CN106269873A - Utilize the method that holding pit and single heating furnace tandem rolling produce hot-rolled orientation silicon steel - Google Patents

Utilize the method that holding pit and single heating furnace tandem rolling produce hot-rolled orientation silicon steel Download PDF

Info

Publication number
CN106269873A
CN106269873A CN201610610322.7A CN201610610322A CN106269873A CN 106269873 A CN106269873 A CN 106269873A CN 201610610322 A CN201610610322 A CN 201610610322A CN 106269873 A CN106269873 A CN 106269873A
Authority
CN
China
Prior art keywords
silicon steel
rolling
heating furnace
blank
special
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610610322.7A
Other languages
Chinese (zh)
Other versions
CN106269873B (en
Inventor
王新江
李勇
韦弦
程官江
张振申
王新志
商存亮
武郁璞
王中岐
王超海
潘宋军
李洪燃
陈冬至
孙广辉
邓杭州
李栋
李敬
夏志升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anyang Iron and Steel Co Ltd
Original Assignee
Anyang Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anyang Iron and Steel Co Ltd filed Critical Anyang Iron and Steel Co Ltd
Priority to CN201610610322.7A priority Critical patent/CN106269873B/en
Publication of CN106269873A publication Critical patent/CN106269873A/en
Application granted granted Critical
Publication of CN106269873B publication Critical patent/CN106269873B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B3/00Rolling materials of special alloys so far as the composition of the alloy requires or permits special rolling methods or sequences ; Rolling of aluminium, copper, zinc or other non-ferrous metals
    • B21B3/02Rolling special iron alloys, e.g. stainless steel

Abstract

The present invention relates to the production method of hot-rolled orientation silicon steel in metallurgical technical field of steel rolling, it is specifically related to a kind of method utilizing holding pit and single heating furnace tandem rolling to produce hot-rolled orientation silicon steel, the orientation silicon steel strand that the present invention utilizes silicon steel special-purpose thermal insulation hole to produce steel-making continuous casting carries out insulation buffering, by planned adjustment and the layout production schedule, use single heating furnace, namely use silicon steel special heating furnace that orientation silicon steel is heated, when rolling by orientation silicon steel lacing at different rolling units, in units of rolling unit, the steel grade met in the orientation silicon steel of rolling condition and common heating furnace is carried out tandem rolling.The present invention utilize silicon steel special-purpose thermal insulation hole insulation silicon steel blank can buffer smelting and rolling rhythm between mismatch, simultaneously ensure silicon steel blank will not cold conditions shove charge, reduce scrappage;Silicon steel blank and other steel grade blanks are used to carry out subdivision tandem rolling, it is possible to increase rolling efficiency, cost-effective.

Description

Utilize the method that holding pit and single heating furnace tandem rolling produce hot-rolled orientation silicon steel
Technical field
The present invention relates to the production method of hot-rolled orientation silicon steel in metallurgical technical field of steel rolling, be specifically related to a kind of utilization The method that holding pit and single heating furnace tandem rolling produce hot-rolled orientation silicon steel.
Background technology
Orientation silicon steel production technology is extremely complex, controls difficulty relatively big, is often described as the artware in steel products.Due to The particularity of its steel grade, alloy content is higher, therefore orientation silicon steel hot rolled coil generally individually uses heating furnace direct loading process to coordinate heat even Milling train group carries out continuous rolling production.Major control difficult point is embodied in: 1. take direct loading process between smelting procedure and rolling process Rhythm of production matching poor;2. the blank that smelting procedure is produced can not cold conditions shove charge, the most all scrap, it is necessary to adopt The mode of cut-off tipping stove or hot shove charge is carried out;3. orientation silicon steel is extremely strict to heating furnace heating technological requirement, heating temperature Degree requires at 1250 DEG C ~ 1350 DEG C, higher than general steel grade temperature requirement, and time inside furnace requires no less than 180min, ratio one simultaneously As steel grade time requirement length many, general steel grade heat time heating time is 120-150min, therefore can not load in mixture with other steel grades, Zhi Nengdan Solely shove charge heating;4. rolling specs is relatively thin, and the rolling milimeter number of monovolume is longer, and hot tandem is to ensure stablizing of rolling in addition Property need to arrange hot rolling material and transition blank at same unit, therefore same rolling unit can not continuous rolling too much, need subdivision Rolling;5. longer for heat time heating time due to orientation silicon steel, it is sometimes desirable to waiting steel rolling, during platform, production capacity is relatively low, and production efficiency is the highest;⑥ Orientation silicon steel needs the heating-up temperature that long-time guarantee is high, the bigger infringement of existence to heating furnace, the cleaning of heating furnace and maintenance Difficulty is greatly, costly.Owing to there is many controlling difficulties and restrictive condition, so orientation silicon steel quantity-produced technology controlling and process Difficulty is very big, and production chains is poor, once goes wrong, and will occur that batch is scrapped, the most disposably can only produce 600 ~ 800 tons, production cost is higher.How to make the motility of its technology controlling and process more preferably, blank less to the influence degree of production efficiency The risk that batch is scrapped is less, production cost is more easily controlled, the problem that the most relevant metallargist endeavours research.
Combining big production actual process requirement for this present invention, buffer capacity is strong, production efficiency is high, safety to develop one The rolling process flow process of the hot-rolled orientation silicon steel volume that coefficient is high, and utilization of succeeding in big production, its technique is prone to Realizing, motility is of a relatively high, it is simple to evading the risk that blank batch is scrapped, its product quality has obtained Downstream Market use simultaneously The consistent accreditation at family.
Summary of the invention
The invention provides a kind of method utilizing holding pit and single heating furnace tandem rolling to produce hot-rolled orientation silicon steel, change Enter heating furnace steel loading mode, use single heating furnace heating, use when rolling orientation silicon steel point rolling unit and other steel grades to press The mode of tandem rolling is carried out, it is achieved that long-time production continuously, improves production efficiency, reduces production cost.
In sum, in order to solve above-mentioned technical problem, the technical scheme of present invention is achieved in that
A kind of method utilizing holding pit and single heating furnace tandem rolling to produce hot-rolled orientation silicon steel, it is characterised in that the method Comprise the steps:
Step one: the rolling scaduled establishment of silicon steel: when confirming plan number, rolling mode, quantity, specification, stock number and beginning Between, enroll plan;
Step 2: judge that blank is the most qualified: after silicon steel strand cuts off online, be delivered to online through blank roller-way by silicon steel blank District of weighing/confirm/detect/judge is made to determine whether qualified, if qualified, proceeds to step 3;Otherwise by underproof silicon steel base Material proceeds to the storage area that rolls off the production line;
Step 3: determine whether direct shove charge: silicon steel blank qualified in described step 2 is transported to blank shove charge and confirms district, Described blank shove charge confirms that district confirms that silicon steel special heating furnace possesses steel loading condition and is then directly loadable into described silicon steel special heating furnace; Otherwise described silicon steel blank is directly rolled off the production line and load in the most preheated silicon steel special-purpose thermal insulation hole, by that analogy;
Step 4: the blank in rolling common heating furnace: after silicon steel special heating furnace described in step 3 is filled, special to silicon steel Carrying out heating operation with heating furnace, heating-up temperature is 1250 DEG C ~ 1350 DEG C, and heat time heating time is no less than 180min, now milling train The blank utilizing common heating furnace to heat normally rolls;
Step 5: the transition blank in rolling common heating furnace: apart from described step 4 silicon steel special heating furnace heating operation When completing also to remain 20-30min, milling train starts to roll the silicon steel transition blank of described common heating furnace, and successive optimization rolling die Type;
Step 6: the silicon steel blank in rolling silicon steel special heating furnace: milling train starts to roll in described step 4 that silicon steel is special to be added Silicon steel blank in hot stove, described common heating furnace enters heating and thermal insulation state;Described silicon steel special heating furnace often goes out one block of silicon While steel blank enters rolling sequence, in blank roller-way or silicon steel special-purpose thermal insulation are cheated, supplement one block of silicon steel blank load silicon steel In special heating furnace, it is ensured that fill silicon steel blank all the time in described silicon steel special heating furnace, the like, until first silicon steel Rolling unit terminates;
Step 7: again rolling common heating furnace in blank: the most described first silicon steel rolling unit terminates, and start into Enter heating and thermal insulation state;If also failing to load the silicon steel blank of described silicon steel special heating furnace, the most directly roll off the production line loading silicon steel The insulation of special-purpose thermal insulation hole;Now milling train then starts again to roll the blank in described common heating furnace, until waiting until next silicon The arrival of steel rolling unit;
Step 8: the rolling of silicon steel rolling unit is carried out according to described step 5 to step 7, by that analogy, until silicon steel blank All rolling terminates.
Further, in described step 3, silicon steel special-purpose thermal insulation hole is persistently incubated by 400 DEG C of-600 DEG C of heat-retaining conditions.
Further, in described step 4, common heating furnace is provided with no less than 2.
Further, in described step 6, first silicon steel rolling unit is all in terminating to refer to silicon steel special heating furnace meets Heating, the silicon steel blank of rolling condition all roll, and in silicon steel special heating furnace, remaining silicon steel blank temporarily can not meet and adds Heat, the condition of rolling.
Further, described in steps in silicon steel refer both to orientation silicon steel.
Present invention beneficial effect compared to existing technology:
The orientation silicon steel strand that the present invention mainly utilizes silicon steel special-purpose thermal insulation hole to produce steel-making continuous casting carries out insulation buffering, By planned adjustment and the layout production schedule, use single heating furnace, namely use silicon steel special heating furnace to orientation silicon steel Heat, when rolling by orientation silicon steel lacing at different rolling units, by satisfied rolling bar in units of rolling unit Steel grade in the orientation silicon steel of part and common heating furnace carries out tandem rolling, specifically:
(1) insulation silicon steel blank in silicon steel special-purpose thermal insulation hole is utilized can to buffer the mismatch between smelting and rolling rhythm, it is ensured that The motility of production process and safety, disposable volume of production continuously can improve about 1 times;
(2) utilize blank shove charge confirm district determine whether direct shove charge, confirm direct shove charge then by direct for silicon steel blank shove charge, no Then silicon steel blank is directly rolled off the production line and load in the most preheated silicon steel special-purpose thermal insulation hole, it is ensured that silicon steel blank will not cold conditions dress Stove, reduces scrappage;
(3) use single heating furnace, namely use silicon steel special heating furnace to concentrate loading silicon steel blank, beneficially energy efficient, stable Heating technique, it is possible to alleviate the damage to heating furnace of the silicon steel high-temperature heating, it is simple to the concentration cleaning of silicon steel heating furnace and maintenance;
(4) silicon steel blank and other steel grade blanks are used to carry out subdivision tandem rolling, it is possible to increase rolling efficiency, it is to avoid milling train Deng steel phenomenon, cost-effective.
Detailed description of the invention
The present invention is further described, in order to be more fully understood that the present invention below in conjunction with specific embodiment, but the present invention Protection domain be not limited to this.
As a example by the present embodiment uses an actual production of hot-rolled orientation silicon steel, one utilizes holding pit and single heating furnace to hand over The method of fork Rolling Production hot-rolled orientation silicon steel, the method comprises the steps:
Step one: according to orientation silicon steel planning, confirmation enterprise number is H1620321, and rolling width is 1250mm, thickness is 2.3mm, it is contemplated that produce volume 80, often volume substance 20t, altogether 1600t, the 1st piece of silicon steel blank continuous casting cut-out moment is in the works 11:30, the numbered 6M01007K01 of silicon steel blank.
Step 2: judge that blank is the most qualified: the 1st block of silicon steel blank that will cut off in step one, warm conveying blank Roller-way is delivered to blank online weighing/confirmation/detection/judgement district, carries out Weighing, heat/lot number confirmation, if silicon steel blank Judge qualified to be transported to subsequent processing, proceed to step 3;If silicon steel blank judges defective, then underproof silicon steel blank is proceeded to Roll off the production line storage area.
Step 3;Determine whether direct shove charge: take the direct shove charge of strand or silicon steel special-purpose thermal insulation pit casting base hot charging shove charge Mode, will be through judging that qualified silicon steel blank is transported to blank shove charge through blank roller-way and confirms district, blank shove charge in step 2 Confirm that district confirms whether silicon steel special heating furnace possesses the condition of the direct shove charge of silicon steel blank, if possessing steel loading condition, directly fills Enter silicon steel special heating furnace;Now silicon steel special heating furnace possesses steel loading condition, and silicon steel blank is directly loadable into the special heating of silicon steel Stove, the moment is 11:50;By that analogy, silicon steel blank is sequentially loaded into silicon steel special heating furnace;Loading the 29th block of silicon steel blank After, silicon steel special heating furnace is filled;Blank shove charge confirms that district confirms that silicon steel special heating furnace does not possess direct shove charge condition, subsequently Deliver to blank shove charge and confirm that the silicon steel blank in district is then loaded by directly rolling off the production line in the most preheated silicon steel special-purpose thermal insulation hole.Silicon steel Special-purpose thermal insulation hole is persistently incubated by 400 DEG C of-600 DEG C of heat-retaining conditions during rolling smelted by silicon steel.
Step 4: the blank in rolling common heating furnace: the silicon steel special heating furnace of silicon steel blank will be filled in step 3 Carrying out heating operation, heating-up temperature is 1250 DEG C ~ 1350 DEG C, and heat time heating time is no less than 180min, and milling train now rolls commonly The Q235B blank of heating furnace.
Step 5: the transition blank in rolling common heating furnace: when 16:40, distance silicon steel blank heating completes also to remain During 20min, milling train starts to roll the silicon steel transition blank Q235B of common heating furnace, and now mill milling specification is progressively to orientation Silicon steel goal standard is close, and successive optimization rolling model;By calculating after having rolled last block transition blank, silicon steel base Material heating should meet rolling condition, i.e. silicon steel blank heating temperature at 1250 DEG C ~ 1350 DEG C, and silicon steel preform heating time is At more than 180min, and start silicon steel blank is carried out block-by-block rolling;Transition blank is because orientation silicon steel hot rolled coil specification relatively Thin, typically within 2.5mm, and hot tandem needs progressively to be rolled to thin by thickness, therefore needs plan ahead transition blank.
Step 6: the silicon steel blank in rolling silicon steel special heating furnace: when 17:05, it is special that milling train starts to roll silicon steel The 1st block of silicon steel blank in heating furnace, common heating furnace enters heating and thermal insulation state;Silicon steel special heating furnace often goes out one block of silicon steel While blank enters rolling sequence, in blank roller-way or silicon steel special-purpose thermal insulation are cheated, supplement one block of silicon steel blank loading silicon steel special With in heating furnace, it is ensured that fill silicon steel blank in silicon steel special heating furnace all the time, the like, until first silicon steel rolling is single Unit terminates.
Step 7: the blank in rolling common heating furnace again: milling train is when 17:56 rolls the 14th block of silicon steel, and silicon steel is special Being unsatisfactory for heating rolling process conditions with the 15th block of silicon steel blank in heating furnace, now silicon steel first module rolling terminates, And initially enter heating and thermal insulation state;If also failing to load the silicon steel blank of silicon steel special heating furnace, loading of the most directly rolling off the production line The insulation of silicon steel special-purpose thermal insulation hole, now milling train starts to roll the Q235B blank of common heating furnace, until waiting until that next silicon steel rolls The arrival of unit processed.
Step 8: the rolling of silicon steel rolling unit is carried out according to step 5 to step 7, by that analogy, until silicon steel blank All rolling terminates.
Being noted that above-described embodiment is illustrative not limiting to technical solution of the present invention, art is general The equivalent leading to technical staff or other amendment made according to prior art, as long as beyond technical solution of the present invention Thinking and scope, within should be included in interest field of the presently claimed invention.

Claims (4)

1. one kind utilizes the method that holding pit and single heating furnace tandem rolling produce hot-rolled orientation silicon steel, it is characterised in that the party Method comprises the steps:
Step one: the rolling scaduled establishment of silicon steel: when confirming plan number, rolling mode, quantity, specification, stock number and beginning Between enroll plan;
Step 2: judge that blank is the most qualified: after orientation silicon steel strand cuts off online, be delivered to through blank roller-way by silicon steel blank It is qualified that online weighing/confirmation/detection/judgement district is made to determine whether, if qualified, proceeds to step 3;Otherwise by underproof silicon Steel blank proceeds to the storage area that rolls off the production line;
Step 3: determine whether direct shove charge: silicon steel blank qualified in described step 2 is transported to blank shove charge and confirms district, Described blank shove charge confirms that district confirms that silicon steel special heating furnace possesses steel loading condition and is then directly loadable into described silicon steel special heating furnace; Otherwise described silicon steel blank is directly rolled off the production line and load in the most preheated silicon steel special-purpose thermal insulation hole;By that analogy;
Step 4: the blank in rolling common heating furnace: after silicon steel special heating furnace described in step 3 is filled, silicon steel is special Heating furnace carries out heating operation according to orientation silicon steel heating technique, and heating-up temperature is 1250 DEG C ~ 1350 DEG C, and heat time heating time is many In 180min, the blank that now milling train utilizes common heating furnace to heat normally rolls;
Step 5: the transition blank in rolling common heating furnace: apart from described step 4 silicon steel special heating furnace heating operation When completing also to remain 20-30min, according to silicon steel rolling specs requirement, milling train starts to roll the silicon steel transition of described common heating furnace Blank, and successive optimization rolling model;
Step 6: the silicon steel blank in rolling silicon steel special heating furnace: milling train starts to roll in described step 4 that silicon steel is special to be added Silicon steel blank in hot stove, described common heating furnace enters heating and thermal insulation state;Described silicon steel special heating furnace often goes out one block of silicon While steel blank enters rolling sequence, in blank roller-way or silicon steel special-purpose thermal insulation are cheated, supplement one block of silicon steel blank load silicon steel In special heating furnace, it is ensured that fill silicon steel blank all the time in described silicon steel special heating furnace, the like, until first silicon steel Rolling unit terminates;
Step 7: the blank in rolling common heating furnace again: the most described first silicon steel rolling unit terminates, and initially enters Heating and thermal insulation state;If also failing to load the silicon steel blank of described silicon steel special heating furnace, the loading silicon steel that the most directly rolls off the production line is special It is incubated with holding pit;Now milling train then starts again to roll the blank in described common heating furnace, until waiting until next silicon steel The arrival of rolling unit;
Step 8: the rolling of silicon steel rolling unit is carried out according to described step 5 to step 7, by that analogy, until silicon steel blank All rolling terminates.
A kind of side utilizing holding pit and single heating furnace tandem rolling to produce hot-rolled orientation silicon steel the most according to claim 1 Method, it is characterised in that in described step 2, silicon steel special-purpose thermal insulation hole is persistently incubated by 400 DEG C of-600 DEG C of heat-retaining conditions.
A kind of side utilizing holding pit and single heating furnace tandem rolling to produce hot-rolled orientation silicon steel the most according to claim 1 Method, it is characterised in that in described step 4, common heating furnace is provided with no less than 2.
A kind of side utilizing holding pit and single heating furnace tandem rolling to produce hot-rolled orientation silicon steel the most according to claim 1 Method, it is characterised in that the silicon steel in described step one ~ step 8 is orientation silicon steel.
CN201610610322.7A 2016-07-29 2016-07-29 Utilize the method for holding pit and single heating furnace tandem rolling production hot-rolled orientation silicon steel Active CN106269873B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610610322.7A CN106269873B (en) 2016-07-29 2016-07-29 Utilize the method for holding pit and single heating furnace tandem rolling production hot-rolled orientation silicon steel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610610322.7A CN106269873B (en) 2016-07-29 2016-07-29 Utilize the method for holding pit and single heating furnace tandem rolling production hot-rolled orientation silicon steel

Publications (2)

Publication Number Publication Date
CN106269873A true CN106269873A (en) 2017-01-04
CN106269873B CN106269873B (en) 2018-01-05

Family

ID=57662834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610610322.7A Active CN106269873B (en) 2016-07-29 2016-07-29 Utilize the method for holding pit and single heating furnace tandem rolling production hot-rolled orientation silicon steel

Country Status (1)

Country Link
CN (1) CN106269873B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110388834A (en) * 2019-07-29 2019-10-29 山东泰山钢铁集团有限公司 A method of it improving steel plant and is heat-fed steel slab rate
CN111020171A (en) * 2019-12-18 2020-04-17 东北轻合金有限责任公司 Method for heating aluminum alloy ingot casting by using continuous charging mode of push type heating furnace
CN113020283A (en) * 2021-03-18 2021-06-25 鞍钢股份有限公司 Shape control method for oriented silicon steel hot-rolled steel strip
CN114309080A (en) * 2021-11-29 2022-04-12 邯郸钢铁集团有限责任公司 Method for judging direct-loading hot-loading on conventional hot continuous rolling production line

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5676771A (en) * 1993-09-29 1997-10-14 Kawasaki Steel Corporation Non-oriented silicon steel sheet and method
US6478899B1 (en) * 1998-02-25 2002-11-12 Ugine S.A. Installation for making cold rolled stainless steel bands
CN101298081A (en) * 2008-06-18 2008-11-05 南京钢铁股份有限公司 Single stand four-roller steckel mill cross-connection control rolling technique
CN101492786A (en) * 2008-01-23 2009-07-29 北京中钢贸科技发展有限公司 Method for producing non-oriented silicon steel
CN101530861A (en) * 2008-03-13 2009-09-16 通化钢铁股份有限公司炼轧厂 Mixed and alternate rolling technique of continuous casting and rolling production line of sheet bar
CN203599213U (en) * 2013-12-03 2014-05-21 武汉钢铁(集团)公司 Device for automatic adjustment of rolling mill roll-gap inclining value

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5676771A (en) * 1993-09-29 1997-10-14 Kawasaki Steel Corporation Non-oriented silicon steel sheet and method
US6478899B1 (en) * 1998-02-25 2002-11-12 Ugine S.A. Installation for making cold rolled stainless steel bands
CN101492786A (en) * 2008-01-23 2009-07-29 北京中钢贸科技发展有限公司 Method for producing non-oriented silicon steel
CN101530861A (en) * 2008-03-13 2009-09-16 通化钢铁股份有限公司炼轧厂 Mixed and alternate rolling technique of continuous casting and rolling production line of sheet bar
CN101298081A (en) * 2008-06-18 2008-11-05 南京钢铁股份有限公司 Single stand four-roller steckel mill cross-connection control rolling technique
CN203599213U (en) * 2013-12-03 2014-05-21 武汉钢铁(集团)公司 Device for automatic adjustment of rolling mill roll-gap inclining value

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110388834A (en) * 2019-07-29 2019-10-29 山东泰山钢铁集团有限公司 A method of it improving steel plant and is heat-fed steel slab rate
CN111020171A (en) * 2019-12-18 2020-04-17 东北轻合金有限责任公司 Method for heating aluminum alloy ingot casting by using continuous charging mode of push type heating furnace
CN111020171B (en) * 2019-12-18 2021-08-13 东北轻合金有限责任公司 Method for heating aluminum alloy ingot casting by using continuous charging mode of push type heating furnace
CN113020283A (en) * 2021-03-18 2021-06-25 鞍钢股份有限公司 Shape control method for oriented silicon steel hot-rolled steel strip
CN114309080A (en) * 2021-11-29 2022-04-12 邯郸钢铁集团有限责任公司 Method for judging direct-loading hot-loading on conventional hot continuous rolling production line
CN114309080B (en) * 2021-11-29 2023-10-03 邯郸钢铁集团有限责任公司 Method for judging direct hot charging of conventional hot continuous rolling production line

Also Published As

Publication number Publication date
CN106269873B (en) 2018-01-05

Similar Documents

Publication Publication Date Title
CN106269873A (en) Utilize the method that holding pit and single heating furnace tandem rolling produce hot-rolled orientation silicon steel
CN102247985B (en) Method for producing steel for stirring tank with limit specification through hot rolling
CN104525560B (en) Effective control method of the 30mm cut deal pitted skins of straight carbon steel/Nb bearing steel 20
CN105149352B (en) Wrought magnesium alloy Strip mends the method for temperature, constant temperature rolling with batching online
CN106734805A (en) Φ 500~650mm Cr6 swaged forging Electro Slag Remelting Steel cold roll blank forging deformation techniques
CN102671940B (en) Rolling method for producing phase changes in finish rolling process of low-grade non-oriented silicon steel
CN104190740B (en) The production method of hot rolled seamless steel tube pipe
CN103878178A (en) Method for producing ultrathin hot-rolled coils from sheet billets by continuous casting and rolling
CN106077091A (en) Low energy consumption hot continuous casting blank Direct Rolling shaped steel Bar Wire Product production method
CN103406352A (en) Heating and rolling method of Ni36 nickel base alloy plate
CN102861887B (en) Hot loading method for medium-thick slabs
CN105921514A (en) Method for producing high-strength Q690D steel plate with thickness of 4 mm on wide and thick plate mill
CN111069499A (en) Forging process method for TC18 titanium alloy large-scale binding support forge piece
CN102151693B (en) Method for rolling low-hardness small-sized spring steel
CN105964966B (en) A kind of technique of bloom strand hot delivery and hot charging
CN101417336A (en) Production technique of large common-substance molybdenum plate
CN101748264A (en) Heating method of weather-proof sheet billet
CN106583466A (en) Rolled steel hot delivery and hot charging technology
CN107904376A (en) A kind of method and device for preventing the flat volume of dual phase steel
CN110153179A (en) The process of the fiery bearing steel of cooling rolling two
CN201400705Y (en) Car bottom furnace used for heating plate blank
CN105714187A (en) Production method for 30CrMnSiA hot rolled steel strip
CN103215433A (en) Heating method for heating industrial pure titanium slab by heating furnaces in series connection
CN102319847B (en) Method for forging small-diameter titanium ingot castings into wide slabs
CN101509726B (en) Veneer heating apparatus and veneer heating production line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant