CN106247007A - Remote major diameter industrial pipeline deadweight conjugates underlying laying direct-burried construction method - Google Patents
Remote major diameter industrial pipeline deadweight conjugates underlying laying direct-burried construction method Download PDFInfo
- Publication number
- CN106247007A CN106247007A CN201610700154.0A CN201610700154A CN106247007A CN 106247007 A CN106247007 A CN 106247007A CN 201610700154 A CN201610700154 A CN 201610700154A CN 106247007 A CN106247007 A CN 106247007A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- underlying
- deadweight
- trench
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/028—Laying or reclaiming pipes on land, e.g. above the ground in the ground
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Pipeline Systems (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The present invention relates to a kind of remote major diameter industrial pipeline deadweight and conjugate underlying laying direct-burried construction method, belong to underground pipeline layout technical field, provide a kind of employing deadweight and conjugate underlying pipeline installation, act on while eliminating torsional stress, avoid and occur the remote major diameter industrial pipeline deadweight of ductile rupture to conjugate underlying laying direct-burried construction method, the technical scheme used, for following the steps below operation, the original ground after clear table flat field spills white lime line according to pipeline planar design position of center line;Arrange pipeline, from the beginning of one end of pipeline, according to regulation width, put ratio of slope and the degree of depth and synchronize retrusive and carry out pipe trench earth excavation;Pipe trench earth excavation is until vacant state occurs in duct bottom, and the pipeline assembled is controlling generation displacement downwards in vertical plane under the potential energy effect of gravity, it is achieved that duct section is the most underlying to be layed in bottom of trench and naturally stretches;The present invention is widely used in underground pipeline layout.
Description
Technical field
The present invention relates to a kind of remote major diameter industrial pipeline deadweight and conjugate underlying laying direct-burried construction method, belong to ground
Underground pipelines laying technology field.
Background technology
At present, domestic underground buried metallic conduit construction technology divides two kinds: Yi Zhongshi, according to expropriation of land circle line setting → clear
Hang to bottom of trench → ditch except surface attachments → pipe canal digging → groove inspection → pipe base processes → dig operation hole → ground stringing
Lower steel pipe is right → ditch under welding → weld seam detection → Crater antiseptic and anticorrosion mend wound → pipeline buttress pour → pipeline both sides return
Fill out compacting → above backfilling of pipe canal of the water pressure test → pipeline, recover landforms.Another kind is, according to expropriation of land circle line setting → removing
Attachment → original ground stringing group to and welding → Non-Destructive Testing → Crater antiseptic mend wound → pipe centerline plane positioning unwrapping wire
→ pipe canal digging checks that bottom of trench absolute altitude → duct segments hangs to bottom of trench → valve interface welding → Non-Destructive Testing → interface anticorrosion
Mend wound → pipeline both sides and be backfilling and compacted → the water pressure test → landfill recovery landforms.
Technique one is first ditching, after original ground stringing, is hung by every tubing section by section with crane to bottom of trench, group to, welding,
Operation all operations under ditch such as detection, anticorrosion, efficiency is low, and dangerous big, long in time limit, occupation of land is many.
Technique two is first ground stringing, be parallel to pipe design centrage side set of locations to, weld, detect, repaired mouth, anti-
Rotten all operations on ditch, after unwrapping wire ditching check of foundation subsoil, hang pipeline to bottom of trench with pipe-laying-out machine, valve interface welds under ditch, detects,
Repaired mouth, anticorrosion, relative technique one improves efficiency, shortens the duration, but pipeline is concentrated and hung several pipe-laying-out machines of needs, is constructed into
This increasing, interim take up an area more, pipeline hang during butt welding of steel tube seam, steel pipe mother metal spiral weld simultaneously by curved, turn round,
Shearing comprehensive function.
Summary of the invention
For solving the technical problem that prior art exists, the invention provides one and use underlying laying of deadweight displacement to manage
Line, eliminates and acts on while torsional stress, it is to avoid occur under the remote major diameter industrial pipeline deadweight displacement of ductile rupture
Put laying direct-burried construction method.
For achieving the above object, under the technical solution adopted in the present invention is the deadweight displacement of remote major diameter industrial pipeline
Put laying direct-burried construction method, follow the steps below operation,
A, setting-out, the original ground after clear table flat field spills white lime line according to pipeline planar design position of center line;
B, pipe arrangement, select the midpoint of adjacent valve well spacing on white lime line, with this center as starting point, along phase negative side
To tubing section by section carry out steel pipe to, weld, detect, repaired mouth mends wound, anticorrosion, purging, until the line sections between valve well exists
Assembling, detection, anticorrosion and purging operation is completed on surface duct planar design centrage;
C, pipe trench excavation of earthwork, from the beginning of one end of pipeline, respectively arrange a backhoe meeting technical parameter in the both sides of pipeline
Excavator, according to regulation width, put ratio of slope and the degree of depth and synchronize retrusive and carry out pipe trench earth excavation, apply simultaneously clinometer,
Infrared distance measurement device controls the ditching degree of depth, ratio of slope, bottom of trench absolute altitude;
The underlying direct-burried of d, pipeline, pipe trench earth excavation is until vacant state occurs in duct bottom, and the pipeline assembled is from gravity
Potential energy effect under control in vertical plane, produce displacement downwards, it is achieved that duct section is the most underlying is layed in bottom of trench nature
Stretch, use dynamic strain monitoring technology that duct section is conjugated underlying laying overall process, landfill, pressure testing, normal water delivery four simultaneously
Planting the typical section weld seam interface under operating mode and carry out on-the-spot tracking dynamic test weld seam strain, construction completes.
Compared with prior art, the present invention has following technical effect that the present invention uses deadweight to conjugate underlying pipeline installation,
Eliminate and act on while torsional stress, it is to avoid generation ductile rupture, improve operating environment, improve effect 1.5 times, it is ensured that
The stability of downward welding technology quality and the safety of operating personnel;Save pipe-laying-out machine machine-team simultaneously, reduce the use of excavator machine-team,
Saving and weld work day, save earthwork excavation and filling amount, save interim floor space, it is achieved that green construction, comprehensive benefit is notable.
Accompanying drawing explanation
Fig. 1 is original ground stringing floor map in the present invention.
Fig. 2 is ground, Central Plains of the present invention tube coupling welding floor map.
Fig. 3 is that in the present invention, pipeline utilizes gravitional force to conjugate underlying process of deployment generalized section.
Fig. 4 is that in the present invention, pipeline ground group connects displacement shop fixtures process schematic cross section.
Detailed description of the invention
In order to make the technical problem to be solved, technical scheme and beneficial effect clearer, below tie
Close drawings and Examples, the present invention is further elaborated.Only should be appreciated that specific embodiment described herein
In order to explain the present invention, it is not intended to limit the present invention.
As shown in Figures 1 to 4, the deadweight of remote major diameter industrial pipeline conjugates underlying laying direct-burried construction method, according to
Following steps operate,
A, setting-out, the original ground after clear table flat field spills white lime line according to pipeline planar design position of center line;
B, pipe arrangement, select the midpoint of adjacent valve well spacing on white lime line, with this center as starting point, along phase negative side
To tubing section by section carry out steel pipe to, weld, detect, repaired mouth mends wound, anticorrosion, purging, until the line sections between valve well exists
Assembling, detection, anticorrosion and purging operation is completed on surface duct planar design centrage;
C, pipe trench excavation of earthwork, from the beginning of one end of pipeline, respectively arrange a backhoe meeting technical parameter in the both sides of pipeline
Excavator, according to regulation width, put ratio of slope and the degree of depth and synchronize retrusive and carry out pipe trench earth excavation, apply simultaneously clinometer,
Infrared distance measurement device controls the ditching degree of depth, ratio of slope, bottom of trench absolute altitude;
The underlying direct-burried of d, pipeline, pipe trench earth excavation is until vacant state occurs in duct bottom, and the pipeline assembled is from gravity
Potential energy effect under control in vertical plane, produce displacement downwards, it is achieved that duct section is the most underlying is layed in bottom of trench nature
Stretch, use dynamic strain monitoring technology that duct section is conjugated underlying laying overall process, landfill, pressure testing, normal water delivery four simultaneously
Plant the typical section weld seam interface under operating mode and carry out on-the-spot tracking dynamic test weld seam strain, make work progress, operational phase pipe
The strain stress of road weld seam controls within the elastic range that safety allows, it is ensured that pipeline uses life cycle management from building to
Running safety, construction completes.
The present invention utilizes self weight of pipeline to carry out lower displacement pipeline installation, it is possible to acts on while effectively eliminating torsional stress, keeps away
Exempted from generation ductile rupture, improved operating environment, improved effect 1.5 times, it is ensured that the stability of downward welding technology quality and
The safety of operating personnel;Save pipe-laying-out machine machine-team simultaneously, reduce the use of excavator machine-team, save and weld work day, save the earthwork and dig
The amount of filling out, saves interim floor space, it is achieved that green construction, and comprehensive benefit is notable.
The foregoing is only presently preferred embodiments of the present invention, not in order to limit the present invention, all essences in the present invention
Any amendment, equivalent and the improvement etc. made within god and principle, all should wrap within the scope of the present invention.
Claims (1)
1. remote major diameter industrial pipeline deadweight conjugates underlying laying direct-burried construction method, it is characterised in that: according to following step
Suddenly operate,
A, setting-out, the original ground after clear table flat field spills white lime line according to pipeline planar design position of center line;
B, pipe arrangement, select the midpoint of adjacent valve well spacing on white lime line, with this center as starting point, along phase negative side
To tubing section by section carry out steel pipe to, weld, detect, repaired mouth mends wound, anticorrosion, purging, until the line sections between valve well exists
Assembling, detection, anticorrosion and purging operation is completed on surface duct planar design centrage;
C, pipe trench excavation of earthwork, from the beginning of one end of pipeline, respectively arrange a backhoe meeting technical parameter in the both sides of pipeline
Excavator, according to regulation width, put ratio of slope and the degree of depth and synchronize retrusive and carry out pipe trench earth excavation, apply simultaneously clinometer,
Infrared distance measurement device controls the ditching degree of depth, ratio of slope, bottom of trench absolute altitude;
The underlying direct-burried of d, pipeline, pipe trench earth excavation is until vacant state occurs in duct bottom, and the pipeline assembled is from gravity
Potential energy effect under control in vertical plane, produce displacement downwards, it is achieved that duct section is the most underlying is layed in bottom of trench nature
Stretch, use dynamic strain monitoring technology that duct section is conjugated underlying laying overall process, landfill, pressure testing, normal water delivery four simultaneously
Planting the typical section weld seam interface under operating mode and carry out on-the-spot tracking dynamic test weld seam strain, construction completes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610700154.0A CN106247007B (en) | 2016-08-22 | 2016-08-22 | The underlying laying direct-burried construction method of remote major diameter industrial pipeline deadweight displacement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610700154.0A CN106247007B (en) | 2016-08-22 | 2016-08-22 | The underlying laying direct-burried construction method of remote major diameter industrial pipeline deadweight displacement |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106247007A true CN106247007A (en) | 2016-12-21 |
CN106247007B CN106247007B (en) | 2017-12-22 |
Family
ID=57596494
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610700154.0A Active CN106247007B (en) | 2016-08-22 | 2016-08-22 | The underlying laying direct-burried construction method of remote major diameter industrial pipeline deadweight displacement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106247007B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108086358A (en) * | 2017-12-13 | 2018-05-29 | 中国二冶集团有限公司 | Heavy caliber long range multitube is the same as ditch Immersed tunnel method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5505565A (en) * | 1993-02-08 | 1996-04-09 | Canales; Joe M. | Apparatus for making up threaded pipe joints into a pipeline |
US20040190995A1 (en) * | 2003-03-24 | 2004-09-30 | Komatsu Ltd. | Pipelayer |
CN1558130A (en) * | 2004-01-30 | 2004-12-29 | 胜利油田胜利石油化工建设有限责任公 | Down-ditch construction method for laying heavy caliber pipeline |
