CN106056357A - Steel structure work installation progress real-time monitoring method and system - Google Patents

Steel structure work installation progress real-time monitoring method and system Download PDF

Info

Publication number
CN106056357A
CN106056357A CN201610372522.3A CN201610372522A CN106056357A CN 106056357 A CN106056357 A CN 106056357A CN 201610372522 A CN201610372522 A CN 201610372522A CN 106056357 A CN106056357 A CN 106056357A
Authority
CN
China
Prior art keywords
progress
data
installation
project
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610372522.3A
Other languages
Chinese (zh)
Inventor
何敏杰
杜兆宇
刘中华
王强强
徐立丰
余国华
李磊
赵切
胡梁军
孟玲霄
周兴东
卢继
俞奇效
郦宏伟
江涛
李娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jinggong Steel Structure Group Co Ltd
Original Assignee
Zhejiang Jinggong Steel Structure Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Jinggong Steel Structure Group Co Ltd filed Critical Zhejiang Jinggong Steel Structure Group Co Ltd
Priority to CN201610372522.3A priority Critical patent/CN106056357A/en
Publication of CN106056357A publication Critical patent/CN106056357A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K7/00Methods or arrangements for sensing record carriers, e.g. for reading patterns
    • G06K7/10Methods or arrangements for sensing record carriers, e.g. for reading patterns by electromagnetic radiation, e.g. optical sensing; by corpuscular radiation
    • G06K7/14Methods or arrangements for sensing record carriers, e.g. for reading patterns by electromagnetic radiation, e.g. optical sensing; by corpuscular radiation using light without selection of wavelength, e.g. sensing reflected white light
    • G06K7/1404Methods for optical code recognition
    • G06K7/1408Methods for optical code recognition the method being specifically adapted for the type of code
    • G06K7/14172D bar codes
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • General Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Primary Health Care (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Electromagnetism (AREA)
  • Toxicology (AREA)
  • Artificial Intelligence (AREA)
  • Computer Vision & Pattern Recognition (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a steel structure work installation progress real-time monitoring method and system. The method comprises the following steps: the first step: decomposing a plan into a plurality of project task plans and the types of members such as included A, B and C, etc; the second step: matching the data association onto the model member, and pasting the two-dimensional bar codes on the finished product steel member; the third step: scanning the two-dimensional bar codes and uploading the installation progress data; the fourth step: obtaining the progress data in real time by a server, and storing and excavating the data; the fifth step: determining each sub-project installation task plan by the system; and the sixth step: outputting the project predication progress result, and making specific measure for the on-site construction status. The steel structure work installation progress real-time monitoring method and system can solve the problems that the steel structure work progress is simple and rough in control and bad in effectiveness at this stage so as to realize the progress management and control of the whole work.

Description

A kind of structural steelwork installation progress method of real-time and system
Technical field
Patent of the present invention belongs to architectural engineering progress control research and development and application, is specifically related to a kind of structural steelwork peace Threading degree method of real-time and system, it is intended to solve the most rough, the effective difference of present stage structural steelwork progress control etc. Problem, thus realize the scientific real-time progress control to project.
Technical background
In recent years, along with structural steelwork application in building structure is more and more extensive, particularly in high-rise, physical culture In the heavy construction structures such as shop, railway station, terminal, these are in large scale, and the building of version complexity is to project progress pipe Reason proposes new challenge.But, existing Management of engineering schedule level can not meet the demand of maximization engineering, its prediction Accuracy is the highest, effective poor, and the latent defects such as technical threshold is high cause scene cannot reasonably formulate construction plan, grasp Construction speed, Optimizing construction resource and to the construction project time management of whole engineering and control.Therefore, it is achieved to structural steelwork What installation progress was real-time become more meticulous, information-based prediction seems that lattice are important.
Management of engineering schedule is related to Project Economy Benefit.Due to the complexity of work progress, dynamic, uncertainty etc. Factor so that in project implementing process, the prediction of progress is very big with control difficulty, and at present for the research shortage of schedule forecasting Clear and definite definition and effective solution.Therefore the present invention combines fuzzy algorithmic approach and realizes the Forecast reasoning to progress.Fuzzy Algorithm is a kind of New Algorithm grown up after key concept-membership function that first U.S. doctor L.A.Zadeh proposes. It does not focus on such as Formal Deduction based on axiom as classical logic or semantic computing based on assignment, but by obscuring The ordered set of instruction composition, according to the result of execution instruction, produces a kind of algorithm of given problem approximate solution.
The present invention is namely based on above-mentioned background, all develops a kind of structural steelwork installation progress side of monitoring in real time in design Method and system, structural steelwork installation progress real time informationization is managed and controls by real realization.
Summary of the invention
The problem that the invention aims to solve the existence of following present stage forecast of construction progress:
(1) schedule is abstract, and workload is big.Owing to gunter drawing, network planning figure calculate complexity, understand difficult, its every Business plan is numerous and complicated in a jumble, to obtain accurate forecast of construction progress, traditional manual mode can only be relied on to carry out progress The calculation amount of plan, but technical staff can increase the most loaded down with trivial details evaluation work, causes work efficiency to reduce, and loses more than gain.
(2) the most rough, effective poor.It is conventional that the method for tradition schedule forecasting is largely dependent upon project administrator Field experience, the method for this empirical is the most rough, is easily subject to the impact of subjective factors, lacks scientific theory foundation, And not from the real-time of progress monitoring, the accuracy causing schedule forecasting is the highest.
For realizing the purpose of the present invention, the present invention specifically provide a kind of structural steelwork installation progress method of real-time and System.
A kind of based on fuzzy algorithmic approach the structural steelwork installation progress method of real-time of the present invention, it includes walking as follows Rapid:
The first step: obtain structural steelwork schedule, be broken down into many sub-projects task scheduling and the A, the B that include, C ... wait element type;
Second step: erection schedule data association is matched on steel construction BIM model component, and on finished steel component, paste two Dimension bar code;
3rd step: when scene carries out Steel Structure Installation, is entered the two-dimensional bar code in different component type by data acquisition equipment Row scanning also uploads installation progress data;
4th step: server obtains progress data in real time, and stores data and excavate;
5th step: current each sub-project is installed task scheduling and judged by system, if plan is installed, then this installation current is appointed Business progression time is the maximum of T installing the beginning and ending timemax;If this plan is not installed, then system carries out K-to acquisition data in real time S inspection and data distributional analysis, extract feature Fuzzy rule, and when predicting non-installation component target advance by fuzzy algorithmic approach Between;
6th step: each sub-project erection schedule is obscured progression time and carries out collecting addition, output project forecast progress knot by system Really, site operation situation is formulated measure targetedly according to schedule forecasting result by project leader.
Described construction program is based on construction project to be built contract provision plan time, determines each sub-project plan Go into operation and the progression time that completes.
Described two-dimensional bar code is unique mark of information characteristics on arbitrary steel beam column, and it passes through technology of Internet of things, it is achieved right The management of the real-time progress of component.
Described K-S verifies as a kind of test of goodness of fit, and it, by acquisition progress data is carried out distributional difference analysis, comes Judge whether progress data result meets the distribution of formulation, thus extract the fuzzy rule of features of construction schedule, realize progress Prediction.
A kind of structural steelwork installation progress real-time monitoring system based on fuzzy algorithmic approach, described system includes:
Data acquisition module, in order to obtain arbitrary steel beam column installation progress data that data acquisition equipment is uploaded;
In order to the current each sub-project of real-time judge, data judge module, installs whether task scheduling is carried out;
Characteristic extracting module, in order to according to the progress data obtained, is extracted by fuzzy algorithmic approach and potential effective of mining data Feature and fuzzy rule, and then realize the schedule forecasting of antithetical phrase installation of project task scheduling;
Data outputting module, collects addition in order to each sub-project installation task is obscured progression time, exports project forecast progress Result.
Described fuzzy algorithmic approach, for data rule being converted into certain distribution by logical reasoning, will fuzzy set data be reflected Penetrate and determine value for prediction.
The beneficial effects of the present invention is:
1, real-time, the dynamic management of science of structural steelwork progress are realized.The present invention combines 2D bar code technology, passes through Internet of Things Net makes the progress msg of steel beam column transmit the most accurately, obtains the installation progress of structural steelwork the most in real time.
2, the schedule forecasting pattern that steel construction industry is traditional is changed.Maintenance data Mining Thought of the present invention, real by system Shi Zidong carries out fuzzy logic analysis to data, provides effective solution for schedule forecasting.
3, become more meticulous analysis and the prediction of progress are conducive to.Compensate for existing schedule forecasting the most rough, effective poor, skill The defects such as art threshold is high, the intelligentized accuracy that improve forecast of construction progress and science, enrich and expanded progress pipe The research of reason.
4, industry, the big market demand of enterprise are supported.Along with fast development and the popularization and application of big data, the present invention can be Enterprise, industry are internally formed complete engineering progress data and analyze system, and its big data mining analysis can promote enterprise, industry letter Breathization and scientific progress control, thus enterprise, the economic benefit of industry and social benefit further.
Accompanying drawing explanation
Fig. 1 is the system flow chart of the present invention.
Detailed description of the invention
The present invention is further described with case study on implementation below in conjunction with the accompanying drawings:
Case study on implementation flow process: see Fig. 1
A kind of structural steelwork installation progress method of real-time of the present invention and system have put into operation, high-rise with Hangzhou As a example by project, sketch a kind of structural steelwork installation progress real-time predicting method based on fuzzy algorithmic approach, specifically comprise the following steps that
The first step: system obtains Hangzhou high-rise steel structure construction program, is broken down into many sub-projects task scheduling Go into operation and complete progression time and the A that includes thereof, B, C ... wait element type
Second step: each sub-project erection schedule data association is matched on steel construction BIM model component by system, plant executive Finished steel component is pasted the two-dimensional bar code of unique information signature identification;
3rd step: when high-rise project construction scene, Hangzhou carries out Steel Structure Installation, on-the-spot director passes through data acquisition equipment Two-dimensional bar code in different component type is scanned and uploads installation progress data;
4th step: server obtains progress data in real time, and stores data and excavate;
5th step: current each sub-project is installed task scheduling and judged by system, if plan is installed, then this installation current is appointed Business progression time is the maximum of T installing the beginning and ending timemax;If this plan is not installed, then system carries out K-to acquisition data in real time S test of goodness of fit and data distributional analysis, and extract feature Fuzzy rule, predict non-installation component plan by fuzzy algorithmic approach Progression time;
6th step: each sub-project erection schedule is obscured progression time and carries out collecting addition, output project forecast progress knot by system Really, site operation situation is formulated measure targetedly according to schedule forecasting result by the high-rise project leader in Hangzhou.
The invention also discloses a kind of structural steelwork installation progress real-time monitoring system based on fuzzy algorithmic approach, described system System includes:
Data acquisition module, in order to obtain arbitrary steel beam column installation progress data that data acquisition equipment is uploaded;
In order to the current each sub-project of real-time judge, data judge module, installs whether task scheduling is carried out;
Characteristic extracting module, in order to according to the progress data obtained, data rule be converted into certain by logical reasoning and to be distributed, Extract the validity feature and fuzzy rule existed with mining data, and then the progress realizing antithetical phrase installation of project task scheduling is pre- Survey;
Data outputting module, collects addition in order to each sub-project installation task is obscured progression time, exports project forecast progress Result.
The technical threshold that instant invention overcomes the prediction of conventional steel Structural Engineering installation progress is high, and accuracy is low, effective poor Etc. defect, and a kind of based on fuzzy algorithmic approach the structural steelwork installation progress real-time predicting method of our company's research and development and system, Precisely in order to solve the problems referred to above and adapt to social reality needs and research and develop, present invention Successful utilization is in company's Project In, and achieve good Expected Results.
One of case that our company applies the method and system that what the case study on implementation of the present invention was announced is, but be not limited to This, the R&D personnel of this area, easily according to above-mentioned case study on implementation, understand the Technology Ways of the present invention, and make difference Amplification and change, but as long as without departing from the implementation path of the present invention and spirit, the most within the scope of the present invention.

Claims (5)

1. a structural steelwork installation progress method of real-time, it is characterised in that it comprises the steps:
The first step: obtain structural steelwork schedule, be broken down into many sub-projects task scheduling and include each Element type;
Second step: erection schedule data association is matched on steel construction BIM model component, and on finished steel component, paste two Dimension bar code;
3rd step: when scene carries out Steel Structure Installation, is entered the two-dimensional bar code in different component type by data acquisition equipment Row scanning also uploads installation progress data;
4th step: server obtains progress data in real time, and stores data and excavate;
5th step: current each sub-project is installed task scheduling and judged by system, if plan is installed, then this installation current is appointed Business progression time is the maximum of T installing the beginning and ending timemax;If this plan is not installed, then system carries out K-to acquisition data in real time S inspection and data distributional analysis, extract feature Fuzzy rule, and when predicting non-installation component target advance by fuzzy algorithmic approach Between;
6th step: each sub-project erection schedule is obscured progression time and carries out collecting addition, output project forecast progress knot by system Really, site operation situation is formulated measure targetedly according to schedule forecasting result by project leader.
A kind of structural steelwork installation progress method of real-time the most according to claim 1, it is characterised in that described two Dimension bar code is unique mark of information characteristics on arbitrary steel beam column, and it passes through technology of Internet of things, it is achieved progress real-time to component Management.
A kind of structural steelwork installation progress real-time predicting method the most according to claim 1, it is characterised in that described K- S verifies as a kind of test of goodness of fit, and it, by acquisition progress data is carried out distributional difference analysis, judges that progress data is tied Whether fruit meets the distribution of formulation, thus extracts the fuzzy rule of features of construction schedule, realizes the prediction to progress.
4. a structural steelwork installation progress real-time monitoring system, it is characterised in that described system includes:
Data acquisition module, in order to obtain arbitrary steel beam column installation progress data that data acquisition equipment is uploaded;
In order to the current each sub-project of real-time judge, data judge module, installs whether task scheduling is carried out;
Characteristic extracting module, in order to according to the installation progress data obtained, to extract by fuzzy algorithmic approach and mining data be potential Validity feature and fuzzy rule, and then realize the schedule forecasting of antithetical phrase installation of project task scheduling;
Data outputting module, collects addition in order to each sub-project installation task is obscured progression time, exports project forecast progress Result.
A kind of structural steelwork installation progress real-time estimate system the most according to claim 4, it is characterised in that described mould Stick with paste algorithm for data rule being converted into certain distribution by logical reasoning, fuzzy set data will be mapped as prediction and determine Value.
CN201610372522.3A 2016-05-31 2016-05-31 Steel structure work installation progress real-time monitoring method and system Pending CN106056357A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610372522.3A CN106056357A (en) 2016-05-31 2016-05-31 Steel structure work installation progress real-time monitoring method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610372522.3A CN106056357A (en) 2016-05-31 2016-05-31 Steel structure work installation progress real-time monitoring method and system

Publications (1)

Publication Number Publication Date
CN106056357A true CN106056357A (en) 2016-10-26

Family

ID=57173058

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610372522.3A Pending CN106056357A (en) 2016-05-31 2016-05-31 Steel structure work installation progress real-time monitoring method and system

Country Status (1)

Country Link
CN (1) CN106056357A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107092967A (en) * 2017-05-27 2017-08-25 武汉理工大学 A kind of ship part, EIC equipment identification code tracking system and method
CN107688908A (en) * 2017-09-06 2018-02-13 北京城乡建设集团有限责任公司 Study and judge the method and device of construction safety risk
CN108320107A (en) * 2018-02-09 2018-07-24 北京天元创新科技有限公司 A kind of web-based task scheduling establishment and execute system and method
CN109389358A (en) * 2018-08-23 2019-02-26 上海水顿智能科技有限公司 Project management system and method based on GIS
CN110378670A (en) * 2019-07-17 2019-10-25 重庆大学 A kind of spatial network technology model and its construction method and application

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103337005A (en) * 2013-05-31 2013-10-02 中建钢构有限公司 Management method for engineering progress and cost management system
CN104573999A (en) * 2015-01-30 2015-04-29 浙江精工钢结构集团有限公司 Application method of steel structure BIM (building information modeling) information platform

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103337005A (en) * 2013-05-31 2013-10-02 中建钢构有限公司 Management method for engineering progress and cost management system
CN104573999A (en) * 2015-01-30 2015-04-29 浙江精工钢结构集团有限公司 Application method of steel structure BIM (building information modeling) information platform

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李天华: "装配式建筑寿命周期管理中BIM与RFID应用研究", 《中国优秀硕士学位论文全文数据库》 *
胡青: "BIM信息技术在某地标建筑工程中的应用", 《山西建筑》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107092967A (en) * 2017-05-27 2017-08-25 武汉理工大学 A kind of ship part, EIC equipment identification code tracking system and method
CN107688908A (en) * 2017-09-06 2018-02-13 北京城乡建设集团有限责任公司 Study and judge the method and device of construction safety risk
CN108320107A (en) * 2018-02-09 2018-07-24 北京天元创新科技有限公司 A kind of web-based task scheduling establishment and execute system and method
CN109389358A (en) * 2018-08-23 2019-02-26 上海水顿智能科技有限公司 Project management system and method based on GIS
CN110378670A (en) * 2019-07-17 2019-10-25 重庆大学 A kind of spatial network technology model and its construction method and application

Similar Documents

Publication Publication Date Title
CN106056357A (en) Steel structure work installation progress real-time monitoring method and system
Dixit Impact of management practices on construction productivity in Indian building construction projects: An empirical study
Pavlovskis et al. Assessment of buildings redevelopment possibilities using MCDM and BIM techniques
Matos et al. COST Action TU 1406 quality specifications for roadway bridges (BridgeSpec)
Hu et al. BIM-based data mining approach to estimating job man-hour requirements in structural steel fabrication
Rui et al. Construction project management based on building information modeling (Bim)
Dziadosz The influence of solutions adopted at the stage of planning the building investment on the accuracy of cost estimation
Nowotarski et al. Lean and agile management synergy in construction of high-rise office building
Nurdiana et al. Assessing risk on the engineering procurement construction (EPC) project from the perspective of the owner: a case study
Gantner et al. Probabilistic approaches to the measurement of embodied carbon in buildings
Han et al. Implementation of construction performance database prototype for curtain wall operation in high-rise building construction
Singh et al. Analysis of labour productivity and determining the parameters which affects it in aluminium formwork system
Munir et al. Building Information Modelling (BIM) value realisation framework for asset owners
Koluksuz Effective project control within the context of lean construction
Okeniyi Project Sustainability: Overview of Sustainability in Project Management
Yousfi et al. Exploring the synergies between Life Cycle cost/Whole Life Cost and building information modeling: A systematic literature review
Kim et al. Evaluating Deterioration levels of utility poles using participatory sensing and fuzzy inference
Shatrova The choice of organizational and technological solutions based on the modeling option
Azimi et al. Resource performance indicators in controlling industrial steel projects
Lee Cost evaluation methodology that can be used in a 3D architectural design environment
Jacobsen et al. Forecasting Construction Labor Productivity Metrics
Farhan et al. Physical progress analysis of structure works using earned value management integrated with artificial neural network
Li et al. A Dynamic Measurement Model of Equipment Procurement Progress for Nuclear Power Project Based on EVM
TEO Productivity of construction project after IR4. 0 Norms
Zhang et al. Dynamic control method and application of coastal engineering project construction cost based on rough sets

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161026