CN106082573B - Gush polluted bed mud processing rubbish primary election system in river lake - Google Patents

Gush polluted bed mud processing rubbish primary election system in river lake Download PDF

Info

Publication number
CN106082573B
CN106082573B CN201610677024.XA CN201610677024A CN106082573B CN 106082573 B CN106082573 B CN 106082573B CN 201610677024 A CN201610677024 A CN 201610677024A CN 106082573 B CN106082573 B CN 106082573B
Authority
CN
China
Prior art keywords
bed mud
slurry transportation
tube
mud
branch pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610677024.XA
Other languages
Chinese (zh)
Other versions
CN106082573A (en
Inventor
芮建良
刘学武
辜晓原
卢驰江
张敏
丁时伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Eco Environmental Group Co Ltd
Original Assignee
Electric Environment Control Technology Co Ltd Jianshui
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Environment Control Technology Co Ltd Jianshui filed Critical Electric Environment Control Technology Co Ltd Jianshui
Priority to CN201610677024.XA priority Critical patent/CN106082573B/en
Publication of CN106082573A publication Critical patent/CN106082573A/en
Priority to PCT/CN2017/084960 priority patent/WO2018032828A1/en
Application granted granted Critical
Publication of CN106082573B publication Critical patent/CN106082573B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F11/00Treatment of sludge; Devices therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F7/00Equipment for conveying or separating excavated material

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Water Supply & Treatment (AREA)
  • Chemical & Material Sciences (AREA)
  • Organic Chemistry (AREA)
  • Mechanical Engineering (AREA)
  • Treatment Of Sludge (AREA)
  • Ocean & Marine Engineering (AREA)

Abstract

The invention provides a kind of river lake to gush polluted bed mud processing rubbish primary election system.The rubbish primary election system includes:First grid maker and the second grid maker, both are arranged in parallel;Bed mud slurry transportation main pipeline, its one end are used to be connected with the mud conveying pipeline of dredging plant;First bed mud slurry transportation branch pipe(tube), the other end of its one end bed mud slurry transportation main pipeline are connected, and the other end of the first bed mud slurry transportation branch pipe(tube) is connected with the first grid maker;Second bed mud slurry transportation branch pipe(tube), its one end is connected with the first bed mud slurry transportation branch pipe(tube), and the link position between the end and the first bed mud slurry transportation branch pipe(tube) is located at the bottom of the first bed mud slurry transportation branch pipe(tube), the other end of the second bed mud slurry transportation branch pipe(tube) is connected with the second grid maker.Apply the technical scheme of the present invention realize the building waste in bed mud mud and house refuse are classified after carry out separating treatment again.

Description

Gush polluted bed mud processing rubbish primary election system in river lake
Technical field
The present invention relates to water conservancy Treatment process field, in particular it relates at the beginning of polluted bed mud processing rubbish is gushed in a kind of river lake Select system.
Background technology
It is in water body and bed mud to be doped with natural cause and human action factor comprehensive role during existing river lake is gushed more A large amount of rubbish, including building waste and house refuse etc..In training of channel work progress is carried out, contained rubbish will be with thin Dredge mud together to dredge out, and can not realize and separate rubbish with bed mud.In the prior art using grid maker to dredging mud Removed the gred, i.e., separated rubbish from mud, but will be entrained with building waste and house refuse in the prior art Mud is together separated by grid maker.Therefore, can not together with the building waste being separated and domestic garbage mixing Realize the classification of building waste and house refuse.
The content of the invention
It is an object of the invention to provide a kind of river lake to gush polluted bed mud processing rubbish primary election system, it is intended to solves existing The problem of classification of building waste and house refuse can not be realized in technology.
In order to solve the above technical problems, the technical scheme is that:A kind of river lake is provided and gushes polluted bed mud processing rubbish Rubbish primary election system, including:First grid maker and the second grid maker, both are arranged in parallel;Bed mud slurry transportation main pipeline, its one end It is connected for the mud conveying pipeline with dredging plant;First bed mud slurry transportation branch pipe(tube), its one end bed mud slurry transportation supervisor The other end in road is connected, and the other end of the first bed mud slurry transportation branch pipe(tube) is connected with the first grid maker;Second bed mud mud Delivery branch pipe road is starched, its one end is connected with the first bed mud slurry transportation branch pipe(tube), and the end and the first bed mud slurry transportation branch Link position between pipeline is located at the bottom of the first bed mud slurry transportation branch pipe(tube), the second bed mud slurry transportation branch pipe(tube) it is another One end is connected with the second grid maker.
Further, the caliber of the first bed mud slurry transportation branch pipe(tube) is more than the caliber of bed mud slurry transportation main pipeline.
Further, the second bed mud slurry transportation branch pipe(tube) is the straight tube being vertically arranged.
Further, polluted bed mud processing rubbish primary election system is gushed in the river lake also includes the first shunting energy dissipating device and second Shunting energy dissipating device, the first shunting energy dissipating device are fixedly connected at the bed mud mud entrance of the first grid maker, the second shunting energy dissipating device It is fixedly connected at the bed mud mud entrance of the second grid maker, the outlet edge of the first shunting energy dissipating device and the bottom of the first grid maker Inwall at mud mud entrance has gap, the outlet edge of the second shunting energy dissipating device and the bed mud mud entrance of the second grid maker The inwall at place has gap.
Further, the first shunting energy dissipating device includes:Bowl-shape buffer component, bowl-shape buffer component are fixedly connected on the first lattice At the bed mud mud entrance of grid machine, the bottom of bowl-shape buffer component offers first and passes through mouth;Arc energy dissipation component, arc energy dissipating Component is fixedly connected at the bed mud mud entrance of the first grid maker, and the bottom of arc energy dissipation component towards bowl-shape buffer component is dashed forward Go out, the inwall at the bed mud mud entrance of the edge of arc energy dissipation component and the first grid maker has gap;Also, the second shunting Structure is identical between sinker and the first shunting energy dissipating device.
Further, multiple first drainage mouths by mouth around first are also provided with bowl-shape buffer component.
Further, multiple second drainage mouths are provided with arc energy dissipation component.
Apply the technical scheme of the present invention, rubbish primary election system effectively can be divided building waste and house refuse Class sorts, and so as to eliminate the heavy sorting work of follow-up work personnel, improves production capacity.
Brief description of the drawings
Fig. 1 is the structural representation that the embodiment of polluted bed mud processing rubbish primary election system is gushed in the river lake of the present invention;
Fig. 2 is Fig. 1 overlooking the structure diagram;
Fig. 3 is the bowl for the first sinker that the embodiment of polluted bed mud processing rubbish primary election system is gushed in the river lake of the present invention The overlooking the structure diagram of shape buffer component;
Fig. 4 is Fig. 3 A-A cross section structure diagram;
Fig. 5 is the arc for the first sinker that the embodiment of polluted bed mud processing rubbish primary election system is gushed in the river lake of the present invention The overlooking the structure diagram of shape energy dissipation component;
Fig. 6 is Fig. 5 B-B cross section structure diagram.
In the accompanying drawings:
10th, bed mud slurry transportation main pipeline;20th, the first bed mud slurry transportation branch pipe(tube);
30th, the second bed mud slurry transportation branch pipe(tube);40th, connecting line;100th, the first grid maker;
200th, the second grid maker;101st, the first shunting energy dissipating device;201st, the second shunting energy dissipating device;
111st, bowl-shape buffer component;112nd, arc energy dissipation component;51st, the first chain harrow tooth assembly;
52nd, the second chain harrow tooth assembly.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
It should be noted that when element is referred to as " being fixed on " or " being arranged at " another element, it can be directly another On one element or it is connected on another element.When an element is referred to as " being connected to " another element, it can be with It is directly to another element or is indirectly connected on another element.
It should also be noted that, the orientation term such as left and right, upper and lower in the present embodiment, be only each other relative concept or Using the normal operating condition of product as reference, and should not be regarded as restrictive.
As depicted in figs. 1 and 2, polluted bed mud processing rubbish primary election system is gushed in the river lake of the present embodiment includes the first grid The grid maker 200 of machine 100 and second, bed mud slurry transportation main pipeline 10 and the first bed mud slurry transportation branch pipe(tube) 20 and the second bed mud Slurry transportation branch pipe(tube) 30, one end of bed mud slurry transportation main pipeline 10 are used to be connected with the mud conveying pipeline of dredging plant, the One end of one bed mud slurry transportation branch pipe(tube) 20 is connected with the other end of bed mud slurry transportation main pipeline 10, the first bed mud mud Delivery branch pipe road 20 is connected with the first grid maker 100, one end and the first bed mud mud of the second bed mud slurry transportation branch pipe(tube) 30 Slurry delivery branch pipe road 20 is connected, and the end of the second bed mud slurry transportation branch pipe(tube) 30 and the first bed mud slurry transportation branch pipe(tube) 20 link position is located at bottom when the first bed mud slurry transportation branch pipe(tube) 20 is fixed, the second bed mud slurry transportation branch pipe(tube) 30 The other end be connected with the second grid maker 200, the first grid maker 100 and the second grid maker 200 are arranged in parallel.
Apply the technical scheme of the present invention, when bed mud slurry transportation main pipeline 10 is fixed, by by the second bed mud mud The one end in delivery branch pipe road 30 is connected to the bottom of the first bed mud slurry transportation branch pipe(tube) 20, because what is included in bed mud mud builds The gravity of building refuse is larger, such as erratic boulder, fragment of brick, gravel etc., and the gravity of house refuse is lighter, for example, polybag, duds thing, Pig hair etc., heavier building waste can convey under self gravitation effect along the bottom wall of bed mud slurry transportation main pipeline 10, and Lighter house refuse then with the flow velocity impulse force of bed mud mud, be mingled in bed mud mud among convey, so as in bed mud mud When starching the junction for flowing through bed mud slurry transportation main pipeline 10 and the second bed mud slurry transportation branch pipe(tube) 30, major part is heavier to build Building refuse can fall into the second bed mud slurry transportation branch pipe(tube) 30 and is separated into the second grid maker 200, and most of Lighter house refuse is then as bed mud mud is separated into the first grid maker 100.So, at the beginning of the rubbish of the present embodiment Select system building waste and house refuse effectively can be carried out into category sorting, it is heavy so as to eliminate follow-up work personnel Sorting work, improve production capacity.
As shown in figure 1, because bed mud mud has certain degree during bed mud slurry transportation main pipeline 10 conveys Flow velocity and fluid impingement force, in order to be more beneficial for allowing building waste to fall into the second bed mud slurry transportation branch pipe(tube) 30 In, therefore, the caliber of the first bed mud slurry transportation branch pipe(tube) 20 is more than the caliber of bed mud slurry transportation main pipeline 10, according to reality Flow velocity, pressure, flow and the bed mud slurry transportation main pipeline 10 and first for the bed mud mud that dredging plant conveying comes in production The parameters such as the caliber of bed mud slurry transportation branch pipe(tube) 20 carry out calculating determination, so as to be close to bed mud slurry transportation main pipeline 10 The building waste of channel bottom movement is fallen into the second bed mud slurry transportation branch pipe(tube) 30.Bed mud slurry transportation main pipeline 10 is excessive To the first bed mud slurry transportation branch pipe(tube) 20 caliber when, be connected by the excessive connecting tube of a taper flaring.
In order to make full use of the Action of Gravity Field of building waste to be built in the second bed mud slurry transportation branch pipe(tube) 30 Refuse classification, therefore, the second bed mud slurry transportation branch pipe(tube) 30 of the present embodiment can be straight tube, and the central axis of the straight tube Vertically set, such building waste will vertically fall into when moving to reach the second bed mud slurry transportation branch pipe(tube) 30 In two grid makers 200.In addition, the first grid maker 100 is connected to the first bed mud slurry transportation branch pipe(tube) 20 by connecting line 40 On, and connecting line 40 is the straight tube being vertically arranged.
With reference to shown in referring to Fig. 1 to Fig. 2, polluted bed mud processing rubbish primary election system is gushed using river lake provided by the present invention System is separated building waste and house refuse, therefore, is isolated by the first chain harrow tooth assembly 51 of the first grid maker 100 The rubbish come is mainly house refuse, and the rubbish master separated by the second chain harrow tooth assembly 52 of the second grid maker 200 To be building waste, the follow-up labour for carrying out manual sorting's building waste and house refuse is liberated to realize.
Gush in the river lake in polluted bed mud processing rubbish primary election system, because the fluid carry-over of bed mud mud is substantial amounts of Husky and mud, and corresponding grid maker is entered with larger pressure or larger flow velocity, bed mud mud is directly entered in grid maker The rake teeth that can then impact in grid maker, by rake teeth impact failure, in order to ensure rake teeth can from fluid impact and constantly Carry out sort rubbish work, thus the river lake gush polluted bed mud processing rubbish primary election system also include the first shunting energy dissipating device 101 and the second shunting energy dissipating device 201, the first shunting energy dissipating device 101 be fixedly connected on the bed mud mud entrance of the first grid maker 100 Place, the second shunting energy dissipating device 201 are fixedly connected at the bed mud mud entrance of the second grid maker 200, the first shunting energy dissipating device 101 Outlet edge and the first grid maker 100 bed mud mud entrance at inwall there is gap, the second shunting energy dissipating device 201 goes out Inwall at the bed mud mud entrance of mouth edge and the second grid maker 200 has gap.
Specifically, the structure composition of the first shunting energy dissipating device 101 in the present invention and the structure of the second shunting energy dissipating device 201 Form it is identical, wherein the first shunting energy dissipating device 101 includes bowl-shape buffer component 111 and arc energy dissipation component 112, bowl-shape buffering structure Part 111 and arc energy dissipation component 112 are fixedly connected with the bed mud mud entrance of the first grid maker 100, bowl-shape buffer component 111 bottom offers first and protruded by mouth, arc energy dissipation component 112 towards the bottom of bowl-shape buffer component, arc energy dissipating Inwall at the bed mud mud entrance of the edge of component 112 and the first grid maker 100 has gap.When bed mud slurry transportation is come in Afterwards, according to have high flow rate, large impact can bed mud mud fall in bowl-shape buffer component 111 and collide, and bowl-shape buffering Component 111 collects bed mud mud buffering flows to arc energy dissipation component 112 by first by mouth, and then bed mud mud arcuately disappears Can component 112 edge flow out and fall on the first chain harrow tooth assembly 51 or the second chain harrow tooth assembly 52 on carry out rubbish Sorting.
In order to make bed mud mud promptly be flowed in the first shunting energy dissipating device 101 or the second shunting energy dissipating device 201 By, so as to ensure herein can flow it is unimpeded, therefore, be also provided with bowl-shape buffer component 111 and set around first by mouth Multiple first drainage mouths, and multiple second drainage mouths are provided with arc energy dissipation component 112, bed mud mud in flow process, Flowed simultaneously by first by mouth, the first drainage mouth, the second drainage, and the edge of bed mud mud arcuately energy dissipation component 112 Outflow.Then, bed mud mud carries out refuse classification on the first chain harrow tooth assembly 51, the second chain harrow tooth assembly 52, and will Rubbish output carries out building waste and the classification of house refuse is stacked.
These are only presently preferred embodiments of the present invention, be not intended to limit the invention, it is all the present invention spirit and All any modification, equivalent and improvement made within principle etc., should be included in the scope of the protection.

Claims (5)

1. polluted bed mud processing rubbish primary election system is gushed in a kind of river lake, the building polluted bed mud is gushed suitable for sorting river lake Rubbish and house refuse, it is characterised in that including:
First grid maker (100) and the second grid maker (200), both are arranged in parallel;
Bed mud slurry transportation main pipeline (10), its one end are used to be connected with the mud conveying pipeline of dredging plant;
First bed mud slurry transportation branch pipe(tube) (20), its one end are connected with the other end of the bed mud slurry transportation main pipeline (10) Logical, the other end of the first bed mud slurry transportation branch pipe(tube) (20) is connected with first grid maker (100);
Second bed mud slurry transportation branch pipe(tube) (30), its one end are connected with the first bed mud slurry transportation branch pipe(tube) (20), And the link position between the end and the first bed mud slurry transportation branch pipe(tube) (20) is located at the first bed mud slurry transportation The bottom of branch pipe(tube) (20), the other end of the second bed mud slurry transportation branch pipe(tube) (30) and second grid maker (200) It is connected;
Gush polluted bed mud processing rubbish primary election system and also disappear including the first shunting energy dissipating device (101) and the second shunting in the river lake Energy device (201), the first shunting energy dissipating device (101) are fixedly connected on the bed mud mud entrance of first grid maker (100) Place, the second shunting energy dissipating device (201) is fixedly connected at the bed mud mud entrance of second grid maker (200), described The outlet edge of first shunting energy dissipating device (101) has with the inwall at the bed mud mud entrance of first grid maker (100) At the bed mud mud entrance of gap, the outlet edge of the second shunting energy dissipating device (201) and second grid maker (200) Inwall has gap;
The first shunting energy dissipating device (101) includes:Bowl-shape buffer component (111), the bowl-shape buffer component (111) is fixed to be connected It is connected at the bed mud mud entrance of first grid maker (100), the bottom of the bowl-shape buffer component (111) offers first Pass through mouth;
Arc energy dissipation component (112), the arc energy dissipation component (112) are fixedly connected on the bottom of first grid maker (100) At mud mud entrance, and the arc energy dissipation component (112) protrudes towards the bottom of the bowl-shape buffer component (111), the arc The edge of shape energy dissipation component (112) has gap with the inwall at the bed mud mud entrance of first grid maker (100);
Also, structure is identical between the second shunting energy dissipating device (201) and the first shunting energy dissipating device (101).
2. polluted bed mud processing rubbish primary election system is gushed in river lake as claimed in claim 1, it is characterised in that first bottom The caliber of mud slurry transportation branch pipe(tube) (20) is more than the caliber of the bed mud slurry transportation main pipeline (10).
3. polluted bed mud processing rubbish primary election system is gushed in river lake as claimed in claim 2, it is characterised in that second bottom Mud slurry transportation branch pipe(tube) (30) is the straight tube being vertically arranged.
4. polluted bed mud processing rubbish primary election system is gushed in river lake as claimed in claim 1, it is characterised in that described bowl-shape slow The multiple first drainage mouths being also provided with around described first by mouth are rushed on component (111).
5. polluted bed mud processing rubbish primary election system is gushed in river lake as claimed in claim 4, it is characterised in that the arc disappears Multiple second drainage mouths can be provided with component (112).
CN201610677024.XA 2016-08-16 2016-08-16 Gush polluted bed mud processing rubbish primary election system in river lake Active CN106082573B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201610677024.XA CN106082573B (en) 2016-08-16 2016-08-16 Gush polluted bed mud processing rubbish primary election system in river lake
PCT/CN2017/084960 WO2018032828A1 (en) 2016-08-16 2017-05-18 Preliminary waste sorting system for treating polluted sediment of river and lake mouth

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610677024.XA CN106082573B (en) 2016-08-16 2016-08-16 Gush polluted bed mud processing rubbish primary election system in river lake

Publications (2)

Publication Number Publication Date
CN106082573A CN106082573A (en) 2016-11-09
CN106082573B true CN106082573B (en) 2018-04-10

Family

ID=58069709

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610677024.XA Active CN106082573B (en) 2016-08-16 2016-08-16 Gush polluted bed mud processing rubbish primary election system in river lake

Country Status (2)

Country Link
CN (1) CN106082573B (en)
WO (1) WO2018032828A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106082573B (en) * 2016-08-16 2018-04-10 中电建水环境治理技术有限公司 Gush polluted bed mud processing rubbish primary election system in river lake

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201588237U (en) * 2009-10-26 2010-09-22 浙江方圆造船有限公司 Energy-dissipating device
CN103611721A (en) * 2013-12-04 2014-03-05 中联重科物料输送设备有限公司 Hydraulic separator and building waste material resource utilization system
CN105000783A (en) * 2015-07-31 2015-10-28 三川德青科技有限公司 Pipe duct sludge reduction and innocent treatment technology and device

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001288775A (en) * 2000-04-05 2001-10-19 Taisei Corp Gravel collecting device for transport pipe
CN202970557U (en) * 2012-11-26 2013-06-05 司军 Sedimentation-type sand-draining mud reclamation device
CN106082573B (en) * 2016-08-16 2018-04-10 中电建水环境治理技术有限公司 Gush polluted bed mud processing rubbish primary election system in river lake

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201588237U (en) * 2009-10-26 2010-09-22 浙江方圆造船有限公司 Energy-dissipating device
CN103611721A (en) * 2013-12-04 2014-03-05 中联重科物料输送设备有限公司 Hydraulic separator and building waste material resource utilization system
CN105000783A (en) * 2015-07-31 2015-10-28 三川德青科技有限公司 Pipe duct sludge reduction and innocent treatment technology and device

Also Published As

Publication number Publication date
CN106082573A (en) 2016-11-09
WO2018032828A1 (en) 2018-02-22

Similar Documents

Publication Publication Date Title
CN107327014B (en) A kind of anti-block apparatus of the pre-buried pipeline of water conservancy
CN106316020B (en) Gush polluted bed mud processing refuse classification regenerative system in river lake
CN104878829B (en) Anti-clogging inverted siphon sewage pipe system
CN106082573B (en) Gush polluted bed mud processing rubbish primary election system in river lake
CN107254863B (en) Joint sand discharge channel
CN203768875U (en) Centrifugal canal silt deposition device
CN106436880A (en) Road side rainwater drainage port anti-blocking rain-sewage separation well
CN208363229U (en) A kind of hydraulic engineering blow-off line
CN207871620U (en) Combine sedimentation basin
CN110227286A (en) A kind of hydrocyclone that can clear up solid in real time
CN206838512U (en) A kind of spiral knot screen for purified cotton processing
CN209907328U (en) Hydraulic guide type urban river garbage collection device
CN206731299U (en) A kind of mineralized waste fluidization sorting unit
CN206701480U (en) Super two sections of heavy medium cyclones of unpressurized feeding
CN206304484U (en) A kind of gas collector and delivery pipe filter net type desander
CN105148573B (en) A kind of sedimentation tank for sewage disposal
CN207605410U (en) Integral cyclone separator for mud and water
CN208594964U (en) Pressure relief device and back-filling system for underground filling plugging
CN209108682U (en) A kind of mudpan spoil disposal collection device
CN208023525U (en) A kind of drawing water structure of hydraulic and hydroelectric engineering
CN209556086U (en) A kind of water pipeline for hydraulic engineering
CN206746098U (en) A kind of sewage water filtration pipeline
CN205061026U (en) Dust material blowing recovery unit
CN206971165U (en) A kind of water conservancy municipal administration river closure works system blocks pond facility
CN207847629U (en) A kind of ore dust collecting

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 518000, Guangdong, Baoan District, Xin'an Xin'an Street 1003 Shenzhen Road, No. six financial port C block

Patentee after: China Power Construction Ecological Environment Group Co., Ltd

Address before: 518000, Guangdong, Baoan District, Xin'an Xin'an Street 1003 Shenzhen Road, No. six financial port C block

Patentee before: The electric environment control technology Co Ltd Jianshui