality evaluation
concrete construction
concrete
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610751195.2A
Other languages
Chinese (zh)
Inventor
叶红星
赵城
雷晓华
谢涛
李军治
陈学武
孙健
方均
李军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Easy-To-Use Viewpoint Science And Technology Ltd In Beijing
Original Assignee
Easy-To-Use Viewpoint Science And Technology Ltd In Beijing
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Easy-To-Use Viewpoint Science And Technology Ltd In Beijing filed Critical Easy-To-Use Viewpoint Science And Technology Ltd In Beijing
Priority to CN201610751195.2A priority Critical patent/CN106339815A/en
Publication of CN106339815A publication Critical patent/CN106339815A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • Educational Administration (AREA)
  • Marketing (AREA)
  • Development Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Stored Programmes (AREA)

Abstract

The invention discloses a concrete construction process structured data realization method. The method comprises the following realization steps: 1) teasing out the concrete construction process, and carrying out structured operation on a quality three-inspection record form, a process quality evaluation form and a unit project quality evaluation form of each process; 2)according to the quality three-inspection record form and the process quality evaluation form of each process, establishing a data item corresponding relationship between the quality three-inspection record form and the process quality evaluation form; and 3) according to quality evaluation index, carrying out automatic quality evaluation on each process of a concrete unit automatically. Through the concrete construction process structured data realization method, repeat entry of construction and supervision unit construction site data is greatly reduced; and according to system built-in configurable quality evaluation criteria, automatic quality evaluation is carried out on each process of the concrete unit automatically, thereby improving quality evaluation work efficiency and data accuracy, and effectively improving quality management level of the construction site.

Description

Concrete construction sequence structure data implementation method
Technical field
The present invention relates to concrete construction association area, especially a kind of concrete construction sequence structure data realization side Method.
Background technology
Operation animation effect is the work progress evaluating the whether standard compliant yardstick engineering project of process quality, is by one The operation of interrelated, the mutual restriction of series is constituted, and process quality is basis, directly affects the total quality of engineering project, The quality of Construction Process of Engineering Project to be controlled, must control the quality of operation first. and construction quality is shape in working procedure Become, in order to construction quality is checked on from postmortem, turn to Prior Control, reach the purpose to put prevention first.
Conventional concrete process quality is tested and comments process to be the list beaten using machine, and then manual typing quality is commented at the scene Determine list, including three inspection tables, process quality evaluation form, element project performance rating table etc., data inputting repeats also inconvenience, with When paper form easily lose, be also not easy preserve.
Content of the invention
It is an object of the invention to overcoming the deficiencies in the prior art, here provides a kind of concrete construction sequence structure number According to implementation method;Concrete construction includes, by concrete construction sequence structure data implementation method, realizing concrete construction Operation supervisor tests when commenting, and is related to the part of performance rating, three inspections, evaluation, examination during realizing automatic push quality management and control Test detection, photo site, report table to a higher authorities for approval;Commented by testing of supervisor's typing quality, difficulty action accomplishment report work to a higher authorities for approval;In inspection of quality The record of any quality control during evaluation, can be reviewed.
The present invention is achieved in that a kind of concrete construction sequence structure data implementation method of construction, and its feature exists In: the step that described concrete construction sequence structure data is realized is as follows;
Step (1): combing goes out concrete construction operation, examines log, process quality evaluation form, list to the quality three of each operation First evaluation of engineering quality table carries out structuring operation;
Step (2): according to quality three inspection log and the process quality evaluation form of each operation, set up three inspection tables and process quality is commented Determine the data item corresponding relation of table;
Step (3): according to the index of performance rating, automatically the performance rating of automatization is carried out to each operation of concrete unit.
It is an advantage of the current invention that: by concrete construction sequence structure data implementation method, greatly reduce construction And the repetition typing of supervisor's job site data, and according to the built-in criteria of quality evaluation joined of system, automatically to mixed The each operation of solidifying soil unit carries out the performance rating of automatization, improves the accuracy that quality tests the work efficiency data commented, Effectively improve the quality management level of job site.
Brief description
Fig. 1 is concrete construction sequence structure data implementation method implementation process diagram of the present invention.
Specific embodiment
Below in conjunction with accompanying drawing 1, the present invention is described in detail, and the technical scheme in the embodiment of the present invention is carried out clearly Chu, it is fully described by it is clear that described embodiment is only a part of embodiment of the present invention, rather than whole embodiments. Based on the embodiment in the present invention, it is all that those of ordinary skill in the art are obtained under the premise of not making creative work Other embodiment, broadly falls into the scope of protection of the invention.
The present invention passes through to improve provides a kind of concrete construction sequence structure data implementation method, and the step that it is realized is such as Under;
Step (1): combing goes out concrete construction operation, examines log, process quality evaluation form, list to the quality three of each operation First evaluation of engineering quality table carries out structuring operation;
Step (2): according to quality three inspection log and the process quality evaluation form of each operation, set up three inspection tables and process quality is commented Determine the data item corresponding relation of table;
Step (3): according to the index of performance rating, automatically the performance rating of automatization is carried out to each operation of concrete unit.
Concrete construction includes, by concrete construction sequence structure data implementation method, realizing concrete construction operation Supervisor tests when commenting, and is related to the part of performance rating, three inspections, evaluation, test inspection during realizing automatic push quality management and control Survey, photo site, report table to a higher authorities for approval;Commented by testing of supervisor's typing quality, difficulty action accomplishment report work to a higher authorities for approval;In inspection of quality evaluation During, the record of any quality control can be reviewed.
By concrete construction sequence structure data implementation method, greatly reduce construction and supervisor job site The repetition typing of data, and according to the built-in criteria of quality evaluation joined of system, automatically each operation of concrete unit is entered The performance rating of row automatization, improves the accuracy that quality tests the work efficiency data commented, and effective to improve construction existing The quality management level of field.
Described above to the disclosed embodiments, makes professional and technical personnel in the field be capable of or uses the present invention. Multiple modifications to these embodiments will be apparent from for those skilled in the art, as defined herein General Principle can be realized without departing from the spirit or scope of the present invention in other embodiments.Therefore, the present invention It is not intended to be limited to the embodiments shown herein, and be to fit to and principles disclosed herein and features of novelty phase one The scope the widest causing.

