CN106290141A - The method measured for plastic conduit degree of being backfilling and compacted - Google Patents

The method measured for plastic conduit degree of being backfilling and compacted Download PDF

Info

Publication number
CN106290141A
CN106290141A CN201510325739.4A CN201510325739A CN106290141A CN 106290141 A CN106290141 A CN 106290141A CN 201510325739 A CN201510325739 A CN 201510325739A CN 106290141 A CN106290141 A CN 106290141A
Authority
CN
China
Prior art keywords
plastic conduit
bar
straight
compacted
backfilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510325739.4A
Other languages
Chinese (zh)
Other versions
CN106290141B (en
Inventor
史春志
刘存华
邢福龙
陈天奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI YADA PLASTIC PRODUCTS CO Ltd
Original Assignee
SHANGHAI YADA PLASTIC PRODUCTS CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI YADA PLASTIC PRODUCTS CO Ltd filed Critical SHANGHAI YADA PLASTIC PRODUCTS CO Ltd
Priority to CN201510325739.4A priority Critical patent/CN106290141B/en
Publication of CN106290141A publication Critical patent/CN106290141A/en
Application granted granted Critical
Publication of CN106290141B publication Critical patent/CN106290141B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pipeline Systems (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a kind of method measured for plastic conduit degree of being backfilling and compacted, it comprises the steps: S1: measure the inner diameter of plastic conduit;S2: choose the length straight-bar more than the inner diameter of described plastic conduit;S3: the two ends of described straight-bar are resisted against the inwall of described plastic conduit;S4: the outer wall at described plastic conduit backfills;S5: observe the deformation of described plastic conduit until described straight-bar comes off from the inwall of described plastic conduit.The present invention has advantage easy and simple to handle, with low cost.

Description

The method measured for plastic conduit degree of being backfilling and compacted
Technical field
The present invention relates to a kind of method measured for plastic conduit degree of being backfilling and compacted.
Background technology
The quality of buried drain pipe road backfill quality, directly affects the life-span of pipeline.In prior art, right Use in job site Special compacted degree measurement apparatus to detect, but operating procedure is complicated, it is impossible to carry out Fast, easy operation.
Summary of the invention
The technical problem to be solved in the present invention is: existing plastic conduit degree of being backfilling and compacted in work progress is surveyed The problem that amount is inconvenient, it is provided that a kind of easy and simple to handle, with low cost for plastic conduit degree of being backfilling and compacted The method measured.
The present invention is to solve above-mentioned technical problem by following technical proposals:
A kind of method measured for plastic conduit degree of being backfilling and compacted, its feature is, it includes walking as follows Rapid:
S1: measure the inner diameter of plastic conduit;
S2: choose the length straight-bar more than the inner diameter of described plastic conduit;
S3: the two ends of described straight-bar are resisted against the inwall of described plastic conduit;
S4: the outer wall at described plastic conduit backfills;
S5: observe the deformation of described plastic conduit until described straight-bar comes off from the inwall of described plastic conduit. By using the length straight-bar more than the inner diameter of plastic conduit so that straight-bar is resisted against plastic conduit After inwall, can make plastic conduit that a certain degree of deformation occurs, the inwall of plastic conduit is produced by straight-bar Active force;And when the outer wall of plastic conduit is by a bigger power (more than the straight-bar active force to inwall) During effect, straight-bar can be made to come off from plastic conduit inwall.
It is preferred that the inner diameter of described plastic conduit is more than 1000mm.
It is preferred that the material of described straight-bar is wooden.
It is preferred that the 101%-103% of the inner diameter of a length of described plastic conduit of described straight-bar.Should The active force that the straight-bar of length range produces for plastic conduit inwall tamps rear plastic conduit with banketing Whether the active force close range suffered by outer wall, can be used to judgement and banket and tamp, and then judges to fill out back Compactness whether conformance with standard.
It is preferred that the 102% of the inner diameter of a length of described plastic conduit of described straight-bar.
It is preferred that among step S3:
Described straight-bar is vertically arranged at the inwall of described plastic conduit.
It is preferred that in step s 4:
Outer wall at the described plastic conduit being parallel to each other with described straight-bar backfills.Due to plastic conduit It is to be embedded in below road surface, the pressure being primarily subjected on vertical direction, and vertical pressure will cause plastic tube Road deformation in the horizontal direction, therefore, in order to prevent plastic conduit deformation in the horizontal direction, needs Plastic conduit both sides in the horizontal direction are tamped.
The most progressive effect of the present invention is: avoids use Special compacted degree measurement apparatus and detects The inconvenience brought, it is simple to detect compactness at the scene in operating process.
Accompanying drawing explanation
Fig. 1 is the flow chart of the method measured for plastic conduit degree of being backfilling and compacted of one embodiment of the invention.
Fig. 2 is the structural representation that the straight-bar of one embodiment of the invention is resisted against the inwall of plastic conduit.
Description of reference numerals:
Plastic conduit 1
Wooden straight-bar 2
Inwall 11
Outer wall 12
Detailed description of the invention
Further illustrate the present invention below by the mode of embodiment, but the most therefore limit the present invention to Among described scope of embodiments.
Embodiment
Understood incorporated by reference to Fig. 1-2, a kind of method measured for plastic conduit degree of being backfilling and compacted, its Comprise the steps:
S1: measure the inner diameter of plastic conduit 1.The preferably inner diameter plastic tube more than 1000mm Road;
S2: choose the length wooden straight-bar 2 more than the inner diameter of plastic conduit 1, wooden straight-bar 2 is long Degree is the 101%-103% of the inner diameter of plastic conduit 1, preferably 102%;
S3: wooden straight-bar 2 is vertically arranged at the inwall 11 of plastic conduit 1, wooden straight-bar 2 Two ends be resisted against the inwall 11 of plastic conduit 1;
S4: the outer wall 12 of the plastic conduit 1 being parallel to each other with wooden straight-bar 2 backfills;
S5: observe the deformation of plastic conduit 1 until wooden straight-bar 2 takes off from the inwall 11 of plastic conduit 1 Fall.
Being understood incorporated by reference to Fig. 1-2, the principle of the present invention is:
First, by length being slightly longer than the wooden straight-bar 2 of the inner diameter of plastic conduit 1 along vertically side To being supported on the inwall 11 of plastic conduit 1, plastic conduit 1 shape is made to become slightly longer on vertical direction, whole The shape of ovalize on body, and the inwall 11 of plastic conduit 1 can produce for wooden straight-bar 2 simultaneously Clamping;
Secondly, the both sides that outer wall 12 and the wooden straight-bar 2 at plastic conduit 1 is parallel to each other backfill, When banket enough consolidations when, banket and the both sides outer wall 12 of plastic conduit 1 can be formed pressure, make The outer wall 12 of plastic conduit 1 by the pressure in horizontal direction, in turn result in plastic conduit 1 perpendicular Nogata upwards deformation further.
Finally, when the deformation of plastic conduit 1 reaches to a certain degree when, wooden straight-bar 2 is from plastic tube Road 1 comes off, can tentatively judge with this, banket and tamped.
Although the foregoing describing the detailed description of the invention of the present invention, but those skilled in the art should managing Solving, these are merely illustrative of, and protection scope of the present invention is defined by the appended claims.This The technical staff in field, can be to these embodiment party on the premise of without departing substantially from the principle of the present invention and essence Formula makes various changes or modifications, but these changes and amendment each fall within protection scope of the present invention.

Claims (7)

1. one kind for plastic conduit degree of being backfilling and compacted measure method, it is characterised in that it include as Lower step:
S1: measure the inner diameter of plastic conduit;
S2: choose the length straight-bar more than the inner diameter of described plastic conduit;
S3: the two ends of described straight-bar are resisted against the inwall of described plastic conduit;
S4: the outer wall at described plastic conduit backfills;
S5: observe the deformation of described plastic conduit until described straight-bar comes off from the inwall of described plastic conduit.
2. the method measured for plastic conduit degree of being backfilling and compacted as claimed in claim 1, its feature Being, the inner diameter of described plastic conduit is more than 1000mm.
3. the method measured for plastic conduit degree of being backfilling and compacted as claimed in claim 1, its feature Being, the material of described straight-bar is wooden.
4. the method measured for plastic conduit degree of being backfilling and compacted as claimed in claim 1, its feature It is, the 101%-103% of the inner diameter of a length of described plastic conduit of described straight-bar.
5. the method measured for plastic conduit degree of being backfilling and compacted as claimed in claim 4, its feature It is, the 102% of the inner diameter of a length of described plastic conduit of described straight-bar.
6. the method measured for plastic conduit degree of being backfilling and compacted as claimed in claim 1, its feature It is, among step S3:
Described straight-bar is vertically arranged at the inwall of described plastic conduit.
7. the method measured for plastic conduit degree of being backfilling and compacted as claimed in claim 6, its feature It is, in step s 4:
Outer wall at the described plastic conduit being parallel to each other with described straight-bar backfills.
CN201510325739.4A 2015-06-12 2015-06-12 Method for the measurement of plastic conduit degree of being backfilling and compacted Active CN106290141B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510325739.4A CN106290141B (en) 2015-06-12 2015-06-12 Method for the measurement of plastic conduit degree of being backfilling and compacted

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510325739.4A CN106290141B (en) 2015-06-12 2015-06-12 Method for the measurement of plastic conduit degree of being backfilling and compacted

Publications (2)

Publication Number Publication Date
CN106290141A true CN106290141A (en) 2017-01-04
CN106290141B CN106290141B (en) 2019-01-01

Family

ID=57650112

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510325739.4A Active CN106290141B (en) 2015-06-12 2015-06-12 Method for the measurement of plastic conduit degree of being backfilling and compacted

Country Status (1)

Country Link
CN (1) CN106290141B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2659382C1 (en) * 2017-05-25 2018-06-29 Общество с ограниченной ответственностью "Группа ПОЛИМЕРТЕПЛО" (ООО "Группа ПОЛИМЕРТЕПЛО") Method for evaluating of condition of polymer pipe

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU714754B2 (en) * 1996-02-28 2000-01-13 William Grant Brown Post and pad foundation assembly
CN101008640A (en) * 2007-02-02 2007-08-01 中南大学 Integrated device for measurement and evaluation of workability of self-compacting concrete
CN102735800A (en) * 2012-06-27 2012-10-17 兰州大学 Measurement apparatus for swelling force change of buffer backfill material along with water absorption change, and measurement method thereof
CN202870056U (en) * 2012-09-26 2013-04-10 山东大学 Test device of grouting reinforcement model for weak dam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU714754B2 (en) * 1996-02-28 2000-01-13 William Grant Brown Post and pad foundation assembly
CN101008640A (en) * 2007-02-02 2007-08-01 中南大学 Integrated device for measurement and evaluation of workability of self-compacting concrete
CN102735800A (en) * 2012-06-27 2012-10-17 兰州大学 Measurement apparatus for swelling force change of buffer backfill material along with water absorption change, and measurement method thereof
CN202870056U (en) * 2012-09-26 2013-04-10 山东大学 Test device of grouting reinforcement model for weak dam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2659382C1 (en) * 2017-05-25 2018-06-29 Общество с ограниченной ответственностью "Группа ПОЛИМЕРТЕПЛО" (ООО "Группа ПОЛИМЕРТЕПЛО") Method for evaluating of condition of polymer pipe

Also Published As

Publication number Publication date
CN106290141B (en) 2019-01-01

Similar Documents

Publication Publication Date Title
CN103215975B (en) Inbuilt method for distributed type sensing cable in foundation pile
CN204402469U (en) Hydraulic fracturing geostress survey die system
CN106013269A (en) Method for testing frictional resistance of inner side wall and outer side wall of pipe pile
CN203465040U (en) Tunnel pressure box fixing device
CN110424448A (en) A kind of underground pipes road subsidence monitoring compensation system and method
CN105220687A (en) Prestressed concrete pipe pile grouting behind shaft or drift lining method fills with core reinforcing construction method
CN105806712A (en) Test device and test system for water pressure in hole
CN106871866B (en) Excavation surface bottom settlement deformation monitoring device and application method thereof
CN110468887A (en) A kind of miniature steel pipe stake body soil pressure and displacement monitoring method
CN110468888A (en) A kind of miniature steel pipe stake body displacement monitor and method
CN104988884A (en) Void deformation monitoring device for face rockfill dam and mounting method
CN115371628A (en) Deformation monitoring device for long-distance water delivery pipeline
CN106290141A (en) The method measured for plastic conduit degree of being backfilling and compacted
CN202852197U (en) Non-excavation correcting device for pipeline centre line deviation after pipe-jacking construction
CN203360989U (en) Filling and compaction device for bituminous pavement subjected to core drilling and sampling
CN103225300B (en) Process and equipment for reinforcing and strengthening concrete filling pile
CN211437420U (en) Be used for aerobic bioreactor technology gas well device of taking out notes
CN205617366U (en) A section of thick bamboo is protected in combination of pile foundation construction
CN205297457U (en) A hole sealing device for determining gas pressure
CN204043825U (en) A kind of stationary installation of horizontally disposed soil pressure cell
CN105155545A (en) Method for fixing guide tube by using guide tube fixing device in diaphragm wall slot segment pouring process
CN205246081U (en) Hidden stainless steel settlement observation point marks piece
CN109029346B (en) Integrated monitoring device and measuring method for osmotic pressure and settlement in soft soil foundation
CN204662373U (en) A deformation monitoring devices that comes to nothing for panel rock-fill dam
CN112431184A (en) Device and method for embedding and installing soil pressure cell through drilling and grouting

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant