CN106284791B - 一种无接缝预制整体式聚氨酯楼板 - Google Patents

一种无接缝预制整体式聚氨酯楼板 Download PDF

Info

Publication number
CN106284791B
CN106284791B CN201510286794.7A CN201510286794A CN106284791B CN 106284791 B CN106284791 B CN 106284791B CN 201510286794 A CN201510286794 A CN 201510286794A CN 106284791 B CN106284791 B CN 106284791B
Authority
CN
China
Prior art keywords
floor
polyurethane
seamless
structural framing
secondary beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510286794.7A
Other languages
English (en)
Other versions
CN106284791A (zh
Inventor
谢青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Tianchuangjicheng Technology Industry Co Ltd
Original Assignee
Hunan Tianchuangjicheng Technology Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Tianchuangjicheng Technology Industry Co Ltd filed Critical Hunan Tianchuangjicheng Technology Industry Co Ltd
Priority to CN201510286794.7A priority Critical patent/CN106284791B/zh
Publication of CN106284791A publication Critical patent/CN106284791A/zh
Application granted granted Critical
Publication of CN106284791B publication Critical patent/CN106284791B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sink And Installation For Waste Water (AREA)

Abstract

发明名称一种无接缝预制整体式聚氨酯楼板摘要本发明涉及一种用于卫生间的无接缝预制整体式聚氨酯楼板,包括:结构框架和聚氨酯楼板,结构框架包括采用金属连接件相互连接的四根主梁和六根次梁,主梁和次梁采用由木方正交叠放胶合成重木结构的层积材;聚氨酯楼板中预埋有供排水系统管道、电线和安装设备的洞口,在工厂模块化生产时,在模具中加入结构框架及预埋金属连接件,然后将供排水系统管道、电线固定在里面,同时预留设备安装的空洞,最后用聚氨酯材料浇筑为一整体楼板直接运到工地直接安装。本发明具有防水性能好、工厂化生产、施工周期短的优点,具有良好的推广应用前景。

Description

一种无接缝预制整体式聚氨酯楼板
技术领域
本发明涉及一种集成式木屋卫生间楼板预制技术,属于建筑模块工厂制作及工地现场组装楼板材料领域。
背景技术
随着生活水平的不断发展,人们更加注重健康环保的居住环境,木屋能够满足人们的需求。目前的木结构房屋卫生间楼板防水性能差,且楼板和管道需要现场铺设,需要耗费大量的人力、物力,且施工速度慢。聚氨酯材料具有导热系数低、防火、耐高温、耐老化、吸水率低等优点,目前在建筑保温材料、电力和环保领域得到广泛的应用,将聚氨酯应用于卫生间楼板,并在工厂进行模块化后直接运到工地现场组装,可有效克服现有木结构房屋卫生间楼板的缺点。
经对现有技术的文献检索发现,中国专利申请号为201220211667.2,发明专利名称为:一种轻质保温预制楼板,该技术涉及一种轻质保温预制楼板技术,该技术在轻质保温板的框体内填充有轻质保温颗粒,在轻质保温板前后两侧铺设钢丝网,钢丝网的前后两侧浇筑有硂层,虽然该技术中的轻质保温板采用聚氨酯发泡板,然而在楼板中需要浇筑硂层,工序复杂,且无法在有效预留卫生间楼板管道及卫视器具安装孔洞的同时解决防水问题。
检索还发现,中国专利申请号为201320479684.9,实用新型名称为:一种波纹钢板阻燃聚氨酯复合房屋结构,该技术公开了一种波纹钢板阻燃聚氨酯复合房屋结构技术,该技术中的墙体和楼板由双层的波纹钢板阻燃聚氨酯复合板组成,在墙体顶部焊接加强板,楼板焊接固定于加强板上,所述波纹钢板阻燃聚氨酯复合板包括上波纹钢板、下波纹钢板和阻燃聚氨酯层,可以看出,该技术并未在解决卫生间楼板需要有效预留卫生间楼板管道及卫视器具安装孔洞的同时解决防水问题。
本发明提出了一种无接缝预制整体式聚氨酯楼板,旨在克服木屋卫生间楼板的缺点,解决一般木结构地板防水性能差的问题,尤其是卫生间,延长楼板使用寿命,同时克服一般现代木结构管道需要现场铺设,耗费人力、物力,施工速度慢的缺点,为木屋卫生间楼板的工厂制作及工地现场组装提供新方法。
发明内容
本发明要解决的技术问题是针对现有技术存在的不足,提出一种无接缝预制整体式聚氨酯楼板,解决传统木结构卫生间楼板存在的问题。
本发明通过以下技术方案实现,所述的无接缝预制整体式聚氨酯楼板包括结构框架和聚氨酯楼板,所述的结构框架包括四根主梁和六根次梁,所述的主梁和次梁采用层积材,所述的层积材为木方正交叠放胶合成重木结构,所述的主梁和次梁采用金属连接件连接;所述的聚氨酯楼板中包括供排水系统管道、电线和安装设备的洞口。
所述的无接缝预制整体式聚氨酯楼板在工厂进行加工,首先在工厂制作模具,在模具中加入结构框架及预埋金属连接件,然后将供排水系统管道、电线固定在里面,同时预留设备安装的洞口,最后用聚氨酯材料浇筑为一整体楼板直接运到工地直接安装。
与现有技术相比,本发明具有以下优点:
1、本发明采用无接缝预制整体式操作,现场直接拼装,克服了传统楼板施工周期长、速度慢等缺点;
2、运用聚氨酯材料作为楼板,提高卫生间楼板的防水性能;
3、楼板工厂化生产,现场组装,缩短了现场施工工期。
附图说明
图1为本发明结构框架布置图。
图2为本发明的污水管道布置图。
图3为本发明的冷热水管道布置图。
图4为本发明的供电线路布置图。
图5为本发明的聚氨酯浇筑平面图。
图6为本发明的卫生间布置平面图。
附图标号:1、主梁;2、次梁;3、污水管道;4、地漏;5、排污管;6、进水口;7、淋浴间位置出水口;8、坐便器位置出水口;9、盥洗台冷水出水口;
10、盥洗台热水出水口;11、淋浴间位置出水口;12、热水管进水口;13、排风扇电线;14、照明设备电线;15、聚氨酯楼板;16、竖向排污管;17、竖向排风管;
18、金属连接件;19、主体框架;20、冷水管;21、热水管。
具体实施方式
下面结合附图对本发明的实施方式作详细说明。
如图1所示,在工厂制作四根主梁1(1a,1b,1c,1d)和六根次梁2(2a,2b),所述的主梁1和次梁2采用层积材,所述的层积材为木方正交叠放胶合成重木结构, 四根主梁1和六根次梁2通过金属连接件18(18a,18b)紧密连接,同时在每根主梁的端头位置预装金属连接件18。如图2所示,在结构框架上安装污水管道3,在管道上部预装地漏4(4a,4b,4c),在坐便器的位置加装排污管5,并将排污管5固定在框架梁上,同时使排污管5保持1%的坡度。
如图3所示,在结构框架上预装冷水管20和热水管21,在冷水管上预装进水口6和坐便器位置出水口8、盥洗台冷水出水口9、淋浴间位置出水口7,在热水管21上预装热水管进水口12、盥洗台热水出水口10、淋浴间位置出水口11。
如图4所示,在结构框架上预装排风扇电线13和照明设备电线14,排风扇电线13和照明设备电线14穿过框架梁上面预留的孔洞,并且将其固定在框架梁上。
如图5所示,制作好模具,将结构框架和预埋的设备放在模具里面,将聚氨酯倒入模具里面,等待风干成型,成型之后形成聚氨酯楼板15。
如图6所示,在建筑施工过程中,聚氨酯楼板15可以直接安装在建筑主体框架19上面,将聚氨酯楼板15里的污水管道3与管道井里的竖向排污管16连接,将聚氨酯楼板15里的冷水管20和热水管21分别和管道井里的冷水管22和热水管23连接,将聚氨酯楼板15里的照明设备电线14和排风扇电线13与其他楼板的电线连接。

Claims (2)

1.一种用于卫生间的无接缝预制整体式聚氨酯楼板,其特征在于所述的无接缝预制整体式聚氨酯楼板包括结构框架和聚氨酯楼板,所述的结构框架包括四根主梁和六根次梁,所述的聚氨酯楼板包括供排水系统管道、电线和安装设备的洞口,所述的主梁和次梁采用层积材,所述的层积材为木方正交叠放胶合成重木结构,所述的主梁和次梁采用金属连接件连接,所述的无接缝预制整体式聚氨酯楼板在工厂进行加工,首先在工厂制作模具,在模具中加入结构框架及预埋金属连接件,然后将供排水系统管道、电线固定在里面,同时预留设备安装的洞口,最后用聚氨酯材料浇筑为一整体。
2.根据权利要求1所述的无接缝预制整体式聚氨酯楼板,其特征在于,所述的无接缝预制整体式聚氨酯楼板浇筑后是结构框架和聚氨酯楼板浇筑在一起的整体式楼板,可运往工地直接安装。
CN201510286794.7A 2015-05-31 2015-05-31 一种无接缝预制整体式聚氨酯楼板 Active CN106284791B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510286794.7A CN106284791B (zh) 2015-05-31 2015-05-31 一种无接缝预制整体式聚氨酯楼板

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510286794.7A CN106284791B (zh) 2015-05-31 2015-05-31 一种无接缝预制整体式聚氨酯楼板

Publications (2)

Publication Number Publication Date
CN106284791A CN106284791A (zh) 2017-01-04
CN106284791B true CN106284791B (zh) 2018-09-14

Family

ID=57654969

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510286794.7A Active CN106284791B (zh) 2015-05-31 2015-05-31 一种无接缝预制整体式聚氨酯楼板

Country Status (1)

Country Link
CN (1) CN106284791B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102018107362A1 (de) 2018-03-28 2019-10-02 Werk Eins Gmbh Verfahren zum Herstellen einer Sanitäreinheit
DE102018107383A1 (de) 2018-03-28 2019-10-02 Werk Eins Gmbh Sanitäreinheit und Verfahren zum Herstellen einer solchen

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1223253A1 (de) * 2001-01-08 2002-07-17 Geberit Technik Ag Sanitäre Einrichtung
CN2804273Y (zh) * 2005-06-20 2006-08-09 韦江平 用于集成组装式活动房屋的卫生间底盘
CN104120822A (zh) * 2013-04-25 2014-10-29 苏州有巢氏系统卫浴有限公司 一种整体卫浴框架发泡瓷砖墙板及其制造方法
CN204356962U (zh) * 2014-12-10 2015-05-27 张跃 一种预制的卫生间楼板
CN204645359U (zh) * 2015-05-31 2015-09-16 湖南天创集成科技实业有限公司 一种无接缝预制整体式聚氨酯楼板

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1223253A1 (de) * 2001-01-08 2002-07-17 Geberit Technik Ag Sanitäre Einrichtung
CN2804273Y (zh) * 2005-06-20 2006-08-09 韦江平 用于集成组装式活动房屋的卫生间底盘
CN104120822A (zh) * 2013-04-25 2014-10-29 苏州有巢氏系统卫浴有限公司 一种整体卫浴框架发泡瓷砖墙板及其制造方法
CN204356962U (zh) * 2014-12-10 2015-05-27 张跃 一种预制的卫生间楼板
CN204645359U (zh) * 2015-05-31 2015-09-16 湖南天创集成科技实业有限公司 一种无接缝预制整体式聚氨酯楼板

Also Published As

Publication number Publication date
CN106284791A (zh) 2017-01-04

Similar Documents

Publication Publication Date Title
CN101353929B (zh) 产业化节能建筑房屋
CN109072612B (zh) 预组装的壁板、多楼层建筑物、建造公共设施壁的方法
CN105421826A (zh) 一种装配式整体卫生间及其建造方法
CN101910530A (zh) 预制建筑构件及组装设备
WO2007134517A1 (fr) Mur de béton composite travaillant en cisaillement pour isolation thermique
CN104695662B (zh) 石材饰面预制外墙板及其生产方法及外墙体系
CN106522359A (zh) 一种全装配式村镇民居类复合墙结构体系及其施工方法
CN106088463A (zh) 一种预制混凝土外墙板及其制备方法
CN105649196A (zh) 一种模块化的建筑体系
CN106284791B (zh) 一种无接缝预制整体式聚氨酯楼板
CN206189685U (zh) 模块化集成楼板及房屋
CN204645359U (zh) 一种无接缝预制整体式聚氨酯楼板
CN106368358A (zh) 模块化集成楼板及房屋
CN105369955B (zh) 一种集成装配式楼板
CN209384432U (zh) 一种可循环使用的预制山墙及其连接构造
CN208039610U (zh) 装配式一体化保温墙板
CN207063610U (zh) 一种由预制构件拼接的变电站建筑
CN201883591U (zh) 一种毛细管吊顶安装结构
CN210105050U (zh) 拐角式高效保温格构式模壳
CN206205140U (zh) 一种全装配式村镇民居类复合墙结构体系
CN201865303U (zh) 用于提高民用建筑首层温度的地面保温系统
CN201865302U (zh) 用于解决民用建筑首层温度偏低的地面保温系统
CN202073176U (zh) 砼密柱石膏复合墙板与加强型砼轻框配置中高层混合结构
CN209779964U (zh) 直板高效保温格构式模壳
CN201517255U (zh) 整体水泥复合保温外墙

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant