CN106320261B - A kind of construction method of overlength basin slope excavating - Google Patents
A kind of construction method of overlength basin slope excavating Download PDFInfo
- Publication number
- CN106320261B CN106320261B CN201610705078.2A CN201610705078A CN106320261B CN 106320261 B CN106320261 B CN 106320261B CN 201610705078 A CN201610705078 A CN 201610705078A CN 106320261 B CN106320261 B CN 106320261B
- Authority
- CN
- China
- Prior art keywords
- slope
- construction
- excavating
- side slope
- reamer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F5/00—Dredgers or soil-shifting machines for special purposes
- E02F5/28—Dredgers or soil-shifting machines for special purposes for cleaning watercourses or other ways
- E02F5/282—Dredgers or soil-shifting machines for special purposes for cleaning watercourses or other ways with rotating cutting or digging tools
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Revetment (AREA)
Abstract
The present invention relates to a kind of construction methods of overlength basin slope excavating, include the following steps:1) wire drag survey, is carried out to existing Qu Ni areas, especially side slope region before formal construction, sorts out accurate slope excavating area fathogram;2), all slope excavating areas depth of water is analyzed, formulates slope excavating technique;Site operations are carried out according to the actual conditions of side slope rule or irregular two kinds of slope construction techniques of formulation, two kinds of slope construction techniques are slope surface hobboing cutter excavating load or stage excavation method;3) science division, is carried out for the applicable side slope of two kinds of technique, side slope is approximately separated into the region that several pieces are applicable in different process;4), polytechnic slitting condition of construction carries out classifying rationally according to the width of each section of side slope;5), the construction technology tissue site operation of different slope excavatings is taken in site tissue subregion.The present invention have field operation slope excavating scheme, on the basis of original productivity, when interest rate it is constant under the premise of, effectively improve more than 20% productivity.
Description
Technical field
The invention belongs to dredging and reclamation technical field, more particularly to a kind of construction method of overlength basin slope excavating.
Background technology
First, basic condition
The development of China's dredging industry has the history of centuries, is quickly sent out in economic globalization tide and international trade
Under the promotion of exhibition, to adapt to the demand of container and tanker enlargement development, China various regions are built harbour, are widened simultaneously one after another
Deep coastal waterway is dug, to improve Navigation capacity, dredging industry has obtained quick development.At the same time, with harbour, navigation channel,
Irrigation and water conservancy and the development in coastal cities, dredging operation field have also obtained largely extending, from traditional harbor approach
Dredging and maintenance, rivers and lakes are administered and water conservancy projects is built, and successively expands to irrigation and water conservancy and reservoir construction and maintenance, national defence
The fields such as engineering construction, environmental protection dredging, land reclamation.
In future, China's dredging work industry will keep fast-developing, and in ship dredging construction, slope excavating construction will be more next
It is more.
The either dredging of port boat or water conservancy, the dredging of environmental protection aspect all suffers from a large amount of slope excavating, and overlength
The operating mode of slope excavating also will be more complicated.To handle these targets, it is necessary to improve waterway construction technical merit, navigation channel is accelerated to build
If with management modernization.Devoting Major Efforts To Developing is wanted using navigation channel canalization, regulation, dredging complete set technology;It is planned in waterway engineering, exploration,
In design, research, construction, management, implement science, specification, efficient dynamic and manage.Active adoption GPS, GIS remote sensing, communication,
The new and high technologies such as computer and control technology;Improve dredging vessel equipment level and dredging technology modernization level.
But at present for different soil properties and slope than excavation technology also lack the analysis of system, in particular for overlength
Slope excavating also lacks the scope of application of various process programs and reasonably defines, up for further studying.
2nd, existing construction method there are the problem of
The not analysis Jing Guo system of existing overlength slope construction, all slope excavatings mostly with same construction technology into
Row, being mostly need not be without effective construction organization, and planless guiding theory, science, does not be easy to cause the high cost operation of ship machine,
It is unfavorable for improving project progress.
Slope construction quality is checked and accepted as dredging work, and an important content of quality grade evaluation standard, is always thin
Dredge the most important thing of Engineering Quality Control.Slope construction quality problems are mainly reflected in two aspects, backbreak and owe to dig.
1st, it backbreaks, on the one hand can cause unnecessary useless side, influence the production efficiency of workboat;
2nd, the side slope near Special zone, such as shore protection, harbour, breakwater building is constructed, and is backbreak excessive, easily
Jeopardize the safety of building, form safety accident.
3rd, it owes to dig excessively, then need to move ship or ship is adjusted to carry out secondary excavation, not only reduce the production efficiency of workboat, simultaneously
Construction cost is also added, after carrying out secondary excavation, is also easily formed and backbreak.
4th, it twists and inhales ship construction operation, the depth and flatness quality in grooving are generally relatively easy to control, the construction quality of appearance
Problem is largely focused on slope excavating region.
Therefore, it is necessary to be proved in detail the various factors for causing to twist suction ship slope construction quality, seek solution and arrange
It applies.
Invention content
The present invention provides a kind of raising productivity to solve technical problem present in known technology, ensures construction peace
Entirely, the construction method of the simply specific overlength basin slope excavating of method.
The present invention is adopted the technical scheme that solve technical problem present in known technology:
A kind of construction method of overlength basin slope excavating, it is characterised in that:Include the following steps:
1) wire drag survey, is carried out to existing Qu Ni areas, especially side slope region before formal construction, is sorted out accurate
Slope excavating area fathogram;
2), all slope excavating areas depth of water is analyzed, formulates slope excavating technique;It is advised according to the actual conditions of side slope
Then or irregular two kinds of slope construction techniques of formulation carry out site operations, and two kinds of slope construction techniques are slope surface hobboing cutter excavating load
Or stage excavation method;
3), existing side slope situation is analyzed, science division is carried out for the applicable side slope of two kinds of technique, side slope is big
Cause is divided into the region that several pieces are applicable in different process;
4), polytechnic slitting condition of construction carries out classifying rationally according to the width of each section of side slope;
5), the construction technology tissue site operation of different slope excavatings is taken in site tissue subregion.
The present invention can also use following technical measures:
The slope surface hobboing cutter excavating load is applicable in more regular slope surface, first using excavation section by section slope surface, again will after the completion
Remaining slot insied width carries out slitting, carries out clearing up in slot one by one:Its technical process is as follows:
2.1) construction item is divided for side slope position;
2.2) ship construction center line is determined;
2.3) ship presses center line spread in position;
2.4) reamer is transferred to planned depth;
2.5) to line of slope traversing construction;
2.6) it is traversing in the process with slope line elevated height reamer;
2.7) reamer is to bench crest rear chassis drilling depth;
2.8) backswing reamer and in the process with slope line height transfer reamer;
2.9) (or designated position) trolley drilling depth after reamer to leg wire of slope;
2.10) step 2.5-2.6-2.7-2.8-2.9 is repeated to completing this trolley.
The stage excavation method is applicable in that earth volume is more, and mud layer thickness is at 4~8 meters, local You Qian areas;It first will be according to mud
Slope surface is divided into step by matter feature, and lower super deficient excavation slope makes the earthwork cave in naturally and forms slope surface, and slot is interior and side slope
Slitting construction in layer successively, technical process are as follows:
2.10) numbers of steps is divided;
2.20) construction slitting is determined;
2.30) ship presses planning center line spread in position;
2.40) it is successively constructed according to the boundary per step and cutting depth when constructing.
The invention has the advantages and positive effects that:The present invention is had the following advantages using above-mentioned technical proposal:
1st, explore a set of slope excavating scheme with field operation, on the basis of original productivity, when it is sharp
Under the premise of rate is constant, more than 20% productivity is effectively improved;
2nd, strive for that the amount of backbreaking complies fully with detail design requirement, avoids unnecessary useless side after slope excavating construction, will dredge
Dredge maximizing the benefits;
3rd, for overlength side slope situation complexity, using the method for simplifying side slope type, a variety of situations are set using different
Construction method, it is ensured that method is simply clear and definite.
4th, monitoring unit is coordinated to carry out embankment STABILITY MONITORING during side slope ship dredging construction, it is ensured that construction safety.
5th, it is layered according to geologic information and on-site actual situations side slope, productivity is maintained into higher level.
Description of the drawings
Fig. 1 is 1 slope construction floor map of embodiment;
Fig. 2 is 1 slope construction reamer position view of embodiment;
Fig. 3 is that 1 cutter suction dredger slope surface of embodiment excavates reamer distance and high process control;
Fig. 4 is the interior construction schematic diagram of progress slot after the completion of 1 slope surface of embodiment;
Fig. 5 is 2 stratified construction of embodiment and step partition structure schematic diagram.
Specific embodiment
In order to further understand the content, features and effects of the present invention, the following examples are hereby given, and coordinate attached drawing
Detailed description are as follows:
Embodiment 1, please refers to Fig.1 to Fig.4, and the main construction for the more regular overlength basin slope excavating of slope surface is appointed
Business feature is swept shallow to arrange slope surface and region, and according to such feature, the construction technology taken is uses slope surface excavating load first
Remaining slot insied width is carried out slitting by excavation section by section slope surface again after the completion, carries out clearing up in slot one by one.Specifically include following step
Suddenly:
1) wire drag survey, is carried out to existing Qu Ni areas, especially side slope region before formal construction, is sorted out accurate
Slope excavating area fathogram;
2), all slope excavating areas depth of water is analyzed, formulates slope excavating technique;It is advised according to the actual conditions of side slope
Slope surface hobboing cutter excavating load is then selected to be excavated, mainly using following technical process:
2.1) construction item is divided for side slope position;
2.2) ship construction center line is determined;
2.3) ship presses center line spread in position;
2.4) reamer is transferred to planned depth;
2.5) to line of slope traversing construction;
2.6) it is traversing in the process with slope line elevated height reamer;
2.7) reamer is to bench crest rear chassis drilling depth;
2.8) backswing reamer and in the process with slope line height transfer reamer;
2.9) (or designated position) trolley drilling depth after reamer to leg wire of slope;
2.10) step 2.5-2.6-2.7-2.8-2.9 is repeated to completing this trolley.
3), existing side slope situation is analyzed, science division is carried out for the applicable side slope of two kinds of technique, side slope is big
Cause is divided into the region that several pieces are applicable in different process;
4), polytechnic slitting condition of construction carries out classifying rationally according to the width of each section of side slope;
5), the construction technology tissue site operation of different slope excavatings is taken in site tissue subregion.
Embodiment 2, referring to Fig. 5, more for slope surface earth volume, at 4~8 meters, local You Qian areas surpass mud layer thickness
The construction technology that long basin slope excavating is taken is staged stage excavation technique;Slope surface will be divided according to shale feature first
For step, lower super deficient excavation slope makes the earthwork cave in naturally and forms slope surface, applied in slot with the layering of side slope successively slitting
Work;Its technical process is as follows:Include the following steps:
1) wire drag survey, is carried out to existing Qu Ni areas, especially side slope region before formal construction, is sorted out accurate
Slope excavating area fathogram;
2), all slope excavating areas depth of water is analyzed, formulates slope excavating technique;According to the irregular selection of side slope
Stage excavation method;Its technical process is as follows:
2.10) numbers of steps is divided;
2.20) construction slitting is determined;
2.30) ship presses planning center line spread in position;
2.40) it is successively constructed according to the boundary per step and cutting depth when constructing.
3), existing side slope situation is analyzed, science division is carried out for the applicable side slope of two kinds of technique, side slope is big
Cause is divided into the region that several pieces are applicable in different process;
4), polytechnic slitting condition of construction carries out classifying rationally according to the width of each section of side slope;
5), the construction technology tissue site operation of different slope excavatings is taken in site tissue subregion.
It is had the following advantages using above-mentioned technical proposal:
1st, explore a set of slope excavating scheme with field operation, on the basis of original productivity, when it is sharp
Under the premise of rate is constant, more than 20% productivity is effectively improved;
2nd, strive for that the amount of backbreaking complies fully with detail design requirement, avoids unnecessary useless side after slope excavating construction, will dredge
Dredge maximizing the benefits;
3rd, for overlength side slope situation complexity, using the method for simplifying side slope type, a variety of situations are set using different
Construction method, it is ensured that method is simply clear and definite.
4th, monitoring unit is coordinated to carry out embankment STABILITY MONITORING during side slope ship dredging construction, it is ensured that construction safety.
5th, it is layered according to geologic information and on-site actual situations side slope, productivity is maintained into higher level.
The above is only the preferred embodiments of the present invention, and not makees limitation in any form to the present invention,
Any simple modification made to the above embodiment of every technical spirit according to the present invention, equivalent variations and modification, belong to
In the range of technical solution of the present invention.
Claims (3)
1. a kind of construction method of overlength basin slope excavating, it is characterised in that:Include the following steps:
1) wire drag survey, is carried out to the side slope region in existing Qu Ni areas before formal construction, accurate side slope is sorted out and opens
Dig area's fathogram;
2), all slope excavating areas depth of water is analyzed, formulates slope excavating technique;According to the actual conditions of side slope rule or
Person irregularly formulates two kinds of slope construction techniques and carries out site operation, and two kinds of slope construction techniques is slope surface hobboing cutter excavating loads or divide
Layer excavating load;
3), existing side slope situation is analyzed, science division is carried out for the applicable side slope of two kinds of technique, side slope is substantially drawn
It is divided into the region that several pieces are applicable in different process;
4), polytechnic slitting condition of construction carries out classifying rationally according to the width of each section of side slope;
5), the construction technology tissue site operation of different slope excavatings is taken in site tissue subregion.
2. the construction method of overlength basin slope excavating according to claim 1, it is characterised in that:The slope surface hobboing cutter is opened
Digging method is applicable in more regular slope surface, and first using excavation section by section slope surface, remaining slot insied width is carried out slitting again after the completion, by
Item cleared up in slot:Its technical process is as follows:
2.1) construction item is divided for side slope position;
2.2) ship construction center line is determined;
2.3) ship presses center line spread in position;
2.4) reamer is transferred to planned depth;
2.5) to line of slope traversing construction;
2.6) it is traversing in the process with slope line elevated height reamer;
2.7) reamer is to bench crest rear chassis drilling depth;
2.8) backswing reamer and in the process with slope line height transfer reamer;
2.9) reamer is to leg wire of slope rear chassis drilling depth;
2.10) step 2.5-2.6-2.7-2.8-2.9 is repeated to completing this trolley.
3. the construction method of overlength basin slope excavating according to claim 1, it is characterised in that:The stage excavation method
Applicable earth volume is more, and mud layer thickness is at 4~8 meters, local You Qian areas;To slope surface be divided by step according to shale feature first
Formula, lower super deficient excavation slope, makes the earthwork cave in naturally and forms slope surface, with side slope successively slitting construction in layer in slot, lead
Want technological process as follows:
2.10) numbers of steps is divided;
2.20) construction slitting is determined;
2.30) ship presses planning center line spread in position;
2.40) it is successively constructed according to the boundary per step and cutting depth when constructing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610705078.2A CN106320261B (en) | 2016-08-22 | 2016-08-22 | A kind of construction method of overlength basin slope excavating |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610705078.2A CN106320261B (en) | 2016-08-22 | 2016-08-22 | A kind of construction method of overlength basin slope excavating |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106320261A CN106320261A (en) | 2017-01-11 |
CN106320261B true CN106320261B (en) | 2018-06-08 |
Family
ID=57741869
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610705078.2A Active CN106320261B (en) | 2016-08-22 | 2016-08-22 | A kind of construction method of overlength basin slope excavating |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106320261B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836181B (en) * | 2017-01-12 | 2020-02-18 | 中交天航南方交通建设有限公司 | Filling and enclosing construction method for hydraulic filling construction |
CN106894384A (en) * | 2017-03-02 | 2017-06-27 | 浙江海洋大学 | It is a kind of in case silt groove prevent channel maintenance method of the point bar to channel accretion |
CN109750706B (en) * | 2019-03-12 | 2020-08-25 | 中交天津航道局有限公司 | Single-layer multi-footage automatic dredging control method for cutter suction dredger |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1191258A (en) * | 1997-02-21 | 1998-08-26 | 同济大学 | Time-space effect method for excavation of foundation pit |
CN102535474A (en) * | 2010-12-13 | 2012-07-04 | 五冶集团上海有限公司 | Construction method for deep-foundation pit excavation |
CN102828517A (en) * | 2012-08-30 | 2012-12-19 | 中铁十三局集团第三工程有限公司 | Hierarchical control construction method of foundation pit excavation at entrance and exit of station |
CN103510520A (en) * | 2013-10-09 | 2014-01-15 | 上海市建工设计研究院有限公司 | Sectionalized construction method of deep and large foundation pit |
KR101605332B1 (en) * | 2015-08-18 | 2016-03-22 | 주식회사 토영기술단 | Construction method of stabilizing slope area using mineral fiber fabric form |
-
2016
- 2016-08-22 CN CN201610705078.2A patent/CN106320261B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1191258A (en) * | 1997-02-21 | 1998-08-26 | 同济大学 | Time-space effect method for excavation of foundation pit |
CN102535474A (en) * | 2010-12-13 | 2012-07-04 | 五冶集团上海有限公司 | Construction method for deep-foundation pit excavation |
CN102828517A (en) * | 2012-08-30 | 2012-12-19 | 中铁十三局集团第三工程有限公司 | Hierarchical control construction method of foundation pit excavation at entrance and exit of station |
CN103510520A (en) * | 2013-10-09 | 2014-01-15 | 上海市建工设计研究院有限公司 | Sectionalized construction method of deep and large foundation pit |
KR101605332B1 (en) * | 2015-08-18 | 2016-03-22 | 주식회사 토영기술단 | Construction method of stabilizing slope area using mineral fiber fabric form |
Also Published As
Publication number | Publication date |
---|---|
CN106320261A (en) | 2017-01-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Li et al. | A review on anthropogenic geomorphology | |
CN106337426B (en) | It is a kind of to increase the anti-prominent precipitation method for gushing stability of artesian water stratum foundation pit | |
CN106320261B (en) | A kind of construction method of overlength basin slope excavating | |
CN101906771B (en) | Three-dimensional soil texture analyzing method for assisting survey, design and construction of dredging engineering | |
CN101422094A (en) | Thick-bed mining subsidence-land dynamic pre-reclamation method at plane mining-area | |
CN102862775B (en) | Distributed storage method of underground water of mine | |
CN109138023A (en) | A kind of continuous wall trench underground method under complex geological condition | |
CN105421286B (en) | A kind of backhoe type dredger is combined with rig ship digs rock construction method | |
CN101775810A (en) | Underground water control construction method in foundation pit dewatering project | |
CN110043312A (en) | A kind of control method of grouting filling ground settlement range | |
CN103614984A (en) | Ecological treatment method oriented to geological environment disasters caused by riverway goafs | |
CN110984132B (en) | Construction method for grooving underground diaphragm wall under complex geological condition | |
CN103967024A (en) | United construction method for forming holes and grooves in deep sandy gravel stratum | |
CN113010997B (en) | Early warning treatment method for pile foundation impact hole forming construction accidents in karst development area | |
CN109989438A (en) | A kind of rich water sand pebble layer ultra-deep ground-connecting-wall forming construction method thereof | |
CN109469066A (en) | Earthmoving machinery combines excavation construction method and system with hydraulic tunneling boring solid | |
CN110489892B (en) | Three-phase coupling reservoir structure description technical method | |
CN103806409B (en) | The milling formation system of gravity type quay bedding and the construction method of Gravity harf structure | |
Abduraimova et al. | Digging and cleaning collectors using excavators equipped with innovative automatic control navigator | |
Mercer et al. | Glengarrisdale: confirmation of Jura's third microlithic phase | |
CN202208912U (en) | Replacement layer structure used for large-volume open caisson foundation stabilization | |
van Haren et al. | An interactive voxel model for mineral resources: loess deposits in Flanders (Belgium). | |
CN116927178B (en) | Construction method of granite boulder geological underground diaphragm wall | |
CN203729259U (en) | Milling forming system of gravity wharf foundation bed | |
Cardu et al. | Productivity and working costs of modern trench-cutters for the construction of concrete diaphragms in an urban environment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |