CN106203969A - A kind of prison check system of steel-making boiler tubing based on BIM - Google Patents
A kind of prison check system of steel-making boiler tubing based on BIM Download PDFInfo
- Publication number
- CN106203969A CN106203969A CN201610761660.0A CN201610761660A CN106203969A CN 106203969 A CN106203969 A CN 106203969A CN 201610761660 A CN201610761660 A CN 201610761660A CN 106203969 A CN106203969 A CN 106203969A
- Authority
- CN
- China
- Prior art keywords
- construction
- computer
- bim
- boiler tubing
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009628 steelmaking Methods 0.000 title claims abstract description 51
- 238000010276 construction Methods 0.000 claims abstract description 119
- 238000009659 non-destructive testing Methods 0.000 claims abstract description 44
- 238000005516 engineering process Methods 0.000 claims abstract description 11
- 239000002918 waste heat Substances 0.000 claims description 34
- 238000000034 method Methods 0.000 claims description 22
- 230000008569 process Effects 0.000 claims description 17
- 238000004088 simulation Methods 0.000 claims description 16
- 238000003466 welding Methods 0.000 claims description 15
- 238000001514 detection method Methods 0.000 claims description 14
- 238000007689 inspection Methods 0.000 claims description 9
- 238000013461 design Methods 0.000 claims description 8
- 239000000463 material Substances 0.000 claims description 8
- 238000009434 installation Methods 0.000 claims description 7
- 238000012550 audit Methods 0.000 claims description 6
- 238000011084 recovery Methods 0.000 claims description 3
- 238000012360 testing method Methods 0.000 claims description 3
- 230000002950 deficient Effects 0.000 claims description 2
- 238000012545 processing Methods 0.000 claims description 2
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 230000006870 function Effects 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 238000004364 calculation method Methods 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 238000011900 installation process Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000009467 reduction Effects 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000017531 blood circulation Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000001427 coherent effect Effects 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 230000008447 perception Effects 0.000 description 1
- 238000013439 planning Methods 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
- 238000012372 quality testing Methods 0.000 description 1
- 230000002123 temporal effect Effects 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/18—Network design, e.g. design based on topological or interconnect aspects of utility systems, piping, heating ventilation air conditioning [HVAC] or cabling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/10—Services
- G06Q50/26—Government or public services
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2113/00—Details relating to the application field
- G06F2113/14—Pipes
Abstract
The invention discloses the prison check system of a kind of steel-making boiler tubing based on BIM, this system is to include OA system, terminal handler, the Internet, pipeline construction side's computer, Non-Destructive Testing side's computer and government supervision department computer, and described OA system is connected by the Internet with terminal handler;Described terminal handler is available with the information processor that BIM technology is modeled;Described pipeline construction side's computer is connected by the Internet with terminal handler;Described Non-Destructive Testing side's computer is connected by the Internet with terminal handler;Described government supervision department computer is connected by the Internet with terminal handler, and the whole operation of this system is that pipeline construction side, Non-Destructive Testing side, government supervision department link up linking and only need to carry out on a public OA platform based on internetwork operation platform.
Description
Technical field
The present invention relates to metallurgical system steel-making waste heat boiler Pipe installing prison inspection field, specifically a kind of based on BIM and
The ultra-large type steel-making waste heat boiler pipeline prison check system of the Internet and construction method, for ultra-large type steel-making waste heat boiler pipeline peace
The prison inspection work carried out in dress engineering.
Background technology
In view of particular hazard and the importance of ultra-large type steel-making waste heat boiler pipeline, State General Administration for Quality Supervision is to ultra-large type
Steel-making waste heat boiler Pipe installing requires must to carry out in a pre-installation informing, in installation process various process qualitys exercise supervision,
Just can run after being issued prison inspection return on qualification by government's quality testing department after installation.Conventional ultra-large type steel-making waste heat boiler pipe
Road is installed and is followed above step, reports nondestructive testing department and government supervision during various operations are carried out and after completing
Department, nondestructive testing department arrangement personnel carry out scene and carry out Non-Destructive Testing, need to carry coherent detection data after having detected
Government supervision departmental staff is transferred to check.According to conventional construction experience, above-mentioned steps is followed in the construction of everywhere pipeline, to item
The mesh duration brings and has a strong impact on.
Summary of the invention
It is an object of the invention to provide the prison check system of a kind of steel-making boiler tubing based on BIM, to solve the above-mentioned back of the body
The problem proposed in scape technology.
For achieving the above object, the present invention provides following technical scheme: the prison of a kind of steel-making boiler tubing based on BIM is examined
System, this system includes OA system, terminal handler, the Internet, pipeline construction side's computer, Non-Destructive Testing side's computer and political affairs
Mansion superintendent office computer, described OA system is connected by the Internet with terminal handler;Described pipeline construction side calculates
Machine, Non-Destructive Testing side's computer and government supervision department computer are connected with terminal handler by the Internet respectively.
Preferably, described pipeline construction side computer, Non-Destructive Testing side's computer and government supervision department computer are platforms
Formula machine, smart mobile phone or panel computer;Described pipeline construction side computer, Non-Destructive Testing side's computer and government supervision department meter
Calculation machine is one or more computers.
Preferably, described terminal handler built-in BIM software, by BIM software data processing.
The invention also discloses the construction method of a kind of steel-making boiler tubing prison check system based on BIM, as follows
Construct:
S1, set up OA system, create tripartite's common platform
The entry password of the most newly-built pipeline construction side, Non-Destructive Testing side and government supervision side and log in close in OA system
Code;
S2, by OA system, terminal handler, the Internet, pipeline construction side's computer, Non-Destructive Testing side's computer and government
Superintendent office's computer is connected by the Internet.Utilize the Internet, each sub-block of whole system is connected, forms an entirety;
S3, utilize on terminal handler BIM technology carry out ultra-large type steel-making waste heat boiler tubing modeling;
Construction party logs in OA system, utilizes computer and BIM technology to carry out ultra-large type steel-making waste heat on terminal handler
Boiler tubing system modelling, each item data of input channel and mouth of pipe weld interval, welding personnel in each mouth of pipe welding process
With data such as welding manners;
S4, Non-Destructive Testing side utilize computer to understand terminal handler institute input channel weld bond welding situation, carry out in time
The Non-Destructive Testing of weld bond
Non-Destructive Testing side logs in OA system, and the weld bond showing terminal handler carries out Non-Destructive Testing, detection is tied simultaneously
Fruit is input in terminal handler BIM modeling in time, Data Enter point and nozzle position one_to_one corresponding in BIM modeling;
S5, the prison inspection of government supervision department
Government supervision department logs in OA system, clicks on every data link of terminal handler BIM modeling, understands weld bond weldering
Connect situation and integral installation situation, nonconformance is indicated, send rectification instruction;
In step S5, construction speed is observed by government supervision department computer whole process by government supervision department, models BIM
The indefinite ground of middle construction data can send instruction, and this instruction can be shown that instruction issuing side information, instruction by OA system
Content includes ordering other two sides to provide definite data, and determines according to the data of feedback in job site data and BIM modeling
Do over again or stop work;
S6, construction party recovery command, rectify and improve, and whole system forms closed loop
Construction party logs in OA system and receives the instruction of government supervision department, for needing the job site of rectification to carry out in time
Rectification, is simultaneously entered information after rectification.Ensure that whole Pipe installing, detection form a perfect closed-loop structure.
Preferably, described S3 includes:
S31, obtain according to equipment and materials dimensional drawing ultra-large type steel-making waste heat boiler tubing basic model;
S32, carry out structure discipline and electromechanical speciality BIM mould according to construction and the demand of user and the basic model obtained
Type models, and obtains the threedimensional model of ultra-large type steel-making waste heat boiler tubing;
S33, carry out structure discipline and electromechanical speciality BIM model checking for the first time, and generate audit report for the first time;
S34, according to first time audit report BIM model adjusted repeatedly and revise, finally giving BIM model;
S35, construction drawing according to BIM model generation ultra-large type steel-making waste heat boiler tubing, and to design drawing
Carry out three-dimensional drawing school to examine, obtain ultra-large type steel-making waste heat boiler tubing construction drawing:
Preferably, described step S35 includes:
S351, the BIM model that waste heat boiler tubing construction drawing of making steel according to ultra-large type is corresponding carry out construction area
Divide, construction speed is simulated and equipment and materials transport simulation these three three-dimensional artificial construction simulation;
S352, result according to these three three-dimensional artificial construction simulation determine ultra-large type steel-making waste heat boiler tubing
Construction area.
Preferably, in described step S4, Non-Destructive Testing can determine the reality of next step arrangement and method for construction according to testing result
Granting no, by Non-Destructive Testing side's computer by the result typing OA system of detection, it is qualified to detect, and continues construction, and detection does not conforms to
Lattice then send command request construction party and do over again and stop next step construction.
Preferably, in described step S5, construction is observed by government supervision department computer whole process by government supervision department
Progress, in modeling BIM, the indefinite place of construction data sends instruction.
Preferably, described pipeline construction side computer, Non-Destructive Testing side's computer and government supervision department computer have
BIM modeling carries out the computer of information reading, display and referential function.
Compared with prior art, the invention has the beneficial effects as follows:
The whole operating process of this system is based on internetwork operation platform, pipeline construction side, Non-Destructive Testing side, government's prison
The department that superintends and directs links up linking and only need to carry out on a public OA platform.Meanwhile, project is to carry out based on the basis of BIM modeling
Every operation input, read, process and rectify and improve, form a blood circulation so that project process is very clear.
Accompanying drawing explanation
Fig. 1: the prison check system flow chart of a kind of steel-making boiler tubing based on BIM.
In figure: 1, OA system, 2, terminal handler, 3, the Internet, 4, pipeline construction side's computer, 5, Non-Destructive Testing side's meter
Calculation machine, 6, government supervision department computer.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Describe, it is clear that described embodiment is only a part of embodiment of the present invention rather than whole embodiments wholely.Based on
Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under not making creative work premise
Embodiment, broadly falls into the scope of protection of the invention.
Referring to Fig. 1, the present invention provides a kind of technical scheme: a kind of ultra-large type based on BIM and the Internet steel-making waste heat
Boiler tubing prison check system, including OA system 1, terminal handler 2, the Internet 3, pipeline construction side's computer 4, Non-Destructive Testing side
Computer 5 and government supervision department computer 6, OA system 1 is connected by the Internet 3 with terminal handler 2;Pipeline construction side counts
Calculation machine 4 is connected by the Internet 3 with terminal handler 2;Non-Destructive Testing side's computer 5 is with terminal handler 2 by the Internet 3 even
Connect;Government supervision department computer 6 is connected by the Internet 3 with terminal handler 2;Wherein pipeline construction side's computer 4, lossless
Detection side's computer 5 and government supervision department computer 6 carry out information reading, display and referential function on BIM models
Computer.
Pipeline construction side's computer 4, Non-Destructive Testing side's computer 5 and government supervision department computer 6 are all desktop computer, intelligence
Energy mobile phone or panel computer, it is simple to tripartite inputs and checks information.
Pipeline construction side's computer 4, Non-Destructive Testing side's computer 5 and government supervision department computer 6 are all one or many
Platform computer.
Terminal handler 2 is by the data in built-in BIM software processes work progress.
Ultra-large type based on BIM steel-making waste heat boiler Pipe installing prison check system is constructed as follows:
S1, set up OA system 1, create tripartite's common platform
Newly-built pipeline construction side, Non-Destructive Testing side and the entry password of government supervision side and login respectively in OA system 1
Password;
S2, by OA system 1, terminal handler 2, the Internet 3, pipeline construction side's computer 4, Non-Destructive Testing side's computer 5
Connected by the Internet 3 with government supervision department computer 6.Utilize the Internet 3, each sub-block of whole system is connected, formed
One entirety;
S3, utilize on terminal handler 2 BIM technology carry out ultra-large type steel-making waste heat boiler tubing modeling;
Construction party logs in OA system 1, utilizes computer and BIM technology to carry out ultra-large type steel-making on terminal handler 2 remaining
Heat boiler tubing models, each item data of input channel and mouth of pipe weld interval, welding people in each mouth of pipe welding process
The data such as member and welding manner;
S31, obtain according to equipment and materials dimensional drawing ultra-large type steel-making waste heat boiler tubing basic model;
S32, carry out structure discipline and electromechanical speciality BIM mould according to construction and the demand of user and the basic model obtained
Type models, and obtains the threedimensional model of ultra-large type steel-making waste heat boiler tubing;
S33, carry out structure discipline and electromechanical speciality BIM model checking for the first time, and generate audit report for the first time;
S34, according to first time audit report BIM model adjusted repeatedly and revise, finally giving BIM model;
S35, construction drawing according to BIM model generation ultra-large type steel-making waste heat boiler tubing, and to design drawing
Carry out three-dimensional drawing school to examine, obtain ultra-large type steel-making waste heat boiler tubing construction drawing;
S351, the BIM model that waste heat boiler tubing construction drawing of making steel according to ultra-large type is corresponding carry out construction area
Divide, construction speed is simulated and equipment and materials transport simulation these three three-dimensional artificial construction simulation;
S352, result according to these three three-dimensional artificial construction simulation determine ultra-large type steel-making waste heat boiler tubing
Construction area.
S4, Non-Destructive Testing side utilize computer to understand terminal handler institute input channel weld bond welding situation, carry out in time
The Non-Destructive Testing of weld bond
Non-Destructive Testing side logs in OA system 1, and the weld bond of terminal handler 2 display is carried out Non-Destructive Testing, simultaneously will detection
Result is input in terminal handler BIM modeling in time, Data Enter point and nozzle position one_to_one corresponding in BIM modeling;
In step S4, whether Non-Destructive Testing can determine the enforcement of next step arrangement and method for construction according to testing result, by nothing
Damaging the detection side's computer 5 result typing OA system 1 by detection, it is qualified to detect, and can continue construction, detect defective, send out
Go out command request construction party do over again and stop next step construction;
S5, the prison inspection of government supervision department
Government supervision department logs in OA system 1, clicks on every data link of terminal handler BIM modeling, understands weld bond
Welding situation and integral installation situation, indicate for nonconformance, sends rectification instruction;
In step S5, construction speed is observed by government supervision department computer 6 is omnidistance by government supervision department, builds BIM
In mould, the indefinite ground of construction data can send instruction, and this instruction can be shown that instruction issuing side information by OA system 1, refers to
Make content include ordering other two sides to provide definite data, and determine according to the data of feedback in job site data and BIM modeling
Surely do over again or stop work;
S6, construction party recovery command, rectify and improve, and whole system forms closed loop
Construction party logs in OA system 1 and receives the instruction of government supervision department, for needing the job site of rectification to enter in time
Row rectification, is simultaneously entered information after rectification.Ensure that whole Pipe installing, detection form a perfect closed-loop structure.
Wherein, it is to whole ultra-large type steel-making waste heat boiler pipe design once to BIM modelling in step S35
" previewing ", the process of modeling is also once comprehensive " three-dimensional school is examined " process simultaneously, can find in the process to be hidden in a large number
Problem in design, promotes global design quality, and input that later stage building site process is greatly decreased.Three-dimensional school is examined process and is mainly wrapped
Include:
(1), structure discipline model three-dimensional school is examined
The threedimensional model of structure discipline is mainly carried out matched moulds by collaborative on-link mode (OLM) by this process, by REVIT software
The functions such as the 3-D view that carries, wandering map, camera view, carry out three-dimensional school and examine, observe ultra-large type steel-making structural elements
Whether the body of waste heat boiler piping facility own, component and space layout have irrational situation, thus find to be hidden in design
In problem, it is to avoid the design alteration in later stage.The most no matter in the conceptual level or in the construction drawing stage, designer can be right
Ultra-large type steel-making waste heat boiler piping facility details is studied intuitively, strengthens the control dynamics of detailing;
(2), electromechanical speciality model three-dimensional school is examined
This process is mainly by the threedimensional model of link structure specialty, and the filter, the three-dimensional that carry in conjunction with REVIT software regard
The functions such as figure, wandering map and camera view, carry out three-dimensional school and examine, get rid of project in time each electromechanical equipment special pipelines model
The collision conflict being likely encountered in construction link, substantially reduces consequent modification application list, it is to avoid due to system various and
Spatial complex and between the pipeline that usually occurs, clash between pipeline and structural elements, or affect clear height and sky in pipeline
Between effect, or cause trouble to construction, cause doing over again or the generation of the situation such as waste.
Construction stage:
Boiler tubing project construction is complicated, and the present invention can utilize BIM system, derives three-dimensional simulation video, guiding construction
Person works, thus ensure construction speed, it is to avoid cause delaying work as drawing lacks;
BIM technology contains the full detail of building, is possible not only to the two and three dimensions drawing providing image visual, and
The information that bill of quantities, construction management, virtual construction, cost estimate etc. are more abundant can be provided, it is simple to each portion of project
Communicating with each other of door, collaborative work.BIM has publishing picture property: as provided integrated pipe line chart, collision detection to detect wrong reports and recommendations
The construction drawing that improvement project etc. are practical.BIM also can derive three-dimensional simulation video, preferably guiding construction person works;
The present invention can realize progress simulation, work progress is monitored in real time, planning of science activities place, control construct into
Degree, resource and quality, it is ensured that the safety of construction, improve construction quality and reduction of erection time;
By the BIM simulation to construction organization, tripartite can very be visually known the time of whole construction and installation link
Node and installation procedure, and clearly the difficult point being held in installation process and main points, construction party can also be further to original peace
Dress scheme is optimized and improves, to improve the safety of efficiency of construction and arrangement and method for construction;
The present invention is by being connected BIM with construction schedule, and spatial information and temporal information are incorporated into one can
Depending on 4D (3D+Time) model in, can intuitively, accurately reflect the work progress of whole building.4D construction simulation technology can
With rational construction plan in project building course, accurate perception construction speed, optimize and use working sources and science
Ground carry out Ground arrangement, construction speed, resource and the quality of whole engineering is managed collectively and controls, with the reduction of erection time,
Reduce cost and improve quality.
Engineering equipment and material are unfamiliar with by a lot of construction teams and groups, are easily caused and miss dress or damage equipment and material, impact
Construction speed.And BIM system comprises all information of building, working procedure simulation can be carried out for construction Difficulties, instruct workman
Construction, it is ensured that construction speed.
Construction data:
In January, 2016, in Zhanjiang steel mill steel-making 350t converter producing system, use this kind based on BIM and interconnection
The ultra-large type steel-making waste heat boiler Pipe installing prison check system of net, whole converter Pipe installing and detection and prison inspection have only used three
Half month, also start the beginning of information-based prison inspection in this field simultaneously.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, permissible
Understand and these embodiments can be carried out multiple change without departing from the principles and spirit of the present invention, revise, replace
And modification, the scope of the present invention be defined by the appended.
Claims (9)
1. the prison check system of a steel-making boiler tubing based on BIM, it is characterised in that include OA system (1), terminal handler
(2), the Internet (3), pipeline construction side's computer (4), Non-Destructive Testing side's computer (5) and government supervision department computer (6),
Described OA system (1) is connected by the Internet (3) with terminal handler (2);Described pipeline construction side's computer (4) is with whole
End processor (2) is connected by the Internet (3);Described Non-Destructive Testing side's computer (5) and terminal handler (2) are by interconnection
Net (3) connects;Described government supervision department computer (6) is connected by the Internet (3) with terminal handler (2).
The prison check system of a kind of steel-making boiler tubing based on BIM, it is characterised in that described pipe
Road construction party computer (4), Non-Destructive Testing side's computer (5) and government supervision department computer (6) are desktop computer, smart mobile phone
Or panel computer;Described pipeline construction side computer (4), Non-Destructive Testing side's computer (5) and government supervision department computer (6)
It is one or more computers.
The prison check system of a kind of steel-making boiler tubing based on BIM, it is characterised in that described end
End processor (2) built-in BIM software, by BIM software data processing.
4. the construction party of the prison check system of steel-making boiler tubing based on a kind of BIM according to any one of claims 1 to 3
Method, it is characterised in that carry out as follows:
S1, set up OA system (1), create tripartite's common platform:
The most newly-built pipeline construction side, Non-Destructive Testing side and the logon account of government supervision side and log in close in OA system (1)
Code;
S2, by OA system (1), terminal handler (2), the Internet (3), pipeline construction side's computer (4), Non-Destructive Testing side calculate
Machine (5) and government supervision department computer (6) are connected by the Internet (3), utilize the Internet (3) by each sub-block of whole system
Connect, form an entirety;
S3, utilize on terminal handler (2) BIM technology carry out ultra-large type steel-making waste heat boiler tubing modeling:
Construction party logs in OA system (1), utilizes computer and BIM technology to carry out ultra-large type steel-making on terminal handler (2) remaining
Heat boiler tubing models, time in mouth of pipe welding process by OA system (1) input channel initial data, mouth of pipe welding
Between, welding personnel name and welding manner;
S4, Non-Destructive Testing side utilize computer to understand the pipe welding port welding situation that terminal handler (2) is inputted, and carry out in time
The Non-Destructive Testing of weld bond:
Non-Destructive Testing side logs in OA system (1), and the weld bond of display upper to terminal handler (2) carries out Non-Destructive Testing, simultaneously will inspection
Survey in result timely input terminal processor BIM modeling, Data Enter point and nozzle position one_to_one corresponding in BIM modeling;
S5, the prison inspection of government supervision department:
Government supervision department logs in OA system (1), clicks on every data link of terminal handler BIM modeling, understands weld bond weldering
Connect situation and integral installation situation, nonconformance is indicated, send rectification instruction;
S6, construction party recovery command, rectify and improve, whole system formation closed loop:
Construction party logs in OA system (1), for needing the job site of rectification to rectify and improve in time, believes after being simultaneously entered rectification
Breath.
The construction method of a kind of steel-making boiler tubing prison check system based on BIM, its feature exists
In, described S3 includes:
S31, obtain according to equipment and materials dimensional drawing ultra-large type steel-making waste heat boiler tubing basic model;
S32, carry out structure discipline and electromechanical speciality BIM model modeling according to construction and the basic model that obtains of user's request,
Threedimensional model to ultra-large type steel-making waste heat boiler tubing;
S33, carry out structure discipline and electromechanical speciality BIM model checking for the first time, and generate audit report for the first time;
S34, according to first time audit report BIM model adjusted repeatedly and revise, finally giving BIM model;
S35, construction drawing according to BIM model generation ultra-large type steel-making waste heat boiler tubing, and carried out design drawing
Three-dimensional drawing school is examined, and obtains ultra-large type steel-making waste heat boiler tubing construction drawing.
The construction method of a kind of steel-making boiler tubing prison check system based on BIM, its feature exists
In, described step S35 includes:
S351, carry out according to ultra-large type steel-making BIM model corresponding to waste heat boiler tubing construction drawing construction area division,
Construction speed simulation and equipment and materials transport simulation these three three-dimensional artificial construction simulation;
S352, result according to these three three-dimensional artificial construction simulation determine the construction of ultra-large type steel-making waste heat boiler tubing
Region.
The construction method of a kind of steel-making boiler tubing prison check system based on BIM, its feature exists
In, in described step S4, whether Non-Destructive Testing root determines the enforcement of next step arrangement and method for construction according to testing result, by lossless
Detection side's computer (5) is by result typing OA system (1) of detection, and it is qualified to detect, and continues construction, detects defective, send
Command request construction party is done over again and stops next step construction.
The construction method of a kind of steel-making boiler tubing prison check system based on BIM, its feature exists
In, in described step S5, construction speed is observed, to BIM by government supervision department computer (6) is omnidistance by government supervision department
In modeling, the indefinite place of construction data sends instruction.
The construction method of a kind of steel-making boiler tubing prison check system based on BIM, its feature exists
In, described pipeline construction side computer (4), Non-Destructive Testing side's computer (5) and government supervision department computer (6) they are at BIM
The computer of information reading, display and referential function is carried out in modeling.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610761660.0A CN106203969A (en) | 2016-08-29 | 2016-08-29 | A kind of prison check system of steel-making boiler tubing based on BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610761660.0A CN106203969A (en) | 2016-08-29 | 2016-08-29 | A kind of prison check system of steel-making boiler tubing based on BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106203969A true CN106203969A (en) | 2016-12-07 |
Family
ID=58089524
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610761660.0A Pending CN106203969A (en) | 2016-08-29 | 2016-08-29 | A kind of prison check system of steel-making boiler tubing based on BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106203969A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106845832A (en) * | 2017-01-20 | 2017-06-13 | 四川理工学院 | Based on BQIM construction quality information management systems |
CN107133338A (en) * | 2017-05-16 | 2017-09-05 | 廊坊市新思维科技有限公司 | Non-destructive Testing Data auditing system |
CN109711114A (en) * | 2019-03-13 | 2019-05-03 | 江苏柯瑞机电工程股份有限公司 | Pipeline construction and management system based on BIM |
CN112485377A (en) * | 2020-11-24 | 2021-03-12 | 南京睿控自动化有限公司 | Intelligent boiler based on BIM structure combines data model |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
-
2016
- 2016-08-29 CN CN201610761660.0A patent/CN106203969A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
Non-Patent Citations (2)
Title |
---|
王丽佳: "基于BIM的智慧建造策略研究", 《中国优秀硕士学位论文全文数据库电子期刊 工程科技II辑》 * |
袁晓 等: "基于智慧城市和BIM理念的建设工程政务监管模式探讨", 《土木建筑工程信息技术》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106845832A (en) * | 2017-01-20 | 2017-06-13 | 四川理工学院 | Based on BQIM construction quality information management systems |
CN107133338A (en) * | 2017-05-16 | 2017-09-05 | 廊坊市新思维科技有限公司 | Non-destructive Testing Data auditing system |
CN109711114A (en) * | 2019-03-13 | 2019-05-03 | 江苏柯瑞机电工程股份有限公司 | Pipeline construction and management system based on BIM |
CN112485377A (en) * | 2020-11-24 | 2021-03-12 | 南京睿控自动化有限公司 | Intelligent boiler based on BIM structure combines data model |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20230065286A1 (en) | Cloud-enabled generation of construction metrics and documentation | |
Ding et al. | A digital construction framework integrating building information modeling and reverse engineering technologies for renovation projects | |
Abanda et al. | BIM in off-site manufacturing for buildings | |
CN108875273B (en) | BIM-based foundation pit engineering forward design and operation and maintenance management system | |
CN109064133A (en) | A kind of engineering whole process management system based on BIM+AR | |
CN106595565A (en) | BIM-based intelligent monitoring system | |
CN105844380A (en) | BIM-based BIM project element management method and system | |
CN106203969A (en) | A kind of prison check system of steel-making boiler tubing based on BIM | |
Jiang et al. | Automated rule-based constructability checking: Case study of formwork | |
Nguyen et al. | Building code compliance checking using BIM technology | |
Kim et al. | Interactive modeler for construction equipment operation using augmented reality | |
CN107330970A (en) | A kind of threedimensional model processing method, server and computer read/write memory medium | |
CN107451737A (en) | A kind of big data O2O check of drawings cloud platform management systems examined for engineering construction figure | |
KR102085271B1 (en) | Vitual Construction Simulation Method | |
Ahmed et al. | A brief discussion on augmented reality and virtual reality in construction industry | |
CN110704904B (en) | Multi-software collaborative three-dimensional planning method for transformer substation | |
CN112232683A (en) | Comprehensive pipe gallery full-period construction management system based on BIM | |
CN110990927A (en) | BIM-based whole process consultation method | |
Ogwueleka et al. | The future of BIM technologies in Africa: prospects and challenges | |
CN104951350A (en) | Aerospace product general assembly technology simulation analysis method | |
CN110181519A (en) | Subway station door fault detection method and system based on the twin robot of number | |
CN106383832A (en) | Data excavation training model forming method | |
Baker et al. | Benchmarking FEMA P-58 performance predictions against observed earthquake data–a preliminary evaluation for the Canterbury earthquake sequence | |
US20150317415A1 (en) | System and method for engineering and detailing steel joints in a steel structure | |
CN111126691A (en) | Project management method and related product |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161207 |