CN106092348B - A kind of permafrost region winter angle geothermometer installation method and replacing options - Google Patents

A kind of permafrost region winter angle geothermometer installation method and replacing options Download PDF

Info

Publication number
CN106092348B
CN106092348B CN201610367975.7A CN201610367975A CN106092348B CN 106092348 B CN106092348 B CN 106092348B CN 201610367975 A CN201610367975 A CN 201610367975A CN 106092348 B CN106092348 B CN 106092348B
Authority
CN
China
Prior art keywords
angle
geothermometer
ground
mounting hole
angle geothermometer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610367975.7A
Other languages
Chinese (zh)
Other versions
CN106092348A (en
Inventor
王毅勇
夏克刚
文彦君
宋佃星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoji University of Arts and Sciences
Original Assignee
Baoji University of Arts and Sciences
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoji University of Arts and Sciences filed Critical Baoji University of Arts and Sciences
Priority to CN201610367975.7A priority Critical patent/CN106092348B/en
Publication of CN106092348A publication Critical patent/CN106092348A/en
Application granted granted Critical
Publication of CN106092348B publication Critical patent/CN106092348B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01KMEASURING TEMPERATURE; MEASURING QUANTITY OF HEAT; THERMALLY-SENSITIVE ELEMENTS NOT OTHERWISE PROVIDED FOR
    • G01K1/00Details of thermometers not specially adapted for particular types of thermometer
    • G01K1/14Supports; Fastening devices; Arrangements for mounting thermometers in particular locations

Abstract

The present invention proposes a kind of permafrost region winter angle geothermometer installation method and replacing options.Dig one for installing the mounting hole of angle geothermometer in earth's surface first, and the center line of the mounting hole with ground at an inclination angle, and the mounting hole bottom is useful for being inserted into the horizontal hole of angle geothermometer induction part;Angle geothermometer is put into mounting hole again, induction part is exposed to the north, and adjustment depth of the angle geothermometer bottom end induction part far from ground is required depth, fills up mounting hole with ground temperature observation field dry soil and is fixed.The tool used is simple, and method is practical.It solves at present in cold winter, once angle geothermometer is damaged, due to soil freezing, the angle geothermometer more renewed is very difficult, or even the problem of to interrupt several days observation data.Installation and replacement suitable for permafrost region winter angle geothermometer.

Description

A kind of permafrost region winter angle geothermometer installation method and replacing options
Technical field
The invention belongs to weather monitoring technical field, it is related to a kind of permafrost region winter angle geothermometer installation method and replacement Method.
Technical background
The soil moisture (ground temperature) is one of important monitoring index of agrology, ecology, agronomy and meteorology.The soil moisture Affect the growth of plant, the formation of development and soil.Various Biochemical processes in soil, as caused by microbial activities Biochemical processes and lifeless chemical process, are all influenced by the soil moisture.The acquisition of the soil moisture generally uses ground Thermometer (also known as 0cm thermometers), ground maximum thermometer, Soil surface minimum temperature table and angle geothermometer are observed, often Angle geothermometer one is cased with four, can measure the soil moisture of 5,10,15,20 centimetres of depth, is meteorological station observation The standard configuration of the soil moisture.
Angle geothermometer is typically mounted in Temperature Field, and by 5cm, 10cm, 15cm and 20cm depth orders are arranged from east to west Row, induction part are exposed to the north, and about 10cm is separated by between table, and table body and ground angle at 45 °, the table body of each table come into line along East and West direction, reveal The table body for going out ground is propped up with wooden (bamboo) frame of fork-shaped.
According to China Meteorological Administration《Surface weather observation specification》Requirement, on the ground that accumulated snow is shallower or the accumulated snow time is shorter Area can push snow aside observation when accumulated snow buries angle geothermometer;But the accumulated snow time is longer and the deeper area of accumulated snow, After accumulated snow buries angle geothermometer, that is, stop observation.Winter easily occurs to freeze the area of folding angle geothermometer, closes on and freezes in soil When, angle geothermometer should all be withdrawn, waits for temperature rise, be further continued for testing.
But under certain specific demands, it is also desirable to which area uses deeper for soil freezing, accumulated snow in winter.In these regional winters Once season, due to soil freezing, the angle geothermometer more renewed was just very difficult, very in use, angle geothermometer is damaged Extremely to interrupt several days observation data.
Invention content
For permafrost region winter have a soil moisture observation requirements and angle geothermometer do not allow after easy to install and damage it is inconvenient more The problem of changing, the present invention propose a kind of permafrost region winter angle geothermometer installation method and replacing options.
A kind of permafrost region winter angle geothermometer installation method digs one for installing angle geothermometer in earth's surface first Mounting hole, and the center line of the mounting hole and ground is at an inclination angle, and the mounting hole bottom is useful for being inserted into curved tube The horizontal hole of warm table induction part;Angle geothermometer is put into mounting hole again, induction part is exposed to the north, and adjusts curved tube ground temperature Depth of the table bottom end induction part far from ground is required depth, fills up mounting hole with ground temperature observation field dry soil and is fixed.
Permafrost region winter angle geothermometer installation method, is realized in accordance with the following steps:
(1) one or more angle geothermometers of preparedness plan installation;One drill rod;Hand hammer;The drying of ground temperature measurement field Soil;Hot water;
(2) it according to the buried depth of every angle geothermometer, calculates separately, measure the embedding depth of every angle geothermometer Mark is simultaneously carried out respectively in degree position;
(3) on observation field ground, the installation site of angle geothermometer is marked from east to west, between adjacent two angle geothermometers There is standoff distance;
(4) in the installation site of first angle geothermometer marked, drill rod insertion underground frozen soil layer is formed with hand hammer First mounting hole is watered against drill rod with kettle, allows hot water to be flowed into along drill rod and constantly rotate drill rod, the bottom of mounting hole The depth on identity distance ground is not less than required fitting depth, and center line and the ground of mounting hole form an inclination angle;
(5) then, first angle geothermometer is put into mounting hole, induction part is exposed to the north, and adjusts curved tube ground temperature Depth of the table bottom end induction part far from ground is required depth, and angle geothermometer and ground are at an inclination angle, with ground temperature observation field Dry soil fills up mounting hole and is fixed, and soil layer, which will accompany, not to interspace tightly, topsoil compacting;
(6) it is sequentially prepared second later mounting hole and angle geothermometer is installed, the same step of step (4) and step (5).
A kind of permafrost region winter angle geothermometer replacing options, implement in accordance with the following steps:
If encountering angle geothermometer damage during observation, the method for replacement is to pull out the angle geothermometer first half of fracture Point, if breaking portion more than upper soll layer, is close to be broken angle geothermometer root insertion soil with drill rod.With kettle pair It drill rod slowly to water, allows hot water to flow into soil along drill rod, while drill rod is firmly pressed original angle geothermometer installation direction, Namely 45 ° of angle is rotatably inserted into underground, this process is repeated, until depth reaches fitting depth.It waits for originally disconnected Split angle geothermometer under ground portion can freely activity when, clamped out with nipper pliers;If breaking portion upper soll layer with Under, it is embedded in drill rod in the soil hole of fracture angle geothermometer, is slowly watered against drill rod with kettle, allow hot water along drill rod It flows into soil, while drill rod is firmly pressed original angle geothermometer installation direction, that is, 45 ° of angle is to underground rotary insertion Enter.Note that if the breaking portion in drill rod and angle geothermometer soil is withstood, can fore-aft travel drill rod, be slightly staggered disconnected Split the breaking portion in angle geothermometer soil.This process is repeated, until depth reaches fitting depth.At this moment, originally The under ground portion for being broken angle geothermometer usually can be freely movable, can be clamped out with nipper pliers.Remaining same step (5) To (6).
Advantageous effect:The present invention proposes a kind of permafrost region winter angle geothermometer installation method and replacing options.It uses Tool it is simple, method is practical.It solves at present in cold winter, once angle geothermometer is damaged, due to soil freezing, The angle geothermometer more renewed is just very difficult, or even the problem of to interrupt several days observation data.Suitable for permafrost region winter The installation of angle geothermometer.
Description of the drawings
Fig. 1 is the angle geothermometer installation method installation effect diagram of the present invention.
Fig. 2 is the angle geothermometer replacing options for using the present invention, in three river station soil moisture observation January in 2004 more Change the 10cm ground thermometer instance datas of damage.
Specific implementation mode
A kind of 1 permafrost region winter angle geothermometer installation method of embodiment, step and condition are as follows:
(1) one or more angle geothermometers of preparedness plan installation;One long 40cm, the drill rod of diameter 1cm;Hand hammer; Nipper plier;The dry soil of ground temperature measurement field;Hot water;
(2) it according to the buried depth of every angle geothermometer, calculates separately, measure the embedding depth of every angle geothermometer Simultaneously mark is carried out with red paint in degree position respectively;
(3) on observation field ground, the installation site of angle geothermometer is marked from east to west, between adjacent two angle geothermometers Mutually it is divided into 10cm;
(4) in the installation site of first angle geothermometer marked, drill rod insertion underground frozen soil layer is formed with hand hammer First mounting hole is watered against drill rod with kettle, allows hot water to be flowed into along drill rod and constantly rotate drill rod, the bottom of mounting hole The depth on identity distance ground is not less than required fitting depth, center line and the ground angle at 45 ° of mounting hole;
(5) then, first angle geothermometer is put into mounting hole, induction part is exposed to the north, and adjusts curved tube ground temperature Depth of the table bottom end induction part far from ground is required depth, angle geothermometer and ground angle at 45 °, is done with ground temperature observation field Dry soil fills up mounting hole and is fixed, and soil layer, which will accompany, not to interspace tightly, topsoil compacting;
Since angle geothermometer induction part and table body there are 135 ° of oblique angles, if being inserted into difficulty, can not exert oneself by force, with Exempt to damage ground thermometer induction part, can be rotated in hole is installed with drill rod and expand hole, until can install;
(6) it is sequentially prepared second later mounting hole and angle geothermometer is installed, the same step of step (4) and step (5).
If encountering angle geothermometer damage during observation, the method for replacement is to pull out the angle geothermometer first half of fracture Point, if breaking portion more than upper soll layer, is close to be broken angle geothermometer root insertion soil with drill rod.With kettle pair It drill rod slowly to water, allows hot water to flow into soil along drill rod, while drill rod is firmly pressed original angle geothermometer installation direction, Namely 45 ° of angle is rotatably inserted into underground, this process is repeated, until depth reaches fitting depth.It waits for originally disconnected Split angle geothermometer under ground portion can freely activity when, clamped out with nipper pliers;If breaking portion upper soll layer with Under, it is embedded in drill rod in the soil hole of fracture angle geothermometer, if encountering angle geothermometer damage during being observed with kettle, The method of replacement is to pull out the angle geothermometer top half of fracture, if breaking portion more than upper soll layer, uses drill rod It is close to be broken angle geothermometer root insertion soil.It is slowly watered against drill rod with kettle, hot water is allowed to flow into soil along drill rod, Drill rod is firmly pressed original angle geothermometer installation direction simultaneously, that is, 45 ° of angle is rotatably inserted into underground, this process It is repeated, until depth reaches fitting depth.When the under ground portion of fracture angle geothermometer originally can be freely movable, use Nipper pliers clamp out;If breaking portion in upper soll layer hereinafter, with drill rod be embedded in fracture angle geothermometer soil hole in, It is slowly watered against drill rod with kettle, allows hot water to flow into soil along drill rod, while drill rod is firmly pressed original angle geothermometer Installation direction, that is, 45 ° of angle are rotatably inserted into underground.Note that if fracture in drill rod and angle geothermometer soil Part withstand, can fore-aft travel drill rod, be slightly staggered fracture angle geothermometer soil in breaking portion.This process is repeatedly It carries out, until depth reaches fitting depth.At this moment, originally the under ground portion of fracture angle geothermometer usually can freely live It is dynamic, it can be clamped out with nipper pliers.Remaining same step (4) to (5).
It slowly waters against drill rod, allows hot water to flow into soil along drill rod, while drill rod is firmly pressed original curved tube ground temperature Table installation direction, that is, 45 ° of angle are rotatably inserted into underground.Note that if disconnected in drill rod and angle geothermometer soil Split part withstand, can fore-aft travel drill rod, be slightly staggered fracture angle geothermometer soil in breaking portion.This process is anti- It is multiple to carry out, until depth reaches fitting depth.At this moment, originally the under ground portion of fracture angle geothermometer usually can be free Activity can be clamped out with nipper pliers.Remaining same step (5) to (6).
Fig. 2 is the concrete application example in scientific research department with angle geothermometer installation method of the invention.According to scientific research need It asks, in January, 2004 has carried out thin solum temperature at Sanjiang Plain ecology experiment station of the Chinese Academy of Sciences (three river stations) Observation, with 3 angle geothermometers, Observational depth is respectively 5cm, 10cm, 15cm, daily 8 points of progress soil moisture observation.Observation Place:Three rivers station comprehensive testing ground.The experiment station is located at Sanjiang Plain in Heilongjiang Province Bielahong basin.District center of standing geography is sat It is designated as 47.35N, 133.31E, height above sea level 55.6m, average temperature of the whole year is 1.9 DEG C, and the soil freezing phase is up to 7 months.
In the soil moisture observation in January, 2004,10cm angle geothermometers were damaged January 12, caused same day soil Earth 10cm temperature, which lacks, to be surveyed.Noon on the same day carries out replacement installation according to the method for the present invention, damage angle geothermometer nipper pliers It takes out, remaining same step (2) to (3).It can be with normal observation when 8 points of observation on January 13.

Claims (2)

1. a kind of permafrost region winter angle geothermometer installation method, it is characterised in that dig one for installing song in earth's surface first The mounting hole of pipe ground thermometer, and the center line of the mounting hole and ground is at an inclination angle, and the mounting hole bottom is useful for inserting Enter the horizontal hole of angle geothermometer induction part;Angle geothermometer is put into mounting hole again, induction part is exposed to the north, adjustment Depth of the angle geothermometer bottom end induction part far from ground be required depth, with ground temperature observation field dry soil fill up mounting hole into Row is fixed;
It realizes in accordance with the following steps:
(1) one or more angle geothermometers of preparedness plan installation;One drill rod;Hand hammer;The dry soil of ground temperature measurement field; Hot water;
(2) it according to the buried depth of every angle geothermometer, calculates separately, measure the embedding depth portion of every angle geothermometer Mark is simultaneously carried out respectively in position;
(3) on observation field ground, the installation site of angle geothermometer is marked from east to west, has phase between adjacent two angle geothermometers Gauge from;
(4) in the installation site of first angle geothermometer marked, drill rod insertion underground frozen soil layer is formed first with hand hammer A mounting hole is watered against drill rod with kettle, allows hot water to be flowed into along drill rod and constantly rotate drill rod, the bottom surface of mounting hole away from The depth on ground is not less than required fitting depth, and center line and the ground of mounting hole form an inclination angle;
(5) then, first angle geothermometer is put into mounting hole, induction part is exposed to the north, adjustment angle geothermometer bottom End depth of the induction part far from ground is required depth, and angle geothermometer, at an inclination angle, is dried with ground with ground temperature observation field Soil fills up mounting hole and is fixed, and soil layer, which will be trained, not to interspace tightly, topsoil compacting;
(6) it is sequentially prepared second later mounting hole and angle geothermometer is installed, the same step of step (4) and step (5).
2. a kind of permafrost region winter angle geothermometer replacing options, it is characterized in that implementing in accordance with the following steps:Pull out the song of fracture Pipe ground thermometer top half is embedded in the soil hole of fracture angle geothermometer with drill rod, if breaking portion is in upper soll layer More than, then it is close to be broken angle geothermometer root insertion soil with drill rod;Slowly watered against drill rod with kettle, allow hot water along Drill rod flows into soil, while firmly drill rod is rotatably inserted by original angle geothermometer installation direction to underground;This process is anti- It is multiple to carry out, until depth reaches fitting depth;When the under ground portion of fracture angle geothermometer originally can be freely movable, with point Mouth pliers clamps out;Remaining angle geothermometer installation method is the same as step in claim 1 (4) to (5).
CN201610367975.7A 2016-05-26 2016-05-26 A kind of permafrost region winter angle geothermometer installation method and replacing options Expired - Fee Related CN106092348B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610367975.7A CN106092348B (en) 2016-05-26 2016-05-26 A kind of permafrost region winter angle geothermometer installation method and replacing options

