CN106120490A - The integrated track of a kind of vertical loop and installation method - Google Patents

The integrated track of a kind of vertical loop and installation method Download PDF

Info

Publication number
CN106120490A
CN106120490A CN201610497525.XA CN201610497525A CN106120490A CN 106120490 A CN106120490 A CN 106120490A CN 201610497525 A CN201610497525 A CN 201610497525A CN 106120490 A CN106120490 A CN 106120490A
Authority
CN
China
Prior art keywords
track
rail
section
profile steel
arrangement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610497525.XA
Other languages
Chinese (zh)
Other versions
CN106120490B (en
Inventor
徐平
曾建新
周汉生
郭继舟
李少祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201610497525.XA priority Critical patent/CN106120490B/en
Publication of CN106120490A publication Critical patent/CN106120490A/en
Application granted granted Critical
Publication of CN106120490B publication Critical patent/CN106120490B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B26/00Tracks or track components not covered by any one of the preceding groups
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses integrated track and the installation method of a kind of vertical loop, including some elementary sections, each elementary section includes rail and supports pedestal, rail is arranged on support pedestal, support pedestal is provided with multiple transverse adjustment device and arrangement for adjusting height, transverse adjustment device and arrangement for adjusting height and is all distributed in rail both sides along rail length direction.Decrease work high above the ground, improve the safety of construction, decrease the labor intensity of workman, be more prone to operation, improve certainty of measurement, improve labor efficiency.

Description

The integrated track of a kind of vertical loop and installation method
Technical field
The present invention relates to technical field of metallurgical equipment, be specifically related to integrated track and the installation side of a kind of vertical loop Method.
Background technology
For response national energy-saving environmental protection policy, economizing the land resource, in metallurgical cold rolling project, the use of vertical loop is got over Coming the most, vertical loop installation period, typically 3~4 months, is the important step determining whole piece galvanized wire construction speed, wherein Vertical loop car track installation is again the critical process determining whole loop system installation progress speed.Conventional construction method is to execute After every section of rail, H profile steel, channel-section steel are the most individually lifted by workman person, it is connected in kink structure in high-altitude, then starts to look for Just, work high above the ground is many, complex operation, quality are difficult to ensure, and need to take driving resource in a large number.In view of the foregoing, it is necessary to A kind of novel track installation mode is provided, improves work efficiency and track centering quality, reduce work high above the ground risk.
Summary of the invention
The technical problem to be solved in the present invention is, in view of the foregoing defects the prior art has, it is provided that a kind of Verticle active The integrated track of set and installation method, decrease work high above the ground, improve the safety of construction, and the work decreasing workman is strong Degree, is more prone to operation, improves certainty of measurement, improve labor efficiency.
The present invention solves that above-mentioned technical problem be the technical scheme is that
The integrated track of a kind of vertical loop, it is characterised in that include that some elementary sections, each elementary section include rail With support pedestal, rail is arranged on support pedestal, supports pedestal and is provided with multiple transverse adjustment device and arrangement for adjusting height, Transverse adjustment device and arrangement for adjusting height are all distributed in rail both sides along rail length direction.
According to technique scheme, described support pedestal includes H profile steel and two channel-section steels, and H profile steel is laterally disposed, two grooves Steel is connected with two edge of a wing end faces of H profile steel respectively, and channel-section steel outward opening is arranged, rail foot is connected with H profile steel web.
According to technique scheme, described transverse adjustment device includes the second regulation bolt and fixed cover, bottom fixed cover Being connected with H profile steel web, the threaded one end of the second regulation bolt screws in fixed cover, and passes and hold out against rail side.
According to technique scheme, described arrangement for adjusting height includes arm-tie and the first regulation bolt, at the bottom of arm-tie and channel-section steel Portion connects, and the upper end of the first regulation bolt is connected with the web of H profile steel by screw thread, and screw thread is passed through in the lower end of the first regulation bolt It is connected with arm-tie.
Use the installation method of above-described integrated track, comprise the following steps:
1) backing plate is set on the ground, to backing plate levelling capturing;
2) assembling each elementary section of track respectively, the assembling of track element section comprises the following steps: installed by rail To supporting on pedestal, transverse adjustment device and arrangement for adjusting height are layed on support pedestal along rail length direction;
3) elementary section of track is positioned on backing plate, by transverse adjustment device and arrangement for adjusting height on backing plate, Levelling and the centering to the rail level of track elementary section, and utilize Sopwith staff to coordinate level gauge that the levelness of track is detected and answered Look into;
4) each unit section of the track adjusted is lifted into high-altitude mounting position and carries out assembly;
5) position degree to the joint of each unit section of track in the air at height, detects and adjusts.
Installation method the most according to claim 5, it is characterised in that described step 2) in, support pedestal and assemble, bag Include following steps: two edge of a wing end faces with H profile steel connect and compose support pedestal respectively by two channel-section steels.
The method have the advantages that
By track being divided into some elementary sections, assemble respectively and levelling, centering in the face of each elementary section on ground, then Carrying out segmentation to hang high-altitude and carry out assembly, between height the most only needs each unit section, joint is detected and is adjusted, and reduces Work high above the ground, improves the safety of construction, is transferred to by extensive work on ground, decrease the labor intensity of workman, To track detecting and centering on ground, it is more prone to operation, improves vertical track detection and the success rate of centering, improve survey Accuracy of measurement, improves labor efficiency.
Accompanying drawing explanation
Fig. 1 is the structural representation of the integrated track of vertical loop in the embodiment of the present invention;
Fig. 2 is the A-A sectional view of Fig. 1;
Fig. 3 is the B-B sectional view of Fig. 1;
In figure, 1-Sopwith staff, 2-first regulates bolt, and 3-second regulates bolt, 4-channel-section steel, 5-H shaped steel, 6-rail, 7- Three bolts, 8-arm-tie.
Detailed description of the invention
The present invention is described in detail with embodiment below in conjunction with the accompanying drawings.
Shown in reference Fig. 1~Fig. 3, the integrated track of the vertical loop in the embodiment that the present invention provides, including Some elementary sections, each elementary section includes rail 6 and supports pedestal, and rail 6 is arranged on support pedestal, supports pedestal and is provided with Multiple transverse adjustment devices and arrangement for adjusting height, transverse adjustment device and arrangement for adjusting height all divide along rail 6 length direction It is distributed in rail 6 both sides, for rail 6 is laterally adjusted and altitude mixture control;By track being divided into some elementary sections, on ground Assemble respectively and levelling, centering in the face of each elementary section, then carry out segmentation and hang high-altitude and carry out assembly, the most only need at height Joint between each unit section is detected and adjusted, decreases work high above the ground, improve the safety of construction, by a large amount of works Transfer on ground, decrease the labor intensity of workman, on the ground to track detecting and centering, be more prone to operation, carry High vertical track detection and the success rate of centering, improve certainty of measurement, improve labor efficiency.
Further, described support pedestal includes H profile steel 5 and two channel-section steels 4, and H profile steel 5 is laterally disposed, 4 points of two channel-section steels Not being connected with two edge of a wing end faces of H profile steel 5, channel-section steel 4 outward opening is arranged, is connected with H profile steel 5 web bottom rail 6;Pass through Channel-section steel 4, H profile steel 5 and track constitute cancelled structure, Stability Analysis of Structures, are on market the general section bar that can buy.
Further, channel-section steel 4 is connected with the edge of a wing end face of H profile steel 5 by the 3rd bolt 7.
Further, described transverse adjustment device includes the second regulation bolt 3 and fixed cover, with H profile steel 5 bottom fixed cover Web connects, and the threaded one end of the second regulation bolt 3 screws in fixed cover, and passes and hold out against rail 6 side;By controlling the second tune The screw-in degree of joint bolt 3 regulates the lateral attitude of rail 6.
Further, described arrangement for adjusting height includes arm-tie 8 and the first regulation bolt 2, and arm-tie 8 connects bottom channel-section steel 4 Connecing, the upper end of the first regulation bolt 2 is connected with the web of H profile steel 5 by screw thread, and screw thread is passed through in the lower end of the first regulation bolt 2 It is connected with arm-tie 8;Regulate the distance between the web of H profile steel 5 and arm-tie 8 by screwing the first bolt, and then regulate H type Highly.
Further, the first bolt is compressed by nut and is connected with H profile steel 5 and arm-tie 8 respectively.
Use the installation method of above-described integrated track, comprise the following steps:
1) backing plate is set on the ground, to backing plate levelling capturing, the datum level adjusted as track installation by backing plate;
2) assembling each elementary section of track respectively, the assembling of track element section comprises the following steps: installed by rail 6 To supporting on pedestal, transverse adjustment device and arrangement for adjusting height are layed on support pedestal along rail 6 length direction;
3) elementary section of track is positioned on backing plate, by transverse adjustment device and arrangement for adjusting height on backing plate, Levelling and the centering to the rail level of track elementary section, and utilize Sopwith staff 1 to coordinate level gauge that the levelness of track is detected and answered Look into;
4) each unit section of the track adjusted is lifted into high-altitude mounting position and carries out assembly;
5) position degree to the joint of each unit section of track in the air at height, detects and adjusts.
Further, described step 2) in, support pedestal and assemble, comprise the following steps: by two channel-section steels 4 respectively with H type Two edge of a wing end faces of steel 5 connect and compose support pedestal.
Further, integrated track type of attachment is cancelled structure, and both sides channel-section steel is connected with kink steel construction, middle H profile steel makees track supports, is individually fixed on the side structure of entry and exit, track from-3.5 meters of absolute altitudes to+24 meters of absolute altitudes, total length 27.5 meters, it is the loose mail supply of material;Version according to integrated track and supply of material state, be divided into 5 sections altogether by integrated track 10 unit modules assemble;In ground difference pre-splicing double flute steel, H profile steel during assembling, then rail is pressed design with H profile steel Size connects fixing, and integral hoisting afterwards, in advance on the backing plate group basal plane of floor leveling, divides by adjusting bolt and jackscrew Other tracking road rail level and side are adjusted so that it is assembly precision reaches to design requirement.
The above presently preferred embodiments of the present invention that is only, can not limit the interest field of the present invention with this certainly, Therefore the equivalence change made according to scope of the present invention patent, still belongs to protection scope of the present invention.

Claims (6)

1. the integrated track of a vertical loop, it is characterised in that include some elementary sections, each elementary section include rail and Supporting pedestal, rail is arranged on support pedestal, supports pedestal and is provided with multiple transverse adjustment device and arrangement for adjusting height, horizontal All it is distributed in rail both sides along rail length direction to adjusting apparatus and arrangement for adjusting height.
The integrated track of vertical loop the most according to claim 1, it is characterised in that described support pedestal includes H type Steel and two channel-section steels, H profile steel is laterally disposed, and two channel-section steels are connected with two edge of a wing end faces of H profile steel respectively, channel-section steel outward opening Arranging, rail foot is connected with H profile steel web.
The integrated track of vertical loop the most according to claim 2, it is characterised in that described transverse adjustment device includes Second regulation bolt and fixed cover, is connected with H profile steel web bottom fixed cover, and the threaded one end of the second regulation bolt screws in fixing Set, and pass and hold out against rail side.
The integrated track of vertical loop the most according to claim 2, it is characterised in that described arrangement for adjusting height includes Arm-tie and the first regulation bolt, arm-tie is connected with bottom channel-section steel, the upper end of the first regulation bolt web by screw thread with H profile steel Connecting, the lower end of the first regulation bolt is connected with arm-tie by screw thread.
5. the installation method of the employing integrated track described in claim 1, it is characterised in that comprise the following steps:
1) backing plate is set on the ground, to backing plate levelling capturing;
2) assembling each elementary section of track respectively, the assembling of track element section comprises the following steps: be installed to rail prop up On support group seat, transverse adjustment device and arrangement for adjusting height are layed on support pedestal along rail length direction;
3) elementary section of track is positioned on backing plate, by transverse adjustment device and arrangement for adjusting height on backing plate, tracking The rail level of road elementary section is levelling and centering, and utilizes Sopwith staff to coordinate level gauge that the levelness of track is detected and checked;
4) each unit section of the track adjusted is lifted into high-altitude mounting position and carries out assembly;
5) position degree to the joint of each unit section of track in the air at height, detects and adjusts.
Installation method the most according to claim 5, it is characterised in that described step 2) in, support pedestal assemble, including with Lower step: two edge of a wing end faces with H profile steel connect and compose support pedestal respectively by two channel-section steels.
CN201610497525.XA 2016-06-29 2016-06-29 The integrated track and installation method of a kind of vertical loop Active CN106120490B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610497525.XA CN106120490B (en) 2016-06-29 2016-06-29 The integrated track and installation method of a kind of vertical loop

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610497525.XA CN106120490B (en) 2016-06-29 2016-06-29 The integrated track and installation method of a kind of vertical loop

Publications (2)

Publication Number Publication Date
CN106120490A true CN106120490A (en) 2016-11-16
CN106120490B CN106120490B (en) 2018-06-19

Family

ID=57285718

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610497525.XA Active CN106120490B (en) 2016-06-29 2016-06-29 The integrated track and installation method of a kind of vertical loop

Country Status (1)

Country Link
CN (1) CN106120490B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112275808A (en) * 2020-09-30 2021-01-29 广东韶钢松山股份有限公司 Loop device
CN114738064A (en) * 2022-04-19 2022-07-12 中国航发动力股份有限公司 Exhaust volute positioning and adjusting device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09316803A (en) * 1996-05-27 1997-12-09 Nishi Nippon Kensetsu Kk Rail hole opening auxiliary device
CN101972886A (en) * 2010-04-02 2011-02-16 无锡华联科技集团有限公司 Walking track mounting structure for gantry digital control cutter
CN203602979U (en) * 2013-12-20 2014-05-21 中铁四局集团有限公司 Urban mass transit 59R2 channel steel track inspection car
CN204690513U (en) * 2015-06-15 2015-10-07 襄阳航生石化环保设备有限公司 A kind of combined orbit adjustment means
CN105606330A (en) * 2016-02-25 2016-05-25 江苏科技大学 Traction track for automobile crash test

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09316803A (en) * 1996-05-27 1997-12-09 Nishi Nippon Kensetsu Kk Rail hole opening auxiliary device
CN101972886A (en) * 2010-04-02 2011-02-16 无锡华联科技集团有限公司 Walking track mounting structure for gantry digital control cutter
CN203602979U (en) * 2013-12-20 2014-05-21 中铁四局集团有限公司 Urban mass transit 59R2 channel steel track inspection car
CN204690513U (en) * 2015-06-15 2015-10-07 襄阳航生石化环保设备有限公司 A kind of combined orbit adjustment means
CN105606330A (en) * 2016-02-25 2016-05-25 江苏科技大学 Traction track for automobile crash test

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112275808A (en) * 2020-09-30 2021-01-29 广东韶钢松山股份有限公司 Loop device
CN114738064A (en) * 2022-04-19 2022-07-12 中国航发动力股份有限公司 Exhaust volute positioning and adjusting device

Also Published As

Publication number Publication date
CN106120490B (en) 2018-06-19

Similar Documents

Publication Publication Date Title
CN105040717B (en) Foundation bolt fixing support and installation method
CN105003080B (en) A kind of fan-shaped steel building construction technology
CN202031179U (en) Centre line aligning and elevation adjusting device of basic embedded bolts
CN109610328A (en) Straddle-type monorail Simple-supported PC Rail Beam in Light Rail high accuracy install method
CN203270600U (en) Fixed support for installing embedded bolts of high-precision equipment
CN105784302A (en) Automobile modal testing apparatus and method
CN107345388A (en) Intelligent beam section Matching installation control system
CN108532743A (en) The aerial steel vestibule Lift-on/Lift-off System of multilayer and its application method
CN106120490A (en) The integrated track of a kind of vertical loop and installation method
CN111550023A (en) Construction method for mounting and fixing building prefabricated part
CN105334014B (en) A kind of adjustable suspension cable method for testing deflection of bridge span
CN208415485U (en) The aerial steel vestibule Lift-on/Lift-off System of multilayer
CN105648854A (en) Special regulating device for construction of trench-reserved tracks of tramcars and application method of special regulating device
CN205426172U (en) Prefabricated wallboard straightness monitoring devices that hangs down
CN111232808B (en) Transverse installation method of prefabricated modular elevator
CN205743048U (en) Correction positioner installed by a kind of curtain wall large-size column
CN209460042U (en) A kind of assembled architecture prefabricated components structural clays device
CN202627214U (en) Beam-column connecting structure for steel reinforced concrete composite structure of high-rise building
CN207019575U (en) Structure steel fabrication angle and bolt hole relative position detector
CN215725947U (en) Prism device for measuring assembled U-shaped beam
CN103290763A (en) Steel template for elevation-adjustable road surface
CN208937010U (en) A kind of measuring tool
CN205673373U (en) 18 roller cold continuous rolling work roll changing orbit adjusting fixtures
CN202791227U (en) Support for hot rolled strip steel pyrometer on-line measurement
CN209812260U (en) Adjustable precision platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant