CN106121136A - Metal and the plastics Roof system that a kind of internally-fixed can fill, tear open, moves, refills - Google Patents

Metal and the plastics Roof system that a kind of internally-fixed can fill, tear open, moves, refills Download PDF

Info

Publication number
CN106121136A
CN106121136A CN201610662709.7A CN201610662709A CN106121136A CN 106121136 A CN106121136 A CN 106121136A CN 201610662709 A CN201610662709 A CN 201610662709A CN 106121136 A CN106121136 A CN 106121136A
Authority
CN
China
Prior art keywords
roof
roof boarding
bar
gland bar
boarding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610662709.7A
Other languages
Chinese (zh)
Other versions
CN106121136B (en
Inventor
梁琨
梁华柱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610662709.7A priority Critical patent/CN106121136B/en
Publication of CN106121136A publication Critical patent/CN106121136A/en
Application granted granted Critical
Publication of CN106121136B publication Critical patent/CN106121136B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D3/00Roof covering by making use of flat or curved slabs or stiff sheets
    • E04D3/36Connecting; Fastening
    • E04D3/366Connecting; Fastening by closing the space between the slabs or sheets by gutters, bulges, or bridging elements, e.g. strips

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

A kind of internally-fixed can fill, tear open, move, the metal refilled and plastics Roof system, including roof purline, prismatic groove roof boarding, roof boarding gland bar, ridge gland bar, roof boarding slope top seal glue laminated bar, roof boarding cornice press strip, prismatic groove roof boarding is placed on roof purline, roof boarding gland bar covers the plate seam between two pieces of prismatic groove roof boardings, roof boarding gland bar fastens with roof purline connection with internally-fixed tie-point in side, roofing indoor, ridge gland bar also fastens with the purlin connection on ridge with internally-fixed tie-point in side, roofing indoor, constitute the component metal material of Roof system or have the nonmetallic materials of sufficient intensity to make, by standardized designs, make in factory process, in-site installation, between component, the node of connection is the most easily made, fully achieve Roof system to fill well, tear open well, fill the best.Accomplish that component is reused, reduce construction costs.

Description

Metal and the plastics Roof system that a kind of internally-fixed can fill, tear open, moves, refills
One, technical field
The present invention relates to a kind of internally-fixed to fill, tear open, move, refill, and there is extremely strong antiseepage, drip-preventing function, fill, tear open, Refill metal and plastics Roof system all easily, can be widely applied to industrial building, civil buildings and public building field Roof system engineering.
Two, background technology
With color steel, color aluminium sheet, the plastic plate metal as representative and plastics Roof system, deeply by engineers and technicians and wide Large user likes, is widely used in the roofworks of various industrial building, civil buildings, public building over more than 100 year. Through application, the improvement of more than 100 years, more progressive, ripe.But this metal Roof system, the connection between roof boarding, room Connection between panel and roof purline is all to carry out in the face (towards terrace) that Roof system is outdoor, is the knot of " extenal fixation formula " Structure, its way has: bridging type is from boring nail connection, concealed fastener type connection, standing-seam formula connection etc., and wherein standing-seam formula connects For closely.The coupling arrangement of these " extenal fixation formulas " all exist " nail ", " seam " exposed leak infiltration hidden danger, this be appoint What roofing all must be prevented from, and is also engineers and technicians and all owners all worries.It is exactly to use chemical glue joint filling perforations adding Also it is difficult to thoroughly eliminate seepage, in addition chemical glue is also become by four seasons temperature and year is the most aging, can produce and chap and seepage.Roofing is once Seepage is the most difficult repairing, and place of dripping is not necessarily leakage, and leakage is not necessarily dripped, and makes us the most worried.
Say again, for traditional " extenal fixation formula " structure Roof system, in order to connect more firmly, more closely, for Antiseep, bridging type connects from boring nail, and nail can bore more and more, and concealed fastener type connection is then detained tighter and tighter, and standing-seam formula connects then More lock is more difficult to out.The roof boarding of traditional " extenal fixation formula " structure Roof system just can only be installed and used once, refills if pulling down Reuse, the own deformation of plate or destruction, use can not be refilled.
The present invention is analyzing the structure Roof system of " extenal fixation formula " exactly, there is the hidden danger of infiltration of leaking and can not weigh The multiple drawback used, finds the newly side of the connection between the connection between roof boarding and roof boarding, roof boarding and roof purline The connecting scheme of case " internally-fixed ", textural from connection is removed a hidden danger, it is to avoid a roof leakage infiltration difficult problem, does simultaneously To can fill, removable, refill use, invention one both reliable effectively, environmental protection again, " internally-fixed " of economy can again The metal fill, tear open, move, refilled and plastics Roof system.
Three, summary of the invention
1, the purpose of the present invention
The purpose of the present invention, it is simply that between connection and roof boarding and the roof purline between roof boarding to be found and roof boarding The new method of connection, removes a hidden danger from the structure way of connection, it is to avoid a roof leakage infiltration difficult problem, creates a kind of internally-fixed The metal can fill, tear open, move, refilled and plastics Roof system.
2, technical solution of the present invention
Metal and the plastics Roof system (Fig. 1,4,8) that a kind of internally-fixed can fill, tear open, moves, refills, including roof purline (1), prismatic groove roof boarding (2), roof boarding gland bar (3), ridge gland bar (4), roof boarding slope top seal glue laminated bar (5), Roof boarding cornice press strip (6), prismatic groove roof boarding (2) is placed on roof purline (1), and roof boarding gland bar (3) covers two Plate seam between block prismatic groove roof boarding (2), the both sides wing (7) of prismatic groove roof boarding (2) implants the groove of roof boarding gland bar (3) (8), in, roof boarding gland bar (3) is in side, roofing indoor and roof purline (1) connection fastening, and ridge gland bar (4) is at roofing Indoor side and the purlin connection fastening on ridge, referred to as " internally-fixed Roof system ", roof boarding slope top seal glue laminated Bar (5) inserts in the bayonet socket (9) on roof boarding gland bar (3) top, slope, and roof boarding cornice press strip (6) inserts roof boarding gland bar (3) in the bayonet socket (10) of cornice end.
The above roof purline (1) aluminium alloy or steel or other metals or nonmetal making, breaking of roof purline Face can be square-tube type section (11), can be c-type section (12), can be H type section (13), can be T-shaped section, it is possible to To be oneself combination (14) of these simple section, or the combined section being mutually combined, the drainage grade of roofing can be adjusted Whole roof purline profile height is designed, it is also possible on the lower junction structure slope of supporting roof purline, at all roof purlines With the internally-fixed tie-point (Fig. 1,4,8) that the intersection of roof boarding gland bar all arranges fixing Roof system.
The above roof boarding gland bar (3) aluminium alloy or steel or other metals or plastic production, gland bar interior Dividing plate (28) both sides are a groove (8) respectively, and the both sides wing (7) for prismatic groove roof boarding (2) is implanted, roof boarding gland bar (3) On both sides outer panel (15) press two seamed edges (16) of prismatic groove roof boarding (2), in all roof boardings gland bar (3) and room The intersection of face purlin (1) all arranges the internally-fixed tie-point (Fig. 1,4,8) of fixing Roof system, the slope of roof boarding gland bar Top arranges bayonet socket (9), inserts for roof boarding slope top seal glue laminated bar (5), and the cornice end of roof boarding gland bar arranges bayonet socket (10), insert for roof boarding cornice press strip (6).
The internally-fixed tie-point of the above fixing Roof system, can be two spiral shells on roof boarding gland bar (3) Bar (17) inserts in the two side holes (19) encasing roof purline U-shaped accessory (18), fixes with bolt, or two bars weld and room Face purlin is fixed (Fig. 1), and internally-fixed tie-point can also be that the breach plate (20) on roof boarding gland bar (3) snaps in roofing Both sides gusset piece (21) on purlin (1), with roof purline (1) is fixed with bolt, or the breach plate on roof boarding gland bar (20) fixing (Fig. 4) with roof purline (1) with welding, internally-fixed tie-point can also be roof boarding gland bar internal partition (28) The oblique hook (29) arranged below upwards, with bolt (31), roof boarding gland bar and roof purline are fixed (figure with fastener (30) 8)。
Above-described fastener (30) steel or aluminium alloy make, and are trihedrals, have bolt hole in bottom surface, and two Side back crossing place is arranged and roof boarding gland bar internal partition (28) oblique hook (29) upwards, the downward oblique hook coordinated mutually (32), if the fastener elastic stronger material manufacture of similar manganese steel, two sides back arranges a pair wrench (33), opens for fastener , facilitate mounting or dismounting to use, if fastener elastic not so good material manufacture such as similar aluminium alloy or Q235 steel etc., be not provided with spanner (33), and open a mouth (34) at the middle part of two sides back junction line, penetrate for bolt, or screw rod penetrates from bottom surface, use Nut fastens.
Above-described prismatic groove roof boarding (2), longitudinally can be with ribbing with aluminium alloy or steel or plastic production, or not Ribbing, the length of individual plates can be identical with roofing length of grade, it is also possible to being connected by several piece plate is a slope, and the both sides wing (7) of plate is planted Enter in the groove (8) of roof boarding gland bar (3), both secured the position of roof boarding, and prevented again capillary tube to seep water.
The above ridge gland bar (4) aluminium alloy or steel or other metals or plastic production, can be opening square Shape section, it is also possible to be herringbone double slopes sections, along ridge gland bar (4) length direction, according to being distributed in of roof boarding crest Ridge gland bar (4) both-side opening (22), presses certain along ridge gland bar (4) length direction at the inner chamber of ridge gland bar (4) Distance arranges moveable hinge connection or the screw rod (23) of welding, and screw rod lower end is fixed with corresponding ridge purlin bolt, or welding Fixing, ridge gland bar (4) covers the seam between two slope roof surface boards of ridge, the biside plate (24) of ridge gland bar (4) point Do not push down two slope roof surface boards of ridge.
The above roof boarding slope top seal glue laminated bar (5), press strip Os Draconis aluminium alloy or steel or other metals or Plastic production, the bayonet socket (9) on the form and dimension of press strip Os Draconis (5) transverse section and top, roof boarding gland bar slope is coordinated mutually and inserts In card inlet, the length of press strip Os Draconis (5) is determined by the spacing of roof boarding gland bar (3), and the downside of press strip Os Draconis (5) arranges one Road bayonet socket (25), the sealing adhesive strip (26) for press strip (5) inserts, and the sealing adhesive strip (26) of press strip fluid sealant makes, press strip The transverse section of the form and dimension of sealing adhesive strip (26) and prismatic groove roof boarding (Fig. 5) is coordinated mutually.
The above roof boarding cornice press strip (6) with aluminium alloy or steel or other metals or plastic production, press strip dragon The bayonet socket (10) of the form and dimension of bone transverse section and roof boarding gland bar (3) cornice end is coordinated mutually, and inserts in bayonet socket, press strip The length of Os Draconis (6) is determined by the spacing of roof boarding gland bar, and the downside of press strip Os Draconis arranges twice short column (27), short column (27) The height of length and the transverse section of prismatic groove roof boarding (Fig. 5) coordinate mutually, correct under short column (27) and press against prismatic groove room The outer surface of panel cornice, to strengthen rigidity at roof boarding cornice, prevents the deformation of prismatic groove roof boarding during strong wind.
The metal above-described fill, tear open, move, refilled and plastics Roof system (Fig. 1,4,8) be applicable to fill, tear open, The aluminium alloy move, refilled and the Roof system of steel-structure house, be also applied for industrial building, civil buildings, public works The Roof system in other houses.
3, the present invention is compared with prior art, its prominent substantive distinguishing features and marked improvement:
(1) metal comes out over more than 100 year with plastics Roof system, and the whole world is all to use " extenal fixation formula node " structure Fix roof boarding, have overlap joint from boring the fixing roofing of nail, have hidden discount from boring the fixing roofing of nail, have within 1899, begin to use so far Standing-seam (Huo Gaowen) roofing, be all node is set to terrace fixes roof boarding at roofing, all there is " the nail exposed Hole " " seam " infiltration leakage hidden trouble, will be with substantial amounts of chemical glue joint filling leakproof mending-leakage.The present invention one is confrontational, at roofing Node is set earthward, uses " internally-fixed node " to fix roof boarding, solve from the node structure way of Roof system Problem, has overturned traditional way, " nail " " seam " infiltration leakage hidden trouble not exposed, it is not necessary to chemical glue joint filling leakproof Antiseepage, does not has chemical glue aging and pollution problem.
Roof system of the present invention, connection fastener between component, bolt or " press strip " compress, it is real to cover, and node is simple, Install well and tear open.During installing in house, using, dismount, move fortune simultaneously, all component strengths, shape and function are not all had Change, lossless lossless, can reuse, its economic benefit can be thought and see.Other Roof systems such as " standing-seams " are to do not Arrive, it is impossible to analogy.
Roof system of the present invention all components all standardization, processing and fabricating and installation ratio " standing-seam " are the most square Just.The section of prismatic groove roof boarding is simple, can produce without special pressing plate machine, and the processing of common folder is the most permissible.And " standing-seam " must could make production by special pressing plate machine, and in-site installation also wants special cap seaming machine, and installation more bothers..
(2) the interior tie-point scheme (Fig. 1,4,8) of the present invention " internally-fixed Roof system " for " one can fill, tears open, The aluminium alloy move, refilled and steel-structure house " Roof system of (ZL201520397778.0, application number 201510315858.1) In interior tie-point scheme (Figure 16) not only have any different, and have significant technological progress.Interior connection in the latter's deck system Point scheme (Figure 16) is to arrange subscript on roof boarding gland bar, and subscript is placed on the face, top of roof purline, uses spiral shell Bolt is fixed deck panels gland bar with roof purline.This node scheme node is arranged on the crack between two adjacent roof panel In, space folder is narrow, and installation operation is inconvenient for, and subscript makes the most cumbersome simultaneously, relatively work consuming feed consumption.The present invention The interior tie-point scheme (Fig. 1,4,8) of " internally-fixed Roof system ", the tie-point between roof boarding gland bar and roof purline Being arranged on the following place of purlin both sides or purlin, space is big here, install very convenient easily, simultaneously in the hook determining tie-point The accessories such as folder, bolt and gusset are easily able to markization, make more convenient.
The ridge gland bar of the present invention " internally-fixed Roof system " has bigger with roof boarding slope top seal glue laminated bar Improvement, structure is simpler, makes well and installs use.The present invention is additionally arranged roof boarding cornice press strip simultaneously, prevents roof boarding cornice The deformation (in traditional scheme, going up from boring nail the most again, again many hidden danger) at place.
(3) prismatic groove roof boarding is placed on roof purline, roof boarding gland bar cover two pieces of prismatic groove roof boardings it Between plate seam, the both sides wing of prismatic groove roof boarding is implanted in the groove of roof boarding gland bar, roof boarding gland bar and ridge gland bar All in side, roofing indoor with " internally-fixed node " and purlin connection fastening, roof boarding slope top seal glue laminated bar insertion roofing In the bayonet socket on top, plate gland bar slope, roof boarding cornice press strip inserts in the bayonet socket of roof boarding gland bar cornice end.Room of the present invention Plane system node is simple, component button component, mutual cooperation, cooperation, and structural safety is smooth rationally, component processing and fabricating Can be with batch production, standardization, site operation is installed the most easy and convenient.
" fastener bolt internally-fixed node " in the present invention, the following upward hook of roof boarding gland bar internal partition and fastener The oblique hook that two sides back crossing place is downward mutually coordinated, when bolt fastens this to " hook " can more hook the tightest, reach roofing The function that plate gland bar is fixing with roof purline." fastener bolt internally-fixed node " solves in other very goodly simultaneously Two difficult problems that fixed node could not solve.The first, manufactures roof boarding gland bar when using aluminium alloy or plastics extruding Time, the most existing in other with fixed pattern node cannot with (because being inconvenient to weld), non-it do not belong to.And the roofing pole of the present invention Gland bar is exactly both can to have made of steel, it is also possible to extrude manufacture with aluminium alloy or plastics.It two is, roof boarding gland bar The following upward hook of internal partition, can be along the roof boarding elongated setting of gland bar, thus can be at roof boarding gland bar and roofing " fastener bolt internally-fixed node " can be used in any position that purlin intersects, it is to avoid due to purlin installing space error or Due to the fixed connection accessory fabrication error on gland bar, the connection accessory position construction and installation to not going up purlin spacing caused Trouble, achieves structure reliable comprehensively, is convenient to mount and dismount, easily the ideal of construction.
" fastener " be sizing standard component, can as " certainly boring nail " high-volume plant produced, be the most all cheap zero Accessory, but " fastener " does not has any damage to component, can reuse with mounting or dismounting, is very good accessory.
Fastener bolt internally-fixed node technology, is innovation and the breakthrough of existing internally-fixed node technology, is also invention The leap of inspiration.
(4) there is " expanding with heat and contract with cold " problem in metal material, aluminum alloy materials, steel and mould scale variations in temperature is reacted also phase Work as sensitivity.The Roof system of the present invention is all aluminum alloy materials or steel or plastics are made, and its each component is to variations in temperature Reaction is coordination, synchronizes." plate wing " is mutually twisted with " press strip groove ", and occlusion closely, secures the position of prismatic groove roof boarding Put, but cooperation again between them, sting " tightly " and " the most dead ", all directions of prismatic groove roof boarding can be cold with flatulence of heat type Contracting, and be uniform, synchronize, the temperature stress of all directions can be transferred through suitable breathing and releived, it is to avoid plate Block crimp or drawing crack.
(5) on roof boarding gland bar (3) of Roof system of the present invention, it is also possible to conveniently arrange solar power plant etc. its His affiliated facility.
The present invention " a kind of internally-fixed can fill, tear open, move, refill metal and plastics Roof system " be one practical, Environmental protection, energy-conservation successful invention, is that roofworks has prominent substantive distinguishing features and significant technological progress.
Four, accompanying drawing explanation:
Fig. 1 is the interior fixed connection point diagram of bolted on connection scheme.
Fig. 2 is roof purline figure.
Fig. 3 is roof boarding gland bar figure.
Fig. 4 is the interior fixed connection point diagram of gusset connecting scheme.
Fig. 5 is prismatic groove roof boarding figure.
Fig. 6 is ridge gland bar figure.
Fig. 7 is roof boarding slope top seal glue laminated bar and cornice press strip figure.
Fig. 8 is the interior fixed connection point diagram of fastener bolted on connection scheme.
Fig. 9 is engineering construction illustration.
Figure 10 is " aluminium alloy a kind of fill, tear open, move, refilled and steel-structure house " (ZL201520397778.0, application Numbers 201510315858.1) Figure 16 in Roof system.
In figure, component serial number name is as follows:
1-roof purline 2-prismatic groove roof boarding
3-roof boarding gland bar 4-ridge gland bar
5-roof boarding slope top seal glue laminated bar 6-cornice press strip
Wing 8-roof boarding gland bar both sides, 7-prismatic groove roof boarding both sides groove
The bayonet socket of the bayonet socket 10-roof boarding gland bar cornice end on top, 9-roof boarding gland bar slope
11-square-tube type section purlin 12-C type section purlin
13-H type section purlin 14-combined section purlin
Both sides outer panel 16-two seamed edges of prismatic groove roof boarding on 15-roof boarding gland bar
On 17-roof boarding gland bar, two screw rod 18-encase the U-shaped accessory of roof purline
Breach plate on 19-U shape accessory two side holes 20-roof boarding gland bar
Both sides gusset piece 22-ridge gland bar both-side opening on 21-roof purline
The biside plate of the screw rod 24-ridge gland bar of 23-ridge gland bar inner chamber
On the downside of the top seal glue laminated bar keel of 25-roof boarding slope, bayonet socket is set
The twice short column of 26-roof boarding slope top seal adhesive tape 27-cornice press strip
28-roof boarding gland bar internal partition
The 29-roof boarding following upward hook of gland bar internal partition
30-fastener 31-fastener bolt
The oblique hook that 32-fastener two sides back crossing place is downward
On the back of 33-fastener two sides, a pair spanner 34-fastener bolt penetrates mouth
Five, detailed description of the invention
1, below in conjunction with accompanying drawing, the present invention is described further.
Metal and the plastics Roof system that internally-fixed can fill, tear open, moves, refills, its component includes: roof purline (1), Prismatic groove roof boarding (2), roof boarding gland bar (3) and ridge gland bar (4), roof boarding slope top seal glue laminated bar (5), cornice Press strip (6).It can be seen from figure 1 that the internally-fixed tie-point of fixing prismatic groove roof boarding (2) is by roof purline (1), prismatic groove room Panel (2), roof boarding gland bar (3) are constituted.Prismatic groove roof boarding (2) is placed on roof purline (1), roof boarding gland bar (3) covering the plate seam between two pieces of prismatics groove roof boarding (2), the both sides wing (7) of prismatic groove roof boarding (2) inserts roof boarding pressure In the both sides groove of cover fillet (3) (8), roof boarding gland bar (3) inner chamber stretches out two screw rods (17) and inserts and encase roof purline U-shaped and join The two side holes (19) of part (18), fixes with bolt, or two bar welding are fixed with roof purline.On roof boarding gland bar (3) Both sides outer panel (15) press two seamed edges (16) of prismatic groove roof boarding (2).Utilize an internally-fixed tie-point, whole Each component of Roof system secures, the nail not exposed and seam, has reached fabulous antiseepage leakproof by the method for structure Purpose.Fig. 4 is the interior fixed connection point of gusset connecting scheme, and the breach plate (20) on roof boarding gland bar (3) snaps in room Both sides gusset piece (21) on face purlin (1), with roof purline (1) is fixed with bolt, or the notched plate on roof boarding gland bar Part (20) welding is fixed with roof purline (1).Fig. 8 is the interior fixed connection point of fastener bolted on connection scheme, roof boarding gland The oblique hook (29) arranged below upwards of bar internal partition (28), with fastener (30) with bolt (31) roof boarding gland bar and roofing Purlin is fixed.
After installing roof boarding slope top seal glue laminated bar (5), then ridge gland bar (4) is installed.As seen from Figure 6, Ridge gland bar (4) can be open rectangle section, it is also possible to be herringbone double slopes sections, along ridge gland bar (4) length side To, it is distributed in ridge gland (4) bar both-side opening (22) according to roof boarding crest, exists along ridge gland bar (4) length direction The inner chamber of ridge gland bar (4) arranges moveable hinge connection or the screw rod (23) of welding at a certain distance, and screw rod lower end is with corresponding Ridge purlin bolt is fixed, or is welded and fixed, and ridge gland bar (4) covers the seam between two slope roof surface boards of ridge, room The biside plate (24) of ridge gland bar (4) pushes down two slope roof surface boards of ridge respectively.Each component same secures, and does not expose Nail and seam, reached fabulous antiseepage leakproof purpose by the structure way of node.
2, engineering construction example
Fig. 8 is engineering construction illustration, be a building residential housing, is completely designed by the technology of the present invention, manufactures, installs Case history.
This engineering is the house of two floors, and construction area is 62.72 square metres.Roofing projected area is 37.85 square metres.
This engineering roof purline selects the compound section of steel square tube to constitute, and totally 9, steel using amount is 0.307 ton.This engineering is By the interior fixed connection point scheme of Fig. 1.0.8 thick corrosion resistant plate makes roof boarding gland bar (26) and ridge gland bar (totally 1 Bar).Prismatic groove roof boarding is pressed into 0.8 thick color aluminium sheet, totally 24 pieces, with plate 40.5 square metres.Roof boarding slope top seal glue Press strip Os Draconis and cornice press strip Os Draconis all make by 20 × 20 steel square tubes, and sealing compound fluid sealant makes.
Through Practical Calculation, at the market price, fee of material and processing charges are 6031 yuan, and in-site installation takes 750 yuan, add up to Total cost is 6781 yuans, and unit roofing manufactures valency and is about 179.00 yuan.Dark with extenal fixation popular in current engineering The cost of buckle Roof system or standing-seam plank house plane system almost flushes.
In this project implementing process, we realize:
1, the various components of " metal Roof system that a kind of internally-fixed can fill, tear open, moves, refills " of the present invention, permissible Accomplish standardization, standardization, it is achieved millworkization makes and produces;
2, in this project implementing process, the process that we accomplish dress, tear open again, refill, truly realize the present invention's Roof system, the tie-point between component is simple, easily make, rationally, and scene installs well and tears open, and building-site cleaning is clean;
3, the present embodiment is not with a chemical glue joint filling, is completed 10 months, experiences many strong wind and heavy rains, drip not Leak not permeable, be successful.

Claims (9)

1. metal and the plastics Roof system that internally-fixed can fill, tear open, moves, refills, this Roof system includes roofing purlin Bar, prismatic groove roof boarding, roof boarding gland bar, ridge gland bar, roof boarding slope top seal glue laminated bar, roof boarding cornice pressure Bar, its feature is: described prismatic groove roof boarding is placed on roof purline, and roof boarding gland bar covers two pieces of prismatic grooves Plate seam between roof boarding, in wing implantation roof boarding gland bar both sides, the both sides groove of prismatic groove roof boarding, roof boarding gland bar exists Side, roofing indoor and roof purline connection fastening, the purlin connection on side, roofing indoor with ridge of the ridge gland bar is tight Gu, roof boarding slope top seal glue laminated bar inserts in the bayonet socket on top, roof boarding gland bar slope, and roof boarding cornice press strip inserts room In the bayonet socket of panel gland bar cornice end.
Metal and the plastics Roof system that a kind of internally-fixed the most according to claim 1 can fill, tear open, moves, refills, it is special Levy and be: described roof purline is to make of aluminium alloy or steel or other metals, and the section of roof purline can be square tube Type section, can be c-type section, can be H type section, can be T-shaped section, it is also possible to be combined section, the row of roofing The water gradient can adjust roof purline profile height and be designed, it is also possible on the lower junction structure slope of supporting roof purline, The intersection of all roof purlines and roof boarding gland bar all arranges the internally-fixed tie-point of fixing Roof system.
Metal and the plastics Roof system that a kind of internally-fixed the most according to claim 1 can fill, tear open, moves, refills, it is special Levy and be: described roof boarding gland bar, be with aluminium alloy or steel or other metals or plastic production, the internal partition of gland bar Both sides are a groove respectively, and the both sides wing for prismatic groove roof boarding is implanted, and the both sides outer panel on roof boarding gland bar presses rib Two seamed edges of shape groove roof boarding, all arrange fixing Roof system in the intersection of all roof boarding gland bars Yu roof purline Internally-fixed tie-point, the top, slope of roof boarding gland bar arranges bayonet socket, inserts for roof boarding slope top seal glue laminated bar, roofing The cornice end of plate gland bar arranges bayonet socket, inserts for roof boarding cornice press strip.
4. according to the internally-fixed tie-point of claim 2 with the fixing Roof system described in claim 3, it is characterised in that: Internally-fixed tie-point can be that two screw rods on roof boarding gland bar insert the two side holes encasing roof purline U-shaped accessory In, to fix with bolt, or two bar welding are fixed with roof purline, internally-fixed tie-point can also be roof boarding gland bar On breach plate snap in roof purline, fix with the both sides gusset piece bolt of roof purline, or on roof boarding gland bar The welding of breach plate is fixed with roof purline, and internally-fixed tie-point can also be setting below of roof boarding gland bar internal partition Put oblique hook upwards, with bolt, roof boarding gland bar is fixed with roof purline with fastener.
Fastener the most according to claim 4, it is characterised in that: fastener is to make of aluminium alloy or steel, is one three Body, has bolt hole in bottom surface, and two sides back crossing place arranges and arranges upwards with the following of roof boarding gland bar internal partition The downward oblique hook that tiltedly hook is coordinated mutually, two sides back arranges a pair spanner, or the middle part at two sides back junction line Open a mouth, penetrate for bolt, or screw rod penetrates from bottom hole, fastens with nut.
Metal and the plastics Roof system that a profit internally-fixed the most according to claim 1 can fill, tear open, moves, refills, it is special Levy and be: described prismatic groove roof boarding is with aluminium alloy or steel or plastic production, longitudinally can be with ribbing, or not ribbing, The length of individual plates can be identical with roofing length of grade, it is also possible to being connected by several piece plate is a slope, and the both sides wing of plate implants roof boarding In the both sides groove of gland bar, both secure the position of roof boarding, and prevent again capillary tube to seep water.
Metal and the plastics Roof system that a kind of internally-fixed the most according to claim 1 can fill, tear open, moves, refills, it is special Levy and be: described ridge gland bar is with aluminium alloy or steel or other metals or plastic production, can be that open rectangle breaks Face, it is also possible to be herringbone double slopes sections, along ridge gland bar length direction, is distributed in ridge gland according to roof boarding crest Bar both-side opening, arranges moveable hinge connection or weldering along ridge gland bar length direction at a certain distance at the inner chamber of ridge gland bar The screw rod connect, screw rod lower end fixes with corresponding ridge purlin bolt, or is welded and fixed, and ridge gland bar covers ridge Seam between two slope roof surface boards, the biside plate of ridge gland bar pushes down two slope roof surface boards of ridge respectively.
Metal and the plastics Roof system that a kind of internally-fixed the most according to claim 1 can fill, tear open, moves, refills, it is special Levy and be: described roof boarding slope top seal glue laminated bar keel is with aluminium alloy or steel or other metals or plastic production, The bayonet socket on the form and dimension of press strip Os Draconis transverse section and top, roof boarding gland bar slope is coordinated mutually, and inserts in bayonet socket, press strip The length of Os Draconis is determined by the spacing of roof boarding gland bar, and the downside of press strip Os Draconis arranges one bayonet socket, for the sealing compound of press strip Bar inserts, and the sealing adhesive strip of press strip fluid sealant makes, the form and dimension of the sealing adhesive strip of press strip and prismatic groove roof boarding Transverse section is coordinated mutually.
Metal and the plastics Roof system that a kind of internally-fixed the most according to claim 1 can fill, tear open, moves, refills, it is special Levy and be: described roof boarding cornice press strip is with aluminium alloy or steel or other metals or plastic production, and press strip Os Draconis are cross-section The bayonet socket of the form and dimension in face and roof boarding gland bar cornice end is coordinated mutually, and inserts in bayonet socket, the length of press strip Os Draconis by The spacing of roof boarding gland bar determines, the downside of press strip Os Draconis arranges twice short column, the length of short column and prismatic groove roof boarding The height of transverse section is coordinated mutually, corrects the outer surface that press against prismatic groove roof boarding cornice, to strengthen roof boarding under short column Rigidity at cornice, prevents the deformation of prismatic groove roof boarding during strong wind.
CN201610662709.7A 2016-08-15 2016-08-15 A kind of metal that internally-fixed can be filled, be torn open, moving, refilling and plastics Roof system Active CN106121136B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610662709.7A CN106121136B (en) 2016-08-15 2016-08-15 A kind of metal that internally-fixed can be filled, be torn open, moving, refilling and plastics Roof system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610662709.7A CN106121136B (en) 2016-08-15 2016-08-15 A kind of metal that internally-fixed can be filled, be torn open, moving, refilling and plastics Roof system

Publications (2)

Publication Number Publication Date
CN106121136A true CN106121136A (en) 2016-11-16
CN106121136B CN106121136B (en) 2018-10-30

Family

ID=57258926

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610662709.7A Active CN106121136B (en) 2016-08-15 2016-08-15 A kind of metal that internally-fixed can be filled, be torn open, moving, refilling and plastics Roof system

Country Status (1)

Country Link
CN (1) CN106121136B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203022235U (en) * 2013-01-06 2013-06-26 高锋新颖建材(苏州)有限公司 Leak-proof device for connecting PC (Polycarbonate) sunshine plates
CN103469971A (en) * 2013-08-28 2013-12-25 辽宁华夏钢结构有限公司 Metal roof system
FR2999205A1 (en) * 2012-12-07 2014-06-13 Saint Gobain System for fastening and sealing e.g. veranda roof, has longitudinal section provided with central and lateral grooves, and supporting edge of two adjacent electrochromic glazings that are arranged in same plane and parallel to roof slope
CN204059770U (en) * 2014-07-28 2014-12-31 杭州赛宁板材有限公司 The upper and lower lock catch batten of water proof type
CN104947794A (en) * 2015-07-07 2015-09-30 林娟 Aluminum-alloy and steel structure house capable of being assembled, disassembled, moved and reassembled
CN206034773U (en) * 2016-08-15 2017-03-22 林娟 Internal stability fixed pattern can be adorned, torn open, moved, metal of reload and plastics roofing system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2999205A1 (en) * 2012-12-07 2014-06-13 Saint Gobain System for fastening and sealing e.g. veranda roof, has longitudinal section provided with central and lateral grooves, and supporting edge of two adjacent electrochromic glazings that are arranged in same plane and parallel to roof slope
CN203022235U (en) * 2013-01-06 2013-06-26 高锋新颖建材(苏州)有限公司 Leak-proof device for connecting PC (Polycarbonate) sunshine plates
CN103469971A (en) * 2013-08-28 2013-12-25 辽宁华夏钢结构有限公司 Metal roof system
CN204059770U (en) * 2014-07-28 2014-12-31 杭州赛宁板材有限公司 The upper and lower lock catch batten of water proof type
CN104947794A (en) * 2015-07-07 2015-09-30 林娟 Aluminum-alloy and steel structure house capable of being assembled, disassembled, moved and reassembled
CN206034773U (en) * 2016-08-15 2017-03-22 林娟 Internal stability fixed pattern can be adorned, torn open, moved, metal of reload and plastics roofing system

Also Published As

Publication number Publication date
CN106121136B (en) 2018-10-30

Similar Documents

Publication Publication Date Title
CA2246096C (en) Roof curb
CN206034773U (en) Internal stability fixed pattern can be adorned, torn open, moved, metal of reload and plastics roofing system
US20060101777A1 (en) Insulating roofing system for flat roofs
CN105986642B (en) The construction of accurate control metal roofing board installation accuracy
CN216405887U (en) Furred ceiling waterproof construction
CN106121136B (en) A kind of metal that internally-fixed can be filled, be torn open, moving, refilling and plastics Roof system
US4706434A (en) Standing seam structure covering system
CN217871443U (en) Organized collection and drainage system
EP2891848A1 (en) An assembly as well as a first profile and a second profile suitable for such an assembly
JP2003313997A (en) Roof floor greening method for building
JP2009270335A (en) Lean-to roof section waterproof gasket, seal structure of outer wall joint section using the gasket, and sealing method for outer wall joint section
CN212026888U (en) Waterproof eaves gutter of pitched roof
CN207727781U (en) A kind of deformation joint of roof connecting structure
CN106193474A (en) The light-weight metal binding structure of cornice and construction method thereof
JP2006161453A (en) Construction method for repairing batten seam roof
CN207295766U (en) Prefabricated board grouting interconnection system pipe gallery
JP3129393U (en) Prefabricated building
CA2521801A1 (en) Insulating roofing system for flat roofs
CN205776999U (en) A kind of steel building lighting roof
GB2023688A (en) Fascia and guttering component
JP3883545B2 (en) Outdoor floorboard connector, outdoor floor using the same, and outdoor floor construction method
CN206337640U (en) Assemble steel structure formula room booth
CN216428336U (en) Assembled valve well
JPH035606Y2 (en)
CN217105857U (en) Gutter edge-closing anti-seepage structure in parapet wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: Liang Kun

Document name: payment instructions

DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: Liang Kun

Document name: payment instructions

DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: Liang Kun

Document name: Notice of Termination of Patent Rights