CN106152228A - 一种新型发电厂热利用系统 - Google Patents
一种新型发电厂热利用系统 Download PDFInfo
- Publication number
- CN106152228A CN106152228A CN201510106160.9A CN201510106160A CN106152228A CN 106152228 A CN106152228 A CN 106152228A CN 201510106160 A CN201510106160 A CN 201510106160A CN 106152228 A CN106152228 A CN 106152228A
- Authority
- CN
- China
- Prior art keywords
- water tank
- pipeline
- cooling tower
- power plant
- heat
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Thermotherapy And Cooling Therapy Devices (AREA)
Abstract
本发明公开了一种新型发电厂热利用系统,包括冷却塔、凝汽器、余热收集器、水箱、居民用暖、游泳馆、宾馆、热泵机组和循环水池;所述余热收集器安装在冷却塔上顶端,冷凝器设置在连接冷却塔和循环水池的管路上;所述热泵机组设置在连接冷却塔和水箱以及连接循环水池和水箱上的管路上;所述居民用暖通过管路连接与水箱接通的管路;所述游泳馆和宾馆连接与水箱连接的管道;该发电厂热利用系统,在冷却塔上设置有郁热收集器,冷却塔上残留的热量经过暖炉传输给水箱进行加热,热水经过管道进而被居民用暖以及游泳馆以及宾馆使用;由于设置有循环水池,冷却塔上的水将会被发电厂发电使用,提高了水源利用率,整体可以达到热量的充分利用。
Description
技术领域
本发明涉及发电厂热利用技术领域,尤其是一种新型发电厂热利用系统。
背景技术
火力发电厂的热利用是一直困扰人们的问题,如何使得电厂的热利用效率最高,一方面可以节省较多的能源资源;另一方面也间接的起到节能减排的作用;目前的诸多发电厂尤其是火力发电厂,一般不能做到热量的充分利用,进而造成能源的浪费。
发明内容
现有技术不能满足人们的需要,为弥补现有技术不足,本发明旨在提供一种新型发电厂热利用系统。
为实现上述目的,本发明采用以下技术方案:一种新型发电厂热利用系统,包括冷却塔、凝汽器、余热收集器、水箱、居民用暖、游泳馆、宾馆、热泵机组和循环水池;所述余热收集器安装在冷却塔上顶端,冷凝器设置在连接冷却塔和循环水池的管路上;所述热泵机组设置在连接冷却塔和水箱以及连接循环水池和水箱上的管路上;所述居民用暖通过管路连接与水箱接通的管路;所述游泳馆和宾馆连接与水箱连接的管道。
作为本发明的进一步技术方案:所述余热收集器还通过设置有安全阀的管路连接水箱。
作为本发明的进一步技术方案:所述连接热泵机组和水箱的管路上连接有设置有阀门的用水管路。
与现有技术相比,本发明的有益效果是:该发电厂热利用系统,在冷却塔上设置有郁热收集器,冷却塔上残留的热量经过暖炉传输给水箱进行加热,热水经过管道进而被居民用暖以及游泳馆以及宾馆使用;由于设置有循环水池,冷却塔上的水将会被发电厂发电使用,提高了水源利用率,整体可以达到热量的充分利用,结构简单,实用性强,易于推广使用。
附图说明
图1为本发明的整体结构示意图;
其中:冷却塔1;凝汽器2;余热收集器3;水箱4;居民用暖5;游泳馆6;宾馆7;热泵机组8;循环水池9。
具体实施方式
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。
请参阅图1,本发明实施例中:一种新型发电厂热利用系统,包括冷却塔1、凝汽器2、余热收集器3、水箱4、居民用暖5、游泳馆6、宾馆7、热泵机组8和循环水池9;所述余热收集器3安装在冷却塔1上顶端,冷凝器2设置在连接冷却塔1和循环水池9的管路上;所述热泵机组8设置在连接冷却塔1和水箱4以及连接循环水池9和水箱4上的管路上;所述居民用暖5通过管路连接与水箱4接通的管路;所述游泳馆6和宾馆7连接与水箱4连接的管道。
作为本发明的进一步技术方案:所述余热收集器3还通过设置有安全阀的管路连接水箱4;所述连接热泵机组8和水箱4的管路上连接有设置有阀门的用水管路。
对于本领域技术人员而言,显然本发明不限于上述示范性实施例的细节,而且在不背离本发明的精神或基本特征的情况下,能够以其它的具体形式实现本发明。因此,无论从哪一点来看,均应将实施例看作是示范性的,而且是非限制性的,本发明的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在本发明内。不应将权利要求中的任何附图标记视为限制所涉及的权利要求。
以上所述,仅为本发明的较佳实施例,并不用以限制本发明,凡是依据本发明的技术实质对以上实施例所作的任何细微修改、等同替换和改进,均应包含在本发明技术方案的保护范围之内。
Claims (3)
1.一种新型发电厂热利用系统,包括冷却塔(1)、凝汽器(2)、余热收集器(3)、水箱(4)、居民用暖(5)、游泳馆(6)、宾馆(7)、热泵机组(8)和循环水池(9);其特征在于:所述余热收集器(3)安装在冷却塔(1)上顶端,冷凝器(2)设置在连接冷却塔(1)和循环水池(9)的管路上;所述热泵机组(8)设置在连接冷却塔(1)和水箱(4)以及连接循环水池(9)和水箱(4)上的管路上;所述居民用暖(5)通过管路连接与水箱(4)接通的管路;所述游泳馆(6)和宾馆(7)连接与水箱(4)连接的管道。
2.根据权利要求1所述的一种新型发电厂热利用系统,特征在于:所述余热收集器(3)还通过设置有安全阀的管路连接水箱(4)。
3.根据权利要求1所述的一种新型发电厂热利用系统,特征在于:所述连接热泵机组(8)和水箱(4)的管路上连接有设置有阀门的用水管路。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510106160.9A CN106152228A (zh) | 2015-03-10 | 2015-03-10 | 一种新型发电厂热利用系统 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510106160.9A CN106152228A (zh) | 2015-03-10 | 2015-03-10 | 一种新型发电厂热利用系统 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106152228A true CN106152228A (zh) | 2016-11-23 |
Family
ID=58064032
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510106160.9A Pending CN106152228A (zh) | 2015-03-10 | 2015-03-10 | 一种新型发电厂热利用系统 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106152228A (zh) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030140786A1 (en) * | 2002-01-31 | 2003-07-31 | Masaki Iijima | Exhaust heat utilization method for carbon dioxide recovery process |
CN201096429Y (zh) * | 2007-07-26 | 2008-08-06 | 张宪金 | 紧凑高效双工况冷却塔热回收节能装置 |
CN202532587U (zh) * | 2012-04-27 | 2012-11-14 | 北京华茂环能科技有限公司 | 一种热泵回收电厂冷凝热用于建筑供暖的系统 |
CN103017237A (zh) * | 2012-12-25 | 2013-04-03 | 浙江工商大学 | 发电厂凝结热回收供热系统 |
KR20140081943A (ko) * | 2012-12-20 | 2014-07-02 | 한국지역난방공사 | 전기 및 열 생산량 증대를 위한 흡수식 히트펌프가 구비된 지역 난방시스템 |
CN204460400U (zh) * | 2015-03-10 | 2015-07-08 | 中能世华(北京)节能科技有限公司 | 一种新型发电厂热利用系统 |
-
2015
- 2015-03-10 CN CN201510106160.9A patent/CN106152228A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030140786A1 (en) * | 2002-01-31 | 2003-07-31 | Masaki Iijima | Exhaust heat utilization method for carbon dioxide recovery process |
CN201096429Y (zh) * | 2007-07-26 | 2008-08-06 | 张宪金 | 紧凑高效双工况冷却塔热回收节能装置 |
CN202532587U (zh) * | 2012-04-27 | 2012-11-14 | 北京华茂环能科技有限公司 | 一种热泵回收电厂冷凝热用于建筑供暖的系统 |
KR20140081943A (ko) * | 2012-12-20 | 2014-07-02 | 한국지역난방공사 | 전기 및 열 생산량 증대를 위한 흡수식 히트펌프가 구비된 지역 난방시스템 |
CN103017237A (zh) * | 2012-12-25 | 2013-04-03 | 浙江工商大学 | 发电厂凝结热回收供热系统 |
CN204460400U (zh) * | 2015-03-10 | 2015-07-08 | 中能世华(北京)节能科技有限公司 | 一种新型发电厂热利用系统 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205119565U (zh) | 道路热源辅助地源热泵系统 | |
CN204739667U (zh) | 一种超导热管电地暖 | |
CN106152228A (zh) | 一种新型发电厂热利用系统 | |
CN204460400U (zh) | 一种新型发电厂热利用系统 | |
CN209229832U (zh) | 一种整体式热水热泵及采暖机组 | |
CN204571390U (zh) | 一种特种植物房 | |
CN104930582A (zh) | 超导热管电地暖 | |
CN204139383U (zh) | 太阳能高层建筑 | |
CN104975892A (zh) | 一种热泵回收余热系统 | |
CN204240640U (zh) | 一种地热水综合利用系统 | |
CN204738848U (zh) | 一种热泵回收余热系统 | |
CN203881001U (zh) | 地下水换热系统 | |
CN104251525A (zh) | 一种室内降温装置 | |
CN204192076U (zh) | 一种水循环式散热座椅 | |
CN204198442U (zh) | 太阳能溴化锂海水淡化系统 | |
CN203810623U (zh) | 一种新型复合式土壤源热泵系统 | |
CN203298630U (zh) | 一种新型采暖散热器 | |
CN202328831U (zh) | 地源热泵辅助太阳能采暖系统 | |
CN207214115U (zh) | 供热风系统 | |
CN202927951U (zh) | 中低温地热锅炉 | |
Shin et al. | AnalySiS of thermal performance of ground-Source heat pump System | |
CN204574600U (zh) | 一种可余热回收的热泵 | |
CN203704203U (zh) | 一种太阳能、空气能和地热能集采一体化节能空调系统 | |
CN204901793U (zh) | 一种煤渣余热利用装置 | |
CN204363483U (zh) | 一种公交车站座椅 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
DD01 | Delivery of document by public notice |
Addressee: Chen Jianghua Document name: Notification of Passing Examination on Formalities |
|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20161123 |