CN106088088A - The stress decentralized stiffening pile of recyclable dowel and construction method thereof - Google Patents

The stress decentralized stiffening pile of recyclable dowel and construction method thereof Download PDF

Info

Publication number
CN106088088A
CN106088088A CN201610642167.7A CN201610642167A CN106088088A CN 106088088 A CN106088088 A CN 106088088A CN 201610642167 A CN201610642167 A CN 201610642167A CN 106088088 A CN106088088 A CN 106088088A
Authority
CN
China
Prior art keywords
dowel
anchoring
supporting body
prestressing force
traction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610642167.7A
Other languages
Chinese (zh)
Other versions
CN106088088B (en
Inventor
刘全林
张扬
张衡
刘斐然
叶由德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Qiangjin Foundation Engineering Co Ltd
Original Assignee
Shanghai Qiangjin Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Qiangjin Foundation Engineering Co Ltd filed Critical Shanghai Qiangjin Foundation Engineering Co Ltd
Priority to CN201610642167.7A priority Critical patent/CN106088088B/en
Publication of CN106088088A publication Critical patent/CN106088088A/en
Application granted granted Critical
Publication of CN106088088B publication Critical patent/CN106088088B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Abstract

The present invention provides the stress decentralized stiffening pile of a kind of recyclable dowel, comprises: anchoring body, prestressing force dowel, traction dowel and supporting body.Anchoring body is jet mixing soil-cement body or the cement mortar body of a major diameter;Supporting body is pushed in anchoring body by drilling rod;After anchoring body maintenance reaches design strength, to the construction prestressing force locking of prestressing force dowel;After anchoring mission completes, fixture is pulled in the cavity of supporting body by stretch-draw traction dowel, and prestressing force dowel is disconnected with supporting body;Traction machine is used all to reclaim out from the stratum of anchoring by dowel.Present invention also offers the construction method of this stiffening pile.The present invention constructs the dispersion of workable, stress, produces anchor force relatively big in weak soil, and anchoring reliability is high, and the response rate of dowel is high, high construction efficiency.Dowel and anchorage recycling, reduce engineering and make, remove underground obstacle, it is achieved that the greenization of anchoring construction technology.

Description

The stress decentralized stiffening pile of recyclable dowel and construction method thereof
Technical field
The present invention relates to technical field of civil engineering, particularly to the support pile used in Deep Foundation Pit Supporting Project.
Background technology
In the most conventional side slope and Deep Foundation Pit Supporting Project, prestress anchorage cable has higher anchor force, the stake of formation Anchor supporting construction is widely applied.But soft soil layer anchoring is the bottleneck of anchorage technology, because the frictional resistance of soft soil layer Low, it is easily generated rheology, these all limit the application of anchorage technology.In addition prestressing force dowel uses steel strand wires, in side slope After completing mission with foundation pit enclosure structure, often stay and form barrier in underground, which also limits the application of this kind of support form. To this end, form higher anchor force in soft soil layer, control the deflection of its weak soil, and complete it in supporting construction mission After, can reclaim out by dowel from the soil body, be an engineering circles difficult problem in the urgent need to address.
For soft soil layer, owing to the water content of weak soil is big, water level is the highest, and dowel all locates below level of ground water.When During Shi Hanzhang, traditional anchoring body diameter only has 100~150mm, less with the bond area of weak soil, in addition the rubbing of weak soil Resistance is relatively low, and the anchor force obtained should be relatively low.Additionally, the rheological property of soft soil layer, when the prestressing force applied is higher, stratum Rheological Deformation characteristic just show substantially, lead Deformation control effect relatively low.
Owing to the construction period requires tight, the curing period that general anchor rod anchored physical ability gives, is the shortest, strong at anchoring body When spending relatively low state, it is necessary to dowel therein carries out stretch-draw, anchoring body is usually made to be damaged by tension and compression.Less pre-when applying During stress, the control effect of deformation is the poorest.Accordingly, it would be desirable to anchor pole (rope) technology that research and development have higher anchor force is soft to meet The requirement of soil supporting.
From the point of view of the technical standard of current anchor pole (rope) supporting and the recovery technology level of anchor pole (rope), these recovery types Bolt support technology, is suitable for the most under certain conditions, as in rock and hard stratum, in the soil layer more than level of ground water Can application.From the point of view of current applicable cases, the response rate of anchor pole (rope) is the highest, typically can only achieve 50%, and different There are some problems in degree ground, such as: construction technology is numerous and diverse, labor strength is big, reclaim needed for equipment complexity is heavy, recovery Rate is relatively low.
For a kind of Recyclable anchor rope with enlarged footing anchor pole as representative, produce stress at enlarged footing and concentrate, on weak soil ground In Ceng, at enlarged footing, deformation and rheology are bigger, and the control to anchorage deformation is difficult.This anchor cable is by the steel of non-binding Twisted wire is around across on the carrier, and when the length of anchor cable is more than 20m, the resistance overcome when reclaiming anchor cable is equal to 2 times of anchor cable length * The frictional resistance of its unit length, extraction of need to turning round on U-shaped supporting body, total resistance that reclaims of generation has been likely larger than single anchor cable Limit stretching force, tensile phenomenon occurs, causes anchor cable all to reclaim.
The electric heating melting used at present unlocks the method reclaimed, and due to anchor cable, to be embedded in the underground time longer, and anchorage cable stretching becomes Shape is relatively big, the wire of energising may be made to be pulled off, it is impossible to electrified regulation, produces the phenomenon that cannot unlock.
Dismountable anchor cable and construction technology thereof, patent of invention number 201210485262.2, use the method unlocked to realize tearing open Unloading anchor cable, find out from Fig. 2 of its description, it is indoor that the anchor cable front portion of card locking is positioned at a big spherical hollow space, its card Not retraining with anchor cable, in installation process, when by axial compressive force effect, it is de-that anchor cable drives card to be easy to from lockhole Open, make work failure of cable.This kind of anchor cable occurs in that work failure of cable case in mono-pattern foundation pit supporting structure of Shenzhen Qian Hai, occurs The Important Project security incident that foundation ditch all collapses, this accident video spreads in the whole country, cause capital construction commission of Shenzhen to send the documents Disable this kind of anchor cable, it was demonstrated that this kind of anchor cable work unreliable.Further, since anchor head is wrapped around in anchoring body, anchoring body For soil cement or cement mortar body, can find from this patent Fig. 2, unlocking fixture block and be followed by bearing plate, the fixture block unlocking pull-out is Do not have position to move, fixture block be moved, it is necessary to bearing plate is moved together, and extrusion space could solve in anchoring body Lock, the pulling force of this unblock is very big, may be broken by drag-line, it is impossible to dismounting anchor cable.Outside it, the recovery line in this patent and unblock Connection between fixture block is Hard link (welding), or bonding, after pull-out unlocks fixture block, is difficult to free between recovery line and fixture block, The reliability reclaiming anchor cable is poor.In weak soil, the anchor cable of many soap-free emulsion polymeization is positioned on an anchor head, after Shi Hanzhang, and will Anchoring body (soil cement or cement mortar body) can be made damaged, cause fastening invalidation.
