CN106304218B - A kind of method and device switched between the base station for realizing user equipment (UE) - Google Patents

A kind of method and device switched between the base station for realizing user equipment (UE) Download PDF

Info

Publication number
CN106304218B
CN106304218B CN201510246159.6A CN201510246159A CN106304218B CN 106304218 B CN106304218 B CN 106304218B CN 201510246159 A CN201510246159 A CN 201510246159A CN 106304218 B CN106304218 B CN 106304218B
Authority
CN
China
Prior art keywords
base station
target
cell
scg
csg cell
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510246159.6A
Other languages
Chinese (zh)
Other versions
CN106304218A (en
Inventor
张大钧
刘爱娟
汪颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Academy of Telecommunications Technology CATT
Datang Mobile Communications Equipment Co Ltd
Original Assignee
China Academy of Telecommunications Technology CATT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Academy of Telecommunications Technology CATT filed Critical China Academy of Telecommunications Technology CATT
Priority to CN201510246159.6A priority Critical patent/CN106304218B/en
Priority to PCT/CN2016/079324 priority patent/WO2016180157A1/en
Publication of CN106304218A publication Critical patent/CN106304218A/en
Application granted granted Critical
Publication of CN106304218B publication Critical patent/CN106304218B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W36/00Hand-off or reselection arrangements
    • H04W36/08Reselecting an access point
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W36/00Hand-off or reselection arrangements
    • H04W36/0005Control or signalling for completing the hand-off
    • H04W36/0055Transmission or use of information for re-establishing the radio link
    • H04W36/0069Transmission or use of information for re-establishing the radio link in case of dual connectivity, e.g. decoupled uplink/downlink

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Mobile Radio Communication Systems (AREA)

Abstract

The invention discloses the method and devices switched between a kind of base station for realizing user equipment, the performance switched between base station to improve UE, when target eNB being avoided to carry out dual link judgement, the CSG cell that may occur has accessed the UE of not permission, or can not be the problems such as UE correctly select the destination node of UE access caused by being conflicted as PCI.The method include that first base station needs to carry out switching of the UE between first base station and the second base station when determination, and when the cell in the target secondary cell group SCG switched is closed user group CSG cell, determine the CSG cell information of the target SCG;The first base station notifies the CSG cell information of the target SCG to second base station.

Description

A kind of method and device switched between the base station for realizing user equipment (UE)
Technical field
The present invention relates to a kind of method switched between field of communication technology more particularly to base station for realizing user equipment (UE) and Device.
Background technique
It is traditional with macro base station with the deployment of numerous local nodes such as more and more Home eNodeB, Microcell, relaying Based on the network architecture network architecture that will gradually develop into more type of base station and coexist, and the network for providing more levels covers Lid.It is a kind of that more evolution are realized by non-ideal link in order to improve the correlated performance under the polymorphic type base station co-existin networks framework Cooperation/polymerization network architecture is suggested between type base station (evolved NodeB, eNB).Under this architecture, user equipment (User Equipment, UE) a part of radio bearer (Radio Bearer, RB) manage in master base station (Master eNB, MeNB) In main plot group (Master Cell Group, MCG), this part RB includes control plane carrying (Signaling Radio Bearer, SRB) and user plane bearer (Data Radio Bearer, DRB), and main plot (Primary Cell, PCell) has Physical uplink control channel (Physical Uplink Control Channel, PUCCH).And other the one of same UE Part is carried on the secondary cell group (Secondary Cell Group, SCG) of prothetic group station (Secondary eNB, SeNB) management On, and a major-minor cell (Primary Secondary Cell, PSCell) has PUCCH.Since same UE is same under the framework When in two eNB have a connection, therefore be referred to as dual link (Dual Connectivity, DC) UE.
Macrocell between UE carry out base station handover operation when, if switching target macrocell support dual link behaviour Make, for target SCG be closed user group (Closed Subscriber Group, CSG) cell or other there may be physics Cell (Small Cell) situation of layer cell identifiers (physical cell identity, PCI) conflict, current mechanism can Can will lead to CSG cell accessed caused by UE or the PCI conflict of not permission can not correct selection target node etc., thus shadow Ring performance of handoffs.
Doubly-linked connection technology is described below.
In a kind of possible multitiered network overlay environment shown in Fig. 1, nonideal number is used between MeNB and SeNB According to/signaling interface --- Xn interface, UE may be simultaneously operated under MeNB and SeNB.When the UE for being connected to MeNB enters SeNB institute When the coverage area of corresponding cell, MeNB can consider according to signal strength or load balancing etc., shift the part or complete of UE Data/the signaling in portion is to SeNB, to obtain the service of SeNB offer.To realize that UE can use the money of MeNB and SeNB simultaneously It polymerize (inter-eNB polymerization) resource between source and base station.Under the scene, multiple RB of UE can respectively by SCG cell and MCG cell carries respectively.The RB for being wherein separated to SeNB may include DRB and/or SRB.
Wherein, the signaling of the SCG addition carried out in the dual link operating process carried out when (inter-eNB) switches between base station Process is as shown in Figure 2.
In conclusion when realizing the handover operation between the base station that macrocell carries out UE according to the prior art, if switching Target SCG be CSG cell or other there may be PCI conflict Small Cell, then target eNB carry out dual link judgement when, It may occur be the correct selection target node of the UE caused by CSG cell has accessed the not UE of permission or conflicted as PCI The problems such as, to influence performance of handoffs.
Summary of the invention
The embodiment of the invention provides the method and devices switched between a kind of base station for realizing user equipment, to improve UE The performance switched between base station, when target eNB being avoided to carry out dual link judgement, it may occur however that CSG cell accessed and do not had The UE having permission, or can not be the problems such as UE correctly select the destination node of UE access caused by being conflicted as PCI.
The method switched between a kind of base station for realizing user equipment (UE) provided in an embodiment of the present invention, this method comprises:
First base station needs to carry out switching of the UE between first base station and the second base station, and the target switched when determining When cell in secondary cell group SCG is closed user group CSG cell, the CSG cell information of the target SCG is determined;
The first base station notifies the CSG cell information of the target SCG to second base station.
In this way, first base station needs to carry out switching of the UE between first base station and the second base station when determination, and And switching target secondary cell group SCG in cell be closed user group CSG cell when, determine the CSG cell of the target SCG Information;The first base station notifies the CSG cell information of the target SCG to second base station, so that the second base station can Decide whether to carry out dual link operation with the CSG cell information according to target SCG, for example, if target SCG is close mode CSG cell, but UE is not belonging to the CSG member, then refusal for target SCG is carried out doubly-linked by the second base station (target eNB) Operation is connect, thus when target eNB being avoided to carry out dual link judgement, it may occur however that CSG cell accessed the UE of not permission.
Preferably, the first base station notifies the CSG cell information of the target SCG especially by switching request message To second base station.
Preferably, the first base station is specifically by the way of the application protocol AP information unit IE newly increased, alternatively, adopting With the mode of radio resource control RRC container container, the CSG cell of the target SCG is believed by switching request message Breath notice is to second base station.
Preferably, the CSG cell information of the target SCG, comprising: the CSG cell member condition of the target SCG is believed Breath and/or E-UTRAN Cell Global Identity ECGI and/or CSG identification information.
Preferably, the CSG cell supports mixing hybrid mode or closure close mode.
The method switched between a kind of base station for realizing user equipment (UE) provided in an embodiment of the present invention, comprising:
Second base station obtains the closed user group CSG cell information for the target secondary cell group SCG that first base station is sent, In, the former base station switched between the base station that the first base station is progress UE, the target that second base station switches between the base station Base station, the target SCG that the target SCG switches between the base station, and the cell in target SCG are CSG cell;
Second base station decides whether to initiate to the target SCG double according to the CSG cell information of the target SCG Operation is established in connection.
Preferably, the CSG cell information of the target SCG, comprising: the CSG cell member condition of the target SCG is believed Breath and/or E-UTRAN Cell Global Identity ECGI and/or CSG identification information.
Preferably, when the CSG cell information of the target SCG includes the CSG cell member status information of the target SCG When;
Second base station decides whether to initiate to the target SCG double according to the CSG cell information of the target SCG Operation is established in connection, comprising:
Second base station is the CSG cell of closed mode as the target SCG, and according to the CSG of the target SCG When determining that the UE is not belonging to the member of CSG cell, it is double to determine that refusal is initiated to the target SCG by cell member status information Operation is established in connection.
The method switched between a kind of base station for realizing user equipment (UE) provided in an embodiment of the present invention, comprising:
First base station needs to carry out switching of the UE between first base station and the second base station, and the target switched when determining When cell in secondary cell group SCG is home base station cells or the cell of open mode, the cell in the target SCG is determined E-UTRAN Cell Global Identity ECGI;
The first base station notifies the ECGI of the cell in the target SCG to second base station.
In this way, first base station needs to carry out switching of the UE between first base station and the second base station when determination, and And the cell in the target secondary cell group SCG of switching is home base station cells of open mode or when cell, determines the mesh Mark the E-UTRAN Cell Global Identity ECGI of the cell in SCG;The first base station will be described The ECGI of cell in target SCG is notified to second base station, so that the second base station (target eNB) can be according to the mesh The ECGI of cell in mark SCG determines the subsequent target SCG node for carrying out dual link operation, avoids caused by being conflicted as PCI The problems such as destination node of UE access can not correctly be selected.
Preferably, the first base station leads to the ECGI of the cell in the target SCG especially by switching request message Know to second base station.
Preferably, the first base station is specifically by the way of the application protocol AP information unit IE newly increased, alternatively, adopting With the mode of radio resource control RRC container container, by switching request message by the cell in the target SCG ECGI is notified to second base station.
The method switched between a kind of base station for realizing user equipment (UE) provided in an embodiment of the present invention, comprising:
The Evolved Universal Terrestrial that second base station obtains the cell in the target secondary cell group SCG that first base station is sent is wireless Access network Cell Global Identity ECGI;Wherein, the first base station is the former base station that switches between the base station for carrying out UE, described the The target BS that two base stations switch between the base station, the target SCG that the target SCG switches between the base station;
According to the ECGI of the cell in the target SCG, the cell in Xiang Suoshu target SCG is initiated double for second base station Operation is established in connection.
The device switched between a kind of base station for realizing user equipment (UE) provided in an embodiment of the present invention, comprising:
First unit, for needing to carry out UE between first base station and the second base station when determining in first base station side When the cell in target secondary cell group SCG for switching, and switching is closed user group CSG cell, determine the target SCG's CSG cell information;
Second unit notifies the CSG cell information of the target SCG to described the in the first base station side Two base stations.
Preferably, the second unit notifies the CSG cell information of the target SCG especially by switching request message To second base station.
Preferably, the second unit is specifically by the way of the application protocol AP information unit IE newly increased, alternatively, adopting With the mode of radio resource control RRC container container, the CSG cell of the target SCG is believed by switching request message Breath notice is to second base station.
Preferably, the CSG cell information of the target SCG, comprising: the CSG cell member condition of the target SCG is believed Breath and/or E-UTRAN Cell Global Identity ECGI and/or CSG identification information.
Preferably, the CSG cell supports mixing hybrid mode or closure close mode.
The device switched between a kind of base station for realizing user equipment (UE) provided in an embodiment of the present invention, comprising:
Third unit, for obtaining the closed user for the target secondary cell group SCG that first base station is sent in the second base station side Group's CSG cell information, wherein the former base station switched between the base station that the first base station is progress UE, second base station is should The target BS switched between base station, the target SCG that the target SCG switches between the base station, and it is small in target SCG Area is CSG cell;
Unit the 4th, in second base station side, according to the CSG cell information of the target SCG, decide whether to The target SCG initiates dual link and establishes operation.
Preferably, the CSG cell information of the target SCG, comprising: the CSG cell member condition of the target SCG is believed Breath and/or E-UTRAN Cell Global Identity ECGI and/or CSG identification information.
Preferably, when the CSG cell information of the target SCG includes the CSG cell member status information of the target SCG When;
Unit the 4th is specifically used for: in second base station side, when the CSG that the target SCG is closed mode is small Area, and according to the CSG cell member status information of the target SCG, when determining that the UE is not belonging to the member of CSG cell, Determine that refusal initiates dual link to the target SCG and establishes operation.
Preferably, the device further includes above-mentioned first unit and second unit.
The device switched between a kind of base station for realizing user equipment (UE) provided in an embodiment of the present invention, comprising:
Unit the 5th, for needing to carry out UE between first base station and the second base station when determining in first base station side When the cell in target secondary cell group SCG for switching, and switching is home base station cells or the cell of open mode, determine The E-UTRAN Cell Global Identity ECGI of cell in the target SCG;
Unit the 6th notifies the ECGI of the cell in the target SCG to described the in the first base station side Two base stations.
Preferably, Unit the 6th leads to the ECGI of the cell in the target SCG especially by switching request message Know to second base station.
Preferably, Unit the 6th is specifically by the way of the application protocol AP information unit IE newly increased, alternatively, adopting With the mode of radio resource control RRC container container, by switching request message by the cell in the target SCG ECGI is notified to second base station.
Preferably, the device further includes the first unit and second unit, and/or, the third unit and the 4th Unit.
The device switched between a kind of base station for realizing user equipment (UE) provided in an embodiment of the present invention, comprising:
Unit the 7th, for obtaining the cell in the target secondary cell group SCG that first base station is sent in the second base station side E-UTRAN Cell Global Identity ECGI;Wherein, between the base station that the first base station is progress UE The former base station of switching, the target BS that second base station switches between the base station, the target SCG switch between the base station Target SCG;
Unit the 8th is used in the second base station side, according to the ECGI of the cell in the target SCG, Xiang Suoshu target SCG In cell initiate dual link establish operation.
Preferably, the device further include: the first unit and second unit, and/or, the third in the device Unit and Unit the 4th, and/or, Unit the 5th and Unit the 6th.
Detailed description of the invention
Fig. 1 is the network architecture schematic diagram of dual link in the prior art;
Fig. 2 is the signaling process schematic diagram that SCG addition is carried out in switchover procedure between base station in the prior art;
The process for the method that Fig. 3 switches between the base station for the first realization user equipment (UE) provided in an embodiment of the present invention is shown It is intended to;
The process for the method that Fig. 4 switches between the base station for second provided in an embodiment of the present invention realization user equipment (UE) is shown It is intended to;
The process for the method that Fig. 5 switches between the base station for the third realization user equipment (UE) provided in an embodiment of the present invention is shown It is intended to;
The process for the method that Fig. 6 switches between the base station for 4th kind provided in an embodiment of the present invention realization user equipment (UE) is shown It is intended to;
The structure for the device that Fig. 7 switches between the base station for the first realization user equipment (UE) provided in an embodiment of the present invention is shown It is intended to;
The structure for the device that Fig. 8 switches between the base station for second provided in an embodiment of the present invention realization user equipment (UE) is shown It is intended to;
The structure for the device that Fig. 9 switches between the base station for the third realization user equipment (UE) provided in an embodiment of the present invention is shown It is intended to;
The structure for the device that Figure 10 switches between the base station for 4th kind provided in an embodiment of the present invention realization user equipment (UE) Schematic diagram;
The structure for the device that Figure 11 switches between the base station for 5th kind provided in an embodiment of the present invention realization user equipment (UE) Schematic diagram.
Specific embodiment
The embodiment of the invention provides the method and devices switched between a kind of base station for realizing user equipment, to improve UE The performance switched between base station, when target eNB being avoided to carry out dual link judgement, it may occur however that CSG cell accessed and do not had The UE that has permission or the problems such as can not correctly select the destination node of UE access caused by being conflicted as PCI.
In technical solution provided in an embodiment of the present invention, when switching between UE progress inter-eNB, if candidate mesh Mark SCG is CSG cell, and when CSG cell support mixing (hybrid) or closure (close) mode, former side eNB needs to notify Target eNB, member status information and/or E-UTRAN (E- about candidate target CSG cell UTRAN) Cell Global Identity (E-UTRAN Cell Global Identifier, ECGI) information (cell unique identification), and/ Or CSG mark (ID), target eNB is according to these information, in that case it can be decided that whether dual link operation is carried out, for example, if the CSG is small Area is close mode, but UE is not belonging to the CSG member, and refusal is carried out dual link operation for the CSG cell by target eNB;This Outside, if the CSG cell is hybrid mode, former side eNB needs the member status information of CSG member notifying target SCG.
In technical solution provided in an embodiment of the present invention, when switching between UE progress inter-eNB, if candidate mesh When mark SCG is the HeNB cell or other Small Cell to conflict there may be PCI of open (open) mode, in order to prevent PCI conflicts, and former side eNB needs to notify target eNB, and about candidate target HeNB cell or there may be the Small of PCI conflict The ECGI information (cell unique identification) of Cell, target eNB can determine the subsequent mesh for carrying out dual link operation according to the information Mark SCG node.
Technical solution provided in an embodiment of the present invention is illustrated with reference to the accompanying drawing.
Referring to Fig. 3, the method that switches between a kind of base station that realizing user equipment (UE) provided in an embodiment of the present invention, comprising:
S101, first base station need to carry out switching of the UE between first base station and the second base station when determining, and switch Target secondary cell group SCG in cell be closed user group CSG cell when, determine the CSG cell information of the target SCG;
S102, the first base station notify the CSG cell information of the target SCG to second base station.
In this way, first base station needs to carry out switching of the UE between first base station and the second base station when determination, and And switching target secondary cell group SCG in cell be closed user group CSG cell when, determine the CSG cell of the target SCG Information;The first base station notifies the CSG cell information of the target SCG to second base station, so that the second base station can Decide whether to carry out dual link operation with the CSG cell information according to target SCG, for example, if target SCG is close mode CSG cell, but UE is not belonging to the CSG member, then refusal for target SCG is carried out doubly-linked by the second base station (target eNB) Operation is connect, thus when target eNB being avoided to carry out dual link judgement, it may occur however that CSG cell accessed the UE of not permission.
Preferably, the first base station notifies the CSG cell information of the target SCG especially by switching request message To second base station.
Preferably, the first base station is specifically by the way of application protocol (AP) information unit (IE) newly increased, or Person, by the way of wireless heterogeneous networks (RRC) container (container), by switching request message by the target SCG's CSG cell information is notified to second base station.
Preferably, the CSG cell information of the target SCG, comprising: the CSG cell member condition of the target SCG is believed Breath and/or E-UTRAN Cell Global Identity (ECGI) and/or CSG identification information.
Preferably, the CSG cell supports mixing (hybrid) mode or closure (close) mode.
Correspondingly, in the second base station side, referring to fig. 4, a kind of base for realizing user equipment (UE) provided in an embodiment of the present invention The method switched between standing, comprising:
S201, the second base station obtain the closed user group CSG cell letter for the target secondary cell group SCG that first base station is sent Breath, wherein the former base station switched between the base station that the first base station is progress UE, what second base station switched between the base station Target BS, the target SCG that the target SCG switches between the base station, and the cell in target SCG are CSG cell;
S202, second base station decide whether to send out to the target SCG according to the CSG cell information of the target SCG It plays dual link and establishes operation.
Preferably, the CSG cell information of the target SCG, comprising: the CSG cell member condition of the target SCG is believed Breath and/or E-UTRAN Cell Global Identity ECGI and/or CSG identification information.
Preferably, when the CSG cell information of the target SCG includes the CSG cell member status information of the target SCG When;
Second base station decides whether to initiate to the target SCG double according to the CSG cell information of the target SCG Operation is established in connection, comprising:
Second base station is the CSG cell of closed mode as the target SCG, and according to the CSG of the target SCG When determining that the UE is not belonging to the member of CSG cell, it is double to determine that refusal is initiated to the target SCG by cell member status information Operation is established in connection.
Referring to Fig. 5, the method that switches between a kind of base station that realizing user equipment (UE) provided in an embodiment of the present invention, comprising:
S301, first base station need to carry out switching of the UE between first base station and the second base station when determining, and switch Target secondary cell group SCG in cell be home base station cells of open mode or when cell, determine in the target SCG Cell E-UTRAN Cell Global Identity ECGI;
S302, the first base station notify the ECGI of the cell in the target SCG to second base station.
In this way, first base station needs to carry out switching of the UE between first base station and the second base station when determination, and And the cell in the target secondary cell group SCG of switching is home base station cells of open mode or when cell, determines the mesh Mark the E-UTRAN Cell Global Identity ECGI of the cell in SCG;The first base station will be described The ECGI of cell in target SCG is notified to second base station, so that the second base station (target eNB) can be according to the mesh The ECGI of cell in mark SCG determines the subsequent target SCG node for carrying out dual link operation, avoids caused by being conflicted as PCI The problems such as destination node of UE access can not correctly be selected.
Preferably, the first base station leads to the ECGI of the cell in the target SCG especially by switching request message Know to second base station.
Preferably, the first base station is specifically by the way of the application protocol AP information unit IE newly increased, alternatively, adopting With the mode of radio resource control RRC container container, by switching request message by the cell in the target SCG ECGI is notified to second base station.
Correspondingly, in the second base station side, referring to Fig. 6, a kind of base for realizing user equipment (UE) provided in an embodiment of the present invention The method switched between standing, comprising:
S401, the second base station obtain the evolved general land of the cell in the target secondary cell group SCG that first base station is sent Ground Radio Access Network Cell Global Identity ECGI;Wherein, the former base station switched between the base station that the first base station is progress UE, The target BS that second base station switches between the base station, the target SCG that the target SCG switches between the base station;
The cell of S402, second base station according to the ECGI of the cell in the target SCG, in Xiang Suoshu target SCG It initiates dual link and establishes operation.
Following specific embodiment is given below for example:
Embodiment 1:
Assuming that the first eNB is carrying out dual link operation, then switching flow specifically includes between base station provided in this embodiment:
Step 1: the first eNB is according to the measurement report of UE and wireless resource management (the Radio Resource of network Management, RRM) information, decision needs to carry out inter-eNB handover operation, in addition, the first eNB judgement may need more Change the operation of SCG;
Step 2: when the cell in one or more target SCG belongs to CSG cell, and target SCG is (in target SCG Cell be CSG cell) support hybrid mode, in addition, the first eNB reported by UE measurement or other modes obtained about The CSG cell information of target SCG, the member status information for specifically including CSG cell (are used to indicate and need to carry out to cut between base station The UE changed whether be CSG cell member information) and the CSG cells such as ECGI, CSG ID information, then the first eNB by these Information gives the 2nd eNB by switching request message informing, wherein the first eNB is original side eNB, the 2nd eNB is target eNB;
Wherein, specifically, the side of application protocol (AP) information unit (IE) newly increased in Xn interface can be used in the first eNB Formula carries the CSG cell information of above-mentioned target SCG, and gives the 2nd eNB by switching request message informing.
Step 3: the 2nd eNB according to the switching request information (the CSG cell information including above-mentioned target SCG) received, into Switch decision between row base station;
Specifically, the 2nd eNB can carry out dual link for the CSG cell according to the CSG cell information determination of target SCG Operation, and need the member status information of CSG cell notifying target SCG.
Step 4: if the cell in the target SCG that the 2nd eNB is selected is CSG cell, the 2nd eNB is according to switching request The ECGI that message carries initiates dual link to the target SCG of selection and establishes operation;
Step 5: the configuration information that the 2nd eNB is returned according to target SCG, in conjunction with the configuration information of the 2nd eNB oneself, Switching response message is returned into the first eNB.
Step 6: the first eNB executes subsequent idle wireless resource control (Radio Resource Control, RRC) Reconfiguration operation.
Step 7: the first eNB discharges original network and interface-free resources.
Embodiment 2:
Assuming that the first eNB is carrying out dual link operation, then switching flow specifically includes between base station provided in this embodiment:
Step 1: the first eNB is according to the measurement report of UE and wireless resource management (the Radio Resource of network Management, RRM) information, decision needs to carry out inter-eNB handover operation, in addition, the first eNB judgement may need more Change the operation of SCG;
Step 2: when the cell in one or more target SCG belongs to CSG cell, and target SCG is (in target SCG Cell be CSG cell) support hybrid mode, in addition, the first eNB reported by UE measurement or other modes obtained about The CSG cell information of target SCG, the member status information for specifically including CSG cell (are used to indicate and need to carry out to cut between base station The UE changed whether be CSG cell member information) and the CSG cells such as ECGI, CSG ID information, then the first eNB by these Information gives the 2nd eNB by switching request message informing, wherein the first eNB is original side eNB, the 2nd eNB is target eNB;
Specifically, the 2nd eNB carries the CSG cell letter of above-mentioned target SCG by the way of RRC container (container) Breath, and the 2nd eNB is given by switching request message informing.
Subsequent step is equal to step three~seven in embodiment 1.
Embodiment 3:
Assuming that the first eNB is carrying out dual link operation, then switching flow specifically includes between base station provided in this embodiment:
Step 1: the first eNB is according to the measurement report of UE and wireless resource management (the Radio Resource of network Management, RRM) information, decision needs to carry out inter-eNB handover operation, in addition, the first eNB judgement may need more Change the operation of SCG;
Step 2: when the cell in one or more target SCG belongs to CSG cell, and target SCG is (in target SCG Cell be CSG cell) support close mode, in addition, the first eNB reported by UE measurement or other modes obtained about The CSG cell information of target SCG, the member status information for specifically including CSG cell (are used to indicate and need to carry out to cut between base station The UE changed whether be CSG cell member information) and the CSG cells such as ECGI, CSG ID information, then the first eNB by these Information gives the 2nd eNB by switching request message informing, wherein the first eNB is original side eNB, the 2nd eNB is target eNB;
Wherein, specifically, the mode for newly increasing AP IE can be used in the first eNB, carries the CSG cell letter of above-mentioned target SCG Breath, and the 2nd eNB is given by switching request message informing.
Step 3: the 2nd eNB according to the switching request information (the CSG cell information including above-mentioned target SCG) received, into Row switch decision;
Specifically, the 2nd eNB can carry out following decision operations:
If UE is not belonging to CSG member, refusal is carried out dual link behaviour for the CSG cell in target SCG by the 2nd eNB Make;
If UE belongs to CSG member, the 2nd eNB confirmation can carry out dual link for the CSG cell in target SCG Operation.
Step 4: if the cell in the target SCG that the 2nd eNB is selected is CSG cell, the 2nd eNB is according to switching request The ECGI that message carries initiates dual link to the target SCG of selection and establishes operation;
Step 5: the configuration information that the 2nd eNB is returned according to target SCG, in conjunction with the configuration information of the 2nd eNB oneself, Switching response message is returned into the first eNB.
Step 6: the first eNB executes subsequent idle wireless resource control (Radio Resource Control, RRC) Reconfiguration operation.
Step 7: the first eNB discharges original network and interface-free resources.
Embodiment 4:
Assuming that the first eNB is carrying out dual link operation, then switching flow specifically includes between base station provided in this embodiment:
Step 1: the first eNB is according to the measurement report of UE and wireless resource management (the Radio Resource of network Management, RRM) information, decision needs to carry out inter-eNB handover operation, in addition, the first eNB judgement may need more Change the operation of SCG;
Step 2: when the cell in one or more target SCG belongs to CSG cell, and target SCG is (in target SCG Cell be CSG cell) support close mode, in addition, the first eNB reported by UE measurement or other modes obtained about The CSG cell information of target SCG, the member status information for specifically including CSG cell (are used to indicate and need to carry out to cut between base station The UE changed whether be CSG cell member information) and the CSG cells such as ECGI, CSG ID information, then the first eNB by these Information gives the 2nd eNB by switching request message informing, wherein the first eNB is original side eNB, the 2nd eNB is target eNB;
Specifically, the 2nd eNB carries the CSG cell information of above-mentioned target SCG by the way of RRC container, and The 2nd eNB is given by switching request message informing.
Step 3: the 2nd eNB according to the switching request information (the CSG cell information including above-mentioned target SCG) received, into Row switch decision;
Specifically, the 2nd eNB can carry out following decision operations:
If UE is not belonging to CSG member, refusal is carried out dual link behaviour for the CSG cell in target SCG by the 2nd eNB Make;
If UE belongs to CSG member, the 2nd eNB confirmation can carry out dual link for the CSG cell in target SCG Operation.
Step 4: if the cell in the target SCG that the 2nd eNB is selected is CSG cell, the 2nd eNB is according to switching request The ECGI that message carries initiates dual link to the target SCG of selection and establishes operation;
Step 5: the configuration information that the 2nd eNB is returned according to target SCG, in conjunction with the configuration information of the 2nd eNB oneself, Switching response message is returned into the first eNB.
Step 6: the first eNB executes subsequent idle wireless resource control (Radio Resource Control, RRC) Reconfiguration operation.
Step 7: the first eNB discharges original network and interface-free resources.
Embodiment 5:
Assuming that the first eNB is carrying out single connection operation, then switching flow specifically includes between base station provided in this embodiment:
Step 1: the first eNB needs to carry out inter-eNB and cuts according to the measurement report of UE and the RRM information of network, decision Operation is changed, in addition, the first eNB determines that the 2nd eNB allows to carry out the operation of SCG dual link;
Step 2: the CSG cell when the cell in one or more target SCG belongs to CSG cell, and in the SCG is supported When hybrid mode, subsequent step is equal to step two~seven in embodiment 1 or embodiment 2.
Embodiment 6:
Assuming that the first eNB is carrying out single connection operation, then switching flow specifically includes between base station provided in this embodiment:
Step 1: the first eNB needs to carry out inter-eNB and cuts according to the measurement report of UE and the RRM information of network, decision Operation is changed, in addition, the first eNB determines that the 2nd eNB allows to carry out the operation of SCG dual link;
Step 2: when the cell in one or more target SCG belongs to CSG cell, and the CSG cell in target SCG When supporting close mode, subsequent step is equal to step two~seven in embodiment 3 or embodiment 4.
Embodiment 7:
Assuming that the first eNB is carrying out dual link operation, then switching flow specifically includes between base station provided in this embodiment:
Step 1: the first eNB is according to the measurement report of UE and wireless resource management (the Radio Resource of network Management, RRM) information, decision needs to carry out inter-eNB handover operation, in addition, the first eNB determination may need more Change the operation of SCG;
Step 2: when family's evolved base station (HeNB) that one or more target SCG belong to open (open) mode is small Area or other there may be PCI conflict Small Cell when, in addition, the first eNB reported by UE measurement or other modes The ECGI information about the cell in target SCG is obtained, then the first eNB is by the ECGI information of the cell in target SCG by cutting Request message is changed to notify to the 2nd eNB;
Wherein, specifically, the mode for newly increasing AP IE can be used in the first eNB, carries target in the present embodiment step 2 The ECGI information of cell in SCG, and the 2nd eNB is given by switching request message informing.
Step 3: according to the switching request information received, (ECGI including the cell in above-mentioned target SCG believes the 2nd eNB Breath), decide whether that dual link behaviour can be carried out for related cell (cell in target SCG) above-mentioned in the present embodiment step 2 Make;
Step 4: if the target SCG of the 2nd eNB selection includes family's evolved base station of above-mentioned opening (open) mode (HeNB) cell or other there may be the Small Cell, the 2nd eNB of PCI conflict according to the ECGI of the cell in target SCG Information initiates dual link to target SCG and establishes operation;
Step 5: the configuration information that the 2nd eNB is returned according to target SCG, in conjunction with the configuration information of the 2nd eNB oneself, Switching response message is returned into the first eNB.
Step 6: the first eNB executes subsequent idle wireless resource control (Radio Resource Control, RRC) Reconfiguration operation.
Step 7: the first eNB discharges original network and interface-free resources.
Embodiment 8:
Assuming that the first eNB is carrying out dual link operation, then switching flow specifically includes between base station provided in this embodiment:
Step 1: the first eNB is according to the measurement report of UE and wireless resource management (the Radio Resource of network Management, RRM) information, decision needs to carry out inter-eNB handover operation, in addition, the first eNB judgement may need more Change the operation of SCG;
Step 2: when family's evolved base station (HeNB) that one or more target SCG belong to open (open) mode is small Area or other there may be PCI conflict Small Cell when, in addition, the first eNB reported by UE measurement or other modes The ECGI information about the cell in target SCG is obtained, then the first eNB is by the ECGI information of the cell in target SCG by cutting Request message is changed to notify to the 2nd eNB;
Wherein, specifically, the mode of RRC container can be used in the first eNB, carries target in the present embodiment step 2 The ECGI information of cell in SCG, and the 2nd eNB is given by switching request message informing.
Subsequent step is equal to step three~seven in embodiment 7.
The device corresponded to the above method is described below.
Referring to Fig. 7, the device that switches between a kind of base station that realizing user equipment (UE) provided in an embodiment of the present invention, comprising:
First unit 11, for needing to carry out UE between first base station and the second base station when determining in first base station side Switching, and switch target secondary cell group SCG in cell be closed user group CSG cell when, determine the target SCG CSG cell information;
Second unit 12, in the first base station side, the CSG cell information of the target SCG to be notified to described Second base station.
Preferably, the second unit notifies the CSG cell information of the target SCG especially by switching request message To second base station.
Preferably, the second unit is specifically by the way of the application protocol AP information unit IE newly increased, alternatively, adopting With the mode of radio resource control RRC container container, the CSG cell of the target SCG is believed by switching request message Breath notice is to second base station.
Preferably, the CSG cell information of the target SCG, comprising: the CSG cell member condition of the target SCG is believed Breath and/or E-UTRAN Cell Global Identity ECGI and/or CSG identification information.
Preferably, the CSG cell supports mixing hybrid mode or closure close mode.
Referring to Fig. 8, the device switched between the base station of second of realization user equipment (UE) provided in an embodiment of the present invention, packet It includes:
Third unit 21, in the second base station side, the closure for obtaining the target secondary cell group SCG that first base station is sent to be used Family group's CSG cell information, wherein the former base station switched between the base station that the first base station is progress UE, second base station is The target BS switched between the base station, the target SCG that the target SCG switches between the base station, and in target SCG Cell is CSG cell;
4th unit 22, for being decided whether in second base station side according to the CSG cell information of the target SCG Dual link, which is initiated, to the target SCG establishes operation.
Preferably, the CSG cell information of the target SCG, comprising: the CSG cell member condition of the target SCG is believed Breath and/or E-UTRAN Cell Global Identity ECGI and/or CSG identification information.
Preferably, when the CSG cell information of the target SCG includes the CSG cell member status information of the target SCG When;
Unit the 4th is specifically used for: in second base station side, when the CSG that the target SCG is closed mode is small Area, and according to the CSG cell member status information of the target SCG, when determining that the UE is not belonging to the member of CSG cell, Determine that refusal initiates dual link to the target SCG and establishes operation.
Preferably, the device further includes above-mentioned first unit and second unit.
Referring to Fig. 9, the device switched between the base station of the third realization user equipment (UE) provided in an embodiment of the present invention, packet It includes:
5th unit 31, for needing to carry out UE between first base station and the second base station when determining in first base station side Switching, and the cell in the target secondary cell group SCG switched is home base station cells of open mode or when cell, really The E-UTRAN Cell Global Identity ECGI of cell in the fixed target SCG;
6th unit 32, in the first base station side, the ECGI of the cell in the target SCG to be notified to described Second base station.
Preferably, Unit the 6th leads to the ECGI of the cell in the target SCG especially by switching request message Know to second base station.
Preferably, Unit the 6th is specifically by the way of the application protocol AP information unit IE newly increased, alternatively, adopting With the mode of radio resource control RRC container container, by switching request message by the cell in the target SCG ECGI is notified to second base station.
Preferably, the device further includes above-mentioned first unit and second unit, and/or, above-mentioned third unit and the 4th single Member.
Referring to Figure 10, the device switched between the base station of the 4th kind of realization user equipment (UE) provided in an embodiment of the present invention, packet It includes:
7th unit 41, for obtaining the cell in the target secondary cell group SCG that first base station is sent in the second base station side E-UTRAN Cell Global Identity ECGI;Wherein, the first base station is to carry out the base station of UE Between the former base station that switches, the target BS that second base station switches between the base station, the target SCG cuts between the base station The target SCG changed;
8th unit 42 is used in the second base station side, according to the ECGI of the cell in the target SCG, Xiang Suoshu target Cell in SCG initiates dual link and establishes operation.
Preferably, the device further include: above-mentioned first unit and second unit, and/or, above-mentioned third unit and the 4th list Member, and/or, above-mentioned Unit the 5th and Unit the 6th.
It should be noted that any device provided in the embodiment of the present invention, can be base station, such as eNB.Described Any cell can be realized by processor.
Referring to Figure 11, the device switched between the base station of the 5th kind of realization user equipment provided in an embodiment of the present invention includes: Processor 500 and memory 520;
When device of the device as the former base station side switched between base station, processor 500, for reading memory 520 In program, execute following process:
In first base station side, need to carry out switching of the UE between first base station and the second base station when determining, and switch Target secondary cell group SCG in cell be closed user group CSG cell when, determine the CSG cell information of the target SCG;
In the first base station side, the CSG cell information of the target SCG is notified to described by transceiver 510 Two base stations.
Preferably, specifically control transceiver 510 is small by the CSG of the target SCG by switching request message for processor 500 Area's information is notified to second base station.
Preferably, processor 500 is specific by the way of the application protocol AP information unit IE newly increased, alternatively, using The mode of radio resource control RRC container container, control transceiver 510 pass through switching request message for the target SCG CSG cell information notify to second base station.
When device of the device as the target BS side switched between base station, processor 500 is also used to read memory Program in 520 executes following process:
In the second base station side, the closed user group CSG cell letter for the target secondary cell group SCG that first base station is sent is obtained Breath, wherein the former base station switched between the base station that the first base station is progress UE, what second base station switched between the base station Target BS, the target SCG that the target SCG switches between the base station, and the cell in target SCG are CSG cell;
In second base station side, according to the CSG cell information of the target SCG, decide whether to send out to the target SCG It plays dual link and establishes operation.
When the CSG cell information of the target SCG includes the CSG cell member status information of the target SCG;
Processor 500 is the CSG cell of closed mode as the target SCG, and small according to the CSG of the target SCG Area member status information when determining that the UE is not belonging to the member of CSG cell, determines that refusal initiates doubly-linked to the target SCG Connect foundation operation.
Preferably, processor 500 is also used to read when device of the device as the former base station side switched between base station Program in memory 520 executes following process:
In first base station side, need to carry out switching of the UE between first base station and the second base station when determining, and switch Target secondary cell group SCG in cell be home base station cells of open mode or when cell, determine in the target SCG Cell E-UTRAN Cell Global Identity ECGI;
In the first base station side, controls transceiver 510 and notify the ECGI of the cell in the target SCG to described the Two base stations.
Preferably, specifically control transceiver 510 will be small in the target SCG by switching request message for processor 500 The ECGI in area is notified to second base station.
Preferably, processor 500 is specific by the way of the application protocol AP information unit IE newly increased, alternatively, using The mode of radio resource control RRC container container, control transceiver 510 pass through switching request message for the target SCG In the ECGI of cell notify to second base station.
When device of the device as the target BS side switched between base station, processor 500 is also used to read memory Program in 520 executes following process:
In the second base station side, the evolved general land of the cell in the target secondary cell group SCG that first base station is sent is obtained Ground Radio Access Network Cell Global Identity ECGI;Wherein, the former base station switched between the base station that the first base station is progress UE, The target BS that second base station switches between the base station, the target SCG that the target SCG switches between the base station;
In the second base station side, according to the ECGI of the cell in the target SCG, the cell in Xiang Suoshu target SCG is initiated Dual link establishes operation.
The transceiver 510, for sending and receiving data under control of the processor 500.
Wherein, in Figure 11, bus architecture may include the bus and bridge of any number of interconnection, specifically by processor The various circuits for the memory that 500 one or more processors represented and memory 520 represent link together.Bus architecture Various other circuits of such as peripheral equipment, voltage-stablizer and management circuit or the like can also be linked together, these It is all it is known in the art, therefore, it will not be further described herein.Bus interface provides interface.Transceiver 510 It can be multiple element, that is, include transmitter and transceiver, provide for over a transmission medium being communicated with various other devices Unit.Processor 500, which is responsible for management bus architecture and common processing, memory 520, can store processor 500 and is executing behaviour Used data when making.
In conclusion under macrocell covering, while being disposed a large amount of small in technical solution provided in an embodiment of the present invention Cell, UE can have connection simultaneously in multiple cells or eNB, and when macrocell switches over operation, if target SCG is CSG cell or other there may be PCI conflict Small Cell, pass through between former eNB and target eNB interaction CSG member Status information or ECGI information, can be avoided CSG cell access not the UE of permission or cause PCI conflict etc., so as to improve cutting Transsexual energy.
It should be understood by those skilled in the art that, the embodiment of the present invention can provide as method, system or computer program Product.Therefore, complete hardware embodiment, complete software embodiment or reality combining software and hardware aspects can be used in the present invention Apply the form of example.Moreover, it wherein includes the computer of computer usable program code that the present invention, which can be used in one or more, The shape for the computer program product implemented in usable storage medium (including but not limited to magnetic disk storage and optical memory etc.) Formula.
The present invention be referring to according to the method for the embodiment of the present invention, the process of equipment (system) and computer program product Figure and/or block diagram describe.It should be understood that every one stream in flowchart and/or the block diagram can be realized by computer program instructions The combination of process and/or box in journey and/or box and flowchart and/or the block diagram.It can provide these computer programs Instruct the processor of general purpose computer, special purpose computer, Embedded Processor or other programmable data processing devices to produce A raw machine, so that being generated by the instruction that computer or the processor of other programmable data processing devices execute for real The device for the function of being specified in present one or more flows of the flowchart and/or one or more blocks of the block diagram.
These computer program instructions, which may also be stored in, is able to guide computer or other programmable data processing devices with spy Determine in the computer-readable memory that mode works, so that it includes referring to that instruction stored in the computer readable memory, which generates, Enable the manufacture of device, the command device realize in one box of one or more flows of the flowchart and/or block diagram or The function of being specified in multiple boxes.
These computer program instructions also can be loaded onto a computer or other programmable data processing device, so that counting Series of operation steps are executed on calculation machine or other programmable devices to generate computer implemented processing, thus in computer or The instruction executed on other programmable devices is provided for realizing in one or more flows of the flowchart and/or block diagram one The step of function of being specified in a box or multiple boxes.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art Mind and range.In this way, if these modifications and changes of the present invention belongs to the range of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to include these modifications and variations.

Claims (27)

1. a kind of method switched between base station for realizing user equipment (UE), which is characterized in that this method comprises:
First base station needs to carry out switching of the UE between first base station and the second base station when determining, and the target switched is auxiliary small When cell in district's groups SCG is closed user group CSG cell, the CSG cell information of the target SCG is determined;
The first base station notifies the CSG cell information of the target SCG to second base station;
Wherein, the former base station switched between the base station that the first base station is progress UE, second base station switches between the base station Target BS.
2. the method according to claim 1, wherein the first base station is especially by switching request message by institute The CSG cell information for stating target SCG is notified to second base station.
3. according to the method described in claim 2, it is characterized in that, the first base station is specifically using the application protocol newly increased The mode of AP information unit IE, alternatively, being disappeared by the way of radio resource control RRC container container by switching request Breath notifies the CSG cell information of the target SCG to second base station.
4. method according to claim 1,2 or 3, which is characterized in that the CSG cell information of the target SCG, comprising: The CSG cell member status information of the target SCG and/or E-UTRAN Cell Global Identity ECGI and/or CSG identification information.
5. the method according to claim 1, wherein the CSG cell is supported mixing hybrid mode or is closed Close close mode.
6. a kind of method switched between base station for realizing user equipment (UE), which is characterized in that this method comprises:
Second base station obtains the closed user group CSG cell information for the target secondary cell group SCG that first base station is sent, wherein institute Stating first base station is the former base station that switches between the base station for carrying out UE, the target BS that second base station switches between the base station, The target SCG that the target SCG switches between the base station, and the cell in target SCG is CSG cell;
Second base station decides whether to initiate dual link to the target SCG according to the CSG cell information of the target SCG Establish operation.
7. according to the method described in claim 6, it is characterized in that, the CSG cell information of the target SCG, comprising: the mesh The CSG cell member status information and/or E-UTRAN Cell Global Identity ECGI of SCG are marked, And/or CSG identification information.
8. the method according to the description of claim 7 is characterized in that the CSG cell information as the target SCG includes the mesh When marking the CSG cell member status information of SCG;
Second base station decides whether to initiate dual link to the target SCG according to the CSG cell information of the target SCG Establish operation, comprising:
Second base station is the CSG cell of closed mode as the target SCG, and according to the CSG cell of the target SCG Member status information when determining that the UE is not belonging to the member of CSG cell, determines that refusal initiates dual link to the target SCG Establish operation.
9. a kind of method switched between base station for realizing user equipment (UE), which is characterized in that this method comprises:
First base station needs to carry out switching of the UE between first base station and the second base station when determining, and the target switched is auxiliary small When cell in district's groups SCG is home base station cells or the cell of open mode, drilling for the cell in the target SCG is determined Into type universal terrestrial access network Cell Global Identity ECGI;
The first base station notifies the ECGI of the cell in the target SCG to second base station;
Wherein, the former base station switched between the base station that the first base station is progress UE, second base station switches between the base station Target BS.
10. according to the method described in claim 9, it is characterized in that, the first base station will especially by switching request message The ECGI of cell in the target SCG is notified to second base station.
11. according to the method described in claim 10, it is characterized in that, the first base station is specifically using the application association newly increased The mode for discussing AP information unit IE, alternatively, passing through switching request by the way of radio resource control RRC container container Message notifies the ECGI of the cell in the target SCG to second base station.
12. a kind of method switched between base station for realizing user equipment (UE), which is characterized in that this method comprises:
Second base station obtains the Evolved Universal Terrestrial wireless access of the cell in the target secondary cell group SCG that first base station is sent Network Cell Global Identity ECGI;Wherein, the former base station switched between the base station that the first base station is progress UE, second base It stands the target BS switched between the base station, the target SCG that the target SCG switches between the base station;
According to the ECGI of the cell in the target SCG, the cell in Xiang Suoshu target SCG initiates dual link for second base station Establish operation.
13. the device switched between a kind of base station for realizing user equipment (UE) characterized by comprising
First unit, for needing to carry out switching of the UE between first base station and the second base station when determining in first base station side, And when the cell in the target secondary cell group SCG switched is closed user group CSG cell, determine that the CSG of the target SCG is small Area's information;
Second unit, in the first base station side, the CSG cell information of the target SCG to be notified to second base It stands;
Wherein, the former base station switched between the base station that the first base station is progress UE, second base station switches between the base station Target BS.
14. device according to claim 13, which is characterized in that the second unit will especially by switching request message The CSG cell information of the target SCG is notified to second base station.
15. device according to claim 14, which is characterized in that the second unit is specifically using the application association newly increased The mode for discussing AP information unit IE, alternatively, passing through switching request by the way of radio resource control RRC container container Message notifies the CSG cell information of the target SCG to second base station.
16. device described in 3,14 or 15 according to claim 1, which is characterized in that the CSG cell information of the target SCG, packet It includes: the CSG cell member status information of the target SCG and/or E-UTRAN global cell mark Know ECGI and/or CSG identification information.
17. device according to claim 13, which is characterized in that the CSG cell support mixing hybrid mode or It is closed close mode.
18. the device switched between a kind of base station for realizing user equipment (UE) characterized by comprising
Third unit, for obtaining the closed user group for the target secondary cell group SCG that first base station is sent in the second base station side CSG cell information, wherein the former base station switched between the base station that the first base station is progress UE, second base station are the base The target BS switched between standing, the target SCG that the target SCG switches between the base station, and the cell in target SCG For CSG cell;
Unit the 4th, for being decided whether according to the CSG cell information of the target SCG to described in second base station side Target SCG initiates dual link and establishes operation.
19. device according to claim 18, which is characterized in that the CSG cell information of the target SCG, comprising: described The CSG cell member status information and/or E-UTRAN Cell Global Identity ECGI of target SCG, And/or CSG identification information.
20. device according to claim 19, which is characterized in that when the CSG cell information of the target SCG includes described When the CSG cell member status information of target SCG;
Unit the 4th is specifically used for: in second base station side, when the CSG cell that the target SCG is closed mode, and And according to the CSG cell member status information of the target SCG, when determining that the UE is not belonging to the member of CSG cell, determine to refuse Dual link, which is initiated, to the target SCG absolutely establishes operation.
21. device described in 8,19 or 20 according to claim 1, which is characterized in that the device further includes that claim 13-17 appoints First unit and second unit in device described in one claim.
22. the device switched between a kind of base station for realizing user equipment (UE) characterized by comprising
Unit the 5th, for needing to carry out switching of the UE between first base station and the second base station when determining in first base station side, And when the cell in the target secondary cell group SCG switched is home base station cells or the cell of open mode, described in determination The E-UTRAN Cell Global Identity ECGI of cell in target SCG;
Unit the 6th, in the first base station side, the ECGI of the cell in the target SCG to be notified to second base It stands;
Wherein, the former base station switched between the base station that the first base station is progress UE, second base station switches between the base station Target BS.
23. device according to claim 22, which is characterized in that Unit the 6th will especially by switching request message The ECGI of cell in the target SCG is notified to second base station.
24. device according to claim 23, which is characterized in that Unit the 6th is specifically using the application association newly increased The mode for discussing AP information unit IE, alternatively, passing through switching request by the way of radio resource control RRC container container Message notifies the ECGI of the cell in the target SCG to second base station.
25. according to device described in claim 22,23 or 24, which is characterized in that the device further includes that claim 13-17 appoints First unit and second unit in device described in one claim, and/or, device described in any claim of claim 18-20 In third unit and Unit the 4th.
26. the device switched between a kind of base station for realizing user equipment (UE) characterized by comprising
Unit the 7th, for obtaining the evolution of the cell in the target secondary cell group SCG that first base station is sent in the second base station side Type universal terrestrial access network Cell Global Identity ECGI;Wherein, switch between the base station that the first base station is progress UE Former base station, the target BS that second base station switches between the base station, the mesh that the target SCG switches between the base station Mark SCG;
Unit the 8th, in the second base station side, according to the ECGI of the cell in the target SCG, in Xiang Suoshu target SCG Cell initiates dual link and establishes operation.
27. device according to claim 26, which is characterized in that the device further include: any claim of claim 13-17 First unit and second unit in the device, and/or, in device described in any claim of claim 18-20 Unit three and Unit the 4th, and/or, Unit the 5th and Unit the 6th in device described in any claim of claim 22-24.
CN201510246159.6A 2015-05-14 2015-05-14 A kind of method and device switched between the base station for realizing user equipment (UE) Active CN106304218B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201510246159.6A CN106304218B (en) 2015-05-14 2015-05-14 A kind of method and device switched between the base station for realizing user equipment (UE)
PCT/CN2016/079324 WO2016180157A1 (en) 2015-05-14 2016-04-14 Method and apparatus for implementing handover of user equipment (ue) between base stations

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510246159.6A CN106304218B (en) 2015-05-14 2015-05-14 A kind of method and device switched between the base station for realizing user equipment (UE)

Publications (2)

Publication Number Publication Date
CN106304218A CN106304218A (en) 2017-01-04
CN106304218B true CN106304218B (en) 2019-05-21

Family

ID=57248573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510246159.6A Active CN106304218B (en) 2015-05-14 2015-05-14 A kind of method and device switched between the base station for realizing user equipment (UE)

Country Status (2)

Country Link
CN (1) CN106304218B (en)
WO (1) WO2016180157A1 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3346764A1 (en) 2017-01-05 2018-07-11 Panasonic Intellectual Property Corporation of America Methods and apparatuses for selecting a radio link in a mobile communication system
CN112218350B (en) * 2017-05-04 2022-10-28 上海朗帛通信技术有限公司 Method and device used in user equipment and base station for wireless communication
CN110741679B (en) * 2018-02-14 2020-12-15 Oppo广东移动通信有限公司 Secondary cell group configuration method and related product
CN110475251A (en) * 2018-05-09 2019-11-19 中兴通讯股份有限公司 A kind of method, apparatus of acquisition of information, equipment and computer storage medium
CN111093232B (en) * 2018-10-23 2021-03-30 电信科学技术研究院有限公司 Switching method, switching device and computer readable storage medium
CN110536483A (en) * 2019-02-13 2019-12-03 中兴通讯股份有限公司 Cell selection and communication control method, device, network element, terminal and storage medium
CN109819491B (en) * 2019-03-21 2021-07-06 创新维度科技(北京)有限公司 Handover control method, base station, and storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014171715A1 (en) * 2013-04-15 2014-10-23 Lg Electronics Inc. Method and apparatus for performing cell reselection in wireless communication system
CN104185227A (en) * 2014-04-14 2014-12-03 中兴通讯股份有限公司 CSG access control method and system under double connection framework
CN104378843A (en) * 2013-08-15 2015-02-25 北京三星通信技术研究有限公司 Method for supporting bearer establishment, base station and MME
CN104378793A (en) * 2013-08-12 2015-02-25 中兴通讯股份有限公司 Switching method, master control base station and controlled base station

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103581960B (en) * 2012-07-27 2019-02-12 中兴通讯股份有限公司 Capability indication information processing method and processing device
WO2015009075A1 (en) * 2013-07-17 2015-01-22 Lg Electronics Inc. Method and apparatus for performing handover procedure for dual connectivity in wireless communication system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014171715A1 (en) * 2013-04-15 2014-10-23 Lg Electronics Inc. Method and apparatus for performing cell reselection in wireless communication system
CN104378793A (en) * 2013-08-12 2015-02-25 中兴通讯股份有限公司 Switching method, master control base station and controlled base station
CN104378843A (en) * 2013-08-15 2015-02-25 北京三星通信技术研究有限公司 Method for supporting bearer establishment, base station and MME
CN104185227A (en) * 2014-04-14 2014-12-03 中兴通讯股份有限公司 CSG access control method and system under double connection framework

Also Published As

Publication number Publication date
CN106304218A (en) 2017-01-04
WO2016180157A1 (en) 2016-11-17

Similar Documents

Publication Publication Date Title
CN106304218B (en) A kind of method and device switched between the base station for realizing user equipment (UE)
US10999786B2 (en) Network management equipment for a cellular communications network
JP2020061792A (en) Wireless terminal, second core network node, and method therefor
JP5728494B2 (en) Flexible subframe
RU2633375C2 (en) Communication control device, base station, terminal device and communication control method
EP3300432B1 (en) Terminal, base station, cell access method and data transmission method
US8774823B2 (en) Cellular network load balancing
EP3177075B1 (en) Communication system, local mobile node and base station
JPWO2018029931A1 (en) Radio access network node, wireless terminal, core network node, and methods thereof
CN102740386B (en) A kind of cell switching method and base station
CN103220815B (en) A kind of inter-base station interface connection method for building up and device
US9516555B2 (en) Methods in a base station for handling handover, base station, computer program and computer program product
KR20150022240A (en) Apparatus and method for providing service to isolated user equipment in device-to-device communication system
KR20130042617A (en) Methods and apparatuses for cell selection in a communications network
CN104472004A (en) Apparatuses, methods, and computer programs for base station transceivers
TW201141249A (en) Method, apparatus and system for interference avoidance in a femtocell network
WO2014183816A1 (en) Partial offloading to pico bs
JP6414208B2 (en) Base station, radio communication system, communication method
CN105432116A (en) Cell handover method, base station and system
CN105580430A (en) Reducing signaling load to the corenetwork caused by frequent cell changes of an user equipment among small cells
US8761772B2 (en) Processing apparatus, mobile communication system, base station apparatus, method for switching connection of mobile station, and non-transitory computer readable medium storing program
US20150223127A1 (en) Method for handover management within heterogeneous networks
CN102076039A (en) Method and device for transmitting switching information
CN104811917A (en) Method for controlling, charging and locating user equipment (UE) in small cell system
US10420026B2 (en) Wireless base station, mobile station, wireless communication system, control method for wireless base station, and recording medium

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100191 No. 40, Haidian District, Beijing, Xueyuan Road

Patentee after: CHINA ACADEMY OF TELECOMMUNICATIONS TECHNOLOGY

Address before: 100191 No. 40, Haidian District, Beijing, Xueyuan Road

Patentee before: CHINA ACADEMY OF TELECOMMUNICATIONS TECHNOLOGY

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210531

Address after: 100085 1st floor, building 1, yard 5, Shangdi East Road, Haidian District, Beijing

Patentee after: DATANG MOBILE COMMUNICATIONS EQUIPMENT Co.,Ltd.

Address before: 100191 No. 40, Haidian District, Beijing, Xueyuan Road

Patentee before: CHINA ACADEMY OF TELECOMMUNICATIONS TECHNOLOGY