CN106216968A - Dual-gripper air vane enclosing cover and the processing method of wheel disc - Google Patents

Dual-gripper air vane enclosing cover and the processing method of wheel disc Download PDF

Info

Publication number
CN106216968A
CN106216968A CN201610750546.8A CN201610750546A CN106216968A CN 106216968 A CN106216968 A CN 106216968A CN 201610750546 A CN201610750546 A CN 201610750546A CN 106216968 A CN106216968 A CN 106216968A
Authority
CN
China
Prior art keywords
wheel disc
welding
reel
wheel
dual
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610750546.8A
Other languages
Chinese (zh)
Inventor
闻诗明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUBEI SHUANGJIAN BLOWER PRODUCTION CO Ltd
Original Assignee
HUBEI SHUANGJIAN BLOWER PRODUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUBEI SHUANGJIAN BLOWER PRODUCTION CO Ltd filed Critical HUBEI SHUANGJIAN BLOWER PRODUCTION CO Ltd
Priority to CN201610750546.8A priority Critical patent/CN106216968A/en
Publication of CN106216968A publication Critical patent/CN106216968A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass
    • B23P15/04Making specific metal objects by operations not covered by a single other subclass or a group in this subclass turbine or like blades from several pieces

Abstract

Dual-gripper air vane enclosing cover and the processing method of wheel disc, weld with reel with reel blanking, reel turning, wheel disc with import circle blanking, wheel box cover die die mould, import circle turning, heat treatment, inspection, wheel disc including wheel disc, remove the steps such as root of weld overlap, heat treatment, inspection, reliable in quality of the present invention, saving raw material, reduction production cost.

Description

Dual-gripper air vane enclosing cover and the processing method of wheel disc
Technical field
The present invention relates to blower fan and manufacture field, be specifically related to dual-gripper air vane enclosing cover and the processing method of wheel disc.
Background technology
It is more and more universal that dual-gripper aerator uses, and its enclosing cover for impeller and the existing processing method of wheel disc be: 1. forge Wheel disc discus;2. heat treatment;3. inspection;4. machine rough turn;5. inspection;6. heat treatment;7. machining half finish turning;8. inspection. This kind of method wheel cap is to be processed by solid forging, and material causes serious waste, and thick owing to being machined out respectively Car and finish turning, cause working (machining) efficiency low, add the manufacturing cost of blower fan.
Summary of the invention
The present invention is directed to defect and the deficiency of prior art, it is provided that a kind of reliable in quality, saving raw material, reduction produce into This dual-gripper air vane enclosing cover and the processing method of wheel disc.
For realizing object above, the technical solution of the present invention is:
Dual-gripper air vane enclosing cover and the processing method of wheel disc, it is characterised in that: comprise the following steps:
1) wheel cap, import circle blanking: 1. wheel cap, import circle are carried out expansion setting-out;2. allowance is determined;3. material is determined Rebound degree and elongation percentage;4. the operability combining designed mould and equipment finally determines blank size;
2) wheel cap mould die mould: 1. design casted die mould according to the mechanical performance of design drawing and material, 2. according to design Drawing making molded line model, 3. pressure testing wheel cap, check whether institute's every data target of molding wheel cap meets design with molded line model Drawing requirement is to improve mould and blank size and to finally improve to qualified;
3) import circle turning: 1. providing rough turn artwork, 2. comparison artwork carries out turning to import circle on lathe;
4) check that wheel cap molded line and import circle turning size are the most qualified;
5) wheel cap and import circle assembly welding: 1. by wheel cap and import circle assembling and spot welding and fix;2. assembly welding spot welding fixed Part is put in electric furnace and is taken out after preheating held for some time;3. weld in holding temperature;4. postwelding dyeing inspection weldering Seam quality, as defective, needs to carry out excavating repair welding;
6) heat treatment: 1. the group welding piece welded is put into electric furnace is heated to about 700~705 DEG C insulation 4 hours after power-off; 2. open after electric furnace cover naturally cools to room temperature by group welding piece when temperature is down to 350 DEG C and take out;
7) inspection;
8) wheel disc, reel blanking: 1. wheel disc, reel are carried out expansion setting-out;2. allowance is determined;3. roughing technique is provided Figure;
9) reel turning: 1. process reel molded line by roughing artwork;2. processing and wheel disc bevel for welding;3. each position is checked Size;
10) wheel disc welds with reel one side: 1. by wheel disc and reel assembling and spot welding and fix;2. the group welding piece that spot welding is fixing is put Take out after entering electric furnace is preheated to 200 DEG C and being incubated two hours;3. welding in insulation, welding temperature is not less than 120 DEG C;4. weld After stain checks weldquality, as defective, needs to carry out excavating repair welding;
11) root of weld overlap is removed in favourable turn processing turning;
12) wheel disc welds with the opposite side of reel: according to step 10) repetitive operation;
13) post weld heat treatment: 1. the group welding piece welded is put into electric furnace is heated to about 750 DEG C insulation 4 hours after power-off; 2. open after electric furnace cover naturally cools to room temperature by group welding piece when temperature is down to 300 DEG C and take out, to eliminate welding stress;
14) inspection: require to check welding quality according to technology.
Described step 2) the 3. the criterion of acceptability in step be molded line and standard jig gap≤1mm.
Criterion of acceptability in described step 4) is wheel cap molded line and model gap≤1mm, import circle turning scale error≤ 0.1mm。
In described step 5), 2. the be preheated to 120 DEG C in electric furnace and be incubated 2 hours in step.
In described step 5) the 3. in step holding temperature be not less than 120 DEG C.
In described step 9), 3. the check each spot size in step, it is desirable to error≤0.1mm.
Compared with prior art, the invention have the benefit that
1, in the present invention wheel cap by original solid forging change into sheet material by after mould molding again with import circle welding, compare biography System technique is by solid forging molding, and not only bulk strength will not change, and new technology greatly reduces raw-material loss, Reducing difficulty of processing, improve working (machining) efficiency, cost reduces about 60%, and wheel cap total quality more wins in the past.
2, in the present invention, step is clear, technique is rigorous, compare solid forging technique its to the requirement of process equipment the most Reducing, such design can not only be substantially reduced the operation easier of operator, and can reduce buying and the dimension of company Accomplish this.
Detailed description of the invention
Embodiment
Dual-gripper air vane enclosing cover and the processing method of wheel disc, it is characterised in that: comprise the following steps:
1) wheel cap, import circle blanking: 1. wheel cap, import circle are carried out expansion setting-out;2. allowance is determined;3. material is determined Rebound degree and elongation percentage;4. the operability combining designed mould and equipment finally determines blank size;
2) wheel cap mould die mould: 1. design casted die mould according to the mechanical performance of design drawing and material, 2. according to design Drawing making molded line model, 3. pressure testing wheel cap, check whether institute's every data target of molding wheel cap meets design with molded line model Drawing requirement to improve mould and blank size and to finally improve to qualified, criterion of acceptability be molded line with standard jig gap≤ 1mm.;
3) import circle turning: 1. providing rough turn artwork, 2. comparison artwork carries out turning to import circle on lathe;
4) checking that wheel cap molded line and import circle turning size are the most qualified, criterion of acceptability is wheel cap molded line and model gap≤1mm, Import circle turning scale error≤0.1mm;
5) wheel cap and import circle assembly welding: 1. by wheel cap and import circle assembling and spot welding and fix;2. assembly welding spot welding fixed Part is put into after being preheated to 120 DEG C in electric furnace and being incubated 2 hours and is taken out;3. weld, 4. under conditions of holding temperature 120 DEG C Postwelding dyeing inspection weldquality, as defective, needs to carry out excavating repair welding;
6) heat treatment: 1. the group welding piece welded is put into electric furnace is heated to about 700~705 DEG C insulation 4 hours after power-off, 2. open after electric furnace cover naturally cools to room temperature by group welding piece when temperature is down to 350 DEG C and take out;
7) inspection;
8) wheel disc, reel blanking: 1. wheel disc, reel are carried out expansion setting-out;2. allowance is determined;3. roughing technique is provided Figure;
9) reel turning: 1. process reel molded line by roughing artwork;2. processing and wheel disc bevel for welding;3. each position is checked Size, it is desirable to error≤0.1mm;
10) wheel disc welds with reel one side: 1. by wheel disc and reel assembling and spot welding and fix;2. the group welding piece that spot welding is fixing is put Take out after entering electric furnace is preheated to 200 DEG C and being incubated two hours;3. welding in insulation, welding temperature is not less than 120 DEG C;4. weld After stain checks weldquality, as defective, needs to carry out excavating repair welding;
11) favourable turn processing turning understands root of weld overlap;
12) wheel disc welds with the opposite side of reel: according to step 10) repetitive operation;
13) post weld heat treatment: 1. the group welding piece welded is put into electric furnace is heated to about 750 DEG C insulation 4 hours after power-off; 2. open after electric furnace cover naturally cools to room temperature by group welding piece when temperature is down to 300 DEG C and take out, to eliminate welding stress;
14) inspection: require to check welding quality according to technology.

Claims (6)

1. dual-gripper air vane enclosing cover and the processing method of wheel disc, it is characterised in that: comprise the following steps:
1) wheel cap, import circle blanking: 1. wheel cap, import circle are carried out expansion setting-out;2. allowance is determined;3. material is determined Rebound degree and elongation percentage;4. the operability combining designed mould and equipment finally determines blank size;
2) wheel cap mould die mould: 1. design casted die mould according to the mechanical performance of design drawing and material, 2. according to design Drawing making molded line model, 3. pressure testing wheel cap, check whether institute's every data target of molding wheel cap meets design with molded line model Drawing requirement is to improve mould and blank size and to finally improve to qualified;
3) import circle turning: 1. providing rough turn artwork, 2. comparison artwork carries out turning to import circle on lathe;
4) check that wheel cap molded line and import circle turning size are the most qualified;
5) wheel cap and import circle assembly welding: 1. by wheel cap and import circle assembling and spot welding and fix;2. assembly welding spot welding fixed Part is put in electric furnace and is taken out after preheating held for some time;3. weld in holding temperature;4. postwelding dyeing inspection weldering Seam quality, as defective, needs to carry out excavating repair welding;
6) heat treatment: 1. the group welding piece welded is put into electric furnace is heated to about 700~705 DEG C insulation 4 hours after power-off; 2. open after electric furnace cover naturally cools to room temperature by group welding piece when temperature is down to 350 DEG C and take out;
7) inspection;
8) wheel disc, reel blanking: 1. wheel disc, reel are carried out expansion setting-out;2. allowance is determined;3. roughing technique is provided Figure;
9) reel turning: 1. process reel molded line by roughing artwork;2. processing and wheel disc bevel for welding;3. each position is checked Size;
10) wheel disc welds with reel one side: 1. by wheel disc and reel assembling and spot welding and fix;2. the group welding piece that spot welding is fixing is put Take out after entering electric furnace is preheated to 200 DEG C and being incubated two hours;3. welding in insulation, welding temperature is not less than 120 DEG C;4. weld After stain checks weldquality, as defective, needs to carry out excavating repair welding;
11) root of weld overlap is removed in favourable turn processing turning;
12) wheel disc welds with the opposite side of reel: according to step 10) repetitive operation;
13) post weld heat treatment: 1. the group welding piece welded is put into electric furnace is heated to about 750 DEG C insulation 4 hours after power-off; 2. open after electric furnace cover naturally cools to room temperature by group welding piece when temperature is down to 300 DEG C and take out, to eliminate welding stress;
14) inspection: require to check welding quality according to technology.
Dual-gripper air vane enclosing cover the most according to claim 1 and the processing method of wheel disc, it is characterised in that: described Step 2) the 3. the criterion of acceptability in step be molded line and standard jig gap≤1mm.
Dual-gripper air vane enclosing cover the most according to claim 1 and the processing method of wheel disc, it is characterised in that:
Criterion of acceptability in described step 4) is wheel cap molded line and model gap≤1mm, import circle turning scale error≤ 0.1mm。
Dual-gripper air vane enclosing cover the most according to claim 1 and the processing method of wheel disc, it is characterised in that: described In step 5), 2. the be preheated to 120 DEG C in electric furnace and be incubated 2 hours in step.
Dual-gripper air vane enclosing cover the most according to claim 1 and the processing method of wheel disc, it is characterised in that: described In step 5) the 3. in step holding temperature be not less than 120 DEG C.
Dual-gripper air vane enclosing cover the most according to claim 1 and the processing method of wheel disc, it is characterised in that: described In step 9), 3. the check each spot size in step, it is desirable to error≤0.1mm.
CN201610750546.8A 2016-08-30 2016-08-30 Dual-gripper air vane enclosing cover and the processing method of wheel disc Pending CN106216968A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610750546.8A CN106216968A (en) 2016-08-30 2016-08-30 Dual-gripper air vane enclosing cover and the processing method of wheel disc

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610750546.8A CN106216968A (en) 2016-08-30 2016-08-30 Dual-gripper air vane enclosing cover and the processing method of wheel disc

Publications (1)

Publication Number Publication Date
CN106216968A true CN106216968A (en) 2016-12-14

Family

ID=57556016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610750546.8A Pending CN106216968A (en) 2016-08-30 2016-08-30 Dual-gripper air vane enclosing cover and the processing method of wheel disc

Country Status (1)

Country Link
CN (1) CN106216968A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106826140A (en) * 2017-04-13 2017-06-13 苏州三和仪器有限公司 A kind of machining manufacture of impeller of high-speed fan
CN108581365A (en) * 2018-06-26 2018-09-28 沈阳透平机械股份有限公司 A kind of processing method of enclosed ternary slot welding impeller
CN113007126A (en) * 2021-02-26 2021-06-22 英飞同仁风机股份有限公司 Multi-stage centrifugal blower partition plate, preparation method thereof and multi-stage centrifugal blower
CN114658686A (en) * 2022-05-05 2022-06-24 山东省章丘鼓风机股份有限公司 Impeller shaft disc of small-sized ventilator and machining method thereof
CN115055926A (en) * 2022-06-06 2022-09-16 江苏金通灵鼓风机有限公司 Forming method of three-dimensional flow impeller

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2268131C1 (en) * 2004-08-30 2006-01-20 Открытое акционерное общество "Энергомашкорпорация" Rotor producing method
CN102091919A (en) * 2009-12-09 2011-06-15 沈阳鼓风机集团有限公司 Machining method of three-dimensional closed impeller
CN102990302A (en) * 2012-11-30 2013-03-27 杭州杭氧透平机械有限公司 Machining method of closed three-elemental impeller with small flow
CN104279186A (en) * 2014-09-17 2015-01-14 杭州杭氧透平机械有限公司 High-flow-rate ultra-large-diameter semi-milling and semi-welding closed ternary impeller and manufacturing method
CN105269278A (en) * 2015-11-19 2016-01-27 湖北双剑鼓风机股份有限公司 Machining method for three-dimensional flow impeller

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2268131C1 (en) * 2004-08-30 2006-01-20 Открытое акционерное общество "Энергомашкорпорация" Rotor producing method
CN102091919A (en) * 2009-12-09 2011-06-15 沈阳鼓风机集团有限公司 Machining method of three-dimensional closed impeller
CN102990302A (en) * 2012-11-30 2013-03-27 杭州杭氧透平机械有限公司 Machining method of closed three-elemental impeller with small flow
CN104279186A (en) * 2014-09-17 2015-01-14 杭州杭氧透平机械有限公司 High-flow-rate ultra-large-diameter semi-milling and semi-welding closed ternary impeller and manufacturing method
CN105269278A (en) * 2015-11-19 2016-01-27 湖北双剑鼓风机股份有限公司 Machining method for three-dimensional flow impeller

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106826140A (en) * 2017-04-13 2017-06-13 苏州三和仪器有限公司 A kind of machining manufacture of impeller of high-speed fan
CN106826140B (en) * 2017-04-13 2019-01-11 苏州三和仪器有限公司 A kind of machining manufacture of impeller of high-speed fan
CN108581365A (en) * 2018-06-26 2018-09-28 沈阳透平机械股份有限公司 A kind of processing method of enclosed ternary slot welding impeller
CN113007126A (en) * 2021-02-26 2021-06-22 英飞同仁风机股份有限公司 Multi-stage centrifugal blower partition plate, preparation method thereof and multi-stage centrifugal blower
CN114658686A (en) * 2022-05-05 2022-06-24 山东省章丘鼓风机股份有限公司 Impeller shaft disc of small-sized ventilator and machining method thereof
CN114658686B (en) * 2022-05-05 2024-02-20 山东省章丘鼓风机股份有限公司 Impeller shaft disc of small ventilator and processing method thereof
CN115055926A (en) * 2022-06-06 2022-09-16 江苏金通灵鼓风机有限公司 Forming method of three-dimensional flow impeller

Similar Documents

Publication Publication Date Title
CN106216968A (en) Dual-gripper air vane enclosing cover and the processing method of wheel disc
CN102941447B (en) A kind of manufacturing processing technic of bolt
CN105583588B (en) A kind of processing method for taper roll bearing Internal and external cycle
CN103639649B (en) A kind of manufacture method of engine inlets
CN105269278B (en) A kind of processing method of three-dimensional flow impeller
CN109014518B (en) Welding device and repairing process for train wheel die holder
CN104175014B (en) A kind of for large thin-wall component accurate welding shaped device and precision machining method
CN104551552B (en) Thermally-formed wheel manufacturing method
CN110405426B (en) Mass production process suitable for plate welding type casings
CN101761541A (en) Manufacturing process for main shaft of large water turbine
CN107824938A (en) Automobile Cold Die Edge overlaying method
CN108443450B (en) Production method of rotor for hydraulic coupler
CN102528218B (en) Method for preventing deformation of large-size thin-wall annular casting during welding process
CN106216967A (en) A kind of processing method of three-dimensional flow impeller wheel cap
CN106514152A (en) Processing method and device for thin-wall multi-rib titanium alloy parts
CN101407013A (en) Little deformation welding process for mini car rear-axle housing
CN104148797B (en) The manufacture method of planetary wheel carrier
CN112676506A (en) Universal joint cross shaft closed forging and forging residual heat normalizing processing technology
CN104175127A (en) Automobile connecting rod die production process
CN212094773U (en) Electromagnetic chuck bottom shell weld assembly tooling structure for lifting wheel steel ingots
CN113579533A (en) Pre-control method for radial precision of electron beam welding structure after blisk welding
CN207057875U (en) One kind automation tea carding machine welding production line
CN111515513A (en) Welding method of high-temperature alloy drum barrel rotor assembly
CN107052729A (en) The processing method of gear
CN104842121A (en) Large semi-toroidal box-shaped structure processing method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161214

RJ01 Rejection of invention patent application after publication