The anchor head of this patent there is also an issue, i.e. when anchor cable is through bearing plate, between anchor cable and anchor head cavity Seal approach is not show, in such high-pressure fluid environment, cement mortar, mud will enter into anchor head along anchor cable edge In, dismounting anchor head operation failure can be made.
In order to improve in soft soil layer, it is thus achieved that bigger anchor force, effectively control deformation, improve the response rate and ensure anchor Guan County is complete, in the urgent need to developing the prestressed anchor fixing structure of a kind of recyclable dowel, to realize the whole of anchoring safety and dowel Reclaim.
Summary of the invention
The technical problem to be solved is, overcome that existing anchor pole (rope) anchor force is relatively low, anchorage deformation is big and Dowel reclaims the technical problem and fault of construction existed, it is provided that one both provided higher anchor force, effectively controlled deformation, again can be square Just reclaim the stress decentralized stiffening pile of the recyclable dowel of anchor cable, also provide for the construction method of this stiffening pile simultaneously.In supporting After having acted on, can reclaim out from the soil body by dowel, make anchoring body depart from dowel, it is achieved the recycling of dowel, Barrier in the earth formation is stayed in removing, reduces the purpose of construction costs.
The technical scheme is that such to solve the problems referred to above:
The stress decentralized stiffening pile of recyclable dowel, comprises: anchoring body, is provided with prestressing force dowel, traction in anchoring body Dowel and supporting body, supporting body is cylindrical, the symmetrical a pair prominent earrings of outer rim;Supporting body upper cover is for holding out against prestressing force Dowel and the plectane of locking plate, lock fixture block and hold out against the mutual wedgewise of fixture block, and prestressing force dowel is anchored at carrying by locking plate symmetry Seat is with on locking fixture block, and traction dowel is anchored at by locking plate and middle holds out against in fixture block, and bottom is a cavity body;Prestressing force Dowel and traction dowel are the steel strand wires of soap-free emulsion polymeization.
Anchoring body is jet mixing soil-cement body or the cement mortar body of a major diameter, and its diameter is more than 150mm, length More than 3m.The anchoring body of major diameter adds the contact area of anchoring body and soft soil layer, although the frictional resistance of weak soil is the highest, but Bigger contact area can obtain higher anchor force, provides condition for obtaining bigger anchor force.
Supporting body is made up of high strength plastics or steel, uses a traction dowel to be connected on one between multiple supporting bodies Body, the prestressing force dowel in previous supporting body passes from the earrings hole outside later supporting body.
Being a cavity sealed by sealing member in supporting body, prestressing force dowel and traction dowel pass in and out position from supporting body Install a prominent round platform sealing device.
Connect a dispersion after supporting body, the active force that supporting body transmission comes is disperseed by longer dispersion In anchoring body;Dispersion is cylinder cage structure, is made up of high strength plastics.Described dispersion is for anchor in soft soil layer The dispersion measure that solid intensity is relatively low and takes, dispersion is installed on after supporting body, is made up of high strength plastics, in cylinder Cage, the active force that supporting body transmission is come, by contact surface bigger between self and anchoring body, distribute it to anchoring body In, in order to avoid anchoring body stress concentration causes damaged;
The anchorage intermediate arrangement that prestressing force dowel locks on Guan Liang or waist rail one draws the hole of traction anchor cable.
The construction method of the stress decentralized stiffening pile of recyclable dowel is as follows:
(1) with jet mixing rig or roof-bolter, the stratum of anchoring forms oblique a, soil cement for major diameter Or cement mortar stiffening pile anchoring body;
(2) install prestressing force dowel and traction dowel at supporting body, and carry out distinguishing mark.
(3) U-shaped spray head is connected with drilling rod, makes two whitewashing mouths of U-shaped spray head penetrate two ears of supporting body In Huan Yuan hole;
(4) utilize the thrust of drilling rod, supporting body is pushed in the anchoring body that will be formed, push process whitewashing drag reduction, take out Go out drilling rod process reinforcing of whitewashing, to improve intensity and the degree of compaction of anchoring body;
(5) when the soil cement anchoring body maintenance of major diameter reaches the intensity that design requires, combination jack pair is used not With the dowel Shi Hanzhang of length, it is locked on Guan Liang or the waist rail of supporting construction with anchorage;
(6) after supporting construction mission completes, first draw dowel with punching jack tension, fixture block will be held out against and be pulled into and hold In the cavity of carrier, the locking plate of prestressing force dowel and locking fixture block disengage, and make prestressing force dowel be disconnected with supporting body;
(7) unlock the anchorage on Guan Liang or waist rail, uses traction machine by prestressing force dowel together with traction dowel Reclaim out from the stratum of anchoring.
The described steel strand wires that prestressing force dowel is soap-free emulsion polymeization, are arranged in supporting body evenly;Steel strand wires are continuously without knot Point;The prestressing force applying prestressing force dowel is delivered on supporting body, by the anchoring body of supporting body outer wrapping to outside stratum Dispersion.
Beneficial effect: owing to its pulling force unlocked is much smaller than the pull-off force of every steel strand wires, easily realize safety mechanical Unlock.Reclaiming the length length equal to anchoring of pull-out anchor cable, the resistance of recovery does not has superposition.The time reclaimed is contracted significantly Short, the response rate reaches more than 99%.
Accompanying drawing explanation
The present invention is described in detail below in conjunction with the accompanying drawings with detailed description of the invention;
Fig. 1 is the stress decentralized stiffening pile structural representation of recyclable dowel of the present invention.
Fig. 2 is the internal structure section of the supporting body of the stress decentralized stiffening pile of recyclable dowel of the present invention Figure.
Fig. 3 is the internal structure plane of the supporting body of the stress decentralized stiffening pile of recyclable dowel of the present invention Figure.
Fig. 4 is that the supporting body of the stress decentralized stiffening pile of recyclable dowel of the present invention is illustrated with dispersion compositions Figure
Fig. 5 is that the series connection supporting body of the stress decentralized stiffening pile of recyclable dowel of the present invention pushes entrance anchoring Body process schematic
Fig. 6 is to unlock schematic diagram during the dowel recovery of the stress decentralized stiffening pile of recyclable dowel of the present invention.
Fig. 7 is that the prestressing force locking anchorage plane of the stress decentralized stiffening pile of recyclable dowel of the present invention is shown It is intended to.
Detailed description of the invention
For the technological means making the present invention realize, creation characteristic, reach purpose and be easy to understand with effect, below knot Conjunction is specifically illustrating, and the present invention is expanded on further.
Stiffening pile structure in the present embodiment is as it is shown in figure 1, substep has applied.Both can in harder soil layer shape Become, be provided that the anchor force of more than 500KN, it is possible to formed in weak soil layer is such as muck soil, it is provided that the anchor of more than 300KN Gu power, after completing support action, dowel can be reclaimed completely.
(1) with jet mixing rig or roof-bolter, formed in the stratum 16 needing anchoring one oblique, major diameter Soil cement or cement mortar stiffening pile anchoring body 1;
(2) install prestressing force dowel 2 and traction dowel 9 at supporting body 3, use between locking fixture block 61 and load bearing seat 62 Locking plate 4 locks prestressing force dowel 2;Holding out against fixture block 6 centre locking plate 4 locking traction dowel 9, as shown in Figures 2 and 3;Locking Fixture block 61 and hold out against fixture block 6 reverse wedge shape each other, is assembled by polylith.Need to carry out between prestressing force dowel 2 and traction dowel 9 Distinguishing mark.
(3) it is the active force that transmitted by supporting body of dispersion for soft soil layer, after supporting body 3, installs one point additional A prose style free from parallelism 17, such as Fig. 4.
(4) U-shaped spray head 14 is connected with drilling rod 13, makes two whitewashing mouths 15 of U-shaped spray head penetrate supporting body 3 In hole, two earrings 10 gardens, as shown in Figure 5;
(4) utilizing the thrust of drilling rod 13, be pushed to by supporting body 3 in the anchoring body 1 that will be formed, the whitewashing of propelling movement process subtracts Resistance, extracts drilling rod process reinforcing of whitewashing out, to improve intensity and the degree of compaction of anchoring body;Supporting body 3 is a hermetic knot Structure, plectane 5 above and cavity cap 7 below all realize sealing by sealing member 8, arrange during the turnover supporting body of dowel simultaneously Round table-like sealing device 11, as in figure 2 it is shown, the serosity so guaranteed in work progress can not penetrate into the inside of supporting body 3.
(5) when soil cement anchoring body 1 maintenance of major diameter reaches the intensity that design requires, combination jack pair is used not With the dowel Shi Hanzhang of length, it is locked on Guan Liang or the waist rail of supporting construction with anchorage 12, as shown in Figure 1;In order to allow Traction dowel is drawn, and sets a hole at anchorage center, as shown in Figure 7.
(6) after supporting construction mission completes, first draw dowel 9 with punching jack tension, make to hold out against fixture block 6 and locking Fixture block 61 departs from, and holds out against fixture block 6 and is connected in the cavity 7 being pulled into supporting body with traction dowel 9, the locking plate 4 of prestressing force dowel 2 Naturally disengage with locking fixture block 61, make prestressing force dowel 2 be disconnected with supporting body 3, as shown in Figure 6;
(7) unlock the anchorage 12 on Guan Liang or waist rail, uses traction machine by prestressing force dowel 2 and traction dowel 9 Reclaim out together from the stratum 16 of anchoring.
The ultimate principle of the present invention, principal character and advantages of the present invention have more than been shown and described.The technology of the industry Personnel, it should be appreciated that the present invention is not restricted to the described embodiments, simply illustrating this described in above-described embodiment and description The principle of invention, the present invention also has various changes and modifications without departing from the spirit and scope of the present invention, and these become Change and improvement both falls within scope of the claimed invention.Claimed scope by appending claims and Equivalent defines.

Claims (7)

  1. The stress decentralized stiffening pile of the most recyclable dowel, comprises: anchoring body, is provided with prestressing force dowel, traction anchor in anchoring body Muscle and supporting body, it is characterised in that supporting body is cylindrical, the symmetrical a pair prominent earrings of outer rim;Supporting body upper cover is Holding out against the plectane of prestressing force dowel and locking plate, lock fixture block and hold out against the mutual wedgewise of fixture block, prestressing force dowel is symmetrical by locking plate Being anchored at load bearing seat with on locking fixture block, traction dowel is anchored at by locking plate and middle holds out against in fixture block, and bottom is a sky Cavity;Prestressing force dowel and traction dowel are the steel strand wires of soap-free emulsion polymeization.
  2. The stress decentralized stiffening pile of recyclable dowel the most according to claim 1, it is characterised in that anchoring body is one The jet mixing soil-cement body of major diameter or cement mortar body, its diameter is more than 150mm, and length is more than 3m.
  3. The stress decentralized stiffening pile of recyclable dowel the most according to claim 1, it is characterised in that supporting body is by height Strong plastics or steel are made, and use a traction dowel to be connected on one between multiple supporting bodies, pre-in previous supporting body Stress dowel passes from the earrings hole outside later supporting body.
  4. The stress decentralized stiffening pile of recyclable dowel the most according to claim 1, it is characterised in that be one in supporting body The individual cavity sealed by sealing member, prestressing force dowel and traction dowel are provided with a prominent round platform from supporting body turnover position Sealing device.
  5. 5. according to the stress decentralized stiffening pile of the recyclable dowel described in right 1, it is characterised in that connect one after supporting body Dispersion, is distributed to the active force that supporting body transmission comes in anchoring body by longer dispersion;Dispersion is cylinder Cage structure, is made up of high strength plastics.
  6. The stress decentralized stiffening pile of recyclable dowel the most according to claim 1, it is characterised in that prestressing force dowel exists On Guan Liang or waist rail, the anchorage intermediate arrangement one of locking draws the hole of traction anchor cable.
  7. The construction method of the stress decentralized stiffening pile of the most recyclable dowel is as follows:
    (1) with jet mixing rig or roof-bolter, the stratum of anchoring forms oblique a, soil cement for major diameter or water Cement mortar stiffening pile anchoring body;
    (2) install prestressing force dowel and traction dowel at supporting body, and carry out distinguishing mark;
    (3) U-shaped spray head is connected with drilling rod, makes two whitewashing mouths of U-shaped spray head penetrate two earrings gardens of supporting body Kong Zhong;
    (4) utilize the thrust of drilling rod, supporting body is pushed in the anchoring body that will be formed, push process whitewashing drag reduction, extract out and bore Bar process reinforcing of whitewashing, to improve intensity and the degree of compaction of anchoring body;
    (5) when the soil cement anchoring body maintenance of major diameter reaches the intensity that design requires, use combination jack pair difference long The dowel Shi Hanzhang of degree, is locked on Guan Liang or the waist rail of supporting construction with anchorage;
    (6) after supporting construction mission completes, first draw dowel with punching jack tension, fixture block will be held out against and be pulled into supporting body Cavity in, the locking plate of prestressing force dowel and locking fixture block disengage, make prestressing force dowel be disconnected with supporting body;
    (7) unlock the anchorage on Guan Liang or waist rail, uses traction machine by prestressing force dowel and to draw together with dowel from anchor Solid stratum in reclaim out.
CN201610642167.7A 2016-08-08 2016-08-08 The construction method of the stress dispersing type stiffening pile of recyclable dowel Active CN106088088B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610642167.7A CN106088088B (en) 2016-08-08 2016-08-08 The construction method of the stress dispersing type stiffening pile of recyclable dowel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610642167.7A CN106088088B (en) 2016-08-08 2016-08-08 The construction method of the stress dispersing type stiffening pile of recyclable dowel

Publications (2)

Publication Number Publication Date
CN106088088A true CN106088088A (en) 2016-11-09
CN106088088B CN106088088B (en) 2018-11-20

Family

ID=57454693

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610642167.7A Active CN106088088B (en) 2016-08-08 2016-08-08 The construction method of the stress dispersing type stiffening pile of recyclable dowel

Country Status (1)

Country Link
CN (1) CN106088088B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677177A (en) * 2017-01-10 2017-05-17 上海强劲地基工程股份有限公司 Anchoring part with recyclable anchor bars
CN108018858A (en) * 2017-12-14 2018-05-11 上海智平基础工程有限公司 A kind of detachable prestressed anchor cable anchorage
CN108894221A (en) * 2018-09-25 2018-11-27 兰州理工大学 Reinforced anchor bolt and its recovery method can be recycled in two generation hands

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10176328A (en) * 1996-12-18 1998-06-30 V S L Japan Kk Removal anchor
CN101235645A (en) * 2007-01-30 2008-08-06 李乐 Reclaiming type anchor bar
CN202347500U (en) * 2011-11-30 2012-07-25 中国水利水电第八工程局有限公司 Integrated cable-penetrating guiding device for U-shaped anchor cable
CN102677670A (en) * 2011-03-11 2012-09-19 王立明 Dismountable-anchor type recoverable anchor rod
CN103046546A (en) * 2012-11-23 2013-04-17 浙江中桥预应力设备有限公司 Detachable anchor cable and construction process thereof
CN204370419U (en) * 2014-12-19 2015-06-03 姚炳祥 Removable pressure-type anchor head
CN204645035U (en) * 2015-04-03 2015-09-16 霍炳旭 A kind of carrying support body disperseing anchor cable pressure
CN205875150U (en) * 2016-08-08 2017-01-11 上海强劲地基工程股份有限公司 Stake of putting more energy into of stress dispersion type of recoverable dowel

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10176328A (en) * 1996-12-18 1998-06-30 V S L Japan Kk Removal anchor
CN101235645A (en) * 2007-01-30 2008-08-06 李乐 Reclaiming type anchor bar
CN102677670A (en) * 2011-03-11 2012-09-19 王立明 Dismountable-anchor type recoverable anchor rod
CN202347500U (en) * 2011-11-30 2012-07-25 中国水利水电第八工程局有限公司 Integrated cable-penetrating guiding device for U-shaped anchor cable
CN103046546A (en) * 2012-11-23 2013-04-17 浙江中桥预应力设备有限公司 Detachable anchor cable and construction process thereof
CN204370419U (en) * 2014-12-19 2015-06-03 姚炳祥 Removable pressure-type anchor head
CN204645035U (en) * 2015-04-03 2015-09-16 霍炳旭 A kind of carrying support body disperseing anchor cable pressure
CN205875150U (en) * 2016-08-08 2017-01-11 上海强劲地基工程股份有限公司 Stake of putting more energy into of stress dispersion type of recoverable dowel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677177A (en) * 2017-01-10 2017-05-17 上海强劲地基工程股份有限公司 Anchoring part with recyclable anchor bars
CN108018858A (en) * 2017-12-14 2018-05-11 上海智平基础工程有限公司 A kind of detachable prestressed anchor cable anchorage
CN108894221A (en) * 2018-09-25 2018-11-27 兰州理工大学 Reinforced anchor bolt and its recovery method can be recycled in two generation hands

Also Published As

Publication number Publication date
CN106088088B (en) 2018-11-20

Similar Documents

Publication Publication Date Title
CN108086334B (en) A kind of recyclable quick prestress anchorage cable and its construction method
CN106321119A (en) Double-layer anchor net cable supporting structure for controlling mining roadway surrounding rock deformation and method thereof
CN107060774A (en) A kind of anti-tunnel portal wall damage device and construction method
CN109441512B (en) Reinforced concrete through anchor cable and construction method thereof
CN204266121U (en) Button anchor system combinations formula pile foundation support table anchorage
CN102330427B (en) Stiffening pile with high uplift resistance
CN102587367A (en) Mechanical connection type anchor rod
CN106088088A (en) The stress decentralized stiffening pile of recyclable dowel and construction method thereof
CN108386217B (en) A kind of the automatic classification expansion head Pulling-Resistant Anchor Rod and its application method of reinforcing soft rock mass
CN103806446B (en) Internally-supporting expansion type anchor rod
CN114150664B (en) Rapid construction device and method for prestressed basalt fiber anchor rod
CN106050282A (en) Anchoring structure and reinforcing method of narrow coal pillar of gob-side entry retaining
CN205875150U (en) Stake of putting more energy into of stress dispersion type of recoverable dowel
CN101949151A (en) Recyclable locking anchor rod and construction method thereof
CN111926810A (en) Anchor recoverable waist-beam-free anchor cable supporting structure and construction method thereof
CN105626109B (en) It is a kind of that there is the method for repeating to apply prestressed cable bolting
CN212316915U (en) Recoverable no waist roof beam anchor rope supporting construction of ground tackle
CN112832837B (en) Method for supporting stoping roadway under close-range coal seam goaf
CN201801863U (en) Recyclable locking type anchor
CN205677538U (en) A kind of anchor bit of Recyclable anchor rope
CN105952381A (en) Anchor rod drill bit capable of recycling anchor cable
CN111926809A (en) Waist-beam-free supporting structure for rapid construction of pile-anchor supporting structure and construction method thereof
CN110725326A (en) Geotechnical engineering slope reinforcement device and method
Ping et al. Combined support technology of large section roadway in high-stress fractured surrounding rock
CN116517595B (en) Soft broken rock mass chamber reinforcing structure and method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant