CN106294821A - A kind of BIM model verification method - Google Patents
A kind of BIM model verification method Download PDFInfo
- Publication number
- CN106294821A CN106294821A CN201610676957.7A CN201610676957A CN106294821A CN 106294821 A CN106294821 A CN 106294821A CN 201610676957 A CN201610676957 A CN 201610676957A CN 106294821 A CN106294821 A CN 106294821A
- Authority
- CN
- China
- Prior art keywords
- bim
- model
- attribute information
- bim model
- standard
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/80—Information retrieval; Database structures therefor; File system structures therefor of semi-structured data, e.g. markup language structured data such as SGML, XML or HTML
- G06F16/83—Querying
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/90—Details of database functions independent of the retrieved data types
- G06F16/93—Document management systems
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/30—Circuit design
- G06F30/36—Circuit design at the analogue level
- G06F30/367—Design verification, e.g. using simulation, simulation program with integrated circuit emphasis [SPICE], direct methods or relaxation methods
Landscapes
- Engineering & Computer Science (AREA)
- Theoretical Computer Science (AREA)
- Physics & Mathematics (AREA)
- Databases & Information Systems (AREA)
- General Engineering & Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Data Mining & Analysis (AREA)
- Business, Economics & Management (AREA)
- General Business, Economics & Management (AREA)
- Microelectronics & Electronic Packaging (AREA)
- Evolutionary Computation (AREA)
- Geometry (AREA)
- Stored Programmes (AREA)
Abstract
The invention provides a kind of BIM model verification method, comprise the following steps: (1) creates BIM normal data model;(2) read the attribute information of BIM model element, form the first data list, read all properties information in BIM normal data model, form the second data list;(3) the first data list is mated with the attribute information in the second data list, if the match is successful, carry out step (4), if it fails to match, carry out step (5);(4) carry out accordance inspection, if the equal conformance with standard of all elements, the then standard compliant information of output element, terminate verification;If there being element not meet standard, carry out step (5);(5) the non-compliant information of output element, feeds back in BIM model by check results, and display does not meets the element of BIM technology standard, terminates verification.The BIM model verification method that the present invention provides, can realize the automatic Verification of BIM model, and verification efficiency is high, and check results is accurate.
Description
Technical field
The present invention relates to a kind of BIM model verification method.
Background technology
In recent years, BIM technology is rapid at the application development of China's building trade, and the application of BIM technology is through engineering
Full life process, it is desirable to each phased project participant reaches unified application target, it is therefore necessary to formulate BIM technology application mark
Accurate.BIM model plays a part to generate and transmission architecture information as carrier, is the core of BIM technology application.Either country
Standard or provincial standard or company standard, the most all can make stipulations to the uniformity of BIM model.Pay at BIM model
Before using, it is necessary to according to BIM technology standard, BIM model is verified, it is ensured that BIM model meets relevant criterion.Project is respectively joined
Different BIM technology standards is there may be, after BIM model needs to convert according to different BIM technology standards from inside, side
Just can verify.Use if BIM model just consigns to each participant of project without criteria check, model criteria can be caused to mix
Disorderly, architecture information is made effectively to transmit.
Shortcoming is compared in research currently, with respect to BIM model criteria method of calibration, the most still based on desk checking, depends on
Manually check whether BIM model meets the standard that project specifies, for the BIM model of the most thousands of elements,
This method inefficiency, and easily make mistakes.
Summary of the invention
Based on above not enough, the technical problem to be solved in the present invention is to provide a kind of BIM model verification method, can realize
The automatic Verification of BIM model, verification efficiency is high, and check results is accurate.
In order to solve above technical problem, present invention employs techniques below scheme:
A kind of BIM model verification method, comprises the following steps:
(1) BIM normal data model is created;
(2) read the attribute information of BIM model element, form the first data list, read in BIM normal data model
All properties information, forms the second data list;
(3) the unique discernible attribute information of each BIM model element in the first data list is read, in the second data
List being inquired about, whether this attribute information exists, if existing, representing that the match is successful, carrying out step (4), if not existing, representing
It fails to match, carries out step (5);
(4) attribute information corresponding with the second data list for the attribute information of the first data list is carried out accordance inspection
Looking into, whether verification BIM model element meets BIM technology standard, if the equal conformance with standard of all elements, then output element conformance with standard
Information, terminate verification;If there being element not meet standard, carry out step (5);
(5) the non-compliant information of output element, feeds back in BIM model by check results, and display does not meets BIM skill
The element of art standard, terminates verification.
BIM normal data model in described step (1) includes one or more BIM technology standards.
The data structure form of the BIM normal data model in described step (1) is data base, XML, EXCEL, TXT literary composition
Shelves.
BIM normal data model in described step (1) includes the genus of the BIM model element of regulation in BIM technology standard
Property information.
Attribute information in described step (2) includes component type, element title, color, coding, physical dimension, material.
Unique discernible attribute information in described step (3) is a kind of attribute information of element or multiple attribute information
Combination.
Step (6) is also included, specifically, do not meet BIM technology standard according to check results amendment after described step (5)
Element, again carry out verification after amendment until meet standard.
Described step (6) is: after BIM model is carried out verification amendment according to one of them BIM technology standard, pass through attribute
Information matches and another BIM technology standard set up corresponding relation, and after verifying according to another BIM technology standard, batch is repaiied
Change attribute information.
In described step (5), also include the step showing non-compliant element, especially by highlighted, mark or
The mode of list shows in BIM model.
Using above technical scheme, the present invention achieves techniques below effect:
The information of BIM model element is mated with the relevant regulations of BIM technology standard by the present invention by data base, energy
Enough automatic Verification BIM models whether conformance with standard, verification efficiency is high, and check results is accurate, can be widely applied to all kinds of building work
In journey project;And user can be helped to revise BIM model comply with project BIM technology standard, it is ensured that BUILDINGS MODELS information is at item
Accurately transmit between each participant of mesh, make BIM technology play greatest benefit in the project.
Accompanying drawing explanation
Fig. 1 is the flow chart of BIM model verification method of the present invention.
Detailed description of the invention
The invention provides a kind of BIM model verification method, comprise the following steps:
(1) BIM normal data model is created, including the attribute information of the BIM model element of regulation in BIM technology standard;
Described attribute information includes component type, element title, color, coding, physical dimension, material.BIM normal data model includes
One or more BIM technology standards, the data structure form of BIM normal data model can be data base, XML, EXCEL, TXT
Document.
(2) by application programming interface (API) coding of BIM modeling software, the genus of BIM model element is read
Property information, form the first data list, read all properties information in BIM normal data model by data access,
Form the second data list;
(3) the unique discernible attribute information of each BIM model element in the first data list is read by program,
Second data list being inquired about, whether this information exists, if existing, representing that the match is successful, carries out step (4), if not existing,
Represent that it fails to match, carries out step (5);A kind of attribute information such as element title or coding can be used as unique discernible genus
Property information is mated, it would however also be possible to employ the unique discernible combination being made up of multiple attribute information is mated, such as element
Title adds coding, it is possible to make different element regions separate;
(4) attribute information corresponding with the second data list for the attribute information of the first data list is carried out accordance inspection
Looking into, whether verification BIM model element meets BIM technology standard, if the equal conformance with standard of all elements, then output element conformance with standard
Information, terminate verification;If there being element not meet standard, carry out step 5;
(5) the non-compliant information of output element, feeds back in BIM model by check results, and display does not meets BIM skill
The element of art standard, terminates verification, can show and not meet standard by the way of highlighted, mark or list in BIM model
Element;
(6) not meeting the element of BIM technology standard according to check results amendment, again carrying out after amendment verifying until meeting
Standard.BIM normal data model can include that multiple BIM technology standard, every kind of BIM technology standard include BIM model element
Multiple attribute informations.After BIM model carries out verification amendment according to some BIM technology standard, can be mated by attribute information
Corresponding relation is set up, batch modification attribute letter after verifying according to new BIM technology standard with another BIM technology standard
Breath.
As a example by metro station project, this project uses BIM technology to be designed, and needs before BIM model is delivered for use
Verify according to metro project BIM technology standard.Metro project BIM technology standard is to the type of every kind of element, color RGB
The attribute such as value, coding has concrete parameter, need to mate these parameters accurately, and other attributes are the longest during verification
Degree, width etc. then do not have concrete parameter value, only need whether judgment component comprises these attributes during verification, and without accurately coupling
Its parameter value.
By application programming interface (API) coding of BIM modeling software, read the attribute of BIM model element
Information, forms the first data list;The all properties information in BIM normal data model, shape is read by data access
Become the second data list.As follows:
First data list
Second data list
It is referred to as unique discernible attribute information with element names, in the first data list, reads element by program
The attribute information of entitled " concrete rectangular column ", if inquiring this information in the second data list, then the match is successful, if not having
Inquire, then it fails to match.Then be successively read in the first data list the type of this element, color rgb value, coding,
Length, width, highly, the information such as concrete strength, protective layer thickness, carry out accordance with the corresponding informance of the second data list
Check, it is judged that the component type of the first data list, color rgb value, coding are the most consistent with the second data list, it is judged that first
The length of data list, width, the most whether there is concrete parameter value, it is judged that the concrete strength of the first data list, protection
The minima whether layer thickness specifies more than BIM technology standard.If the equal conformance with standard of all elements, then output element conformance with standard
Information, terminate verification;If there being element not meet standard, carry out step, the non-compliant information of output element, verification is tied
Fruit feeds back in BIM model, and display does not meets the element of BIM technology standard, terminates verification.
Finally it is noted that these are only the preferred embodiments of the present invention, it is not limited to the present invention, although
Being described in detail the present invention with reference to embodiment, for a person skilled in the art, it still can be to aforementioned
Technical scheme described in each embodiment is modified, or wherein portion of techniques feature carries out equivalent, but all
Within the spirit and principles in the present invention, any modification, equivalent substitution and improvement etc. made, should be included in the protection of the present invention
Within the scope of.
Claims (9)
1. a BIM model verification method, it is characterised in that comprise the following steps:
(1) BIM normal data model is created;
(2) read the attribute information of BIM model element, form the first data list, read owning in BIM normal data model
Attribute information, forms the second data list;
(3) the unique discernible attribute information of each BIM model element in the first data list is read, in the second data list
Whether this attribute information of middle inquiry exists, if existing, represents that the match is successful, carrying out step (4), if not existing, representing coupling
Failure, carries out step (5);
(4) attribute information corresponding with the second data list for the attribute information of the first data list is carried out accordance inspection, school
Test whether BIM model element meets BIM technology standard, if all equal conformance with standard of element, the then standard compliant letter of output element
Breath, terminates verification;If there being element not meet standard, carry out step (5);
(5) the non-compliant information of output element, feeds back in BIM model by check results, and display does not meets BIM technology mark
Accurate element, terminates verification.
BIM model verification method the most according to claim 1, it is characterised in that: the BIM criterion numeral in described step (1)
One or more BIM technology standards are included according to model.
BIM model verification method the most according to claim 1, it is characterised in that: the BIM criterion numeral in described step (1)
It is data base, XML, EXCEL, TXT document according to the data structure form of model.
BIM model verification method the most according to claim 1, it is characterised in that: the BIM criterion numeral in described step (1)
The attribute information of the BIM model element of regulation in BIM technology standard is included according to model.
BIM model verification method the most according to claim 1, it is characterised in that: the attribute information bag in described step (2)
Include component type, element title, color, coding, physical dimension, material.
BIM model verification method the most according to claim 1, it is characterised in that: uniquely can recognize that in described step (3)
A kind of attribute information that attribute information is element or the combination of multiple attribute information.
BIM model verification method the most according to claim 1, it is characterised in that: after described step (5), also include step
(6), specifically, do not meet the element of BIM technology standard according to check results amendment, again carry out after amendment verifying until meeting
Standard.
BIM model verification method the most according to claim 7, it is characterised in that: described step (6) is: press BIM model
After carrying out verification amendment according to one of them BIM technology standard, it is right to be set up by attribute information coupling and another BIM technology standard
Should be related to, batch modification attribute information after verifying according to another BIM technology standard.
BIM model verification method the most according to claim 1, it is characterised in that: in described step (5), also include display
The step of non-compliant element, the mode especially by highlighted, mark or list shows in BIM model.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610676957.7A CN106294821A (en) | 2016-08-16 | 2016-08-16 | A kind of BIM model verification method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610676957.7A CN106294821A (en) | 2016-08-16 | 2016-08-16 | A kind of BIM model verification method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106294821A true CN106294821A (en) | 2017-01-04 |
Family
ID=57679238
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610676957.7A Pending CN106294821A (en) | 2016-08-16 | 2016-08-16 | A kind of BIM model verification method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106294821A (en) |
Cited By (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106934855A (en) * | 2017-03-20 | 2017-07-07 | 王凯 | Building 3D model building methods and device |
CN107341286A (en) * | 2017-05-27 | 2017-11-10 | 广州地铁设计研究院有限公司 | A kind of check method of BIM model elements |
CN107341209A (en) * | 2017-06-26 | 2017-11-10 | 清华大学 | BIM model specifications detection means and detection method based on semantic retrieval |
CN107436967A (en) * | 2017-06-26 | 2017-12-05 | 福建省建筑设计研究院 | Specialized knowledge base collaboration interventional systems and its collaboration interventional method based on BIM |
CN107766313A (en) * | 2017-10-19 | 2018-03-06 | 平安科技(深圳)有限公司 | The introduction method and its terminal of a kind of data list |
CN107967574A (en) * | 2017-12-21 | 2018-04-27 | 深圳拎得清软件有限公司 | Digitlization check of drawings method and its system based on BIM |
CN108805510A (en) * | 2017-04-27 | 2018-11-13 | 中国铁道科学研究院铁道建筑研究所 | A kind of construction drawing design BIM model compliance checking methods and system |
CN109670192A (en) * | 2017-10-13 | 2019-04-23 | 上海宝冶建设工业炉工程技术有限公司 | A kind of component ID batch extracting method based on BIM |
CN109726470A (en) * | 2018-12-27 | 2019-05-07 | 深圳市数字城市工程研究中心 | A kind of check method, device and the medium of threedimensional model index |
CN110414170A (en) * | 2019-08-05 | 2019-11-05 | 重庆建工第三建设有限责任公司 | A kind of construction pre-assembly method and system based on BIM technology |
CN110717212A (en) * | 2019-09-27 | 2020-01-21 | 贵州百胜工程建设咨询有限公司 | BIM (building information modeling) model checking method |
CN111209614A (en) * | 2019-10-21 | 2020-05-29 | 广州市第一市政工程有限公司 | BIM technology-based one-key identification method for high beam plate |
CN111667577A (en) * | 2020-04-30 | 2020-09-15 | 中铁第一勘察设计院集团有限公司 | Method for detecting geometric shape information of four-electrical engineering component model |
CN111663783A (en) * | 2020-07-16 | 2020-09-15 | 广州城建职业学院 | Assembly type building concrete pouring device based on BIM |
CN111680070A (en) * | 2020-06-03 | 2020-09-18 | 清华大学 | Building information model transferring and examining method and system based on visual programming |
CN112784341A (en) * | 2021-01-29 | 2021-05-11 | 广联达科技股份有限公司 | BIM (building information modeling) model attribute determination method and device, computer equipment and storage medium |
CN114139262A (en) * | 2021-12-02 | 2022-03-04 | 浙江华东工程数字技术有限公司 | BIM model creation method and system based on BIM model data standard |
CN114154217A (en) * | 2021-12-02 | 2022-03-08 | 浙江华东工程数字技术有限公司 | BIM model attribute verification method and system based on BIM model data standard |
CN114792036A (en) * | 2022-06-02 | 2022-07-26 | 广东工业大学 | Method, device and medium for judging conversion of standard part into non-standard part |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090125283A1 (en) * | 2007-09-26 | 2009-05-14 | David Conover | Method and apparatus for automatically determining compliance with building regulations |
CN102855229A (en) * | 2011-06-30 | 2013-01-02 | 镇江雅迅软件有限责任公司 | Self-defined statistical report form generating system based on EXCEL form |
CN103353871A (en) * | 2013-05-31 | 2013-10-16 | 国家电网公司 | Interoperation picture file checking method based on CIM/G standard |
-
2016
- 2016-08-16 CN CN201610676957.7A patent/CN106294821A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090125283A1 (en) * | 2007-09-26 | 2009-05-14 | David Conover | Method and apparatus for automatically determining compliance with building regulations |
CN102855229A (en) * | 2011-06-30 | 2013-01-02 | 镇江雅迅软件有限责任公司 | Self-defined statistical report form generating system based on EXCEL form |
CN103353871A (en) * | 2013-05-31 | 2013-10-16 | 国家电网公司 | Interoperation picture file checking method based on CIM/G standard |
Non-Patent Citations (1)
Title |
---|
孙澄宇 等: "建筑设计中BIM模型的自动规范检查方法研究", 《建筑科学》 * |
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106934855A (en) * | 2017-03-20 | 2017-07-07 | 王凯 | Building 3D model building methods and device |
CN108805510A (en) * | 2017-04-27 | 2018-11-13 | 中国铁道科学研究院铁道建筑研究所 | A kind of construction drawing design BIM model compliance checking methods and system |
CN108805510B (en) * | 2017-04-27 | 2021-11-23 | 中国铁道科学研究院铁道建筑研究所 | Construction drawing design BIM model compliance auditing method and system |
CN107341286A (en) * | 2017-05-27 | 2017-11-10 | 广州地铁设计研究院有限公司 | A kind of check method of BIM model elements |
CN107341209B (en) * | 2017-06-26 | 2020-05-12 | 清华大学 | BIM model specification detection device and detection method based on semantic retrieval |
CN107341209A (en) * | 2017-06-26 | 2017-11-10 | 清华大学 | BIM model specifications detection means and detection method based on semantic retrieval |
CN107436967A (en) * | 2017-06-26 | 2017-12-05 | 福建省建筑设计研究院 | Specialized knowledge base collaboration interventional systems and its collaboration interventional method based on BIM |
CN109670192A (en) * | 2017-10-13 | 2019-04-23 | 上海宝冶建设工业炉工程技术有限公司 | A kind of component ID batch extracting method based on BIM |
CN107766313A (en) * | 2017-10-19 | 2018-03-06 | 平安科技(深圳)有限公司 | The introduction method and its terminal of a kind of data list |
CN107766313B (en) * | 2017-10-19 | 2019-05-07 | 平安科技(深圳)有限公司 | A kind of introduction method and its terminal of data list |
CN107967574A (en) * | 2017-12-21 | 2018-04-27 | 深圳拎得清软件有限公司 | Digitlization check of drawings method and its system based on BIM |
CN109726470A (en) * | 2018-12-27 | 2019-05-07 | 深圳市数字城市工程研究中心 | A kind of check method, device and the medium of threedimensional model index |
CN110414170A (en) * | 2019-08-05 | 2019-11-05 | 重庆建工第三建设有限责任公司 | A kind of construction pre-assembly method and system based on BIM technology |
CN110717212A (en) * | 2019-09-27 | 2020-01-21 | 贵州百胜工程建设咨询有限公司 | BIM (building information modeling) model checking method |
CN111209614A (en) * | 2019-10-21 | 2020-05-29 | 广州市第一市政工程有限公司 | BIM technology-based one-key identification method for high beam plate |
CN111667577A (en) * | 2020-04-30 | 2020-09-15 | 中铁第一勘察设计院集团有限公司 | Method for detecting geometric shape information of four-electrical engineering component model |
CN111680070A (en) * | 2020-06-03 | 2020-09-18 | 清华大学 | Building information model transferring and examining method and system based on visual programming |
CN111663783A (en) * | 2020-07-16 | 2020-09-15 | 广州城建职业学院 | Assembly type building concrete pouring device based on BIM |
CN112784341A (en) * | 2021-01-29 | 2021-05-11 | 广联达科技股份有限公司 | BIM (building information modeling) model attribute determination method and device, computer equipment and storage medium |
CN112784341B (en) * | 2021-01-29 | 2023-10-27 | 广联达科技股份有限公司 | Method, device, computer equipment and storage medium for determining attribute of BIM model |
CN114139262A (en) * | 2021-12-02 | 2022-03-04 | 浙江华东工程数字技术有限公司 | BIM model creation method and system based on BIM model data standard |
CN114154217A (en) * | 2021-12-02 | 2022-03-08 | 浙江华东工程数字技术有限公司 | BIM model attribute verification method and system based on BIM model data standard |
CN114792036A (en) * | 2022-06-02 | 2022-07-26 | 广东工业大学 | Method, device and medium for judging conversion of standard part into non-standard part |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106294821A (en) | A kind of BIM model verification method | |
Edirisinghe et al. | Comparative analysis of international and national level BIM standardization efforts and BIM adoption | |
Howell et al. | Building information modeling two years later–huge potential, some success and several limitations | |
CN102855304B (en) | Variable-clause electronic contract automatic generation method in business to customer (B2C) transaction | |
CN110717212B (en) | BIM (building information modeling) model checking method | |
CN108376376A (en) | Construction engineering quality management standardized method based on BIM models | |
US20080209313A1 (en) | System and method for document tagging templates | |
CN105975562A (en) | Method and apparatus for automatically generating budget table of engineering drawing | |
EP4071697A1 (en) | Data management system, management method, and management program | |
CN113360975B (en) | View construction method, device and storage medium of building information model | |
KR101472324B1 (en) | Automatic System and method for Generating Structural Drawings | |
CN104820764A (en) | Method and device for producing electronic assembly technologic document | |
CN104732332A (en) | Order splitting method and device based on e-commerce | |
CN114154217A (en) | BIM model attribute verification method and system based on BIM model data standard | |
CN110347709A (en) | A kind of construction method and system of regulation engine | |
CN110246040A (en) | Trade management method, electronic equipment and computer storage medium based on alliance's chain | |
CN109784738A (en) | The measures and procedures for the examination and approval and examination & approval device | |
CN104951864A (en) | Systematically copied standard system data construction system in residential development | |
CN110110530A (en) | Information Rights Management method, apparatus and storage device based on BIM platform | |
Bazjanac | Improving building energy performance simulation with software interoperability | |
CN107169732A (en) | A kind of long-range endorsement system of file intelligent informationization | |
CN116415911A (en) | Method and system based on Internet of Rights (IoR) contract | |
CN106354761A (en) | Identification handling method used in electronic data of instruction books and device thereof | |
CN108171567B (en) | Order forwarding method and equipment and computer storage medium | |
CN102467443A (en) | Nuclear power station security level software testing method and system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 510010 No. 204 Huanshi West Road, Guangzhou City, Guangdong Province Applicant after: Guangzhou Metro Design and Research Institute Co., Ltd. Address before: 510010 No. 204 Huanshi West Road, Guangzhou City, Guangdong Province Applicant before: Guangzhou Metro Design & Research Institute Co., Ltd. |
|
CB02 | Change of applicant information | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170104 |
|
RJ01 | Rejection of invention patent application after publication |