CN106218808A CN201610601498.6A CN201610601498A CN106218808A CN 106218808 A CN106218808 A CN 106218808A CN 201610601498 A CN201610601498 A CN 201610601498A CN 106218808 A CN106218808 A CN 106218808A
Authority
CN
China
Prior art keywords
pushes away
away
support component
installation
height
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610601498.6A
Other languages
Chinese (zh)
Other versions
CN106218808B (en
Inventor
陈雄剑
何志年
王世浩
付志斌
潘荣坚
吕岩
齐超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Shipyard International Co Ltd
Original Assignee
Guangzhou Shipyard International Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Shipyard International Co Ltd filed Critical Guangzhou Shipyard International Co Ltd
Priority to CN201610601498.6A priority Critical patent/CN106218808B/en
Publication of CN106218808A publication Critical patent/CN106218808A/en
Application granted granted Critical
Publication of CN106218808B publication Critical patent/CN106218808B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B71/00Designing vessels; Predicting their performance

Abstract

The present invention discloses a kind of auxiliary mould and side pushed away for installation side and pushes away installation method.Wherein, auxiliary mould includes assistance platform and a support component, prop up support component to be arranged on assistance platform and can move along the length direction of assistance platform, prop up support component to include supporting body and two vertical rods, vertical rod is arranged at intervals at the both sides supporting body along the width supporting body, and the height adjustable of vertical rod, so that the side being placed on a support component pushes away and there is gap between assistance platform.The auxiliary mould of the present invention pushes away for installation side, side passage can be moved to position to be installed by dragging a support component, side pushes away and will not produce friction between assistance platform, avoid side to push away to be worn, and the height of vertical rod can be regulated according to actual needs so that the height at peak place that pushes away of side without departing from boats and ships for installing the height of the peak accommodating chamber that this side pushes away, it is to avoid side pushes away generation scratching between boats and ships, the installation making side push away smoothly completes, and improves the installation effectiveness that side pushes away.

Description

A kind of auxiliary mould and side pushed away for installation side pushes away installation method
Technical field
The present invention relates to shipbuilding technical field, be specifically related to a kind of auxiliary mould pushed away for installation side and application The side of this auxiliary mould pushes away installation method.
Background technology
Along with the growing of shipbuilding industry and progress, common axle adds the propelling pattern of oar and can not meet the special ship of part Type for the requirement of flexibility ratio, therefore a lot of specialized ship types all have employed sideways-acting propeller (hereinafter referred to as " side pushes away ") as its Lateral direction controlling.Mostly being positioned at, owing to this side pushes away, the region that fore and aft line type is bigger, it is more that deck hangs the part waftd, often Cause using loop wheel machine to assist installation.And side pushes away according to ship model features different sizes, its weight is typically at several tons to two 30 tons, manpower is therefore purely relied on to be inconvenient to install.
In existing mounting technique, the main mode using chain block is installed.First have to the circle pushed away in side On cylinder weld substantial amounts of calabash draw code, for calabash by means of power and transposition.Owing in cylinder, space ratio is narrow, substantially it is desirable that Body is all fabricated to an overall module together with blade and shaft coupling when of making and installs by producer, so pacifies The space of dress will be at full stretch, uses chain block to be difficult to control to angle when installing, and careless slightly will produce scratching and lead Cause unnecessary damage.
Summary of the invention
It is an object of the present invention to provide a kind of auxiliary mould pushed away for installation side, to improve the installation effect that side pushes away Rate.
Further object is that a kind of side of offer pushes away installation method, its installation effectiveness is high, can be prevented effectively from side Push away generation scratching between boats and ships.
For reaching this purpose, the present invention by the following technical solutions:
On the one hand, it is provided that a kind of auxiliary mould pushed away for installation side, including assistance platform and a support component, described support Assembly is arranged on described assistance platform and can move along the length direction of described assistance platform, and described support component includes supporting Body and two vertical rods, described vertical rod is arranged at intervals at the both sides of described support body along the width of described support body, And the height adjustable of described vertical rod, so that the side being placed on described support component pushes away between existing between described assistance platform Gap.
On the other hand, it is provided that a kind of side pushes away installation method, comprises the following steps:
S10, boats and ships have the receiving chamber that receiving side pushes away, and the upside accommodating chamber is provided with for installing the installation that described side pushes away Hole, described receiving chamber has the first opening and the second opening being oppositely arranged, outside described receiving chamber and close on described first and open Set up described auxiliary mould at Kou, make the height at the peak place that the side being placed on described auxiliary mould pushes away be not more than institute Stating the height at the place, upside accommodating chamber, the upper surface of described assistance platform is slightly above the minimum point in described receiving chamber;
S20, in the upside in described receiving chamber and it is provided for outstanding drawing the first of the first calabash near described second opening part Hang code, and be provided in the both sides of described installing hole outstanding drawing the second of the second calabash to hang code;
S30, described side is pushed away it is placed on described support component, utilize described first calabash to be drawn in by described support component Described receiving intracavity is until the mounting flange that described side pushes away is positioned at the lower section of described installing hole;
S40, described second calabash is utilized to ajust the position that the described side below described installing hole pushes away;
S50, by mounting flange described side pushed away and be fixed in described installing hole, complete to install.
Beneficial effects of the present invention: the auxiliary mould of the present invention is when installation side pushes away, by dragging a support component Moving side passage to position to be installed, side pushes away and will not produce friction between assistance platform, it is to avoid side pushes away and is worn, and subtracts simultaneously Move active force when side pushes away less, and the height of vertical rod can be regulated the most in real time, so that the peak institute that side pushes away Height without departing from boats and ships for installing the height of the peak accommodating chamber that this side pushes away, the installation making side push away is the completeest Become, improve the installation effectiveness that side pushes away.
Accompanying drawing explanation
Fig. 1 is the structural representation of the auxiliary mould pushed away for installation side of the embodiment of the present invention.
Fig. 2 is the structural representation of a support component of the embodiment of the present invention.
Fig. 3 is the A direction view of Fig. 2.
Fig. 4 is the B direction view of Fig. 2.
Fig. 5 is the structural representation of the guide rail of the embodiment of the present invention.
Fig. 6 is the position view before the side push-and-pull of the embodiment of the present invention enters to accommodate chamber.
Fig. 7 is that the side push-and-pull of the embodiment of the present invention enters to the position view accommodated below the installing hole in chamber.
Fig. 8 is the position view after the side of the embodiment of the present invention pushes away installation.
Fig. 9 is the cut-away view in the receiving chamber (side push-and-pull enter accommodate chamber after) of the embodiment of the present invention.
In Fig. 1 to 9:
1, assistance platform;11, main platform body;12, guide rail;121, groove;2, support component is propped up;21, body is supported;211, long Bar;212, quarter butt;22, vertical rod;
100, boats and ships;110, chamber is accommodated;111, the first opening;112, the second opening;113, first code is hung;114, second hang Code;120, installing hole;130, limiting section;
200, side pushes away;210, mounting flange;220, spherical portion;230, blade portion;
300, auxiliary mould.
Detailed description of the invention
Further illustrate technical scheme below in conjunction with the accompanying drawings and by detailed description of the invention.
In describing the invention, it is to be understood that orientation or the position of the instruction such as term " interior ", " length direction " are closed System, for based on orientation shown in the drawings or position relationship, is for only for ease of the description present invention and simplification describes rather than instruction Hint indication device or element must have specific orientation, with specific azimuth configuration and operation, be not understood that For limitation of the present invention.
In the present invention, unless otherwise clearly defined and limited, fisrt feature second feature it " on " or D score Can include that the first and second features directly contact, it is also possible to include that the first and second features are not directly contact but by it Other characterisation contact between.And, fisrt feature second feature it " on " include that fisrt feature is in second feature just Top and oblique upper, or it is merely representative of fisrt feature level height higher than second feature.Fisrt feature is at the D score of second feature Including fisrt feature immediately below second feature and obliquely downward, or it is merely representative of fisrt feature level height less than second feature.
A kind of auxiliary mould pushed away for installation side described in embodiments of the invention, including assistance platform 1 and support group Part 2, described support component 2 is arranged on described assistance platform 1 and can move along the length direction of described assistance platform 1, described Propping up support component 2 to include supporting body 21 and two vertical rods 22, described vertical rod 22 is arranged along the width interval supporting body 21 In the both sides of described support body 21, and the height adjustable of described vertical rod 22, so that the side being placed on described support component 2 pushes away Gap is there is between 200 and assistance platform 1.During the application of this auxiliary mould, first side is pushed away 200 and is transferred to a support component by loop wheel machine On 2, it is placed on support component 2 as it is shown in figure 1, this side pushes away 200, side passage can be moved to waiting pacify by dragging a support component 2 Holding position, side push away the spherical portion 220 of 200 support on body 21 and and assistance platform 1 between there is gap, will not time mobile And producing friction between assistance platform 1, it is to avoid side pushes away 200 and is worn, the mobile side of minimizing simultaneously pushes away active force when 200.This In embodiment, the height of vertical rod 22 can be regulated according to actual needs in real time, so that side pushes away the height at the peak place of 200 not Can beyond on boats and ships for installing the height that this side pushes away the peak accommodating chamber 110 of 200, make side push away 200 installation the completeest Become.
Specifically, described support body 21 includes parallel and spaced two stocks 211, two described stocks 211 Length all extend along the length of described assistance platform 1, fixed by two quarter butts 212 between two described stocks 211, described The two ends of quarter butt 212 are connected with two described stocks 211 respectively, each described stock 211 is provided with one described vertical Bar 22.As shown in Figures 2 and 3, two stock 211 intervals are arranged, and connect by two quarter butts 212 are fixing, lean on when side pushes away 200 When being placed on support body 21 by vertical rod 22, side pushes away the spherical portion 220 of 200 and is located just on two stocks 211, makes spherical portion On the downside of in the of 200 unsettled, i.e. there is gap between spherical portion 220 and assistance platform 1, be subject to during movement to avoid side to push away 200 To abrasion.
Specifically, the angle between the plane at vertical rod 22 and described support body 21 place is 30 °~120 °, two vertical rods 22 are oppositely arranged, and tilt simultaneously towards the other side, it is also possible to tilt simultaneously towards the direction deviating from the other side, to push away 200 steady in side Surely rest in vertical rod 22, it is to avoid side pushes away 200 and shakes in moving process and affect installation effectiveness.As shown in Figure 4, originally Vertical rod 22 in embodiment tilts 60 ° simultaneously towards the other side.
Described support body 21 uses round steel to make, and needs the length direction shifting dragging a support component 21 along assistance platform 1 Time dynamic, supporting contacting between body 21 and assistance platform 1 is linear contact lay, compared with traditional face contact, decreases support originally Frictional force between body 21 and assistance platform 1.
As the present embodiment preferred embodiment, as shown in Figure 1 and Figure 5, described assistance platform 1 includes main platform body 11 With the guide rail 12 being welded in described main platform body 11, described guide rail 12 has two spaced grooves 121, described in two Stock 211 lays respectively in described groove 121, and can slide along described groove 121.In the present embodiment, assistance platform 1 sets The movement of a support component 2 is play the guiding role by the guide rail 12 put.
As the present embodiment further preferred embodiment, it is also possible to arrange between groove 121 and support body 21 Roller or ball, use rolling friction, prop up the frictional force between support component 2 and guide rail 12 with further reduction.
Main platform body 11 in the present embodiment is Height Adjustable, and it is made up of some high-order supports, and an adjacent described high position is propped up It is bolted between support, meanwhile, also by bolt between high-order support with ground (basal plane supported for a fixing high position) Fixing, described main platform body 11 is respectively arranged with diagonal brace 121 along the both sides of its width, with the most fixing assistance platform 1.
Embodiments of the invention also provide for a kind of side and push away installation method, and this side pushes away installation method and comprises the following steps:
S10, boats and ships 100 have receiving side and push away the receiving chamber 110 of 200, and the upside accommodating chamber 110 is provided with for installing Stating side and push away the installing hole 120 of 200, described receiving chamber 110 has the first opening 111 and the second opening 112 being oppositely arranged, in institute State outside receiving chamber 110 and close on and set up the auxiliary mould 300 described in example performed as described above at described first opening 111, make to be placed on The height at the peak place that the side on described auxiliary mould 300 pushes away 200 is not more than the height at the place, upside in described receiving chamber 110 Degree, the upper surface of described assistance platform 1 is slightly above the minimum point in described receiving chamber 110;
In the present embodiment, side pushes away 200 and is made up of spherical portion mounting flange 210, spherical portion 220 and blade portion 230, installs Front first side is pushed away 200 it be assembled into a complete module, side is pushed away 200 the most again and is placed on a support component 2, and make side push away Upward, by adjusting the height of the vertical rod 22 of a support component 2, the side that can adjust pushes away position and the angle of 200 to mounting flange 210 Degree, ready for follow-up installation.Being borehole structure owing to accommodating chamber 110, the upper surface of described assistance platform 1 is slightly above institute When stating the minimum point accommodating chamber 110, support assembly 2 can be made to draw in smoothly in receiving chamber 110.
S20, in the upside in described receiving chamber 110 and be provided at described second opening 112 outstanding drawing the first calabash First hang code 113, and be provided for outstanding drawing at described installing hole 120 along the both sides of the length direction in described receiving chamber 110 The second of second calabash hangs code 114;
By accommodate the proper position in chamber 110 arrange in order to outstanding draw calabash hang code, traditional to replace Chain block, can accurately control side and push away movement and the setting angle of 200, it is to avoid side push away 200 mobile or when installing with Accommodating and occur scratching to cause unnecessary damage between chamber 110, meanwhile, side pushes away the installation of 200 and is not limited by installing space.
S30, described side is pushed away 200 it is placed on described support component 2, utilize described first calabash by described support component In 2 draw in described receiving chamber 110 until described side pushes away the mounting flange 210 of 200 and is positioned at the lower section of described installing hole 120;
First calabash is arranged and the upside accommodating chamber 110 at the second opening 112, can be pushed away side by the first calabash A support component 2 at 200 places is by drawing on auxiliary mould 100 to accommodating in chamber 110, owing to using the first calabash accurately to control That makes a support component 2 pulls angle, and therefore, a support component 2 and will not accommodate generation scratching between chamber 110 in drawing process. Side can be pushed away 200 by the first calabash and draw in and just accommodate side and push away in the receiving chamber 110 of 200 by the present embodiment.
S40, utilize described second calabash to ajust the described side below described installing hole 120 to push away the position of 200;
By the first calabash, side is pushed away 200 to draw in accommodating in chamber 110, make mounting flange 210 just to installing hole 120, it After, side can be ajusted by the second calabash at installing hole 120 and push away the position of 200, make axis and the installing hole of mounting flange 210 The axis of 120 is parallel, is drawn in installing hole 120 by mounting flange 210 by the second calabash, to carry out installation preparation.
S50, by mounting flange 210, described side is pushed away 200 and be fixed in described installing hole 120, complete to install.
Mounting flange 210 is fixed and in installing hole 120 side can push away after good installation site 200.
As the present embodiment preferred embodiment, it is spaced in described receiving chamber 110 and is fixedly installed two limiting sections 130, the distance between the inner side of two described limiting sections 130 is equal to the width of described support component 2.In the present embodiment, logical Cross and limiting section 130 is set, the first calabash can be made to pull a support component 2, strictly to control side along the length direction of limiting section 130 Push away 200 draw in angle, the side on support component 2 push away 200 draw in receiving chamber 110 after, side pushes away the mounting flange 210 of 200 It is located exactly at the lower section of installing hole 120, improves working performance.
Preferably, the surface in described support component 2 and described receiving chamber 110 all scribbles lubricant.The present embodiment uses Huang Oil is as lubricant, and side pushes away 200 before drawing in receiving chamber 110, first at a support component 2 and the surface smear one that accommodates chamber 110 Layer butter is to reduce friction.
Described side pushes away 200 and includes spherical portion 220 and the blade portion 230 being connected with described spherical portion 220, described spherical portion The side of 220 is provided with described mounting flange 210, described side pushes away 200 and is placed on described support component and rests on described In vertical rod 22, so that the bottom of spherical portion 220 is unsettled, i.e. between spherical portion 220 and assistance platform 1, there is gap, use complete The height that described side pushes away the peak of 200 measured by instrument of standing, and adjusts this height by described vertical rod 22, so that described side pushes away 200 The height at peak place be not more than the height at place, upside in described receiving chamber 110.Specifically, the axis of spherical portion 220 And the angle between horizontal plane is 24 °, and the lowermost end of spherical portion 220 is slightly above the upper surface of assistance platform 1.
In the present embodiment, before installation side pushes away 200, need to push away according to side the overall dimensions of 200, calculate and draw in receiving chamber When 110 and need the angle controlled, then one corresponding auxiliary mould 300 of design, it is ensured that side pushes away 200 and drawing in when installing Shi Pingwen safety;The region causing using loop wheel machine is covered, it is possible to use existing high-order support is (high-order on the outstanding deck waftd The size of cross section supported is 1 meter * 1 meter, highly has 1 meter, 1.2 meters, 1.5 meters, the sizes such as 2 meters, can be as required Freely form different height) form special assistance platform 1, assistance platform 1 is laid by leading that two channel-section steels form Rail 12, smooth transition between guide rail 12 and receiving chamber 110.
The side of the present invention pushes away installation method and has the advantage that
(1) present invention is by designing the supporting tool of suitable angle, and the angle making side push away in the pull-in procedure is controlled System, it is to avoid damage the parts such as blade when that calabash being drawn in because of misoperation and cause unnecessary doing over again, add safety Property;
(2) by using a high position to support body of setting for this platform, and on platform body, set up track, make track and accommodate chamber Smooth transition, overcomes owing to outside plate hangs the impact produced of wafing, ensure that seriality and the safety of operation simultaneously;
(3) decrease substantial amounts of calabash and draw the hands tail work such as the welding job of code, and follow-up batch benefit mill.
The present invention passes through this installation method, improves the working performance at scene, originally uses chain block to need when installing Yao Liangge teams and groups the most about 15 people installs 16 hours, and the risk of damaged in collision is relatively big, pacifies according to the method for the present invention Dress, it is only necessary to Liang Ge teams and groups the most about 8 people installs 6 hours.
The present invention changes the operation form of existing extensive style, improves working performance by auxiliary mould, for other operation Form is offered reference and reference.
Above example is only used for illustrating the method detailed of the present invention, the invention is not limited in above-mentioned method detailed, i.e. Do not mean that the present invention has to rely on above-mentioned method detailed and could implement.Person of ordinary skill in the field is it will be clearly understood that right Any improvement of the present invention, the equivalence of raw material each to product of the present invention is replaced and the interpolation of auxiliary element, concrete way choice Deng, within the scope of all falling within protection scope of the present invention and disclosure.

Claims (10)

1. the auxiliary mould pushed away for installation side, it is characterised in that include assistance platform and a support component, described support group Part is arranged on described assistance platform and can move along the length direction of described assistance platform, and described support component includes supporting this Body and two vertical rods, described vertical rod is arranged at intervals at the both sides of described support body along the width of described support body, and The height adjustable of described vertical rod, so that the side being placed on described support component pushes away and there is gap between described assistance platform.
The auxiliary mould pushed away for installation side the most according to claim 1, it is characterised in that described support body includes putting down Capable and spaced two stocks, the length of two described stocks all extends along the length direction of described assistance platform, two Being fixed by two quarter butts between described stock, the two ends of described quarter butt are connected with two described stocks respectively, described in each A described vertical rod it is provided with on stock.
The auxiliary mould pushed away for installation side the most according to claim 2, it is characterised in that two described vertical rods set relatively Put, and tilt simultaneously towards the direction near the other side or away from the other side, described vertical rod and the plane at described support body place Between angle be 30 °~120 °.
The auxiliary mould pushed away for installation side the most according to claim 2, it is characterised in that described support body uses circle Steel is made.
The auxiliary mould pushed away for installation side the most according to claim 2, it is characterised in that described assistance platform includes putting down Platform main body and the guide rail being welded in described main platform body, described guide rail has two spaced grooves, two described length Bar lays respectively in described groove, and can slide along described groove.
The auxiliary mould pushed away for installation side the most according to claim 5, it is characterised in that the height of described main platform body Scalable.
7. a side pushes away installation method, it is characterised in that comprise the following steps:
S10, boats and ships have the receiving chamber that receiving side pushes away, and the upside accommodating chamber is provided with for installing the installing hole that described side pushes away, Described receiving chamber has the first opening and the second opening being oppositely arranged, outside described receiving chamber and close on described first opening part Set up the auxiliary mould described in any one of claim 1 to 6, make the peak place that the side being placed on described auxiliary mould pushes away Height be not more than the height at place, upside in described receiving chamber, the upper surface of described assistance platform is slightly above described receiving chamber Minimum point;
S20, in the upside in described receiving chamber and it is provided for outstanding drawing the first of the first calabash to hang code near described second opening part, And be provided in the both sides of described installing hole outstanding drawing the second of the second calabash to hang code;
S30, described side is pushed away it is placed on described support component, utilize described first calabash to be drawn in by described support component described Accommodate intracavity until the mounting flange that described side pushes away is positioned at the lower section of described installing hole;
S40, described second calabash is utilized to ajust the position that the described side below described installing hole pushes away;
S50, by mounting flange described side pushed away and be fixed in described installing hole, complete to install.
Side the most according to claim 7 pushes away installation method, it is characterised in that described receiving intracavity is spaced and is fixedly installed Two limiting sections, the distance between the inner side of two described limiting sections is equal to the width of described support component.
Side the most according to claim 7 pushes away installation method, it is characterised in that described support component and the table in described receiving chamber Face all scribbles lubricant.
Side the most according to claim 7 pushes away installation method, it is characterised in that described side pushes away and includes spherical portion and with described The blade portion that spherical portion is connected, the side of described spherical portion is provided with described mounting flange, is pushed away described side and is placed on described On support component and rest in described vertical rod, so that the bottom of described spherical portion is unsettled, side described in total station survey is used to push away The height of peak, and adjust this height by described vertical rod, so that the height at peak place that described side pushes away is not more than The height at the place, upside in described receiving chamber.
CN201610601498.6A 2016-07-27 2016-07-27 A kind of auxiliary mould pushed away for installation side and side push away installation method Active CN106218808B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610601498.6A CN106218808B (en) 2016-07-27 2016-07-27 A kind of auxiliary mould pushed away for installation side and side push away installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610601498.6A CN106218808B (en) 2016-07-27 2016-07-27 A kind of auxiliary mould pushed away for installation side and side push away installation method

Publications (2)

Publication Number Publication Date
CN106218808A true CN106218808A (en) 2016-12-14
CN106218808B CN106218808B (en) 2018-09-07

Family

ID=57533103

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610601498.6A Active CN106218808B (en) 2016-07-27 2016-07-27 A kind of auxiliary mould pushed away for installation side and side push away installation method

Country Status (1)

Country Link
CN (1) CN106218808B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107878674A (en) * 2017-10-19 2018-04-06 中船黄埔文冲船舶有限公司 A kind of split type side propeller enters cabin method
CN114834611A (en) * 2022-05-23 2022-08-02 江南造船(集团)有限责任公司 Installation device for ship fin stabilizer

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090032618A (en) * 2007-09-28 2009-04-01 삼성중공업 주식회사 Vessel structure for thruster motor maintenance
CN101462588A (en) * 2008-12-31 2009-06-24 广州文冲船厂有限责任公司 Mounting structure and mounting method for shipping lateral thruster
CN201343140Y (en) * 2008-12-31 2009-11-11 广州文冲船厂有限责任公司 Mounting structure of ship side thruster
CN101665144A (en) * 2009-09-29 2010-03-10 大连船舶重工集团有限公司 Method for mounting large-sized side pushing device on drilling platform
KR20120018881A (en) * 2010-08-24 2012-03-06 현대중공업 주식회사 Installation method for thruster of drillship
CN102765463A (en) * 2012-08-03 2012-11-07 扬帆集团股份有限公司 Installation method of bow transverse thrust unit

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090032618A (en) * 2007-09-28 2009-04-01 삼성중공업 주식회사 Vessel structure for thruster motor maintenance
CN101462588A (en) * 2008-12-31 2009-06-24 广州文冲船厂有限责任公司 Mounting structure and mounting method for shipping lateral thruster
CN201343140Y (en) * 2008-12-31 2009-11-11 广州文冲船厂有限责任公司 Mounting structure of ship side thruster
CN101665144A (en) * 2009-09-29 2010-03-10 大连船舶重工集团有限公司 Method for mounting large-sized side pushing device on drilling platform
KR20120018881A (en) * 2010-08-24 2012-03-06 현대중공업 주식회사 Installation method for thruster of drillship
CN102765463A (en) * 2012-08-03 2012-11-07 扬帆集团股份有限公司 Installation method of bow transverse thrust unit

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107878674A (en) * 2017-10-19 2018-04-06 中船黄埔文冲船舶有限公司 A kind of split type side propeller enters cabin method
CN114834611A (en) * 2022-05-23 2022-08-02 江南造船(集团)有限责任公司 Installation device for ship fin stabilizer

Also Published As

Publication number Publication date
CN106218808B (en) 2018-09-07

Similar Documents

Publication Publication Date Title
CN102173367B (en) Stern hydraulic rudder installing walking trolley
CN104139832B (en) Mounting method of integral stern shaft tube on naval architecture and ocean engineering
CN209243581U (en) A kind of stringer set up for And of Varying Depth steel girder segment
CN105066795B (en) A kind of adapter rotates docking Automatic-falling retracting device
CN1970387A (en) Ship screw shaft assembly integral installation method
KR101164893B1 (en) Double float type marine column structure construction apparatus
CN101549593A (en) Multifunctional movable spray-printing device for medium-diameter steel pipe
CN106218808A (en) A kind of auxiliary mould and side pushed away for installation side pushes away installation method
CN205429595U (en) Cable laying auxiliary device
CN207933903U (en) The slipping-shoe device of box girder with variable cross section pushing tow
CN206789992U (en) A kind of liftable cable wellhead pulley of pulley
CN106134494B (en) A kind of device for the integration test of satellite Compact Range
CN205764512U (en) Cone cylinder welding tooling
CN101992369A (en) Hydraulic drive automatic gyrorotor butting tooling equipment
CN201824084U (en) Hydraulic driving type revolving body automatic butt joint tooling equipment
CN208879885U (en) For earthing bullet tank reinforcing rib fanning strip groove cut-off apparatus
CN206278228U (en) Anchoring and mooring system
CN105083467B (en) A kind of shipbuilding axle rudder system bracing wire frock
CN201423807Y (en) Multifunctional movable medium-diameter steel tube spray printing device
CN204185183U (en) Continuous hot-rolling mill strip edge heater inductive head more changing device
CN209455021U (en) It is a kind of for docking ground refueling device of the Aircraft Air by oil head
CN210664880U (en) Adjusting pedestal for watertight test of concrete pouring guide pipe
CN105441634A (en) Protection device and protection method for desulfuration rollover oil cap
CN207470189U (en) For the shield long range translating station-crossing device of karst area
CN107165644A (en) A kind of combined type TBM misses the stop method

Legal Events

Date Code Title Description