CN106339549A CN201610747268.0A CN201610747268A CN106339549A CN 106339549 A CN106339549 A CN 106339549A CN 201610747268 A CN201610747268 A CN 201610747268A CN 106339549 A CN106339549 A CN 106339549A
Authority
CN
China
Prior art keywords
gas
oil
time
measuring
calculating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610747268.0A
Other languages
Chinese (zh)
Inventor
杨浩
陈文祥
段云星
吴少诚
孙哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Geosciences Beijing
Original Assignee
China University of Geosciences Beijing
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Geosciences Beijing filed Critical China University of Geosciences Beijing
Priority to CN201610747268.0A priority Critical patent/CN106339549A/en
Publication of CN106339549A publication Critical patent/CN106339549A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/02Agriculture; Fishing; Forestry; Mining

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Earth Drilling (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Business, Economics & Management (AREA)
  • Animal Husbandry (AREA)
  • Mining & Mineral Resources (AREA)
  • Agronomy & Crop Science (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Marine Sciences & Fisheries (AREA)

Abstract

The invention discloses a measuring and calculating method of the upwelling speed of oil gas. The method is obtained by improving a common late time method serving as a basis, wherein the improvements comprise an improvement on a parameter measuring, calculating and solving method and an improvement on a measuring and calculating formula; according to the method, automatic measurement and calculation are realized by compiling measuring and calculating statements by virtue of Microsoft EXCEL.EXE software. According to the method, the problems that the measurement of parameters is insufficiently accurate, and the design of the formula is insufficiently rigorous existing in the traditional late time method are solved, the accuracy of measurement and calculation of the upwelling speed of the oil gas is improved, and important significance for improving drilling facilities and the safety of persons is realized.

Description

A kind of measuring method of Ascending Velocity For Oil & Gas
Technical field
The invention belongs to technical field of geophysical exploration is and in particular to a kind of measuring method of Ascending Velocity For Oil & Gas.
Background technology
After opening oil-gas Layer, stop drilling well for some reason, during making a trip or quiescent time, if shaft bottom Pressure is less than strata pressure, and oil gas entrance pit shaft is simultaneously up.Observe whether hydrocarbon stratum enters pit shaft by the method surveying aftereffect, So that in time adjustment property of drilling fluid is it is ensured that the safety of drilling well.Specific way is, after static a period of time under get into bottom, Circulating fluid, by observing the situation of drill-hole returns, if having display that oil gas returns out (such as: have in mud oil bloom or Gas) or mud density decline, show that oil gas enters pit shaft.By measuring and calculating it is to be understood that the upwelling speed of oil gas.
In drilling well and Downhole Construction, Ascending Velocity For Oil & Gas are the important technology data weighing downhole safety, are true Determine the important technology foundation of next step arrangement and method for construction measure.Ascending Velocity For Oil & Gas are too high, well kick blowout problem will be led to occur, make Descend destruction, the destruction to ground environment and the serious threat to wellbore construction safety of petroleum resources in couples.In particular with The continuous complication expanding year by year with underground situation in oil-gas exploration and development region, is carried with safety to drilling well and underground work technology Go out higher requirement, the measuring and calculating of Ascending Velocity For Oil & Gas has been also required that more accurate, more convenient.
For the measuring and calculating of Ascending Velocity For Oil & Gas, traditional method includes " lagged time method " and " volumetric method " two methods. Undoubtedly, both measuring methods are correct in theory.But, the key parameter that both approaches are related to is slow To the accuracy problem of time, mud pumpage, very big impact is brought on the accuracy of measuring and calculating.
Lagged time method is the method that situ of drilling well has been used up.The main deficiency of this method, one is lagged time Measurement is comparatively laborious;Two be lagged time survey calculation in be subject to " drilling fluid delivery ratio " impact and drilling tool inner downlink time Impact, it is difficult to ensure that the accuracy of measuring and calculating;Three is that the measuring and calculating and Ascending Velocity For Oil & Gas measuring and calculating of lagged time enters under different Under drilling tool number of times and state, data consistency is poor;Four is to be introduced into the display time oil gas not being invaded section in upwelling speed measuring and calculating, Lack comprehensive;Five is unreasonable with the lagged time measuring and calculating Ascending Velocity For Oil & Gas of drilling cuttings;Six is not account for compound well feelings Condition;Etc..Meanwhile, the general actual conditions not measuring lagged time of development well drilling well and underground work scene, are also that impact should The reality that method is calculated.
For volumetric method, scene application is less.The occurrence poor accuracy of mainly mud pumpage, hole capacity is not yet Easily accurately determine, therefore estimation precision is low.
Ascending Velocity For Oil & Gas measuring method, as well control operation key technology point, directly decides how job site determines Drilling fluid/density of completion fluids and performance parameter, can provide safeguard for pit shaft safety work.In existing Ascending Velocity For Oil & Gas measuring and calculating side Under method, because of oil gas well fluids difference, pit shaft and BHA not parity problem, to a certain degree affect well control job safety.
By further investigation, five kinds of Ascending Velocity For Oil & Gas measuring methods of summary and induction, define each measuring and calculating respectively The corresponding applicable elements of method and measure formula, each have pluses and minuses as follows: Ascending Velocity For Oil & Gas measuring and calculating had been used up in the past Lagged time method and volumetric method are calculating, but two methods are all fallen termination of pumping by mud pump circulation discharge capacity, midway and gas rises The impact such as slippage, volumetric method is also affected by Open-Hole Section hole enlargement ratio;Total hydrocarbon Time Method can eliminate the longer shortcoming of Selecting time, But by hole enlargement ratio, discharge capacity, midway, termination of pumping is affected;Total hydrocarbon Time Method and density hours method have intercommunity, i.e. total hydrocarbon The rising of display and decline impact drilling fluid density change, two methods not only simple and direct and also can reference pair ratio mutually, total hydrocarbon Time Method makes up error when drilling fluid density measures, and density hours method makes up the instrumental transmission time difference of total hydrocarbon Time Method;Follow Ring test method is only affected by oil gas layer depth selection, is not bored displacement volume by under hole enlargement ratio, drilling tool band check-valves, pump is arranged Amount, midway fall pump impact, can visual in imagely judge whether meet pull out of hole require, but the method exist take the production time long Shortcoming, in order to overcome the shortcoming of these methods, based on the most frequently used lagged time method, carry out studying and finally draw improvement Lagged time method.
Content of the invention
In order to overcome the shortcomings of existing oil and gas upwelling speed measuring method presence, improve oil security control ability, this Invention provides a kind of measuring method of Ascending Velocity For Oil & Gas, and methods described is existing measuring method to be carried out with synthesis improvement and shape Become.
For realizing above-mentioned target, the present invention employs the following technical solutions:
A kind of measuring method of Ascending Velocity For Oil & Gas, methods described, based on conventional lagged time method, improves and draws. Including the measuring and calculating improvement of parameter acquiring method and the improvement of measure formula.
Described measuring and calculating parameter acquiring method improvement include the display time determine method improve and oil reservoir position judging method Improve.
The display time determines that method is improved: one of total hydrocarbon change presence significantly from low value to the mutation of too high value changes Point (flex point), using this flex point as the display time;
Oil reservoir position judging method improves as follows:
When only single gas-bearing formation: choose this gas-bearing formation well depth and be used for calculating;
When having many gas-bearing formations, judge oil reservoir position by the following method:
(1) there are multiple gas-bearing formations relatively far apart, but a certain top gas-bearing formation is more active, always Ascending Velocity For Oil & Gas are had bright Development rings, then this should be selected to enliven gas-bearing formation and be used for calculating;
(2) it is multiple peak values to total gas curve, there is the situation of multiple oil-gas Layer, the choosing method of oil-gas Layer is according to oil-gas Layer The total gas curve in figure total hydrocarbon base value drawn before and after distribution situation and actual oil/gas show to be determined to this shadow with change procedure Sound oil-gas Layer top circle the most shallow is as hOilValue.
Measure formula improves:
Lagged time method measure formula originally is:
It is improved to:
Wherein: vOn alterAscending Velocity For Oil & Gas, m/h;hOilOil-gas Layer top depth, m;hDrill bitDuring circulating fluid, drill bit is located Depth, m;tAobviousIt is recycled to the time that oil gas flex point occurs, h from turn on pump;The t termination of pumping time, h;tLateDrill bit place depth Lagged time, h;tQuietIt is drilled into total quiescent time of this turn on pump, h from termination of pumping;C drilling tool displacement effect correction factor.
Described formula improves content and includes:
Quiescent time improve: consider drilling fluid quiescent time simultaneously add turn on pump circulation after to the time seeing oil/gas show.
The midway termination of pumping time improves: the oil/gas show flex point time should deduct the time t that pump is switched in midway, be only and really open The oil gas flex point time is seen after pump.
The correction with back-pressure valve for the drilling tool: consider the impact of drilling tool displacement effect, had with oil gas section constant-volume principle:
Wherein h1 is to alter height on the actual oil gas that should ask for, and h2 is the height considering drilling tool displacement effect.
Simultaneously in order to reduce scene using the manual difficulty calculating Ascending Velocity For Oil & Gas and loaded down with trivial details degree, by correlative study, Above-mentioned classics lagged time method and revised lagged time method can by now widely used Microsoft excel.exe software, Carry out automatic measurement & calculation by writing measuring and calculating sentence.
A kind of measuring method of Ascending Velocity For Oil & Gas, the method comprising the steps of:
1) manually ask for the well depth of drill bit circulation position and correspond to the lagged time at bit location under discharge capacity;
2) after asking for lagged time, termination of pumping, record the termination of pumping time, carry out short trip 10-15 column;
3) get into last time under and ask at lagged time position, turn on pump circulates, record Running pump time;
4) during well room observation oil/gas show, write down and start display time, time to peak and end time;
5) calculate termination of pumping respectively to show with oil/gas show time t between the turn on pump quiet stopping time, and determine abnormal oil-gas Layer position;
6) fill in detection parameter according to improvement lagged time method related content;
7), after asking for correlation computations parameter, the idealization lagged time method formula calculating instrument of establishment, consideration can be used respectively After between the quiet stopping time, lagged time method improves formula calculating instrument, midway termination of pumping improves formula calculating instrument and carries in back-pressure valve correction Alter speed calculating instrument etc. and calculate Ascending Velocity For Oil & Gas.
It is not smart that advantages of the present invention and having the beneficial effect that overcomes the parameter measurement that traditional lagged time method exists Really, the not rigorous problem of formula design, improves the accuracy of oil and gas upwelling speed measuring and calculating, for raising drilling facilities and people Member's security is significant.
Specific embodiment
Embodiment
A kind of measuring method of Ascending Velocity For Oil & Gas, methods described, based on conventional lagged time method, improves Draw.Including the measuring and calculating improvement of parameter acquiring method and the improvement of measure formula.
Described measuring and calculating parameter acquiring method improvement include the display time determine method improve and oil reservoir position judging method Improve.
The display time determines that method is improved: one of total hydrocarbon change presence significantly from low value to the mutation of too high value changes Point (flex point), using this flex point as the display time;
Oil reservoir position judging method improves as follows:
When only single gas-bearing formation: choose this gas-bearing formation well depth and be used for calculating;
When having many gas-bearing formations, judge oil reservoir position by the following method:
(1) there are multiple gas-bearing formations relatively far apart, but a certain top gas-bearing formation is more active, always Ascending Velocity For Oil & Gas are had bright Development rings, then this should be selected to enliven gas-bearing formation and be used for calculating;
(2) it is multiple peak values to total gas curve, there is the situation of multiple oil-gas Layer, the choosing method of oil-gas Layer is according to oil-gas Layer The total gas curve in figure total hydrocarbon base value drawn before and after distribution situation and actual oil/gas show to be determined to this shadow with change procedure Sound oil-gas Layer top circle the most shallow is as hOilValue.
Measure formula improves:
Lagged time method measure formula originally is:
It is improved to:
Wherein: vOn alterAscending Velocity For Oil & Gas, m/h;hOilOil-gas Layer top depth, m;hDrill bitDuring circulating fluid, drill bit is located Depth, m;tAobviousIt is recycled to the time that oil gas flex point occurs, h from turn on pump;The t termination of pumping time, h;tLateDrill bit place depth Lagged time, h;tQuietIt is drilled into total quiescent time of this turn on pump, h from termination of pumping;C drilling tool displacement effect correction factor.
Described formula improves content and includes:
Quiescent time improve: consider drilling fluid quiescent time simultaneously add turn on pump circulation after to the time seeing oil/gas show.
The midway termination of pumping time improves: the oil/gas show flex point time should deduct the time t that pump is switched in midway, be only and really open The oil gas flex point time is seen after pump.
The correction with back-pressure valve for the drilling tool: consider the impact of drilling tool displacement effect, had with oil gas section constant-volume principle:
Wherein h1 is to alter height on the actual oil gas that should ask for, and h2 is the height considering drilling tool displacement effect.
Simultaneously in order to reduce scene using the manual difficulty calculating Ascending Velocity For Oil & Gas and loaded down with trivial details degree, by correlative study, Above-mentioned classics lagged time method and revised lagged time method can by now widely used Microsoft excel.exe software, Carry out automatic measurement & calculation by writing measuring and calculating sentence.
A kind of measuring method of Ascending Velocity For Oil & Gas, the method comprising the steps of:
1) manually ask for the well depth of drill bit circulation position and correspond to the lagged time at bit location under discharge capacity;
2) after asking for lagged time, termination of pumping, record the termination of pumping time, carry out short trip 10-15 column;
3) get into last time under and ask at lagged time position, turn on pump circulates, record Running pump time;
4) during well room observation oil/gas show, write down and start display time, time to peak and end time;
5) calculate termination of pumping respectively to show with oil/gas show time t between the turn on pump quiet stopping time, and determine abnormal oil-gas Layer position;
6) fill in detection parameter according to improvement lagged time method related content, referring to table 1;
7), after asking for correlation computations parameter, calculated using the oil and gas upwelling speed software for calculation of establishment and speed is altered on oil gas Degree, referring to table 2.
Table 1 improves lagged time method and calculates Ascending Velocity For Oil & Gas relevant parameter detection record
Table 2 improves lagged time method and calculates Ascending Velocity For Oil & Gas automation computation sheet
, with discharge capacity 50.32 l/s circulating fluid wellbore clearance 3h, oil-gas Layer top depth is 3572m, records taking x well as a example Lagged time 83min at 3795m circulation position.Determine that the flex point time is oil gas according to oil/gas show process record oil/gas show The display time is 65min, and quiescent time is 15h.The midway termination of pumping time is 0, and live borehole size is 316.5mm, drilling tool size 177.8mm, takes correction factor c to be 0.6844.With aforementioned improved lagged time method formula and drilling tool band back-pressure valve result of calculation Correction formula and execl.exe automation computation sheet, calculating Ascending Velocity For Oil & Gas is 25.53m/h.Using this speed as rear The foundation of continuous operating decision.This well follow-up pull out of hole, well logging, under get into bottom turn on pump circulation used time 54h, in above operation process Logging equipment does not monitor that total hydrocarbon changes, and the well control problem such as overflow.In sum, using slow after of the present invention correction To in the case of Time Method formula and drilling tool band back-pressure valve to result of calculation correction, record Ascending Velocity For Oil & Gas 25.53m/h and meet Field operation needs.
It is last that it is noted that obvious, above-described embodiment is only intended to clearly illustrate example of the present invention, and simultaneously The non-restriction to embodiment.For those of ordinary skill in the field, can also do on the basis of the above description Go out change or the variation of other multi-forms.There is no need to be exhaustive to all of embodiment.And thus drawn The obvious change stretched out or change among still in protection scope of the present invention.

Claims (9)

1. a kind of measuring method of Ascending Velocity For Oil & Gas it is characterised in that: methods described based on conventional lagged time method, Improve and draw, including the measuring and calculating improvement of parameter acquiring method and the improvement of measure formula;Methods described is by Microsoft Excel.exe software, realizes automatic measurement & calculation by writing measuring and calculating sentence.
2. as claimed in claim 1 a kind of measuring method of Ascending Velocity For Oil & Gas it is characterised in that: described measuring and calculating parameter ask for The improvement of method include the display time determine method improve and oil reservoir position judging method improve.
3. as claimed in claim 1 or 2 a kind of measuring method of Ascending Velocity For Oil & Gas it is characterised in that: the described display time The method that determines is improved and is, using one present in total hydrocarbon change procedure significantly from low value to the flex point of too high value changes as aobvious Show the time.
4. as claimed in claim 1 or 2 a kind of measuring method of Ascending Velocity For Oil & Gas it is characterised in that oil reservoir position judgment Method is improved as follows:
1) when only single gas-bearing formation, choose this gas-bearing formation well depth and be used for calculating;
2) when having many gas-bearing formations, judge oil reservoir position by the following method:
A, there are multiple gas-bearing formations relatively far apart, but a certain top gas-bearing formation is more active, always Ascending Velocity For Oil & Gas is had bright Development rings, then this should be selected to enliven gas-bearing formation and be used for calculating;
B, it is multiple peak values to total gas curve, there is the situation of multiple oil-gas Layer, the choosing method of oil-gas Layer is according to oil-gas Layer The total gas curve in figure total hydrocarbon base value drawn before and after distribution situation and actual oil/gas show to be determined to this shadow with change procedure Sound oil-gas Layer top circle the most shallow is as hOilValue.
5. as claimed in claim 1 a kind of measuring method of Ascending Velocity For Oil & Gas it is characterised in that: described formula improves content Improve and the correction with back-pressure valve for the drilling tool including quiescent time improvement, midway termination of pumping time.
6. a kind of Ascending Velocity For Oil & Gas as described in claim 1 or 5 measuring method it is characterised in that: described quiescent time Improvement be it is considered to drilling fluid quiescent time simultaneously add turn on pump circulation after to the time seeing oil/gas show.
7. a kind of Ascending Velocity For Oil & Gas as described in claim 1 or 5 measuring method it is characterised in that: the termination of pumping of described midway Time improvement is that the oil/gas show flex point time should deduct the time t that pump is switched in midway, sees oil gas flex point after being only real turn on pump Time.
8. a kind of Ascending Velocity For Oil & Gas as described in claim 1 or 5 measuring method it is characterised in that: described drilling tool is taken back The correction of pressure valve is it is considered to the impact of drilling tool displacement effect, is had with oil gas section constant-volume principle:
Wherein h1 is to alter height on the actual oil gas that should ask for, and h2 is the height considering drilling tool displacement effect.
9. as claimed in claim 1 a kind of measuring method of Ascending Velocity For Oil & Gas it is characterised in that methods described include following Step:
1) manually ask for the well depth of drill bit circulation position and correspond to the lagged time at bit location under discharge capacity;
2) after asking for lagged time, termination of pumping, record the termination of pumping time, carry out short trip 10-15 column;
3) get into last time under and ask at lagged time position, turn on pump circulates, record Running pump time;
4) during well room observation oil/gas show, write down and start display time, time to peak and end time;
5) calculate termination of pumping respectively to show with oil/gas show time t between the turn on pump quiet stopping time, and determine abnormal oil-gas Layer position;
6) fill in detection parameter according to improvement lagged time method related content;
7), after asking for correlation computations parameter, Ascending Velocity For Oil & Gas are calculated using the calculating instrument relying on excel.exe establishment.
CN201610747268.0A 2016-08-29 2016-08-29 Measuring and calculating method of upwelling speed of oil gas Pending CN106339549A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610747268.0A CN106339549A (en) 2016-08-29 2016-08-29 Measuring and calculating method of upwelling speed of oil gas

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610747268.0A CN106339549A (en) 2016-08-29 2016-08-29 Measuring and calculating method of upwelling speed of oil gas

Publications (1)

Publication Number Publication Date
CN106339549A true CN106339549A (en) 2017-01-18

Family

ID=57822439

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610747268.0A Pending CN106339549A (en) 2016-08-29 2016-08-29 Measuring and calculating method of upwelling speed of oil gas

Country Status (1)

Country Link
CN (1) CN106339549A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107066768A (en) * 2017-06-06 2017-08-18 长江大学 Ascending Velocity For Oil & Gas computational methods
CN110485992A (en) * 2018-05-14 2019-11-22 中国石油化工股份有限公司 One kind being drilled well Ascending Velocity For Oil & Gas calculation method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101139925A (en) * 2006-09-08 2008-03-12 西南石油大学 Method for while-drilling testing reservoir parameter property and adjusting well drilling action in real time
WO2015112522A1 (en) * 2014-01-24 2015-07-30 Caterpillar Inc. Pump system with automated testing

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101139925A (en) * 2006-09-08 2008-03-12 西南石油大学 Method for while-drilling testing reservoir parameter property and adjusting well drilling action in real time
WO2015112522A1 (en) * 2014-01-24 2015-07-30 Caterpillar Inc. Pump system with automated testing

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
宋广健,等: "油气上窜速度计算方法的改进与应用", 《石油钻采工艺》 *
李基伟,等: "油气上窜速度的精确计算方法", 《科学技术与工程》 *
王文忠,等: "油气上窜速度计算公式的修正", 《断块油气田》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107066768A (en) * 2017-06-06 2017-08-18 长江大学 Ascending Velocity For Oil & Gas computational methods
CN110485992A (en) * 2018-05-14 2019-11-22 中国石油化工股份有限公司 One kind being drilled well Ascending Velocity For Oil & Gas calculation method
CN110485992B (en) * 2018-05-14 2021-11-26 中国石油化工股份有限公司 Method for calculating oil gas channeling speed for well drilling and completion

Similar Documents

Publication Publication Date Title
US10030499B2 (en) Geological monitoring console
RU2687668C1 (en) Method and system for combined tracking of a well drilling process
US9091781B2 (en) Method for estimating formation permeability using time lapse measurements
AU2010353772B2 (en) Systems and methods for horizontal well correlation and geosteering
Cleary et al. Experimental and modeling evidence for major changes in hydraulic fracturing design and field procedures
Zlotnik Interpretation of slug and packer tests in anisotropic aquifers
Peters et al. Criteria to determine borehole formation temperatures for calibration of basin and petroleum system models
CN106014387A (en) Bottom hole pressure real-time prediction and control method
CN105178943A (en) Method for correcting well shaft pressure in real time
CN108301825A (en) A kind of high temperature and pressure reservoir pore pressure analysis method
CN106250984A (en) The determination methods of the oil water relation pattern of oil well and device
Liang et al. Intelligent early warning model of early-stage overflow based on dynamic clustering
CN106339549A (en) Measuring and calculating method of upwelling speed of oil gas
EP3368742B1 (en) Tubular wear volume determination using stretch correction
CN110532507A (en) A method of the fine and close oily reservoir Drilling ratio of well of improving the standard
Kalinec et al. Estimation of 3D distribution of pore pressure from surface drilling data-application to optimal drilling and frac hit prevention in the eagle ford
CN104632186A (en) Method and device for detecting and processing secondary well controlling parameters after primary well controlling failure
CN104251135B (en) Highly-deviated well space in-place method
Wutherich et al. Detecting induced fractures using drilling data to gain insights into unconventional fracture growth
Lee et al. Leak-off test interpretation and modeling with application to geomechanics
AlHusseini et al. Estimation Pore and Fracture Pressure Based on Log Data; Case Study: Mishrif Formation/Buzurgan Oilfield at Iraq
CN113803055B (en) Oil-water interface depth determining method and early warning method for preventing production well water channeling
Noah Pore pressure evaluation from well logging and drilling exponent at Amal field, Gulf of Suez area, Egypt
US11248999B2 (en) Method and apparatus for measuring slip velocity of drill cuttings obtained from subsurface formations
Kuroda et al. Field measurement of the formation stress depletion and the pore pressure depletion in the Eagle Ford

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170118