CN106099827A - Complete thread guide devices in a kind of 10KV transformer platform area and preparation method thereof - Google Patents

Complete thread guide devices in a kind of 10KV transformer platform area and preparation method thereof Download PDF

Info

Publication number
CN106099827A
CN106099827A CN201610727569.7A CN201610727569A CN106099827A CN 106099827 A CN106099827 A CN 106099827A CN 201610727569 A CN201610727569 A CN 201610727569A CN 106099827 A CN106099827 A CN 106099827A
Authority
CN
China
Prior art keywords
cable
main cable
line terminal
spark gap
connection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610727569.7A
Other languages
Chinese (zh)
Inventor
梁茂盛
卢义雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG XINWOM ELECTRICAL Co Ltd
Original Assignee
ZHEJIANG XINWOM ELECTRICAL Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG XINWOM ELECTRICAL Co Ltd filed Critical ZHEJIANG XINWOM ELECTRICAL Co Ltd
Priority to CN201610727569.7A priority Critical patent/CN106099827A/en
Publication of CN106099827A publication Critical patent/CN106099827A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G15/00Cable fittings
    • H02G15/08Cable junctions
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R43/00Apparatus or processes specially adapted for manufacturing, assembling, maintaining, or repairing of line connectors or current collectors or for joining electric conductors
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/14Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for joining or terminating cables

Abstract

The invention discloses complete thread guide devices in a kind of 10KV transformer platform area and preparation method thereof, connect on main cable and have the first pre-branched cable, the end of described first pre-branched cable is provided with connection spark gap terminated line terminal, one end of described main cable is provided with connection equipment end binding post, the other end connects connection conductor termination line terminals or disconnecting switch terminated line terminal, described connection equipment end binding post is located on main cable near the one end connecting spark gap terminated line terminal, described connection conductor termination line terminals or disconnecting switch terminated line terminal are located on main cable the one end away from spark gap terminated line terminal, it is additionally provided with electricity testing grounding ring on described main cable, electricity testing grounding ring is connecting between conductor termination line terminals and the first pre-branched cable.The present invention solves the Insulation Problems of the pre-branch of 10KV cable, it is possible to reduce in-site installation, on-the-spot professional and professional equipment can reduce even without.

Description

Complete thread guide devices in a kind of 10KV transformer platform area and preparation method thereof
Technical field
The present invention relates to field of cable technology, be specifically related to a kind of complete thread guide devices in 10KV transformer platform area and making thereof Method.
Background technology
Pre-branched cable is factory when producing main cable by the cable of user's design drawing prefabricated branch line, branch line Factory is previously fabricated on main cable, and branch line cross-sectional sizes and branch line length etc. are to require to determine according to design, advantage It is greatly to shorten construction period, Master Cost and operating expenses is greatly reduced, ensure that the reliability of distribution larger.
Only having 1KV and the pre-branch of following cable in the past, nobody develops the pre-branch of 10KV cable, and all 10KV cables need Branch all must use 10KV cable accessory to carry out insulation processing when connecting or connect equipment, needs the personnel of specialty and specialty Equipment.
Summary of the invention
The invention aims to make up the deficiencies in the prior art, it is provided that a kind of on-site construction time that reduces Complete thread guide devices in 10KV transformer platform area and preparation method thereof.
In order to reach the purpose of the present invention, technical scheme is as follows:
The complete thread guide devices in a kind of 10KV transformer platform area, has main cable, it is characterised in that on described main cable Connect and have the first pre-branched cable, the end of described first pre-branched cable to be provided with connection spark gap terminated line terminal, described One end of main cable is provided with connection equipment end binding post, the other end connects to have and connects conductor termination line terminals or keep apart Closing terminated line terminal, described connection equipment end binding post is located on main cable near connecting the one of spark gap terminated line terminal End, described connection conductor termination line terminals or disconnecting switch terminated line terminal are located on main cable and are terminated line end away from spark gap Son one end, described main cable is additionally provided with electricity testing grounding ring, electricity testing grounding ring be positioned at connection conductor termination line terminals and Between first pre-branched cable.
The manufacture method of the complete thread guide devices in a kind of 10KV transformer platform area, does pre-bifurcation to 10KV wire before dispatching from the factory Reason, comprises the following steps:
Use hydraulic pressure to be crimped on main cable and connect the first pre-branched cable;
Connection conductor termination line terminals is connected on main cable;
Use hydraulic pressure crimping that electricity testing grounding ring is installed;
Use hydraulic pressure crimping to install and connect spark gap terminated line terminal;
Install and connect equipment end binding post;
Each exposed end is carried out insulation processing.
The invention have the benefit that
Solving the Insulation Problems of the pre-branch of 10KV cable, it is possible to reduce in-site installation, on-the-spot professional and specialty set Standby can reduce even without.By former site preparation spark gap lead-in wire and installation binding post, installation electricity testing grounding ring, lead The work such as wire end line terminals (or disconnecting switch terminated line terminal), fuse terminated line terminal are fully integrated.
Accompanying drawing explanation
Fig. 1 is the structural representation of the complete thread guide devices in 10KV transformer platform area.
Detailed description of the invention
Below in conjunction with embodiment, the invention will be further described, but protection scope of the present invention is not limited solely to implement Example.
Shown in Fig. 1, the complete thread guide devices in a kind of 10KV transformer platform area, there is main cable 1, described main cable Connecting on 1 and have the first pre-branched cable 2, the end (upper end of Fig. 1) of described first pre-branched cable 2 is provided with connection spark gap Terminated line terminal 3, is used for connecting spark gap.One end of described main cable 1 be provided with connection equipment end binding post 4, another End connection has connection conductor termination line terminals 6 or disconnecting switch terminated line terminal, and master is located at by described connection equipment end binding post 4 On dry cable 1 near connect spark gap terminated line terminal 3 one end (upper end of Fig. 1), described connection conductor termination line terminals 6 or Disconnecting switch terminated line terminal is located on main cable 1 lower end of one end Fig. 1 away from spark gap terminated line terminal 3).Described master Being additionally provided with electricity testing grounding ring 5 on dry cable 1, electricity testing grounding ring 5 is positioned at connection conductor termination line terminals 6 and the first pre-branch electricity Between cable 2, and it is located close to connect the position of conductor termination line terminals 6.
The manufacture method of the complete thread guide devices in a kind of 10KV transformer platform area, comprises the following steps:
Use hydraulic pressure to be crimped on main cable 1 and connect the first pre-branched cable 2;
Connection conductor termination line terminals 6 is connected on main cable 1;
Use hydraulic pressure crimping that electricity testing grounding ring 5 is installed;
Use hydraulic pressure crimping to install and connect spark gap terminated line terminal 3;
Install and connect equipment end binding post 4;
Each exposed end is carried out insulation processing.
Last it is noted that above example only in order to the present invention is described and and unrestricted technology described in the invention Scheme, therefore, although this specification with reference to each above-mentioned embodiment to present invention has been detailed description, but, this Field it is to be appreciated by one skilled in the art that still the present invention can be modified or equivalent, and all without departing from this The technical scheme of the spirit and scope of invention and improvement thereof, it all should be contained in scope of the presently claimed invention.

Claims (2)

1. the complete thread guide devices in 10KV transformer platform area, has main cable (1), it is characterised in that described main cable Upper connection has the first pre-branched cable (2), the end of described first pre-branched cable to be provided with connection spark gap terminated line terminal (3), one end of described main cable is provided with connection equipment end binding post (4), the other end connects connection conductor wire end wiring Terminal (6), described connection equipment end binding post is located on main cable near the one end connecting spark gap terminated line terminal, institute State connection conductor termination line terminals and be located on main cable the one end away from spark gap terminated line terminal, on described main cable also Being provided with electricity testing grounding ring (5), electricity testing grounding ring is connecting between conductor termination line terminals and the first pre-branched cable.
The manufacture method of the complete thread guide devices in a kind of 10KV transformer platform area the most according to claim 1, it is characterised in that Before dispatching from the factory, 10KV wire is done pre-branch process, comprises the following steps:
Use hydraulic pressure to be crimped on main cable and connect the first pre-branched cable;
Connection conductor termination line terminals is connected on main cable;
Use hydraulic pressure crimping electricity testing grounding ring;
Use hydraulic pressure crimping to install and connect spark gap terminated line terminal;
Install and connect equipment end binding post;
Each exposed end is carried out insulation processing.
CN201610727569.7A 2016-08-24 2016-08-24 Complete thread guide devices in a kind of 10KV transformer platform area and preparation method thereof Pending CN106099827A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610727569.7A CN106099827A (en) 2016-08-24 2016-08-24 Complete thread guide devices in a kind of 10KV transformer platform area and preparation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610727569.7A CN106099827A (en) 2016-08-24 2016-08-24 Complete thread guide devices in a kind of 10KV transformer platform area and preparation method thereof

Publications (1)

Publication Number Publication Date
CN106099827A true CN106099827A (en) 2016-11-09

Family

ID=57226415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610727569.7A Pending CN106099827A (en) 2016-08-24 2016-08-24 Complete thread guide devices in a kind of 10KV transformer platform area and preparation method thereof

Country Status (1)

Country Link
CN (1) CN106099827A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107768109A (en) * 2017-11-28 2018-03-06 山东电工电气集团新能科技有限公司 A kind of prefabricated transformer of batch production with new lead wire and preparation method thereof
CN110212337A (en) * 2019-05-05 2019-09-06 贵州电网有限责任公司 A kind of 10kV distribution transforming rack prepackage type high pressure lead wire unit equipment

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3353007B1 (en) * 2001-08-28 2002-12-03 三菱電線工業株式会社 Branch connection method of cable and branch connector
CN2708520Y (en) * 2004-06-08 2005-07-06 奉化市奉金电力线路金具厂 Puncturing transformer earthing clip
CN201528061U (en) * 2009-10-13 2010-07-14 林良伟 Direct fine-adjustment type electricity-testing grounding ring
CN203607125U (en) * 2013-12-17 2014-05-21 加铝(天津)铝合金产品有限公司 Pre-branch cable
CN204732271U (en) * 2015-05-06 2015-10-28 江苏其厚智能电气设备有限公司 Integrated combination oil-immersed power transformer
CN105846195A (en) * 2016-05-26 2016-08-10 广州番禺电缆集团有限公司 Wiring device with grounding connector for electrical distribution box
CN106207530A (en) * 2016-08-24 2016-12-07 浙江新沃电气有限公司 The complete thread guide devices in a kind of 10KV transformer platform area

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3353007B1 (en) * 2001-08-28 2002-12-03 三菱電線工業株式会社 Branch connection method of cable and branch connector
JP2003070146A (en) * 2001-08-28 2003-03-07 Mitsubishi Cable Ind Ltd Branch connecting method for cable and branch connector
CN2708520Y (en) * 2004-06-08 2005-07-06 奉化市奉金电力线路金具厂 Puncturing transformer earthing clip
CN201528061U (en) * 2009-10-13 2010-07-14 林良伟 Direct fine-adjustment type electricity-testing grounding ring
CN203607125U (en) * 2013-12-17 2014-05-21 加铝(天津)铝合金产品有限公司 Pre-branch cable
CN204732271U (en) * 2015-05-06 2015-10-28 江苏其厚智能电气设备有限公司 Integrated combination oil-immersed power transformer
CN105846195A (en) * 2016-05-26 2016-08-10 广州番禺电缆集团有限公司 Wiring device with grounding connector for electrical distribution box
CN106207530A (en) * 2016-08-24 2016-12-07 浙江新沃电气有限公司 The complete thread guide devices in a kind of 10KV transformer platform area

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107768109A (en) * 2017-11-28 2018-03-06 山东电工电气集团新能科技有限公司 A kind of prefabricated transformer of batch production with new lead wire and preparation method thereof
CN110212337A (en) * 2019-05-05 2019-09-06 贵州电网有限责任公司 A kind of 10kV distribution transforming rack prepackage type high pressure lead wire unit equipment

Similar Documents

Publication Publication Date Title
CN103972825B (en) Manufacture method around packet mode transition joint
CN203734209U (en) Live working device for cable bypass
CN106099827A (en) Complete thread guide devices in a kind of 10KV transformer platform area and preparation method thereof
CN104021860B (en) A kind of aluminium alloy prefabricated branch cable and manufacture method thereof
CN105047274A (en) Prefabricated cable and cable assembly using prefabricated cable
CN106207530A (en) The complete thread guide devices in a kind of 10KV transformer platform area
CN110311265A (en) Low temperature resistant pre-fabricated electric cables
CN201629521U (en) Strengthened waterproof multi-core cable drawing device
CN205846394U (en) A kind of pre-fabricated electric cables
CN105789934A (en) Cable connector
CN101645548A (en) Method for grounding single-core high-voltage cable metal sheath
CN204423965U (en) A kind of multicore aluminium alloy pre-branched cable
CN205583173U (en) Cable connector
CN204190345U (en) 110kV and the cross interconnected protective earthing case of above band detection of electrical leakage type
CN102945703A (en) Pre-fabricated branch cable
CN201490354U (en) Grounding system of metal sheath of single-core high-voltage cable
CN204089143U (en) A kind of mineral cable list core intermediate connector
CN207587505U (en) A kind of prefabricated transformer of batch production with novel lead wire
CN202650673U (en) Auto-branch electric wire and cable
KR20110064775A (en) Sleeve for connecting two electric wires
CN206208928U (en) Intelligent substation phase tests Special test line
CN203674679U (en) Cable connector
CN104600533A (en) Internal wire margin control method of electric connector
CN107768109A (en) A kind of prefabricated transformer of batch production with new lead wire and preparation method thereof
CN203982873U (en) Elevator hoistways light conduits

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161109