CN106193288A - A kind of precast concrete node pouring ECC layer - Google Patents

A kind of precast concrete node pouring ECC layer Download PDF

Info

Publication number
CN106193288A
CN106193288A CN201610549820.5A CN201610549820A CN106193288A CN 106193288 A CN106193288 A CN 106193288A CN 201610549820 A CN201610549820 A CN 201610549820A CN 106193288 A CN106193288 A CN 106193288A
Authority
CN
China
Prior art keywords
layer
prefabricated
steel plate
ecc
pouring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610549820.5A
Other languages
Chinese (zh)
Other versions
CN106193288B (en
Inventor
张军
陈耀钢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU ZHONGNAN CONSTRUCTION INDUSTRY GROUP CO LTD
Nantong University
Original Assignee
Jiangsu Zhongnan Construction Industry Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Zhongnan Construction Industry Group Co Ltd filed Critical Jiangsu Zhongnan Construction Industry Group Co Ltd
Priority to CN201610549820.5A priority Critical patent/CN106193288B/en
Publication of CN106193288A publication Critical patent/CN106193288A/en
Application granted granted Critical
Publication of CN106193288B publication Critical patent/CN106193288B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • E04B1/215Connections specially adapted therefor comprising metallic plates or parts
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

本发明公开了一种浇筑ECC层的预制混凝土节点,包括方钢管、预制梁、预制柱;预制梁和预制柱为若干箍筋同轴且相互平行的设置在钢筋骨架的外圈,方钢管同轴纵向内置于预制柱,方钢管的两侧纵向端面上分别设有钢板1,钢板1的横向端连接内置于预制梁的钢板2,钢板1和钢板2连接后处于同一纵向面,方钢管外侧面与预制柱之间、钢板2之间、钢板1之间组成的区域构成主浇筑区域,主浇筑区域内浇筑工程水泥基复合材料ECC层。本发明的一种浇筑ECC层的预制混凝土节点具有施工速度快、节点连接方便、强度高、质量控制更有保障等优点,且更具有安全性、适用性、耐久性以及经济性。

The invention discloses a prefabricated concrete node for pouring an ECC layer, comprising square steel pipes, prefabricated beams, and prefabricated columns; the prefabricated beams and prefabricated columns are coaxial and parallel to each other and arranged on the outer ring of the steel skeleton, and the square steel pipes are The shaft is built into the prefabricated column longitudinally, and steel plates 1 are respectively arranged on the longitudinal end faces of both sides of the square steel pipe. The area formed between the sides and the prefabricated columns, between the steel plates 2, and between the steel plates 1 constitutes the main pouring area, and the engineering cement-based composite material ECC layer is poured in the main pouring area. The prefabricated concrete node for pouring the ECC layer of the present invention has the advantages of fast construction speed, convenient node connection, high strength, more guaranteed quality control, etc., and has more safety, applicability, durability and economy.

Description

一种浇筑ECC层的预制混凝土节点A kind of prefabricated concrete node for pouring ECC layer

技术领域technical field

本发明涉及一种混凝土节点,具体涉及一种浇筑ECC层的预制混凝土节点。The invention relates to a concrete node, in particular to a prefabricated concrete node for pouring an ECC layer.

背景技术Background technique

目前,矩形钢管混凝土组合结构已普遍应用于建筑工程,矩形钢管混凝土组合结构技术近几年已得到长足发展,矩形钢管混凝土组合结构因其承载力高,延展性好等优点在工程中大量应用,随着超高层及大跨度建筑结构的不断出现,矩形钢管混凝土连接点成为了建筑结构设计中的重要内容之一,连接节点直接影响了结构承载条件下的整体性能以及与其相连结构的承重性能,因此连接节点结构的性能是不容忽视的。At present, rectangular concrete-filled steel tube composite structures have been widely used in construction projects. The technology of rectangular steel-filled concrete-filled composite structures has been greatly developed in recent years. Rectangular steel-filled concrete-filled composite structures have been widely used in engineering because of their high bearing capacity and good ductility. With the continuous emergence of super high-rise and long-span building structures, rectangular concrete-filled steel tube connection points have become one of the important contents in the design of building structures. The connection points directly affect the overall performance of the structure under load-bearing conditions and the load-bearing performance of the connected structures. Therefore, the performance of the connected node structure cannot be ignored.

目前在我国,对于工程水泥基复合材料ECC(Engineered CementitiousComposites)的研究和应用还较少,实际工程用的最多的依旧是普通混凝土。At present in our country, the research and application of engineering cement-based composite materials ECC (Engineered Cementitious Composites) is still less, and the most used in actual engineering is still ordinary concrete.

发明内容Contents of the invention

为解决现有技术的不足,本发明的目的在于提供一种具有更高安全性、适用性、耐久性以及经济性的预制混凝土节点。In order to solve the deficiencies of the prior art, the purpose of the present invention is to provide a prefabricated concrete node with higher safety, applicability, durability and economy.

为了实现上述目标,本发明采用如下的技术方案:In order to achieve the above object, the present invention adopts the following technical solutions:

一种浇筑ECC层的预制混凝土节点,包括方钢管、预制梁、预制柱;所述预制梁和预制柱为若干箍筋同轴且相互平行的设置在钢筋骨架的外圈,所述方钢管同轴纵向内置于预制柱,所述方钢管的两侧纵向端面上分别设有钢板1,所述钢板1的横向端连接内置于预制梁的钢板2,所述钢板1和钢板2连接后处于同一纵向面,所述方钢管外侧面与预制柱之间、钢板2之间、钢板1之间组成的区域构成主浇筑区域,所述主浇筑区域内浇筑工程水泥基复合材料ECC层。A prefabricated concrete node for pouring an ECC layer, comprising square steel pipes, prefabricated beams, and prefabricated columns; the prefabricated beams and prefabricated columns are coaxial and parallel to each other and arranged on the outer ring of the steel skeleton, and the square steel pipes are The shaft is built into the prefabricated column longitudinally, and steel plates 1 are respectively arranged on the longitudinal end faces of both sides of the square steel pipe. The transverse ends of the steel plates 1 are connected to the steel plates 2 built in the prefabricated beams. In the longitudinal plane, the area formed between the outer side of the square steel pipe and the prefabricated columns, between the steel plates 2 and between the steel plates 1 constitutes the main pouring area, and the engineering cement-based composite material ECC layer is poured in the main pouring area.

方钢管设置在预制柱节点中,连接钢板1与钢板2,增强了节点的整体性能与强度。The square steel pipe is set in the prefabricated column node, connecting the steel plate 1 and the steel plate 2, which enhances the overall performance and strength of the node.

钢板1和钢板2用于预制柱节点和预制梁节点连接,承受拉/压应力。Steel plate 1 and steel plate 2 are used for connection of prefabricated column joints and prefabricated beam joints, and bear tension/compression stress.

上述方钢管的外圈设有横向钢筋骨架。The outer ring of the above-mentioned square steel pipe is provided with a transverse reinforcement skeleton.

钢筋骨架构成结构实体,加强预制梁和预制柱的整体强度;箍筋增加斜截面的抗剪应力,并连接联结受力主筋共同作用。The reinforced skeleton constitutes a structural entity and strengthens the overall strength of prefabricated beams and prefabricated columns; stirrups increase the shear stress of oblique sections, and connect and connect the main reinforcements to act together.

上述钢板2与预制梁的两内侧纵向面固定连接。The above-mentioned steel plate 2 is fixedly connected with the two inner longitudinal surfaces of the prefabricated beam.

上述方钢管内浇筑混凝土层。A concrete layer is poured in the square steel pipe.

上述预制梁内后浇筑混凝土层或工程水泥基复合材料ECC层。The post-casting concrete layer or the engineering cement-based composite material ECC layer in the above-mentioned prefabricated beam.

上述预制柱内后浇筑混凝土层或工程水泥基复合材料ECC层。The post-casting concrete layer or engineering cement-based composite material ECC layer in the above-mentioned prefabricated column.

上述钢板1和钢板2通过螺栓连接。The above-mentioned steel plate 1 and steel plate 2 are connected by bolts.

通过螺栓使钢板1与钢板2紧密结合,通过摩擦面将钢板2上的力传递到钢板1,即将预制梁上的力传递到预制柱上。螺栓连接强化钢板之间的连接强度,且在预制梁受到损伤后,方便维修或更换预制梁,而不涉及预制柱,维护整体的安全性。The steel plate 1 and the steel plate 2 are tightly combined by bolts, and the force on the steel plate 2 is transmitted to the steel plate 1 through the friction surface, that is, the force on the prefabricated beam is transmitted to the prefabricated column. The bolt connection strengthens the connection strength between the steel plates, and after the prefabricated beam is damaged, it is convenient to repair or replace the prefabricated beam without involving the prefabricated column, maintaining the overall safety.

本发明的有益之处在于:本发明的一种浇筑ECC层的预制混凝土节点的梁柱采用内置钢结构,利用高强螺栓连接内置钢板,相对传统连接方式,具有施工速度快、节点连接方便、强度高、质量控制更有保障等优点,且更具有安全性、适用性、耐久性以及经济性。The benefit of the present invention is that: the beam column of the prefabricated concrete node of the pouring ECC layer adopts a built-in steel structure, and the built-in steel plate is connected by high-strength bolts. Compared with the traditional connection method, it has the advantages of fast construction speed, convenient node connection, and high strength High quality, more secure quality control and other advantages, and more safety, applicability, durability and economy.

通过结构的改进,在循环荷载作用下,预制混凝土节点的最终破坏处从节点的核心区域,转向预制梁中钢板末端以及螺栓连接部位,破坏位置得到外移,符合“强柱弱梁”的原则。Through the improvement of the structure, under the action of cyclic load, the final damage point of the precast concrete joint is shifted from the core area of the joint to the end of the steel plate in the precast beam and the bolt connection part, and the damage position is moved outward, which is in line with the principle of "strong column and weak beam". .

预制混凝土节点在提高承载力的同时,保持了较好的延性,并且在节点主浇筑区域采用工程水泥基复合材料ECC进行浇筑,同时预埋了方钢管,对节点区域进行了加强,提高了节点的耗能性,符合“强节点、弱构件”的设计原则。The prefabricated concrete joint maintains good ductility while improving the bearing capacity, and the engineering cement-based composite material ECC is used for pouring in the main pouring area of the joint, and square steel pipes are pre-buried to strengthen the joint area and improve the joint strength. The energy consumption is in line with the design principle of "strong nodes, weak components".

工程水泥基复合材料ECC的使用,提高了节点的抗震性能和耐损伤能力,进而减小了震后用来修复节点的费用,并且ECC的配置,可利用工业废料粉煤灰代替约50%的水泥孰料,实现废物再循环利用,成本更低。The use of engineering cement-based composite material ECC improves the seismic performance and damage resistance of the joints, thereby reducing the cost of repairing joints after the earthquake, and the configuration of ECC can use industrial waste fly ash to replace about 50% of the joints. Cement clinker realizes waste recycling with lower cost.

此外,ECC很好的密实性,有效阻止有害物质向构件材料内部的渗透,提高了构件的耐久性,延长了结构的使用年限,In addition, the good compactness of ECC effectively prevents the penetration of harmful substances into the interior of the component material, improves the durability of the component, and prolongs the service life of the structure.

附图说明Description of drawings

图1为本发明的一种浇筑ECC层的预制混凝土节点的结构示意图的侧视图。Fig. 1 is a side view of a schematic structural diagram of a prefabricated concrete node for pouring an ECC layer according to the present invention.

图2为本发明的一种浇筑ECC层的预制混凝土节点的结构示意图的俯视图。Fig. 2 is a top view of a structural schematic diagram of a prefabricated concrete node for pouring an ECC layer according to the present invention.

图3为本发明的一种浇筑ECC层的预制混凝土节点的结构示意图的透视图。Fig. 3 is a perspective view of a structural schematic diagram of a prefabricated concrete node for pouring an ECC layer according to the present invention.

图4为本发明的一种浇筑ECC层的预制混凝土节点的结构示意图的外观图。Fig. 4 is an appearance diagram of a structural schematic diagram of a prefabricated concrete node for pouring an ECC layer according to the present invention.

图5为有限元软件ABAQUS模拟现浇混凝土节点的滞回曲线。Figure 5 is the hysteretic curve of the cast-in-place concrete joint simulated by the finite element software ABAQUS.

图6为有限元软件ABAQUS模拟预制混凝土节点的滞回曲线。Figure 6 is the hysteretic curve of the precast concrete joint simulated by the finite element software ABAQUS.

图7为有限元软件ABAQUS模拟预制混凝土节点主浇筑区域内浇筑ECC层和浇筑混凝土C60层的荷载-位移骨架曲线。Fig. 7 is the load-displacement skeleton curve of the poured ECC layer and the poured concrete C60 layer in the main pouring area of the precast concrete joint simulated by the finite element software ABAQUS.

附图中标记的含义如下:1、方钢管,2、预制柱,3、预制梁,4、钢板1,5、钢板2,6、箍筋,7、钢筋骨架。The meanings of the marks in the attached drawings are as follows: 1. square steel pipe, 2. prefabricated column, 3. prefabricated beam, 4. steel plate 1, 5, steel plate 2, 6. stirrup, 7. steel skeleton.

具体实施方式detailed description

以下结合附图和具体实施例对本发明作具体的介绍。The present invention will be specifically introduced below in conjunction with the accompanying drawings and specific embodiments.

一种预制混凝土节点,包括方1钢管、3预制梁、2预制柱;3预制梁和2预制柱为若干6箍筋同轴且相互平行的设置在7钢筋骨架的外圈,1方钢管同轴纵向内置于2预制柱,1方钢管的两侧纵向端面上分别设有4钢板1,4钢板1的横向端通过螺栓连接内置于预制梁3的5钢板2,4钢板1和5钢板2连接后处于同一纵向面,所述1方钢管外侧面与2预制柱之间、5钢板2之间、4钢板1之间组成的区域构成主浇筑区域,所述主浇筑区域内浇筑工程水泥基复合材料ECC层。A prefabricated concrete node, including square 1 steel pipe, 3 prefabricated beams, 2 prefabricated columns; 3 prefabricated beams and 2 prefabricated columns are a number of 6 stirrups coaxial and parallel to each other and arranged on the outer ring of 7 steel bar skeletons, 1 square steel pipe with The shaft is built in 2 prefabricated columns longitudinally, and 4 steel plates 1 are respectively arranged on the longitudinal end faces of both sides of 1 square steel pipe, and the transverse ends of 4 steel plates 1 are connected by bolts to 5 steel plates 2 built in prefabricated beam 3, 4 steel plates 1 and 5 steel plates 2 After being connected on the same longitudinal plane, the area composed of the outer side of the 1 square steel pipe and the 2 prefabricated columns, the 5 steel plates 2, and the 4 steel plates 1 constitutes the main pouring area, and the engineering cement base is poured in the main pouring area. Composite ECC layer.

1方钢管的外圈设有横向7钢筋骨架。The outer ring of the 1-square steel pipe is provided with a horizontal 7-bar skeleton.

5钢板2与3预制梁的两内侧纵向面固定连接。5. The two inner longitudinal surfaces of the steel plate 2 and 3. the prefabricated beam are fixedly connected.

1方钢管内浇筑混凝土层。Concrete layer is poured in 1 square steel pipe.

3预制梁和2预制柱内后浇筑混凝土层或工程水泥基复合材料ECC层。3 prefabricated beams and 2 prefabricated columns post-cast concrete layer or engineered cement-based composite material ECC layer.

现浇混凝土节点在循环荷载作用下,最终破坏处为节点核心区域,而预制混凝土节点的破坏则集中在3预制梁中钢板末端以及螺栓连接部位,与现浇混凝土节点相比,破坏位置得到外移,符合“强柱弱梁”的原则。Under the action of cyclic load, the final failure of the cast-in-place concrete joint is the core area of the joint, while the damage of the precast concrete joint is concentrated at the end of the steel plate and the bolt connection part of the 3 prefabricated beams. It is in line with the principle of "strong columns and weak beams".

图5和图6为分别为通过有限元软件ABAQUS模拟现浇混凝土节点、预制混凝土节点的滞回曲线,从图5和图6可见,与现浇混凝土节点相比,预制节点的承载力提高了28.22%,等效阻尼系数提高了58.86%,并且两者位移延性系数平均值均大于3,符合钢筋混凝土结构位移延性系数大于2.57的要求。Figure 5 and Figure 6 are the hysteretic curves of the cast-in-place concrete joints and precast concrete joints simulated by the finite element software ABAQUS respectively. 28.22%, the equivalent damping coefficient increased by 58.86%, and the average value of the displacement ductility coefficients of the two is greater than 3, which meets the requirements of the reinforced concrete structure displacement ductility coefficient greater than 2.57.

说明预制混凝土节点在提高承载力的同时,保持了较好的延性,并且在节点后浇区采用工程水泥基复合材料ECC进行浇筑,同时预埋了方钢管1,对节点区域进行了加强,提高了节点的耗能性,符合“强节点、弱构件”的设计原则。It shows that the precast concrete joints maintain good ductility while improving the bearing capacity, and the engineering cement-based composite material ECC is used for pouring in the post-casting area of the joints, and the square steel pipe 1 is pre-buried to strengthen the joint area and improve The energy consumption of the nodes is guaranteed, which is in line with the design principle of "strong nodes, weak components".

通过有限元软件ABAQUS模拟预制混凝土节点主浇筑区域内浇筑混凝土C60层、浇筑ECC层的受拉损伤因子,主浇筑区域内浇筑ECC层和浇筑混凝土C60层的预制混凝土节点破坏模式相近,损伤均主要集中在螺栓连接位置、浇筑面以及梁中钢板末端,当浇筑材料为混凝土C60时,节点损伤程度明显要比浇筑工程水泥基复合材料ECC的节点损伤严重。The tensile damage factors of the poured concrete C60 layer and the poured ECC layer in the main pouring area of the precast concrete joints were simulated by the finite element software ABAQUS, and the failure modes of the precast concrete joints of the poured ECC layer and the poured concrete C60 layer in the main pouring area were similar, and the damages were both major Concentrated on the bolt connection position, the pouring surface and the end of the steel plate in the beam. When the pouring material is concrete C60, the damage degree of the joints is obviously more serious than that of the cement-based composite material ECC in the pouring project.

图7为有限元软件ABAQUS模拟预制混凝土节点主浇筑区域内浇筑ECC层和浇筑混凝土C60层的荷载-位移骨架曲线。Fig. 7 is the load-displacement skeleton curve of the poured ECC layer and the poured concrete C60 layer in the main pouring area of the precast concrete joint simulated by the finite element software ABAQUS.

表1为主浇筑区域内浇材ECC层和混凝土C60层的节点特征量对比:Table 1 Comparison of node feature quantities between pouring material ECC layer and concrete C60 layer in the main pouring area:

Characteristic values of specimen with different late-pouringmaterialCharacteristic values of specimen with different late-pouringmaterial

表1Table 1

从图7可见,浇筑混凝土C60的节点骨架曲线的初始刚度要比浇筑ECC的节点稍大,这是因为工程水泥基复合材料ECC的基体中并不包含粗骨料,同时为了保证能够充分发挥材料的受拉应变-硬化效应,其基体中砂子的粒径和含量也受到了限制,这在一定程度上降低了ECC的刚度,此外,由于掺入了PVA纤维,使基体的孔隙率增大,匀质性降低,这也造成了ECC的弹性模量要比普通混凝土低,因而ECC节点骨架曲线的初始刚度要比混凝土C60节点低。It can be seen from Fig. 7 that the initial stiffness of the joint skeleton curve of poured concrete C60 is slightly larger than that of poured ECC joints. This is because the matrix of engineering cement-based composite ECC does not contain coarse Due to the tensile strain-hardening effect, the particle size and content of the sand in the matrix are also limited, which reduces the stiffness of the ECC to a certain extent. In addition, due to the incorporation of PVA fibers, the porosity of the matrix increases. The homogeneity is reduced, which also causes the elastic modulus of ECC to be lower than that of ordinary concrete, so the initial stiffness of the skeleton curve of ECC joints is lower than that of concrete C60 joints.

此外,对比ECC节点与混凝土C60节点的骨架曲线可知,虽然两种节点所能承担的最大荷载相差不大,但是变形能力有着明显的差异,表1列出了两种浇筑材料下节点的主要特征量,从中可以看出ECC节点的屈服位移和极限位移均比混凝土C60节点大,其平均位移延性系数同混凝土C60节点相比,提高了8.16%,并且在达到峰值荷载后,ECC节点骨架曲线下降更缓慢,这是由于当节点曲线进入下降段后,随着裂缝不断扩展,ECC中的PVA纤维发挥的阻裂作用开始明显,造成荷载曲线下降缓慢,其峰值应变明显大于普通混凝土,其中高强度的ECC极限拉应变可达3%左右,这表明PVA纤维能够明显提高ECC基体的塑性变形能力,并且由于塑形变形能力的增加,节点的耗能性能也相应的有所提高,由表1可知,同混凝土C60节点相比,ECC节点的等效阻尼系数提高了21.26%。In addition, comparing the skeleton curves of ECC joints and concrete C60 joints, it can be seen that although the maximum load that the two joints can bear is not much different, there is a significant difference in deformation capacity. Table 1 lists the main characteristics of the joints under the two pouring materials It can be seen that the yield displacement and ultimate displacement of ECC joints are larger than that of concrete C60 joints, and its average displacement ductility coefficient is 8.16% higher than that of concrete C60 joints, and after reaching the peak load, the skeleton curve of ECC joints decreases Slower, this is because when the node curve enters the descending section, as the cracks continue to expand, the crack resistance effect of the PVA fiber in ECC begins to be obvious, causing the load curve to decline slowly, and its peak strain is significantly greater than that of ordinary concrete. Among them, the high-strength The ultimate tensile strain of the ECC can reach about 3%, which shows that PVA fiber can significantly improve the plastic deformation capacity of the ECC matrix, and due to the increase in the plastic deformation capacity, the energy dissipation performance of the nodes is also improved accordingly, as can be seen from Table 1 , compared with concrete C60 joints, the equivalent damping coefficient of ECC joints increased by 21.26%.

因此,当预制混凝土节点的主浇筑区域采用工程水泥基复合材料ECC时,节点的抗震性能和耐损伤能力均有所提高,进而减小了震后用来修复节点的费用,并且配置ECC时,可利用工业废料粉煤灰代替约50%的水泥孰料,实现废物再循环利用,此外,ECC的密实性很好,在正常使用条件下,构件表面能够长期不开裂,有效阻止了有害物质向构件材料内部的渗透,提高了构件的耐久性,继而延长了结构的使用年限。Therefore, when the main pouring area of precast concrete joints adopts engineering cement-based composite material ECC, the seismic performance and damage resistance of the joints are improved, thereby reducing the cost of repairing joints after the earthquake, and when ECC is configured, Industrial waste fly ash can be used to replace about 50% of cement clinker to realize waste recycling. In addition, the compactness of ECC is very good. Under normal use conditions, the surface of components can not crack for a long time, effectively preventing harmful substances from flowing into Penetration inside the component material improves the durability of the component, which in turn prolongs the service life of the structure.

综合社会、经济、环境三要素进行考虑,采用ECC材料比采用普通混凝土约有37%的成本优势,因而对于本发明中的节点形式,采用ECC作为主浇筑区域的浇筑材料符合安全性、适用性、耐久性以及经济性的结构设计功能要求。Considering the three elements of society, economy and environment, the use of ECC materials has a cost advantage of about 37% compared with ordinary concrete. Therefore, for the node form in the present invention, the use of ECC as the pouring material in the main pouring area is in line with safety and applicability , durability and economical structural design functional requirements.

以上显示和描述了本发明的基本原理、主要特征和优点。本行业的技术人员应该了解,上述实施例不以任何形式限制本发明,凡采用等同替换或等效变换的方式所获得的技术方案,均落在本发明的保护范围内。The basic principles, main features and advantages of the present invention have been shown and described above. Those skilled in the industry should understand that the above-mentioned embodiments do not limit the present invention in any form, and all technical solutions obtained by means of equivalent replacement or equivalent transformation fall within the protection scope of the present invention.

Claims (7)

1. the precast concrete node pouring ECC layer, it is characterised in that include square steel tube, precast beam, prefabricated post;Described Precast beam and prefabricated post are the outer ring being arranged on framework of steel reinforcement that some stirrups are coaxial and are parallel to each other, and described square steel tube is coaxially indulged To being built in prefabricated post, the both sides longitudinal terminal surface of described square steel tube being respectively equipped with steel plate 1, the transverse end of described steel plate 1 connects Being built in after the steel plate 2 of precast beam, described steel plate 1 and steel plate 2 connect and be in same longitudinal surface, described square steel tube lateral surface is with pre- Between post processed, between steel plate 2, between steel plate 1, the region of composition constitutes main casting area, pours engineering in described main casting area Cement-base composite material ECC layer.
A kind of precast concrete node pouring ECC layer the most according to claim 1, it is characterised in that described square steel tube Outer ring be provided with transverse steel skeleton.
A kind of precast concrete node pouring ECC layer the most according to claim 1, it is characterised in that described steel plate 2 with Inside the two of precast beam, longitudinal surface is fixing connects.
A kind of precast concrete node pouring ECC layer the most according to claim 1, it is characterised in that described square steel tube Interior casting concrete layer.
A kind of precast concrete node pouring ECC layer the most according to claim 1, it is characterised in that described precast beam Interior after-pouring concrete layer or engineered cementitious based composites ECC layer.
A kind of precast concrete node pouring ECC layer the most according to claim 1, it is characterised in that described prefabricated post Interior after-pouring concrete layer or engineered cementitious based composites ECC layer.
A kind of precast concrete node pouring ECC layer the most according to claim 1, it is characterised in that described steel plate 1 He Steel plate 2 is bolted.
CN201610549820.5A 2016-07-13 2016-07-13 A kind of precast concrete node pouring ECC layers Expired - Fee Related CN106193288B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610549820.5A CN106193288B (en) 2016-07-13 2016-07-13 A kind of precast concrete node pouring ECC layers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610549820.5A CN106193288B (en) 2016-07-13 2016-07-13 A kind of precast concrete node pouring ECC layers

Publications (2)

Publication Number Publication Date
CN106193288A true CN106193288A (en) 2016-12-07
CN106193288B CN106193288B (en) 2019-08-16

Family

ID=57478089

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610549820.5A Expired - Fee Related CN106193288B (en) 2016-07-13 2016-07-13 A kind of precast concrete node pouring ECC layers

Country Status (1)

Country Link
CN (1) CN106193288B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605103A (en) * 2017-10-08 2018-01-19 华东交通大学 A composite reinforced ECC/concrete composite column with FRP bar-steel bars
CN109853727A (en) * 2018-12-29 2019-06-07 华南理工大学 Recoverable function steel bar concrete frame energy dissipation node

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2758208B2 (en) * 1989-05-31 1998-05-28 大成建設株式会社 Joint method between column and steel reinforced concrete beam
CN201605670U (en) * 2010-03-12 2010-10-13 张剑 Rigid connection node of concrete-filled tubular column and reinforced concrete beam
CN103774754A (en) * 2014-01-07 2014-05-07 同济大学 Prefabricated ECC-RC combination beam column joint component
CN103953124A (en) * 2014-05-15 2014-07-30 苏州工业园区设计研究院股份有限公司 Section-steel concrete beam and ordinary concrete column nodal region structure
KR101451167B1 (en) * 2013-07-26 2014-10-15 한국교통대학교산학협력단 Hollowed Precast reinforced concrete Assembly And Connecting Method Thereof
CN104499568A (en) * 2014-12-19 2015-04-08 东南大学 Square steel pipe fabricated column-prefabricated superposed beam integrally-fabricated frame and construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2758208B2 (en) * 1989-05-31 1998-05-28 大成建設株式会社 Joint method between column and steel reinforced concrete beam
CN201605670U (en) * 2010-03-12 2010-10-13 张剑 Rigid connection node of concrete-filled tubular column and reinforced concrete beam
KR101451167B1 (en) * 2013-07-26 2014-10-15 한국교통대학교산학협력단 Hollowed Precast reinforced concrete Assembly And Connecting Method Thereof
CN103774754A (en) * 2014-01-07 2014-05-07 同济大学 Prefabricated ECC-RC combination beam column joint component
CN103953124A (en) * 2014-05-15 2014-07-30 苏州工业园区设计研究院股份有限公司 Section-steel concrete beam and ordinary concrete column nodal region structure
CN104499568A (en) * 2014-12-19 2015-04-08 东南大学 Square steel pipe fabricated column-prefabricated superposed beam integrally-fabricated frame and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605103A (en) * 2017-10-08 2018-01-19 华东交通大学 A composite reinforced ECC/concrete composite column with FRP bar-steel bars
CN109853727A (en) * 2018-12-29 2019-06-07 华南理工大学 Recoverable function steel bar concrete frame energy dissipation node

Also Published As

Publication number Publication date
CN106193288B (en) 2019-08-16

Similar Documents

Publication Publication Date Title
CN202017302U (en) Engineering fiber reinforced cementitious composites (ECC) connecting beam
CN102912895B (en) High-ductility coupled shear wall
Jain et al. Emergency repair of severely damaged reinforced concrete column elements under axial compression: An experimental study
CN103774754A (en) Prefabricated ECC-RC combination beam column joint component
Lin et al. Experimental study on interior precast concrete beam-column connections with UHPC core shells
CN105464288A (en) Composite bar-reinforced ECC and concrete composite beam and construction method thereof
CN103774755A (en) Prestressed prefabricated ECC-RC combination beam column joint component
CN206707122U (en) A kind of concrete filled steel tube component of the steel tube confinement of sandwich
CN205063178U (en) Engineered cementitious composites combination beam component
CN110005129A (en) FRP reinforced fiber high-strength light-weight aggregate concrete beam member and manufacturing method
CN107217788A (en) Full FRP muscle enhancing ECC Combined concrete beams and preparation method thereof
CN103306426B (en) Repair type span centre bolt connects high ductility beam
CN102936940A (en) Enhanced ultra-high-performance concrete component made of mixed fiber reinforced plastic (FRP) bars
CN107605103A (en) A composite reinforced ECC/concrete composite column with FRP bar-steel bars
CN202596028U (en) Carbon fiber pres-stressed reinforcing steel and high strength steel bar ultra-high toughness fiber reinforced cement-based composite beam structure
CN201972287U (en) Ultrathin bottom plate with superhigh strength for lamination board
CN106917470A (en) The steel tube confinement concrete-filled rectangular steel tube component and its processing method of a kind of sandwich
CN110029777A (en) A kind of prestressed FRP rebar fiber high-strength light aggregate concrete beam and preparation method thereof
CN103061450B (en) High-strength reinforcing steel bar self-compaction steel fiber ultrahigh-strength concrete transfer girder
CN206888351U (en) A kind of new-type FRP rebar and reinforcing bar hybrid reinforcement ECC concrete composite beams
CN106193288B (en) A kind of precast concrete node pouring ECC layers
CN102587576B (en) Combined precast column with nodes
CN107842107A (en) A kind of part uses the profile steel concrete column steel beam joint of fibre reinforced concrete
CN207332114U (en) A kind of steel tube confinement concrete-filled rectangular steel tube component of sandwich
CN215405593U (en) Profiled steel sheet high-toughness combined bridge floor

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20190625

Address after: Jiangsu province Nantong City sik Road No. 9

Applicant after: NANTONG University

Applicant after: JIANGSU ZHONGNAN CONSTRUCTION INDUSTRY GROUP Co.,Ltd.

Address before: 226124 north of Changle Town, Haimen, Nantong, Jiangsu

Applicant before: JIANGSU ZHONGNAN CONSTRUCTION INDUSTRY GROUP Co.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190816

CF01 Termination of patent right due to non-payment of annual fee