Claims (1)

1. a kind of concrete construction sequence structure data implementation method it is characterised in that: described concrete construction sequence structure The step changing data realization is as follows;
Step (1): combing goes out concrete construction operation, examines log, process quality evaluation form, list to the quality three of each operation First evaluation of engineering quality table carries out structuring operation;
Step (2): according to quality three inspection log and the process quality evaluation form of each operation, set up three inspection tables and process quality is commented Determine the data item corresponding relation of table;
Step (3): according to the index of performance rating, automatically the performance rating of automatization is carried out to each operation of concrete unit.
CN201610751195.2A 2016-08-30 2016-08-30 Concrete construction process structured data realization method Pending CN106339815A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610751195.2A CN106339815A (en) 2016-08-30 2016-08-30 Concrete construction process structured data realization method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610751195.2A CN106339815A (en) 2016-08-30 2016-08-30 Concrete construction process structured data realization method

Publications (1)

Publication Number Publication Date
CN106339815A true CN106339815A (en) 2017-01-18

Family

ID=57822725

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610751195.2A Pending CN106339815A (en) 2016-08-30 2016-08-30 Concrete construction process structured data realization method

Country Status (1)

Country Link
CN (1) CN106339815A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107480171A (en) * 2017-06-29 2017-12-15 中国建筑局(集团)有限公司 Database combining construction process and engineering data and manufacturing method
CN110987082A (en) * 2019-12-21 2020-04-10 广州新稳房屋安全鉴定有限公司 Safety detection method for reinforced concrete building structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107480171A (en) * 2017-06-29 2017-12-15 中国建筑局(集团)有限公司 Database combining construction process and engineering data and manufacturing method
CN110987082A (en) * 2019-12-21 2020-04-10 广州新稳房屋安全鉴定有限公司 Safety detection method for reinforced concrete building structure

Similar Documents

Publication Publication Date Title
CN106940839B (en) Power transmission and transformation project quality data management and control system and method
CN106507372A (en) A kind of wireless network zone-skipping coverage detection method, device and communication system
CN105069587B (en) A kind of relay protection check device based on mobile interchange
CN102110053A (en) Random testing method based on Android
CN110691369B (en) Indoor signal leakage analysis method and system based on MDT
CN103439592A (en) Method for intelligently testing intelligent substation on site
CN101833499A (en) Software testing validating method based on reachability tree
CN108469739A (en) Remote home packing quality control system based on Internet of Things, video and artificial intelligence
CN104754590A (en) Method and device for assessing LTE (long term evolution) network sites
CN110189311A (en) A kind of calculation method of transmission line of electricity screen of trees hidden danger region trees felling area
CN106339815A (en) Concrete construction process structured data realization method
CN105306471A (en) System and method for management and control of access control policy of security domain boundary equipment of smart grid
CN115908432A (en) Material output quality detection system and prediction method
CN103675529B (en) The protective relaying device automatic test approach of feature based word and device
CN105116301A (en) Data auxiliary determining method based on dynamic statistics
CN203011829U (en) Cuvette, water quality concentration detecting device and water quality monitoring system
CN103839215A (en) Multi-dimensional comprehensive information security assessment service platform system
CN106375037A (en) Wireless signal test method
CN105976273A (en) Highly roller compacted concrete dam construction procedure quality evaluation system and method
CN106909508A (en) A kind of information system testing results method and system
CN105761162B (en) Electric power enterprise technical standard evaluation method
CN109104730A (en) A kind of network road measurement method, equipment and system
CN109982333A (en) A kind of site selecting method and system that TD-LTE depth covering benefit is blind
CN106524953A (en) Flatness detecting method for stator laminates
CN114035531A (en) Automatic calibration method for stability control device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170118