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610367975.7A CN106092348B (en) 2016-05-26 2016-05-26 A kind of permafrost region winter angle geothermometer installation method and replacing options

Publications (2)

Publication Number Publication Date
CN106092348A CN106092348A (en) 2016-11-09
CN106092348B true CN106092348B (en) 2018-10-16

Family

ID=57230257

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610367975.7A Expired - Fee Related CN106092348B (en) 2016-05-26 2016-05-26 A kind of permafrost region winter angle geothermometer installation method and replacing options

Country Status (1)

Country Link
CN (1) CN106092348B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110361108A (en) * 2019-06-19 2019-10-22 戴长雷 Cold low temp area ground temperature automated watch-keeping facility and monitoring method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877448A (en) * 2012-10-24 2013-01-16 中铁西北科学研究院有限公司 Deformation monitoring datum point device applicable to permafrost regions and method for mounting deformation monitoring datum point device
CN205262618U (en) * 2015-12-25 2016-05-25 北京师范大学 A quick installing support for angle geothermometer

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877448A (en) * 2012-10-24 2013-01-16 中铁西北科学研究院有限公司 Deformation monitoring datum point device applicable to permafrost regions and method for mounting deformation monitoring datum point device
CN205262618U (en) * 2015-12-25 2016-05-25 北京师范大学 A quick installing support for angle geothermometer

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
一种安装曲管地温表的方法;祝忠毅 等;《河南气象》;19951231(第4期);第41页 *

Also Published As

Publication number Publication date
CN106092348A (en) 2016-11-09

Similar Documents

Publication Publication Date Title
Irmak et al. Principles and operational characteristics of Watermark granular matrix sensor to measure soil water status and its practical applications for irrigation management in various soil textures
Palmer et al. Factors influencing permafrost temperatures across tree line in the uplands east of the Mackenzie Delta, 2004–2010
Lokoshchenko et al. Underground urban heat island below Moscow city
Schneider et al. Influence of surface and subsurface heterogeneity on observed borehole temperatures at a mountain permafrost site in the Upper Engadine, Swiss Alps
Wu et al. The thermal effect of differential solar exposure on embankments along the Qinghai–Tibet Railway
Williams et al. CBD-180 Ground Temperatures
CN110199604B (en) Method for preventing and treating salinization of soil in irrigation area based on freeze thawing effect
Adderley et al. Soils and palaeo-climate based evidence for irrigation requirements in Norse Greenland
Malloy et al. Fen restoration on a bog harvested down to sedge peat: A hydrological assessment
Greenwood et al. Evaporation from vegetation in landscapes developing secondary salinity using the ventilated-chamber technique: IV. Evaporation from a regenerating forest of Eucalyptus wandoo on land formerly cleared for agriculture
Abramov et al. Mountain permafrost on active volcanoes: field data and statistical mapping, Klyuchevskaya volcano group, Kamchatka, Russia
CN106092348B (en) A kind of permafrost region winter angle geothermometer installation method and replacing options
Starr et al. Real-time soil water dynamics over large areas using multisensor capacitance probes and monitoring system
Osterkamp et al. Evidence for a cyclic variation of permafrost temperatures in northern Alaska
Ng et al. Comparative study of rainfall infiltration into a bare and a grassed unsaturated expansive soil slope
CN106013181A (en) Expansive soil side slope protective method based on surface-layer moisture content control
CN205681812U (en) A kind of located fertilization instrument
Wilkison et al. Observations on preferential flow and horizontal transport of nitrogen fertilizer in the unsaturated zone
Cordeiro et al. Water table contribution and diurnal water redistribution within the corn root zone.
CN104730102A (en) Continuous temperature-change multi-stage gradient freezing instrument
CN107091701A (en) A kind of hard soil being easily installed or frozen soil geothermometry device
CN210323009U (en) Runoff pond for karst stony desertification area
Fyodorov-Davydov et al. Spatial and temporal observations of seasonal thaw in the northern Kolyma Lowland
Leonard et al. Accelerated snowmelt protocol to simulate climate change induced impacts on snowpack dependent ecosystems
Repelewska-Pękalowa et al. Active-layer dynamics at the Calypsostranda CALM site, Recherche Fiord region, Spitsbergen

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181016

Termination date: 20190526