KR101056661B1 (en) * | 2009-08-05 | 2011-08-12 | 한국가스공사 | Finishing method of daily construction section |
CN102261519A (en) * | 2011-04-15 | 2011-11-30 | 胜利油田胜利石油化工建设有限责任公司 | Method for assisting sliding, floating and down-ditching of pipeline by air bags |
CN102518873A (en) * | 2011-12-29 | 2012-06-27 | 中铁上海工程局市政工程有限公司 | Method for paving large-diameter pipeline in soft soil in jacking and pulling combined manner |
CN105485424A (en) * | 2015-11-26 | 2016-04-13 | 天津市安维康家科技发展有限公司 | Automatic continuous laying operation method for large-diameter pipelines and operating robot |
-
2016
- 2016-08-22 CN CN201610700154.0A patent/CN106247007B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5505565A (en) * | 1993-02-08 | 1996-04-09 | Canales; Joe M. | Apparatus for making up threaded pipe joints into a pipeline |
US20040190995A1 (en) * | 2003-03-24 | 2004-09-30 | Komatsu Ltd. | Pipelayer |
CN1558130A (en) * | 2004-01-30 | 2004-12-29 | 胜利油田胜利石油化工建设有限责任公 | Down-ditch construction method for laying heavy caliber pipeline |
KR101056661B1 (en) * | 2009-08-05 | 2011-08-12 | 한국가스공사 | Finishing method of daily construction section |
CN102261519A (en) * | 2011-04-15 | 2011-11-30 | 胜利油田胜利石油化工建设有限责任公司 | Method for assisting sliding, floating and down-ditching of pipeline by air bags |
CN102518873A (en) * | 2011-12-29 | 2012-06-27 | 中铁上海工程局市政工程有限公司 | Method for paving large-diameter pipeline in soft soil in jacking and pulling combined manner |
CN105485424A (en) * | 2015-11-26 | 2016-04-13 | 天津市安维康家科技发展有限公司 | Automatic continuous laying operation method for large-diameter pipelines and operating robot |
Non-Patent Citations (2)
Title |
---|
何江: "非开挖铺设地下管线技术的发展现状", 《工程建设与设计》 * |
方舟: "水平导向钻机在地下管道", 《建设机械技术与管理》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108086358A (en) * | 2017-12-13 | 2018-05-29 | 中国二冶集团有限公司 | Heavy caliber long range multitube is the same as ditch Immersed tunnel method |
CN108086358B (en) * | 2017-12-13 | 2020-08-11 | 中国二冶集团有限公司 | Large-caliber long-distance multi-pipe same-ditch immersed pipe construction method |
Also Published As
Publication number | Publication date |
---|---|
CN106247007B (en) | 2017-12-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102383431B (en) | Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof | |
CN106351312A (en) | Pipeline and construction method thereof | |
CN110306449B (en) | Method for connecting new box culvert and existing road box culvert | |
CN102817378B (en) | Construction method of extra-large diameter shield tunnel penetrating through urban overhead pile foundations in close range | |
CN110924978A (en) | Construction method for preventing instability of shield tunnel under high-sensitivity stratum condition | |
CN102261519B (en) | Method for assisting sliding, floating and down-ditching of pipeline by air bags | |
CN105546213B (en) | A kind of flexible composite pipe rapid construction device and construction method | |
CN202247942U (en) | Overhanging type lifter foundation | |
CN114108656A (en) | Construction method of foundation pit support | |
CN106247007B (en) | The underlying laying direct-burried construction method of remote major diameter industrial pipeline deadweight displacement | |
CN206157860U (en) | Drainage pipeline | |
CN112815144A (en) | Artificial pipe jacking construction process | |
CN104328814A (en) | Great-depth seafloor pipeline post-trenching process | |
CN209162799U (en) | Underground continuous wall connector leakage-resistant device | |
CN110486531A (en) | It a kind of artificial push pipe and rams and manages united pipeline construction method | |
CN102758434B (en) | Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof | |
KR100999880B1 (en) | Apparatus for pressing steel pipe and method for well foundation construction using thereof | |
CN210217743U (en) | Steel structure sleeve for trenchless construction | |
CN102052517A (en) | Horizontal connecting system for regional underground vertical pipes and connecting construction method thereof | |
JP5115456B2 (en) | Laying and burying pipelines on steep slopes | |
CN106968271B (en) | Underground pipe gallery excavates and the construction method of support | |
CN204059173U (en) | A kind of pedestrian overcrossing | |
CN219061652U (en) | Middle-short range underground pipeline jacking pipe tunnel construction device | |
CN110258520A (en) | A kind of construction method of underground continuous wall under the operating condition suitable for low clearance | |
CN104109995B (en) | A kind of pedestrian overcrossing and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |