CN106320582A - Improved perforated aluminum sheet curtain wall and installation method thereof - Google Patents

Improved perforated aluminum sheet curtain wall and installation method thereof Download PDF

Info

Publication number
CN106320582A
CN106320582A CN201610835370.6A CN201610835370A CN106320582A CN 106320582 A CN106320582 A CN 106320582A CN 201610835370 A CN201610835370 A CN 201610835370A CN 106320582 A CN106320582 A CN 106320582A
Authority
CN
China
Prior art keywords
bolt
pierced aluminum
aluminum plank
curtain wall
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610835370.6A
Other languages
Chinese (zh)
Other versions
CN106320582B (en
Inventor
陆建兵
余长顺
张中陵
江志林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Huadian construction (Group) Co.,Ltd.
Original Assignee
Nanjing China Construction Decoration Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing China Construction Decoration Engineering Co Ltd filed Critical Nanjing China Construction Decoration Engineering Co Ltd
Priority to CN201610835370.6A priority Critical patent/CN106320582B/en
Publication of CN106320582A publication Critical patent/CN106320582A/en
Application granted granted Critical
Publication of CN106320582B publication Critical patent/CN106320582B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Load-Bearing And Curtain Walls (AREA)
  • Securing Of Glass Panes Or The Like (AREA)

Abstract

The invention discloses an improved perforated aluminum sheet curtain wall. The improved perforated aluminum sheet curtain wall comprises a keel fixed on the wall surface, a bottom plate is fixed to the front face of the keel through first bolts, a nut of each first bolt is located on the back face of the keel, a screw of each first bolt is internally provided with a threaded blind hole, perforated aluminum sheets are fixed above the bottom plate through second bolts which are fixed in the corresponding threaded blind holes, and a first gasket is connected between every two adjacent perforated aluminum sheets through a third bolt. The invention further provides an installation method of the perforated aluminum sheet curtain wall. Accordingly, the deficiencies of the prior art can be improved, and the installation precision of the curtain wall in a complex surface structure is improved.

Description

The Pierced Aluminum Plank curtain wall of a kind of improvement and installation method thereof
Technical field
The present invention relates to technical field of building construction, the Pierced Aluminum Plank curtain wall of a kind of improvement and installation method thereof.
Background technology
Along with the progress of science and technology, high buildings and large mansions are in a compact mass, add decoration to high buildings and large mansions and have become as the modern times and build The important elements built, this just it is also proposed higher requirement to the alien invasion decoration of building curtain wall.Along with the development of building curtain wall, Increasing aluminium sheet starts to apply on the alien invasion of vast building, forms aluminum facade, and the most ripe and perfect, The most more aesthetic feeling.Modern building profile is intricate, building curtain wall alien invasion from unification, Regularization to diversification, multiple Hydridization develops.Original aluminum facade structure cannot meet the demand of the complicated curtain wall of surface texture.
Summary of the invention
The technical problem to be solved in the present invention is to provide Pierced Aluminum Plank curtain wall and the installation method thereof of a kind of improvement, it is possible to solve Certainly the deficiencies in the prior art, improve the installation accuracy of curtain wall in complex surface structures.
For solving above-mentioned technical problem, the technical solution used in the present invention is as follows.
The Pierced Aluminum Plank curtain wall of a kind of improvement, including the Os Draconis being fixed on metope, by first on described Os Draconis front Bolt is fixed with base plate, and the nut of the first bolt is positioned at the Os Draconis back side, is provided with tapped blind hole, base plate in the screw rod of the first bolt Top be fixed with Pierced Aluminum Plank by the second bolt, second is bolted in tapped blind hole, before adjacent Pierced Aluminum Plank Connected by the 3rd bolt and have the first pad.
As preferably, described Os Draconis include several rectangular framework, are fixed with the first reinforcement in each rectangular framework, the One reinforcement is arranged along any one diagonal of rectangular framework, and the first reinforcement is provided above first connecting rod, first connecting rod Two ends are connected on rectangular framework another one diagonal by the first spring body, arrange between the first reinforcement and first connecting rod There is the second spring body.
As preferably, described first is bolted on the first reinforcement, and base plate contacts with first connecting rod.
As preferably, the outside of described second bolt connects flexible metallic sheath, elastic metallic set by the second block rubber Length be from top to bottom gradually increased more than the length of the second bolt, the internal diameter of elastic metallic set, the bottom of elastic metallic set sets Being equipped with several breach, the inner side of breach is provided with metal clips, and metal clips top is provided with the first block rubber, when the second spiral shell When bolt is connected with tapped blind hole, the outer wall of the first block rubber and the first bolt contacts.
As preferably, described first pad includes the groove contacted with Pierced Aluminum Plank, is in aluminum of boring a hole above groove The safe edge of plate top surface, the lower section of groove is in the fixing end of Pierced Aluminum Plank bottom surface, fixing end is provided with and wears for the 3rd bolt The through hole crossed, is provided with rubber layer in groove, the lower section of rubber layer is provided with two support columns, and support column passes through the second connecting rod Being connected to runner, runner shaft is connected in the first pad.
As preferably, between adjacent bottom plates, it is filled with rubber strip.
The installation method of the Pierced Aluminum Plank curtain wall of a kind of above-mentioned improvement, comprises the following steps:
A, by base plate paving on Os Draconis, use the first bolt that base plate is pre-fixed;
B, on base plate place foam cushion block, set Pierced Aluminum Plank on foam cushion block upper berth and use the second bolt that Pierced Aluminum Plank is carried out Pre-fix;
C, between Pierced Aluminum Plank, place the first pad, the first bolt and the second bolt are locked, when second the most simultaneously When the locking torque of bolt reaches the 80% of standard torque, foam cushion block is removed, then the first bolt is continued locking to standard Moment of torsion;Then the position of Pierced Aluminum Plank is adjusted, uses the 3rd bolt that the first pad is pre-fixed;Then by second Bolt continues locking to standard torque;Finally again the position of Pierced Aluminum Plank is adjusted, then the 3rd bolt is continued lock Tight to standard torque.
What employing technique scheme was brought has the beneficial effects that: the present invention is by arranging two-layer laying structure, base plate Upper strata Pierced Aluminum Plank can be corrected and support, improve the uniformity of whole Pierced Aluminum Plank support force.Second bolt is solid It is scheduled in the first bolt, it is possible to use outside the first bolt and the raising of the fixed connection structure of Os Draconis, Pierced Aluminum Plank installation is firm Degree.First reinforcement can improve the rigidity of Os Draconis, and first connecting rod is used for the vibration between Os Draconis and base plate and installation process Elastic deformation buffer.Elastic metallic set outside second bolt can be to the first bolt and second during locking Produce positioning action between bolt and base plate, improve the stability that the first bolt and the second bolt are fixing.First pad is used for real Show the levelling function between different Pierced Aluminum Planks in Pierced Aluminum Plank installation process.
Accompanying drawing explanation
Fig. 1 is the structure chart of one detailed description of the invention of the present invention.
Fig. 2 is the structure chart of Os Draconis in one detailed description of the invention of the present invention.
Fig. 3 is the structure chart of one detailed description of the invention Elastic metallic sheath of the present invention.
Fig. 4 is the structure chart of the first pad in one detailed description of the invention of the present invention.
In figure: 1, Os Draconis;2, the first bolt;3, base plate;4, tapped blind hole;5, the second bolt;6, Pierced Aluminum Plank;7, first Pad;8, the 3rd bolt;9, the first reinforcement;10, first connecting rod;11, the first spring body;12, the second spring body;13, elastic Metallic sheath;14, breach;15, metal clips;16, the first block rubber;17, the second block rubber;18, safe edge;19, fixing end;20、 Through hole;21, rubber layer;22, support column;23, the second connecting rod;24, runner;25, rubber strip;26, torsion spring;27, groove;28、 Rectangular framework.
Detailed description of the invention
The standardized element that uses in the present invention all can commercially, shaped piece according to description and accompanying drawing Record all can carry out customized, and the concrete connected mode of each part all uses the bolt of maturation, rivet, weldering in prior art Connect, the conventional means such as stickup, be not described in detail in this.
With reference to Fig. 1-4, one detailed description of the invention of the present invention includes the Os Draconis 1 being fixed on metope, described Os Draconis 1 front On be fixed with base plate 3 by the first bolt 2, the nut of the first bolt 2 is positioned at Os Draconis 1 back side, arranges in the screw rod of the first bolt 2 Having tapped blind hole 4, the top of base plate 3 is fixed with Pierced Aluminum Plank 6 by the second bolt 5, and the second bolt 5 is fixed on tapped blind hole 4 In, connected by the 3rd bolt 8 before adjacent Pierced Aluminum Plank 6 and have the first pad 7.Os Draconis 1 include several rectangular framework 28, Being fixed with the first reinforcement 9 in each rectangular framework 28, the first reinforcement 9 is arranged along any one diagonal of rectangular framework 28, First reinforcement 9 is provided above first connecting rod 10, and the two ends of first connecting rod 10 are connected to rectangle bone by the first spring body 11 On frame 28 another one diagonal, between the first reinforcement 9 and first connecting rod 10, it is provided with the second spring body 12.First bolt 2 Being fixed on the first reinforcement 9, base plate 3 contacts with first connecting rod 10.The outside of the second bolt 5 is by the second block rubber 17 even Being connected to elastic metallic set 13, the length of elastic metallic set 13 is more than the length of the second bolt 5, and the internal diameter of elastic metallic set 13 is by upper Being gradually increased under to, the bottom of elastic metallic set 13 is provided with several breach 14, and the inner side of breach 14 is provided with metal clips 15, metal clips 5 top is provided with the first block rubber 16, when the second bolt 5 is connected with tapped blind hole 4, and the first block rubber 16 Contact with the outer wall of the first bolt 2.First pad 7 includes the groove 27 contacted with Pierced Aluminum Plank 6, is position above groove 27 In the safe edge 18 of Pierced Aluminum Plank 6 end face, the lower section of groove 27 is in the fixing end 19 of Pierced Aluminum Plank 6 bottom surface, on fixing end 19 Being provided with the through hole 20 passed for the 3rd bolt 8, be provided with rubber layer 21 in groove 27, the lower section of rubber layer 21 is provided with two Support column 22, support column 22 is connected to runner 24 by the second connecting rod 23, and runner 24 axle is connected in the first pad 7.The adjacent end Rubber strip 25 it is filled with between plate 3.
It addition, be provided with torsion spring 26 in the junction of support column 22 and the second connecting rod 23, torsion spring 26 is used for limiting support The rotation of post 22, and provide elastic restoring force to the support column 22 rotated.
The installation method of the Pierced Aluminum Plank curtain wall of above-mentioned improvement, comprises the following steps:
A, base plate 3 is laid on Os Draconis 1, uses the first bolt 2 that base plate 3 is pre-fixed;
B, on base plate 3 place foam cushion block, set Pierced Aluminum Plank 6 on foam cushion block upper berth and use the second bolt 5 to Pierced Aluminum Plank 6 Pre-fix;
C, between Pierced Aluminum Plank 6, place the first pad 7, the first bolt 2 and the second bolt 5 are locked the most simultaneously, when When the locking torque of the second bolt 5 reaches the 80% of standard torque, foam cushion block is removed, then the first bolt 2 is continued locking To standard torque;Then the position of Pierced Aluminum Plank 6 is adjusted, uses the 3rd bolt 8 that first pad 7 is pre-fixed; Then the second bolt 5 is continued locking to standard torque;Finally again the position of Pierced Aluminum Plank 6 is adjusted, then by Three bolts 8 continue locking to standard torque.
The present invention is applicable to the curtain wall of labyrinth and installs.The installation accuracy of curtain wall is high, and the life-span is long.
In describing the invention, it is to be understood that term " longitudinally ", " laterally ", " on ", D score, "front", "rear", The orientation of the instruction such as "left", "right", " vertically ", " level ", " top ", " end ", " interior ", " outward " or position relationship are for based on accompanying drawing institute The orientation shown or position relationship, be for only for ease of and describe the present invention rather than instruction or imply that the device of indication or element must Must have specific orientation, with specific azimuth configuration and operation, be therefore not considered as limiting the invention.
The ultimate principle of the present invention and principal character and advantages of the present invention have more than been shown and described.The technology of the industry Personnel, it should be appreciated that the present invention is not restricted to the described embodiments, simply illustrating this described in above-described embodiment and description The principle of invention, without departing from the spirit and scope of the present invention, the present invention also has various changes and modifications, and these become Change and improvement both falls within scope of the claimed invention.Claimed scope by appending claims and Equivalent defines.

Claims (7)

1. the Pierced Aluminum Plank curtain wall improved, including the Os Draconis (1) being fixed on metope, it is characterised in that: described Os Draconis (1) Being fixed with base plate (3) by the first bolt (2) on front, the nut of the first bolt (2) is positioned at Os Draconis (1) back side, the first bolt (2) being provided with tapped blind hole (4) in screw rod, the top of base plate (3) is fixed with Pierced Aluminum Plank (6) by the second bolt (5), the Two bolts (5) are fixed in tapped blind hole (4), and being connected by the 3rd bolt (8) before adjacent Pierced Aluminum Plank (6) has the first pad Sheet (7).
The Pierced Aluminum Plank curtain wall of improvement the most according to claim 1, it is characterised in that: described Os Draconis (1) include several Rectangular framework (28), is fixed with the first reinforcement (9) in each rectangular framework (28), the first reinforcement (9) is along rectangular framework (28) any one diagonal is arranged, and the first reinforcement (9) is provided above first connecting rod (10), the two ends of first connecting rod (10) It is connected on rectangular framework (28) another one diagonal by the first spring body (11), the first reinforcement (9) and first connecting rod (10) the second spring body (12) it is provided with between.
The Pierced Aluminum Plank curtain wall of improvement the most according to claim 2, it is characterised in that: described first bolt (2) is fixed on On first reinforcement (9), base plate (3) contacts with first connecting rod (10).
The Pierced Aluminum Plank curtain wall of improvement the most according to claim 1, it is characterised in that: the outside of described second bolt (5) Connecting flexible metallic sheath (13) by the second block rubber (17), the length of elastic metallic set (13) is more than the second bolt (5) Length, the internal diameter of elastic metallic set (13) is from top to bottom gradually increased, and the bottom of elastic metallic set (13) is provided with several and lacks Mouth (14), the inner side of breach (14) is provided with metal clips (15), and metal clips (5) top is provided with the first block rubber (16), When the second bolt (5) is connected with tapped blind hole (4), the first block rubber (16) contacts with the outer wall of the first bolt (2).
The Pierced Aluminum Plank curtain wall of improvement the most according to claim 4, it is characterised in that: described first pad (7) include with The groove (27) that Pierced Aluminum Plank (6) contacts, groove (27) top is in the safe edge (18) of Pierced Aluminum Plank (6) end face, groove (27) lower section is in the fixing end (19) of Pierced Aluminum Plank (6) bottom surface, fixing end (19) is provided with and wears for the 3rd bolt (8) The through hole (20) crossed, is provided with rubber layer (21) in groove (27), the lower section of rubber layer (21) is provided with two support columns (22), Support column (22) is connected to runner (24) by the second connecting rod (23), and runner (24) axle is connected in the first pad (7).
The Pierced Aluminum Plank curtain wall of improvement the most according to claim 1, it is characterised in that: adjacent bottom plates is filled with between (3) Rubber strip (25).
7. the installation method of the Pierced Aluminum Plank curtain wall of the improvement described in a claim 1-6 any one, it is characterised in that bag Include following steps:
A, base plate (3) is laid on Os Draconis (1), uses the first bolt (2) that base plate (3) is pre-fixed;
B, place foam cushion block base plate (3) is upper, set Pierced Aluminum Plank (6) on foam cushion block upper berth and use the second bolt (5) to wearing Hole aluminium sheet (6) pre-fixes;
C, between Pierced Aluminum Plank (6), place the first pad (7), the first bolt (2) and the second bolt (5) are carried out the most simultaneously Locking, when the locking torque of the second bolt (5) reaches the 80% of standard torque, removes foam cushion block, then by the first bolt (2) locking is continued to standard torque;Then the position of Pierced Aluminum Plank (6) is adjusted, uses the 3rd bolt (8) to the first pad Sheet (7) pre-fixes;Then the second bolt (5) is continued locking to standard torque;Position to Pierced Aluminum Plank (6) the most again Put and be adjusted, then the 3rd bolt (8) is continued locking to standard torque.
CN201610835370.6A 2016-09-21 2016-09-21 A kind of improved Pierced Aluminum Plank curtain wall and its installation method Active CN106320582B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610835370.6A CN106320582B (en) 2016-09-21 2016-09-21 A kind of improved Pierced Aluminum Plank curtain wall and its installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610835370.6A CN106320582B (en) 2016-09-21 2016-09-21 A kind of improved Pierced Aluminum Plank curtain wall and its installation method

Publications (2)

Publication Number Publication Date
CN106320582A true CN106320582A (en) 2017-01-11
CN106320582B CN106320582B (en) 2018-11-02

Family

ID=57786851

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610835370.6A Active CN106320582B (en) 2016-09-21 2016-09-21 A kind of improved Pierced Aluminum Plank curtain wall and its installation method

Country Status (1)

Country Link
CN (1) CN106320582B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202380612U (en) * 2011-11-28 2012-08-15 南京金中建幕墙装饰有限公司 Combined type clamp for perforated splint of point-supported glass curtain wall
CN202969643U (en) * 2012-10-26 2013-06-05 沈阳远大铝业工程有限公司 Hidden type connecting structure of large-aperture perforated plate
CN104100027A (en) * 2014-07-31 2014-10-15 蒋凤昌 Four-claw positioning clamp and method for mounting perforated aluminum plate curtain wall
CN204326330U (en) * 2014-12-12 2015-05-13 江苏龙升节能科技股份有限公司 Double-layer Opening Pierced Aluminum Plank curtain wall system
KR101545267B1 (en) * 2014-08-11 2015-08-21 이장호 Wire curtain wall for construction
CN205557941U (en) * 2016-02-19 2016-09-07 江苏通州四建集团有限公司 Outer wall perforation aluminum curtain wall
CN205577201U (en) * 2016-05-05 2016-09-14 南京华典建筑装饰工程有限公司 Modified curtain installation component
CN205577196U (en) * 2016-04-27 2016-09-14 南京华典建筑装饰工程有限公司 Connecting device for glass curtain wall

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202380612U (en) * 2011-11-28 2012-08-15 南京金中建幕墙装饰有限公司 Combined type clamp for perforated splint of point-supported glass curtain wall
CN202969643U (en) * 2012-10-26 2013-06-05 沈阳远大铝业工程有限公司 Hidden type connecting structure of large-aperture perforated plate
CN104100027A (en) * 2014-07-31 2014-10-15 蒋凤昌 Four-claw positioning clamp and method for mounting perforated aluminum plate curtain wall
KR101545267B1 (en) * 2014-08-11 2015-08-21 이장호 Wire curtain wall for construction
CN204326330U (en) * 2014-12-12 2015-05-13 江苏龙升节能科技股份有限公司 Double-layer Opening Pierced Aluminum Plank curtain wall system
CN205557941U (en) * 2016-02-19 2016-09-07 江苏通州四建集团有限公司 Outer wall perforation aluminum curtain wall
CN205577196U (en) * 2016-04-27 2016-09-14 南京华典建筑装饰工程有限公司 Connecting device for glass curtain wall
CN205577201U (en) * 2016-05-05 2016-09-14 南京华典建筑装饰工程有限公司 Modified curtain installation component

Also Published As

Publication number Publication date
CN106320582B (en) 2018-11-02

Similar Documents

Publication Publication Date Title
CN206942035U (en) A kind of metope integration installation structure
CN107700710B (en) Fill wall construction column template design checking and construction method
CN104895318A (en) Aluminum alloy template system and construction method of same
CN111677163B (en) Construction method of glass curtain wall
CN101413334B (en) Architecture art embossment stone wall surface dried hanging structure and construction method thereof
CN104763123B (en) Unit assembling type installation method of irregular arc-shaped GRG decoration board
CN103334564B (en) The method of wall brick mounting structure and installation wall brick
CN105971272A (en) Fabricated type reinforced concrete constructional column adopting aluminum templates and block filling wall and construction method
CN103437475A (en) Construction method of architectural structure gypsum board with paper surface hung ceiling
CN108894488A (en) A kind of construction method of Novel section steel keel steel and wood composite template
CN110005192A (en) Concrete floor aluminium, plank sheathing splicing construction and its installation method
CN104631663A (en) Lightgage steel joist composite wall body and construction technology
CN106337516A (en) Construction method of light-steel keel partition wall
CN105637159A (en) Formwork element
CN206477577U (en) A kind of door-window opening mould in building structure construction
CN106437146A (en) Template used for casting floor beam and construction method of floor beam
CN106320582A (en) Improved perforated aluminum sheet curtain wall and installation method thereof
CN117211554A (en) Restoration method for ancient building wall
CN104389348B (en) A kind of installation method with covering arch structure
CN103850374B (en) Element type curtain wall system
US3138230A (en) Window sill structures
CN101476374B (en) Reinforcement apparatus for stair step plate, step plate with the same and its production method
CN210342560U (en) Dry-type worker method aerial decoration subassembly
CN209457376U (en) Structural wall boundary Template Location fixed structure
CN205025087U (en) Closed stair steel form device of clear water concrete saw flute profile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 210000 C3 District, science and Technology Park, science and Technology University, 1 Guanghua Road, Qinhuai District, Nanjing, Jiangsu

Applicant after: Nanjing Huadian Construction Co., Ltd.

Address before: 210000 C3 District, science and Technology Park, science and Technology University, 1 Guanghua Road, Qinhuai District, Nanjing, Jiangsu

Applicant before: Nanjing China Construction Decoration Engineering Co., Ltd.

GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 210000 C3 District, science and Technology Park, science and Technology University, 1 Guanghua Road, Qinhuai District, Nanjing, Jiangsu

Patentee after: Nanjing Huadian construction (Group) Co.,Ltd.

Address before: 210000 C3 District, science and Technology Park, science and Technology University, 1 Guanghua Road, Qinhuai District, Nanjing, Jiangsu

Patentee before: NANJING HUADIAN CONSTRUCTION Co.,Ltd.