Specific embodiment
Refer to Fig. 1, there is provided a kind of network line structural planning method of power network of embodiment, comprise the following steps:
S110:The length of the DC line and network line in electricity grid network circuit is obtained, and by the two of DC line
Rectification side is equivalent to load bus in side, obtains equivalent load node, and inverter side in the both sides of DC line is equivalent to generate electricity
Node, obtains equivalent generating node.
In power network, can typically there is a plurality of HVDC transmission line i.e. DC line to transmit direct current, then to carry
The reasonability and accuracy of height transmission of electricity wheeling rates, need to consider DC line, so that, it is straight in acquisition electricity grid network circuit first
Flow Line, and DC line is carried out equivalent, generally, the both sides of DC line are respectively rectification side and inverse in power network
Become side, rectification side is equivalent to load bus, to obtain equivalent load node, inverter side is equivalent to generating node, to obtain
Equivalent generating node, so temporarily can not consider the factor of DC line in electricity grid network.
S120:The power for obtaining each node in the initial power and power network of each network line increases each net of unit megawatt hour
The target power on winding thread road, according to the initial power and target power of each network line, the power for obtaining each network line becomes
Change amount, the length of power variation and network line according to each network line obtains the exchange megawatt of each node in power network
Kilometer.
Wherein, each node includes load bus and generating node in power network.That is, not considering AC line temporarily
Under conditions of the influence on road, the changed power of each network line is obtained when increasing by million power of unit watt by calculating each node
Amount, then the power variation according to each network line is multiplied with the length of network line, calculates the exchange megawatt of each node
Kilometer.Change after the exchange megawatt kilometer finger joint point increase unit megawatt of node to network totle drilling cost, network totle drilling cost is each
The power of network line and the length product sum of network line.In power network, node can be divided into generating node and be born
Lotus node, so that, in power network, each node includes load bus and generating node, and the rectification side of DC line is equivalent
It is load bus, so that the equivalent load node for obtaining belongs to the load bus in power network, the inverter side of DC line is equivalent
It is generating node, so that the equivalent load node for obtaining belongs to the load bus in power network.In the exchange megawatt kilometer of each node
Exchange megawatt kilometer including equivalent generating node and equivalent load node.
S130:Obtain the head end branch road being connected with equivalent load node and the end branch being connected with equivalent generating node
Road, by Power Flow Tracing Method according to head end branch road, traces into the generating node that power is provided for equivalent load node, by tide
Stream tracking traces into the load bus for receiving equivalent generating node power output according to end branch.
In order to improve the reasonability and accuracy of transmission of electricity wheeling rates, it is necessary to consider DC line, accordingly it is desirable to find out with
The connected circuit of DC line head end, that is, find out the head end branch road being connected with equivalent load node, by adverse current tracking, with
Which generating node is track trace into for equivalent load node power output to generating node, and need to find out and DC line end
The connected circuit in end, that is, find out the end branch being connected with equivalent generating node, by following current tracking, traces into load section
Point, that is, trace into equivalent generating node for which load bus provides power.
S140:The length of DC line is shared to each generating node for tracing into and each load bus for tracing into,
The direct current length contributory value of each node in power network is obtained, according to the direct current length contributory value of each node in power network, in calculating power network
The direct current megawatt kilometer of each node.
The length of DC line is shared to each generating node for tracing into and each load bus for tracing into, due to
Track to generating node and load bus may have multiple, so as to need the length by DC line share to trace into each
Generating node and each load bus for tracing into.The length of every DC line is shared the length of each node in power network
It is added, can obtain the direct current length contributory value of each node in power network, according to the direct current length contributory value of each node in power network, calculates
The direct current megawatt kilometer of each node in power network, specifically, unit million is multiplied by by length is shared according to the direct current of each node in power network
Power, calculates the direct current megawatt kilometer of each node in power network.
That is, the length of DC line to be given each generating node for tracing into and each load bus for tracing into
Undertake, for example, the length of DC line is 100, if the amortization ratio to generating and load is set as 2 in advance:3, then by direct current
The length 100 of circuit gives each load bus for tracing into each generating node and tracing into according to the amortization ratio respectively, i.e., directly
In the length 100 of Flow Line 40 share and are undertaken to each generating node for tracing into, and remaining 60 is shared to each load for tracing into
Node undertakes, that is, the direct current megawatt kilometer of each generating node for tracing into is then for 40 are multiplied by the power of unit million, and what is traced into is each negative
The direct current megawatt kilometer of lotus node is then for 60 are multiplied by the power of unit million.Specifically, the length of every DC line is shared into section
The direct current megawatt kilometer of point is added, and the direct current megawatt kilometer of node is can obtain, for example, above-mentioned direct current megawatt kilometer is 40 tracking
The generating node for arriving is also relevant with another DC line, i.e., also for the equivalent load node of another DC line provides work(
Rate, now, another length of DC line is 50, and it is 20 to share to the length of the generating node for tracing into, then have two
The length of DC line has shares the above-mentioned generating node for tracing into, the direct current megawatt kilometer of the above-mentioned generating node for tracing into
Share the direct current megawatt kilometer sum of the generating node for tracing into for the length of two DC lines.
The length of DC line is shared to each generating node for tracing into and each load section for tracing into by above-mentioned
The direct current that point step can obtain each generating node for tracing into shares length and the direct current of each load bus for tracing into is shared
Length, because generating node and load bus are the divisions of each node in power network, i.e., each node is to include generating node in power network
And load bus, the direct current of each generating node that acquisition is traced into shares length and the direct current of each load bus for tracing into divides
Stand length, is that the direct current for obtaining each generating node for tracing into and each load bus for tracing into each node of power network is shared
Length, the load bus not traced into power network and the generating node not traced into are equivalently employed without sharing DC line
Length, is equivalently employed without direct current megawatt kilometer so that, the direct current for knowing each generating node for tracing into share length and with
Track to each load bus direct current share length after, you can know that the direct current of each node in power network shares length.
S150:The exchange megawatt kilometer of each node is added with the direct current megawatt kilometer of each node, the total of each node is obtained
Megawatt kilometer, the total megawatt of kilometer according to each node obtains each region megawatt kilometer.
Total megawatt of kilometer of each node for obtaining is to consider exchange megawatt kilometer it is contemplated that direct current megawatt kilometer, according to
Total megawatt of kilometer of each node, each region megawatt kilometer of acquisition is more rationally and accurate, so that, transmission of electricity wheeling rates can be improved and determined
Reasonability and accuracy.
S160:Predetermined system enlarging coefficient and the preset security factor are obtained, coefficient, default peace are extended according to predetermined system
Total divisor and each region megawatt kilometer, calculate each region transmission of electricity wheeling rates.
Predetermined system enlarging coefficient reflects the expense of unit length Typical Route, and the preset security factor reflects system to safety
The cost of the system redundancy capacity that the requirement of nargin is caused, will each region megawatt kilometer carry out linear transformation to obtain each region defeated
Electric wheeling rates, specifically, region transmission of electricity wheeling rates are that region megawatt kilometer, predetermined system enlarging coefficient and the preset security factor multiply
Product.Total megawatt of kilometer of the node obtained by said process is the direct current megawatt kilometer and the sum for exchanging megawatt kilometer of node,
The region megawatt kilometer obtained by total megawatt of kilometer of node equivalent to have also contemplated that direct current and exchange, then according to each region million
It is more accurate and reasonable that watt kilometer obtains each region transmission of electricity wheeling rates.Each power generation region of power network and each load area are according to transmission of electricity
Wheeling rates reclaim power cost, then, it is determined that after each region transmission of electricity wheeling rates, then the economic benefit in each region is also true therewith
Fixed, each region transmission of electricity wheeling rates are more reasonable and accurate, and the economic benefit ratio in each region is more reasonable, and generating and user both sides are
Preferable economic benefit can be obtained.
S170:Newly-increased node is obtained, according to the transmission of electricity of each region wheeling rates and newly-increased node, the network line of power network is planned
Structure.
After the transmission of electricity wheeling rates to each region determine, when there is newly-increased node to need to be added in power network, in order to ensure
The economic benefit of newly-increased node and the reasonability of power network, electricity is added to by according to each region transmission of electricity wheeling rates by newly-increased node
Realize making rational planning for power network in net.
The network line structural planning method of above-mentioned power network, according to the power variation and network line of each network line
Length, obtain power network in each node exchange megawatt kilometer, the length of DC line is shared to each generating section for tracing into
Point and each load bus for tracing into, obtain the direct current length contributory value of each node, and the direct current length according to each node is shared
Value, calculates the direct current megawatt kilometer of each node in power network, by each node in the exchange megawatt kilometer of each node in power network and power network
Direct current megawatt kilometer be added, obtain total megawatt of kilometer of each node in power network, total megawatt of kilometer of such node is what is considered
Exchange megawatt kilometer it is contemplated that direct current megawatt kilometer so that, each region that the total megawatt of kilometer subsequently according to node is calculated is defeated
Electric wheeling rates are more reasonable, then, further according to each region transmission of electricity wheeling rates, newly-increased node are added in power network, to plan power network
Network line structure, be according to each region transmit electricity wheeling rates, newly-increased node is planned into power network, to update the net of power network
Winding thread line structure, can so be conducive to planning the section in newly-increased node and which region due to each region transmission of electricity wheeling rates rationally
Point is connected to ensure newly-increased node economic benefit, so that, newly-increased node is reasonably planned to power network.
Wherein in one embodiment, the length of DC line is shared to each generating node for tracing into and traced into
Each load bus, obtain the direct current length contributory value of each node in power network, direct current according to each node in power network point length stand
Value, S140 includes the step of the direct current megawatt kilometer of each node in calculating power network:
The default generating of acquisition shares ratio with load;
The power partition coefficient of each head end branch road and the power distribution of each end branch are obtained by Power Flow Tracing Method
Coefficient;
According to default generating and the work(for sharing ratio, the power partition coefficient of each head end branch road and each end branch of load
Rate distribution coefficient, the length of DC line is shared to each generating node for tracing into and each load bus for tracing into, and is obtained
The direct current length contributory value of each node in power taking net;
The direct current of each node in power network is shared into length to be multiplied with the power of unit million, the direct current million of each node in power network is obtained
Watt kilometer.
When the power that multiple nodes are provided is received, it according to power partition coefficient is receiving power that each node is to node
Node power is provided, which node can be traced for equivalent load node provides power by Power Flow Tracing Method, and can
The power partition coefficient of the head end branch road that acquisition is connected with equivalent load node, the power partition coefficient of head end branch road is head end
The power of branch road is to the sensitivity coefficient of equivalent load bus injecting power, i.e. power distribution of the equivalent load node on this branch road
The factor, just may know that this distribution power of the equivalent load bus injecting power on the branch road.According to power partition coefficient, will be straight
The length of Flow Line is shared to each generating node for tracing into and each load bus for tracing into, and obtains the direct current of each node
Megawatt kilometer.For example, the length of DC line is 100, default generating is shared than being 2 with load:3, the length of DC line
It is 40 to share to the length of each generating node for tracing into, and it is 60 to share to the length of each load bus for tracing into.AC line
Allocation proportion of the power on road on head end branch road is the power partition coefficient of head end branch road, if the quantity of head end branch road is 2,
And the power partition coefficient relative to DC line of two head end branch roads is 0.5, it is equivalent load to be due to head end branch road
Node provides the node of power, is to connect generating node and equivalent load node, so that, it is 0.5 that head end branch road shares length
40 are multiplied by, similarly, if the quantity of the end branch for obtaining is 2, its power partition coefficient is respectively 0.4 and 0.6, then end branch
The length shared is respectively 0.4 and is multiplied by 60 and 0.6 and is multiplied by 60.Then the direct current of each node in power network is shared into length and list
Million power of position are multiplied, and obtain the direct current megawatt kilometer of each node in power network.
Wherein in one embodiment, respectively by power network each node exchange megawatt kilometer with power network each node it is straight
Stream megawatt kilometer is added, and obtains total megawatt of kilometer of each node in power network, according to total megawatt of kilometer of each node in power network, obtains
The step of each region megawatt kilometer, S150 included:
The exchange megawatt kilometer of each node in power network is added with the direct current megawatt kilometer of each node in power network respectively, is obtained
Total megawatt of kilometer of each node in power network;
The power of each individual node accounts for the work(of individual node region interior nodes general power in each node in acquisition power network
Rate ratio, according to total megawatt of kilometer of each node in the power proportions and power network of each individual node, obtains each region million respectively
Watt kilometer.
In the present embodiment, megawatt kilometer is the change of every increase unit megawatt power network totle drilling cost, that is to say, that be cost
Variable, region megawatt kilometer is that the total megawatt of weighted sum of kilometer of each node in region is average, wherein, total megawatt of kilometer of node
Weight be the power of node, that is to say, that in a region, region megawatt kilometer is by total megawatt of public affairs of regional nodes
In be multiplied by weight and sue for peace after divided by weight sum.Region megawatt kilometer be multiplied by predetermined system spreading coefficient and preset security because
Son can obtain region transmission of electricity wheeling rates.
Wherein in one embodiment, region includes power generation region and load area, and each region transmission of electricity wheeling rates include
Each power generation region transmission of electricity wheeling rates and each load area transmission of electricity wheeling rates.
Fig. 2 is referred to, newly-increased node is obtained, according to the transmission of electricity of each region wheeling rates and newly-increased node, the net of power network is planned
Before the step of winding thread line structure S270, also include:
S261:According to each power generation region interior nodes general power and each power generation region transmission of electricity wheeling rates, power generation region is calculated
Total transmission of electricity wheeling rates, according to each load area interior nodes general power and each load area transmission of electricity wheeling rates, calculated load area
Total transmission of electricity wheeling rates in domain.
That is, power generation region may have multiple, the transmission of electricity wheeling rates of each power generation region and each power generation region interior nodes
The general power sum of products calculates total transmission of electricity wheeling rates of power generation region, and load area may have multiple, the transmission of electricity of each load area
Total transmission of electricity wheeling rates in wheeling rates and each load area interior nodes general power sum of products calculated load region.
S262:When always the transmit electricity ratio of wheeling rates of total transmission of electricity wheeling rates occupied area domain of load area is not equal to preset ratio
When, modifying factor is set, according to modifying factor to total transmission of electricity wheeling rates and the net of always transmitting electricity of load area of power generation region
Expense is modified respectively.
Wherein, region is always transmitted electricity total transmission of electricity wheeling rates of total transmission of electricity wheeling rates and the power generation region that wheeling rates are load area
Sum.
When total transmission of electricity wheeling rates occupied area domain of load area always transmit electricity the ratio of wheeling rates be not equal to preset ratio when, that is, bear
Total transmission of electricity wheeling rates in lotus region and total transmission of electricity wheeling rates of power generation region are unsatisfactory for the benefit ratio for generating electricity and load is obtained,
Need to be modified it.
S263:Total transmission of electricity wheeling rates according to revised load area account for revised region and always transmit electricity the ratio of wheeling rates
The example condition equal with preset ratio, calculates the value of modifying factor.
By introducing modifying factor, and it is total to account for revised region according to total transmission of electricity wheeling rates of revised load area
Transmit electricity the ratio condition equal with preset ratio of wheeling rates, calculate the value of modifying factor, that is to say, that according to the amendment of acquisition
It is full after the value of the factor is modified respectively to the total transmission of electricity wheeling rates and total transmission of electricity wheeling rates of load area to power generation region
The benefit ratio that foot is generated electricity and load is obtained.
S264:According to the value of modifying factor, transmitted electricity to power generation region wheeling rates and load area transmission of electricity wheeling rates difference
It is modified, obtains revised power generation region transmission of electricity wheeling rates and revised load area transmission of electricity wheeling rates.
After the value for obtaining modifying factor, according to the value of modifying factor, transmitted electricity to power generation region wheeling rates and loading zone
Domain transmission of electricity wheeling rates are modified respectively, obtain revised power generation region transmission of electricity wheeling rates and revised load area is defeated
Electric wheeling rates, so that the amendment to wheeling rates of transmitting electricity is realized, so that each region transmission of electricity wheeling rates are more rationally and accurate.
Wherein in one embodiment, the initial power of each network line is obtained, it is single in each node in acquisition power network respectively
The power of individual node increases unit megawatt hour, the target power of each network line, initial power according to each network line and
Target power, obtains the power variation of each network line, the power variation and network line according to each network line
Length, S120 includes the step of the exchange megawatt kilometer of each node in acquisition power network:
The initial power of each network line is obtained, the power of individual node increases unit in each node in acquisition power network respectively
Megawatt hour, the target power of each network line;
According to the initial power and target power of each network line, the power variation of each network line is obtained;
According to the default conversion factor of each network line, the length to each network line is converted respectively, obtains each net
The datum length on winding thread road;
The power variation of network line is multiplied with the datum length of network line, the exchange million of each network line is obtained
Watt kilometer variable quantity, the exchange megawatt kilometer variable quantity summation to each network line, obtains the exchange megawatt of each node in power network
Kilometer.
Before exchange megawatt kilometer variable quantity is calculated, the certain type of network line of certain voltage class is selected first
Used as benchmark, its length is constant, and the length of other kinds of networking circuit is multiplied by default conversion factor and obtains datum length, with true
The length for protecting whole network circuit more meets reality, so that, the region transmission of electricity wheeling rates for calculating are more rationally accurate.For example, can
On the basis of selected 400 kilovolts networking circuit, the default conversion factor of 275 kilovolts of networking circuit is 1.74,132 kilovolts of net
The default conversion factor on winding thread road is 2.61.
The network line structural planning method of above-mentioned power network is illustrated with a specific embodiment below.
First, the network structure information of a node and network line is read from the file for prestoring, and obtains electricity
Each area information in net, by counting each area information, can obtain the quantity of power generation region and the quantity of load area, and can
The power and the length of network line of a node are obtained, length is converted using default conversion factor, by network line
Length conversion on the basis of length.
Then, the initial power of each network line is obtained, the power for obtaining power network interior joint increases unit megawatt hour, each net
The target power on winding thread road, according to the initial power and target power of each network line, the power for obtaining each network line becomes
Change amount, the length of power variation and network line according to each network line obtains the exchange megawatt kilometer of node.Specifically
Ground, the initial power according to each netting twine road is multiplied and sues for peace with corresponding datum length first, obtains basic megawatt of kilometer.
Each node increases the power of unit million, after the power that reference mode increases unit million, calculates new basic million
Watt kilometer.
The exchange megawatt kilometer of power network interior joint is obtained by basic megawatt of new kilometer is subtracted into basic megawatt of kilometer.
The power partition coefficient of each head end branch road and the power distribution of each end branch are obtained by Power Flow Tracing Method
Coefficient, the structure chart of network line as shown in Figure 3, wherein, AB is DC line, and DA, EA, AC, CB, BF and BG are exchange
Circuit, can be equivalent to equivalent load node by node A, and alternating current circuit DA and EA provides power for node A, and node B is equivalent
It is equivalent generating node, node B provides power, the length of DC line AB shared and gives node D, E, F for circuit BF and BG
And G, and calculate the direct current megawatt kilometer of each node in power network, will the exchange megawatt kilometer of each node in power network it is each with power network
The direct current megawatt kilometer of node is added, and total megawatt of kilometer of each node in power network is obtained, according to total megawatt of each node in power network
Kilometer, obtains each region megawatt kilometer.
The exchange megawatt kilometer of each node in power network is added with the direct current megawatt kilometer of each node in power network, power network is obtained
In each node total megawatt of kilometer, the power for obtaining node accounts for the power proportions of node region interior nodes general power, according to
In power network in each node in the power proportions and power network of each individual node each node total megawatt of kilometer, each region is obtained respectively
Megawatt kilometer.
Obtain predetermined system enlarging coefficient and the preset security factor, according to predetermined system extend coefficient, preset security because
Sub and each region megawatt kilometer, calculates each region transmission of electricity wheeling rates, and specific formula is:
TG,h=mZone,G,h×E×S。
TD,m=mZone,D,m×E×S。
Wherein, TG,hIt is power generation region h transmission of electricity wheeling rates, mZone,G,hIt is h megawatts of kilometer of power generation region, TD,mIt is load area
M transmission of electricity wheeling rates, mZone,D,mIt is m megawatts of kilometer of load area, E is that predetermined system extends coefficient, and S is the preset security factor, by
It is unsatisfactory for requiring in the generating obtained according to each region transmission of electricity wheeling rates and the benefit ratio of load, then needs to transmit electricity each region
Wheeling rates are modified.Specifically, first, transmitted electricity net according to each power generation region interior nodes general power and each power generation region
Take, calculate total transmission of electricity wheeling rates of power generation region, transmitted electricity according to each load area interior nodes general power and each load area
Expenses of surfing in Internet, total transmission of electricity wheeling rates in calculated load region.
When total transmission of electricity wheeling rates occupied area domain of load area always transmit electricity the ratio of wheeling rates be not equal to preset ratio when, set
Total transmission of electricity wheeling rates of power generation region and total transmission of electricity wheeling rates of load area are entered by modifying factor respectively according to modifying factor
Row is corrected, and specific formula is:
Wherein, region is always transmitted electricity total transmission of electricity wheeling rates of total transmission of electricity wheeling rates and the power generation region that wheeling rates are load area
Sum.
According to total transmission of electricity wheeling rates R of revised load areaCT,DRevised region is accounted for always to transmit electricity wheeling rates (RCT,G+
RCT,D) ratio (p=RCT,D/(RCT,D+RCT,G)) share than equal condition with load with generating electricity, calculating modifying factor C
Value, that is to say, that the total transmission of electricity wheeling rates to load area are modified, and the total transmission of electricity wheeling rates to power generation region are repaiied
Just, so that, that is to say, that the ratio of wheeling rates of always being transmitted electricity to total transmission of electricity wheeling rates occupied area domain of load area is modified, and makes
Total transmission of electricity wheeling rates R of revised load areaCT,DRevised region is accounted for always to transmit electricity wheeling rates (RCT,G+RCT,D) ratio
(p=RCT,D/(RCT,D+RCT,G)) with generate electricity and load is shared than the same, RCT,GIt is always transmitting electricity for revised power generation region
Expenses of surfing in Internet,It is power generation region h interior nodes general powers, total power generation region is G, total load area is D, PG,iIt is total hair
The power of power generation region h interior joints i in electric region G,It is power generation region h interior joints sum in total power generation region G.
It is load area m interior nodes general powers, PD,iIt is the power of total load area D intermediate load region m interior joints i,For total bears
Lotus region D intermediate load region m interior joint sums.
According to the value of modifying factor C, to power generation region transmission of electricity wheeling rates mZone,G,hAnd load area transmission of electricity wheeling rates
mZone,D,mIt is modified respectively, obtains revised power generation region transmission of electricity wheeling rates T 'G,hAnd revised load area transmission of electricity
Wheeling rates T 'D,m, specific formula is:
T′G,h=(mZone,G,h+C)×E×S/1000。
T′D,m=(mZone,D,m-C)×E×S/1000。
Revised power generation region transmission of electricity wheeling rates and revised load area transmission of electricity wheeling rates are obtained, that is, is obtained
Revised each region transmission of electricity wheeling rates were obtained, further according to revised each region transmission of electricity wheeling rates and newly-increased node, planning
The network configuration of power network, that is, the network structure of power network is updated, newly-increased node is reasonably added in power network.
Refer to Fig. 4, there is provided a kind of network line structural planning device of power network of embodiment, including:
Equivalent modules 410, the length for obtaining DC line and network line in electricity grid network circuit, and will be straight
Rectification side is equivalent to load bus in the both sides of Flow Line, equivalent load node is obtained, by inverter side in the both sides of DC line
Generating node is equivalent to, equivalent generating node is obtained.
In power network, can typically there is a plurality of HVDC transmission line i.e. DC line to transmit direct current, then to carry
The reasonability and accuracy of height transmission of electricity wheeling rates, need to consider DC line, so that, it is straight in acquisition electricity grid network circuit first
Flow Line, and DC line is carried out equivalent, generally, the both sides of DC line are respectively rectification side and inverse in power network
Become side, rectification side is equivalent to load bus, to obtain equivalent load node, inverter side is equivalent to generating node, to obtain
Equivalent generating node, so temporarily can not consider the factor of DC line in electricity grid network.
Exchange megawatt kilometer acquisition module 420, for each node in the initial power and power network that obtain each network line
Power increase each network line of unit megawatt hour target power, initial power and target work(according to each network line
Rate, obtains the power variation of each network line, and the length of power variation and network line according to each network line is obtained
The exchange megawatt kilometer of each node in power taking net, wherein, each node includes load bus and generating node in power network.
That is, under conditions of the influence for temporarily not considering DC line, unit is increased by calculating each node
The power variation of each network line is obtained during watt million power, then according to the power variation and network line of each network line
Length be multiplied, calculate the exchange megawatt kilometer of each node.After the exchange megawatt kilometer finger joint point of node increases unit megawatt
Change to network totle drilling cost, network totle drilling cost is the length product sum of the power with network line of each network line.In electricity
In net, node can be divided into generating node and load bus so that, in power network, each node include load bus and
Generating node, and the rectification side of DC line is equivalent to load bus, so that during the equivalent load node for obtaining belongs to power network
Load bus, the inverter side of DC line is equivalent to generating node, so that during the equivalent load node for obtaining belongs to power network
Load bus.The exchange megawatt kilometer of each node includes the exchange megawatt public affairs of equivalent generating node and equivalent load node
In.
Tracking module 430, for obtain the head end branch road that is connected with equivalent load node and with equivalent generating node phase
End branch even, by Tracing power flow device according to head end branch road, traces into the generating that power is provided for equivalent load node
Node, by Tracing power flow device according to end branch, traces into the load bus for receiving equivalent generating node power output.
In order to improve the reasonability and accuracy of transmission of electricity wheeling rates, it is necessary to consider DC line, accordingly it is desirable to find out with
The connected circuit of DC line head end, that is, find out the head end branch road being connected with equivalent load node, by adverse current tracking, with
Which generating node is track trace into for equivalent load node power output to generating node, and need to find out and DC line end
The connected circuit in end, that is, find out the end branch being connected with equivalent generating node, by following current tracking, traces into load section
Point, that is, trace into equivalent generating node for which load bus provides power.
Direct current megawatt kilometer acquisition module 440, for the length of DC line to be shared to each generating node for tracing into
And each load bus for tracing into, obtain power network in each node direct current length contributory value, according in power network each node it is straight
Stream length contributory value, calculates the direct current megawatt kilometer of each node in power network.
The length of DC line is shared to each generating node for tracing into and each load bus for tracing into, due to
Track to generating node and load bus may have multiple, so as to need the length by DC line share to trace into each
Generating node and each load bus for tracing into.The length of every DC line is shared the length of each node in power network
It is added, can obtain the direct current length contributory value of each node in power network, according to the direct current length contributory value of each node in power network, calculates
The direct current megawatt kilometer of each node in power network, specifically, unit million is multiplied by by length is shared according to the direct current of each node in power network
Power, calculates the direct current megawatt kilometer of each node in power network.
That is, the length of DC line to be given each generating node for tracing into and each load bus for tracing into
Undertake, for example, the length of DC line is 100, if the amortization ratio to generating and load is set as 2 in advance:3, then by direct current
The length 100 of circuit gives each load bus for tracing into each generating node and tracing into according to the amortization ratio respectively, i.e., directly
In the length 100 of Flow Line 40 share and are undertaken to each generating node for tracing into, and remaining 60 is shared to each load for tracing into
Node undertakes, that is, the direct current megawatt kilometer of each generating node for tracing into is then for 40 are multiplied by the power of unit million, and what is traced into is each negative
The direct current megawatt kilometer of lotus node is then for 60 are multiplied by the power of unit million.Specifically, the length of every DC line is shared into section
The direct current megawatt kilometer of point is added, and the direct current megawatt kilometer of node is can obtain, for example, above-mentioned direct current megawatt kilometer is 40 tracking
The generating node for arriving is also relevant with another DC line, i.e., also for the equivalent load node of another DC line provides work(
Rate, now, another length of DC line is 50, and it is 20 to share to the length of the generating node for tracing into, then have two
The length of DC line has shares the above-mentioned generating node for tracing into, the direct current megawatt kilometer of the above-mentioned generating node for tracing into
Share the direct current megawatt kilometer sum of the generating node for tracing into for the length of two DC lines.
The length of DC line is shared to each generating node for tracing into and each load section for tracing into by above-mentioned
The direct current that point step can obtain each generating node for tracing into shares length and the direct current of each load bus for tracing into is shared
Length, because generating node and load bus are the divisions of each node in power network, i.e., each node is to include generating node in power network
And load bus, the direct current of each generating node that acquisition is traced into shares length and the direct current of each load bus for tracing into divides
Stand length, is that the direct current for obtaining each generating node for tracing into and each load bus for tracing into each node of power network is shared
Length, the load bus not traced into power network and the generating node not traced into are equivalently employed without sharing DC line
Length, is equivalently employed without direct current megawatt kilometer so that, the direct current for knowing each generating node for tracing into share length and with
Track to each load bus direct current share length after, you can know that the direct current of each node in power network shares length.S150:Will be each
The exchange megawatt kilometer of node is added with the direct current megawatt kilometer of each node, total megawatt of kilometer of each node is obtained, according to each section
Total megawatt of kilometer of point, obtains each region megawatt kilometer.
Total megawatt of kilometer of each node for obtaining is to consider exchange megawatt kilometer it is contemplated that direct current megawatt kilometer, according to
Total megawatt of kilometer of each node, each region megawatt kilometer of acquisition is more rationally and accurate, so that, transmission of electricity wheeling rates can be improved and determined
Reasonability and accuracy.
Transmission of electricity wheeling rates computing module 460, for obtaining predetermined system enlarging coefficient and the preset security factor, according to pre-
If system enlarging coefficient, the preset security factor and each region megawatt kilometer, each region transmission of electricity wheeling rates are calculated.
Predetermined system enlarging coefficient reflects the expense of unit length Typical Route, and the preset security factor reflects system to safety
The cost of the system redundancy capacity that the requirement of nargin is caused, will each region megawatt kilometer carry out linear transformation to obtain each region defeated
Electric wheeling rates, specifically, region transmission of electricity wheeling rates are that region megawatt kilometer, predetermined system enlarging coefficient and the preset security factor multiply
Product.Total megawatt of kilometer of the node obtained by said process is the direct current megawatt kilometer and the sum for exchanging megawatt kilometer of node,
The region megawatt kilometer obtained by total megawatt of kilometer of node equivalent to have also contemplated that direct current and exchange, then according to each region million
It is more accurate and reasonable that watt kilometer obtains each region transmission of electricity wheeling rates.Each power generation region of power network and each load area are according to transmission of electricity
Wheeling rates reclaim power cost, then, it is determined that after each region transmission of electricity wheeling rates, then the economic benefit in each region is also true therewith
Fixed, each region transmission of electricity wheeling rates are more reasonable and accurate, and the economic benefit ratio in each region is more reasonable, and generating and user both sides are
Preferable economic benefit can be obtained.
Planning module 470, for obtaining newly-increased node, according to the transmission of electricity of each region wheeling rates and newly-increased node, planning electricity
The network line structure of net.
After the transmission of electricity wheeling rates to each region determine, when there is newly-increased node to need to be added in power network, in order to ensure
The economic benefit of newly-increased node and the reasonability of power network, electricity is added to by according to each region transmission of electricity wheeling rates by newly-increased node
Realize making rational planning for power network in net.
The network line structural planning device of above-mentioned power network, according to the power variation and network line of each network line
Length, obtain power network in each node exchange megawatt kilometer, the length of DC line is shared to each generating section for tracing into
Point and each load bus for tracing into, obtain the direct current length contributory value of each node, and the direct current length according to each node is shared
Value, calculates the direct current megawatt kilometer of each node in power network, by each node in the exchange megawatt kilometer of each node in power network and power network
Direct current megawatt kilometer be added, obtain total megawatt of kilometer of each node in power network, total megawatt of kilometer of such node is what is considered
Exchange megawatt kilometer it is contemplated that direct current megawatt kilometer so that, each region that the total megawatt of kilometer subsequently according to node is calculated is defeated
Electric wheeling rates are more reasonable, then, further according to each region transmission of electricity wheeling rates, newly-increased node are added in power network, to plan power network
Network line structure, be according to each region transmit electricity wheeling rates, newly-increased node is planned into power network, to update the defeated of power network
The structure of electric line, can so be conducive to planning in newly-increased node and which region due to each region transmission of electricity wheeling rates rationally
Node is connected to ensure newly-increased node economic benefit, so that, newly-increased node is reasonably planned to power network.
Wherein in one embodiment, direct current megawatt kilometer acquisition module 440 includes:
Share than acquisition module, for obtaining default generate electricity and load shares ratio;
Distribution coefficient acquisition module, for obtained by Tracing power flow device each head end branch road power partition coefficient and
The power partition coefficient of each end branch;
Share length acquisition module, for according to the default power distribution for sharing ratio, each head end branch road generated electricity with load
The power partition coefficient of coefficient and each end branch, the length of DC line is shared to each generating node for tracing into and
Each load bus for tracing into, obtains the direct current length contributory value of each node in power network;
Direct current megawatt kilometer computing module, for the direct current of each node in power network to be shared into length with the power phase of unit million
Multiply, obtain the direct current megawatt kilometer of each node in power network.
When the power that multiple nodes are provided is received, it according to power partition coefficient is receiving power that each node is to node
Node provide power, which node can be traced for equivalent load node provides power and can obtain by Power Flow Tracing Method
The power partition coefficient of connected head end branch road is obtained, the power partition coefficient of branch road is the power of branch road to node injection
The power distribution factor of the sensitivity coefficient of power, i.e. node on this branch road, just may know that minor node injecting power in the node
On distribution power.According to power partition coefficient, by the length of DC line share to each generating node for tracing into and with
Each load bus that track is arrived, and obtain the direct current megawatt kilometer of each node.For example, the length of DC line is 100, presets and generate electricity
With sharing than being 2 for load:3, it is 40 that the length of DC line is shared to the length of each generating node for tracing into, share to
The length of each load bus that track is arrived is 60.Allocation proportion of the power of DC line on head end branch road is head end branch road
Power partition coefficient, if the quantity of head end branch road is 2, and two power partition coefficients relative to DC line of head end branch road
0.5 is, is connection generating node and equivalent load section because head end branch road is node that power is provided for equivalent load node
Point, so that, head end branch road shares length for 0.5 is multiplied by 40, similarly, if the quantity of the end branch for obtaining is 2, its power point
Distribution coefficient is respectively 0.4 and 0.6, then the length that end branch is shared is respectively 0.4 and is multiplied by 60 and 0.6 and is multiplied by 60.Then
The direct current of each node in power network is shared into length to be multiplied with the power of unit million, the direct current megawatt kilometer of each node in power network is obtained.
Wherein in one embodiment, region megawatt kilometer acquisition module 450 includes:
Total megawatt of kilometer acquisition module, for respectively by each node in the exchange megawatt kilometer of each node in power network and power network
Direct current megawatt kilometer be added, obtain power network in each node total megawatt of kilometer;
Region megawatt kilometer computing module, the power for obtaining each individual node in each node in power network accounts for individual node
The power proportions of region interior nodes general power, according to total million of each node in the power proportions and power network of each individual node
Watt kilometer, obtains each region megawatt kilometer respectively.
In the present embodiment, megawatt kilometer is the change of every increase unit megawatt power network totle drilling cost, that is to say, that be cost
Variable, region megawatt kilometer is that the total megawatt of weighted sum of kilometer of each node in region is average, wherein, total megawatt of kilometer of node
Weight be the power of node, that is to say, that in a region, region megawatt kilometer is by total megawatt of public affairs of regional nodes
In be multiplied by weight and sue for peace after divided by weight sum.Region megawatt kilometer be multiplied by predetermined system spreading coefficient and preset security because
Son can obtain region transmission of electricity wheeling rates.
Fig. 5, Shi Lizhong are referred to, region includes power generation region and load area, and each region transmission of electricity wheeling rates include each
Power generation region transmission of electricity wheeling rates and each load area transmission of electricity wheeling rates;
The network line structural planning device of above-mentioned power network also includes:
Subregion is always transmitted electricity wheeling rates computing module 561, for according to each power generation region interior nodes general power and each hair
Electric region transmission of electricity wheeling rates, calculate total transmission of electricity wheeling rates of power generation region, according to each load area interior nodes general power and respectively
Load area transmission of electricity wheeling rates, total transmission of electricity wheeling rates in calculated load region.
That is, power generation region may have multiple, the transmission of electricity wheeling rates of each power generation region and each power generation region interior nodes
The general power sum of products calculates total transmission of electricity wheeling rates of power generation region, and load area may have multiple, the transmission of electricity of each load area
Total transmission of electricity wheeling rates in wheeling rates and each load area interior nodes general power sum of products calculated load region.
Correcting module 562, for always being transmitted electricity the ratio of wheeling rates when total transmission of electricity wheeling rates occupied area domain of load area
When preset ratio, modifying factor is set, according to modifying factor to total transmission of electricity wheeling rates of power generation region and load area
Total transmission of electricity wheeling rates are modified respectively, wherein, region always transmit electricity total transmission of electricity wheeling rates that wheeling rates are load area with generate electricity
Total transmission of electricity wheeling rates sum in region.
When total transmission of electricity wheeling rates occupied area domain of load area always transmit electricity the ratio of wheeling rates be not equal to preset ratio when, that is, bear
Total transmission of electricity wheeling rates in lotus region and total transmission of electricity wheeling rates of power generation region are unsatisfactory for the benefit ratio for generating electricity and load is obtained,
Need to be modified it.
Correction value computing module 563, revised area is accounted for for the total transmission of electricity wheeling rates according to revised load area
Domain is always transmitted electricity the ratio condition equal with preset ratio of wheeling rates, calculates the value of modifying factor.
By introducing modifying factor, and it is total to account for revised region according to total transmission of electricity wheeling rates of revised load area
Transmit electricity the ratio condition equal with preset ratio of wheeling rates, calculate the value of modifying factor, that is to say, that according to the amendment of acquisition
It is full after the value of the factor is modified respectively to the total transmission of electricity wheeling rates and total transmission of electricity wheeling rates of load area to power generation region
The benefit ratio that foot is generated electricity and load is obtained.
Wheeling rates correcting module 564, for the value according to modifying factor, transmitted electricity to power generation region wheeling rates and loading zone
Domain transmission of electricity wheeling rates are modified respectively, obtain revised power generation region transmission of electricity wheeling rates and load area was transmitted electricity net
Take.
After the value for obtaining modifying factor, according to the value of modifying factor, transmitted electricity to power generation region wheeling rates and loading zone
Domain transmission of electricity wheeling rates are modified respectively, obtain revised power generation region transmission of electricity wheeling rates and revised load area is defeated
Electric wheeling rates, so that the amendment to wheeling rates of transmitting electricity is realized, so that each region transmission of electricity wheeling rates are more rationally and accurate.
Wherein in one embodiment, an exchange megawatt kilometer acquisition module 420 includes:
Power acquisition module, the initial power for obtaining each network line, obtaining the power of power network interior joint increases single
Position megawatt hour, the target power of each network line;
Variable quantity acquisition module, for initial power and target power according to each network line, obtains each grid line
The power variation on road;
Conversion module, for the default conversion factor according to each network line, the length to each network line is carried out respectively
Conversion, obtains the datum length of each network line;
Exchange megawatt kilometer computing module, for by the datum length phase of the power variation of network line and network line
Multiply, obtain the exchange megawatt kilometer variable quantity of each network line, the exchange megawatt kilometer variable quantity summation to each network line is obtained
Obtain the exchange megawatt kilometer of each node in power network.
Before exchange megawatt kilometer variable quantity is calculated, the certain type of network line of certain voltage class is selected first
Used as benchmark, its length is constant, and the length of other kinds of networking circuit is multiplied by default conversion factor and obtains datum length, with true
The length for protecting whole network circuit more meets reality, so that, the region transmission of electricity wheeling rates for calculating are more rationally accurate.For example, can
On the basis of selected 400 kilovolts networking circuit, the default conversion factor of 275 kilovolts of networking circuit is 1.74,132 kilovolts of net
The default conversion factor on winding thread road is 2.61.
Each technical characteristic of above example can be combined arbitrarily, to make description succinct, not to above-described embodiment
In each technical characteristic it is all possible combination be all described, as long as however, the combination of these technical characteristics do not exist lance
Shield, is all considered to be the scope of this specification record.
Above example only expresses several embodiments of the invention, and its description is more specific and in detail, but can not be because
This and be construed as limiting the scope of the patent.It should be pointed out that for the person of ordinary skill of the art, not
On the premise of departing from present inventive concept, various modifications and improvements can be made, these belong to protection scope of the present invention.Cause
This, the protection domain of patent of the present invention should be determined by the appended claims.