CN106025925B - A kind of Operation Van of long-span electric transmission line maintenance - Google Patents

A kind of Operation Van of long-span electric transmission line maintenance Download PDF

Info

Publication number
CN106025925B
CN106025925B CN201610534644.8A CN201610534644A CN106025925B CN 106025925 B CN106025925 B CN 106025925B CN 201610534644 A CN201610534644 A CN 201610534644A CN 106025925 B CN106025925 B CN 106025925B
Authority
CN
China
Prior art keywords
cage
main wheel
wheel frame
door
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610534644.8A
Other languages
Chinese (zh)
Other versions
CN106025925A (en
Inventor
黄海东
成强
严佩锋
薛斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Maintenance Branch of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Maintenance Branch of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Maintenance Branch of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610534644.8A priority Critical patent/CN106025925B/en
Publication of CN106025925A publication Critical patent/CN106025925A/en
Application granted granted Critical
Publication of CN106025925B publication Critical patent/CN106025925B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Landscapes

  • Elevator Door Apparatuses (AREA)
  • Platform Screen Doors And Railroad Systems (AREA)

Abstract

The invention discloses a kind of Operation Van of long-span electric transmission line maintenance, including operation cage, the main wheel frame being horizontally arranged at the top of operation cage, and the head pulley being movably arranged on main wheel frame;Characterized in that, the length of main wheel frame is more than the length of operation cage;Head pulley is separately mounted to the both ends of main wheel frame;Also be hinged on operation cage to be provided with accessory whorl frame, the both ends of accessory whorl top of the trellis are separately installed with auxiliary pulley, bottom is provided with handle, and pulling handle can make accessory whorl frame rotate the mated condition for changing head pulley and cable around jointed shaft.The beneficial effects of the invention are as follows:Operation cage is directly fixedly connected with main wheel frame, alleviates and problem is rocked present in operation process;And main wheel frame has longer size, further improves the stability on direct of travel and avoids toppling;Possess the accessory whorl frame that can be rotated manually and change contact situation of the head pulley with cable so as to realize that obstacle detouring is without hindrance current.

Description

A kind of Operation Van of long-span electric transmission line maintenance
Technical field
The invention belongs to Maintenance of Electric Transmission Line technical field, and in particular to a kind of operation of long-span electric transmission line maintenance Car.
Background technology
Great span category tall and slender structure of the height more than 100 meters, in power transmission sequence Great span be primarily subjected to wind load, Earthquake load and installation load, wherein especially using Wind effects as Sheng.Rivers and lakes river seashore edge at the general position of Great span, wind environment are disliked It is bad, thus the dynamic response in the case where wind lotus acts on is particularly strong, therefore Great span often adds the group of stockbridge damper using dump wire clamp Close precautions against earthquakes.Due to the importance and particularity of Great span, eliminate Great span defect and often require that high standard, high efficiency.So And because Great span is towering, work high above the ground especially ground wire, optical cable operation, to operating personnel's psychological bearing capability and labor intensity Etc. being proposed high requirement, certain difficulty is caused for defect elimination work.
For ground line defect, the common driving outlet defect elimination mode of generally use.Common driving is by front and rear two pulley and support Frame forms.Operating personnel side is sat or ridden on support frame, and outlet is realized by front and rear two pulley.But common driving does not possess more Barrier ability.For Great span tower, defect elimination uses pin hook outlet method at present, during operation, will go out stitch and is hooked on ground wire, optical cable On, caprone cable is respectively fastened on the pin ring of bipod hook and makees balance rope, restrict along tower top frame aisle backward at about 20 meters with people Member's manipulation, to keep outlet personnel to be in stand up position all the time in outlet operation process, prevents from losing center of gravity.Outlet personnel stand To going out on stitch hook, a waist rope is beaten on optical cable (among two hooks), first carries lateral crus, pin hook moves forward 0.4~0.6m, mobile Waist rope, then inboard pin is carried, pin hook is moved forward, proceeds to setting defect elimination.Therefore, traditional defect elimination mode, operating personnel go along the line Enter not only to overcome that body is hanging, is difficult to the difficulty that makes power, and advance slowly, the outlet time is long, physical demands is big, work effect Rate is low, and the psychological pressure of personnel is huge.
The content of the invention
It is an object of the invention to overcome deficiency of the prior art, there is provided a kind of work of long-span electric transmission line maintenance Industry car, there is obstacle detouring current function, and possess higher stability, meet the job requirements under mal-condition.
To solve prior art problem, the invention discloses a kind of Operation Van of long-span electric transmission line maintenance, including Operation cage, the main wheel frame being horizontally arranged at the top of operation cage, and the head pulley being movably arranged on main wheel frame;Main wheel frame Length be more than operation cage length;Head pulley is separately mounted to the both ends of main wheel frame;It is also be hinged on operation cage to be provided with Accessory whorl frame, the both ends of accessory whorl top of the trellis are separately installed with auxiliary pulley, bottom is provided with handle, pull handle can make accessory whorl frame around Jointed shaft rotates the mated condition for changing head pulley and cable.
Preferably, operation cage includes the bottom plate stood for operating personnel, the cage fence being fixed on bottom plate, Yi Jizhuan The dynamic cage door on cage fence;Cage door can outwardly open around rotary shaft to be passed in and out for operating personnel, can also pass through cage Door lock mechanism on door movable end pins cage door and cage fence to ensure the safety of operating personnel.
Preferably, door lock mechanism includes lock strap, clamping screw, and locking nut;Two through holes, cage are offered in lock strap The movable end of door also offers through hole, and lock strap is enclosed on cage fence, and clamping screw can pass through the through hole in lock strap and cage door And it is screwed into the locking that locking nut realizes cage door.
Preferably, cage fence and cage door include the cross bar of montant and its protective action to play a supportive role, montant with By being welded and fixed at cross-car.
Preferably, the wheel groove depth of head pulley and auxiliary pulley is all higher than cable diameter.
Preferably, operation cage integrally uses symmetrical structure.
Preferably, lock strap is U-shaped structure, and two through holes in lock strap are coaxially so that clamping screw passes through.
Preferably, the center of the bottom of operation cage also installs stable lead additional.
The device have the advantages that:
1. operation cage is directly fixedly connected with main wheel frame, alleviates and problem is rocked present in operation process;And main wheel Frame has longer size, further improves the stability on direct of travel and avoids toppling;Possesses the accessory whorl that can be rotated manually Frame changes contact situation of the head pulley with cable so as to realize that obstacle detouring is without hindrance current.
2. realize the disengaging of operating personnel using cage door, and be equipped with door lock mechanism realize the locking of cage door and operation cage from And meet the requirement of safety work.
3. door lock mechanism is simple in construction, reliable and stable, all parts can be obtained by common procurement, reduce further Manufacturing cost.
4. the wheel groove depth of head pulley and auxiliary pulley is all higher than the diameter of cable, so that head pulley and auxiliary pulley and cable Coordinate more firm stable, avoid that off-line situation occurs during traveling so as to ensure safety of advancing.
5. operation cage integrally uses symmetrical structure, and is equipped with stable lead, so as to improve in operation process because making Stability during industry personnel activity, mitigate the psychological burden of operating personnel.
Brief description of the drawings
Fig. 1 is structural perspective when cage door of the present invention is closed;
Fig. 2 is the structural front view of the present invention;
Fig. 3 is the structure left view of the present invention;
Fig. 4 is the partial enlarged drawing at A in Fig. 1;
Fig. 5 is structural perspective when cage door of the present invention is opened.
Reference:
1 bottom plate;2 cage fences;3 cage doors;4 main wheel framves;5 head pulleys;6 accessory whorl framves;7 auxiliary pulley;8 handles;9 lock straps;10 Clamping screw;11 locking nuts;12 cables.
Embodiment
The invention will be further described below in conjunction with the accompanying drawings.Following examples are only used for clearly illustrating the present invention Technical scheme, and can not be limited the scope of the invention with this.
As shown in Fig. 1 to 5, a kind of Operation Van of long-span electric transmission line maintenance, including operation cage, it is horizontally arranged at Main wheel frame 4 at the top of operation cage, and the head pulley 5 being movably arranged on main wheel frame 4.
Operation cage includes the bottom plate 1 stood for operating personnel, the cage fence 2 being fixed on bottom plate 1, and rotates peace Cage door 3 on cage fence 2;Cage door 3 can outwardly open around rotary shaft to be passed in and out for operating personnel, can also pass through cage door Door lock mechanism on 3 movable ends pins cage door 3 and cage fence 2 to ensure the safety of operating personnel.Cage fence 2 and cage door 3 include the montant that plays a supportive role and the cross bar of its protective action, montant with cross-car by being welded and fixed.Operation cage Frame integrally uses symmetrical structure, and the center of its bottom also installs stable lead additional, so as to improve stability.
Door lock mechanism includes the lock strap 9 of U-shaped structure, clamping screw 10, and locking nut 11;Two are offered in lock strap 9 Individual coaxial through hole, the movable end of cage door 3 also offer through hole, and lock strap 9 is enclosed on cage fence 2, and clamping screw 10 can be worn Cross lock strap 9 and through hole in cage door 3 and be screwed into the locking that locking nut 11 realizes cage door 3.
The length of main wheel frame 4 is more than the length of operation cage, and head pulley 5 is separately mounted to the both ends of main wheel frame 4;Operation cage Also it is hinged on frame and accessory whorl frame 6 is installed, the both ends at the top of accessory whorl frame 6 is separately installed with auxiliary pulley 7, bottom is provided with handle 8, pull Fixed handle 8 can make accessory whorl frame 6 rotate the mated condition for changing head pulley 5 and cable 12 around jointed shaft.
The wheel groove depth of head pulley 5 and auxiliary pulley 7 is all higher than the diameter of cable 12, is prevented so that cable 12 is embedded in race bottom land Cable 12 departs from from race.
The operation principle and process of the present invention
Operating personnel locks cage door 3 after entering in operation cage, then manipulates Operation Van and is advanced along cable 12, when running into When wire clamp or stockbridge damper, control crank 8 make accessory whorl frame 6 rotate so that positioned at front the relative activity cage body of auxiliary pulley 7 decline, The head pulley 5 in the front of auxiliary pulley 7 is departed from cable 12, now just manipulate Operation Van and continue to make main cunning above forward Wheel 5 clears the jumps, and then rotates backward accessory whorl frame 6 again and makes the relative activity cage body of auxiliary pulley 7 above rise so as to depart from line Cable 12, then manipulating Operation Van makes the auxiliary pulley 7 also clear the jumps, and in this way all pulleys can be made to cross barrier successively Hinder thing so as to realize barrier free accessibility.
Described above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, without departing from the technical principles of the invention, some improvement and deformation can also be made, these are improved and deformation Also it should be regarded as protection scope of the present invention.

Claims (4)

1. a kind of Operation Van of long-span electric transmission line maintenance, including operation cage, are horizontally arranged at the top of operation cage Main wheel frame, and the head pulley being movably arranged on main wheel frame;Characterized in that, the length of main wheel frame is more than the length of operation cage Degree;Head pulley is separately mounted to the both ends of main wheel frame;It is also be hinged on operation cage that accessory whorl frame, the both ends of accessory whorl top of the trellis are installed Be separately installed with auxiliary pulley, bottom is provided with handle, pull handle can make accessory whorl frame around jointed shaft rotate change head pulley with The mated condition of cable;Operation cage includes the bottom plate stood for operating personnel, the cage fence being fixed on bottom plate, Yi Jizhuan The dynamic cage door on cage fence;Cage door can outwardly open around rotary shaft to be passed in and out for operating personnel, can also pass through cage Door lock mechanism on door movable end pins cage door and cage fence to ensure the safety of operating personnel;
Door lock mechanism includes lock strap, clamping screw, and locking nut;Two through holes, the movable end of cage door are offered in lock strap Also through hole is offered, lock strap is enclosed on cage fence, and the through hole that clamping screw can be through lock strap and in cage door is simultaneously screwed into locking Nut realizes the locking of cage door;
Lock strap is U-shaped structure, and two through holes in lock strap are coaxially so that clamping screw passes through;The center of the bottom of operation cage is also Install stable lead additional.
A kind of 2. Operation Van of long-span electric transmission line maintenance according to claim 1, it is characterised in that cage fence And cage door includes the montant that plays a supportive role and the cross bar of its protective action, montant with cross-car by being welded and fixed.
A kind of 3. Operation Van of long-span electric transmission line maintenance according to claim 1, it is characterised in that head pulley with The wheel groove depth of auxiliary pulley is all higher than cable diameter.
A kind of 4. Operation Van of long-span electric transmission line maintenance according to claim 1, it is characterised in that operation cage It is overall to use symmetrical structure.
CN201610534644.8A 2016-07-08 2016-07-08 A kind of Operation Van of long-span electric transmission line maintenance Active CN106025925B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610534644.8A CN106025925B (en) 2016-07-08 2016-07-08 A kind of Operation Van of long-span electric transmission line maintenance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610534644.8A CN106025925B (en) 2016-07-08 2016-07-08 A kind of Operation Van of long-span electric transmission line maintenance

Publications (2)

Publication Number Publication Date
CN106025925A CN106025925A (en) 2016-10-12
CN106025925B true CN106025925B (en) 2017-12-05

Family

ID=57108381

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610534644.8A Active CN106025925B (en) 2016-07-08 2016-07-08 A kind of Operation Van of long-span electric transmission line maintenance

Country Status (1)

Country Link
CN (1) CN106025925B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106602458A (en) * 2016-11-28 2017-04-26 国家电网公司 Portable obstacle-crossing high-voltage transmission line ground wire outlet device
CN110829277B (en) * 2019-11-21 2020-08-21 张华伟 Stringing auxiliary device for electric power engineering
CN114039305B (en) * 2021-11-11 2023-09-01 国网新疆电力有限公司乌鲁木齐供电公司 Adjustable transmission line overhauls driving device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5494132A (en) * 1994-02-14 1996-02-27 Hansen; Harry L. Side-loading suspension frame and ladder assembly for maintenance of energized power transmission lines
CN104577870A (en) * 2014-12-11 2015-04-29 国家电网公司 Automatic obstacle-crossing type overhead earth wire pay-off tool for maintenance
CN204680989U (en) * 2015-06-12 2015-09-30 国网四川省电力公司资阳供电公司 A kind of damping flying car for overhauling overhead ground wire
CN205846578U (en) * 2016-07-08 2016-12-28 国网江苏省电力公司检修分公司 A kind of Operation Van of long-span electric transmission line maintenance

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5494132A (en) * 1994-02-14 1996-02-27 Hansen; Harry L. Side-loading suspension frame and ladder assembly for maintenance of energized power transmission lines
CN104577870A (en) * 2014-12-11 2015-04-29 国家电网公司 Automatic obstacle-crossing type overhead earth wire pay-off tool for maintenance
CN204680989U (en) * 2015-06-12 2015-09-30 国网四川省电力公司资阳供电公司 A kind of damping flying car for overhauling overhead ground wire
CN205846578U (en) * 2016-07-08 2016-12-28 国网江苏省电力公司检修分公司 A kind of Operation Van of long-span electric transmission line maintenance

Also Published As

Publication number Publication date
CN106025925A (en) 2016-10-12

Similar Documents

Publication Publication Date Title
CN106025925B (en) A kind of Operation Van of long-span electric transmission line maintenance
CN105337218B (en) A kind of transmission line of electricity lowering or hoisting gear
CN104967050B (en) Electronic manned driving can be drawn
CN104577870B (en) A kind of active obstacle type overhauls property-line driving
CN205846578U (en) A kind of Operation Van of long-span electric transmission line maintenance
CN106215384A (en) Concrete bar climbing work platforms and climbing device thereof
CN208561580U (en) A kind of electric power well lid opening and closing vehicle
DE102010043199A1 (en) Device and method for mounting a rotor to the drive train of a wind turbine
CN211450103U (en) Large wide-angle security monitoring camera
CN107212673A (en) It is a kind of electric up-down bed
CN204243623U (en) A kind of active obstacle type maintenance property-line driving
CN211470690U (en) Special combined hanging basket for equipotential operation of multi-loop vertically-arranged wires
CN204607534U (en) Electric force pole tower or line bar machinery climbing device
CN113879418A (en) Cross locking type robot for climbing telegraph pole
CN208632051U (en) A kind of hanging basket for the maintenance of high tower lamp
CN205687439U (en) A kind of Large Towers machine travel dolly tensioner
CN206720273U (en) A kind of conveying pipeline lift rotary platform
CN207194431U (en) Attachment type raise scaffold spring linkage fall arrest wall-attached supporting seat
CN202081372U (en) Suspension bridge for passage of amusement submarine
CN205778610U (en) A kind of lateral aperture or inclined hole drilling tool jacking system
CN206502569U (en) A kind of automatic hydraulic tripping gear
CN206992588U (en) A kind of moveable double bundle conductor Distance limiter
CN208995161U (en) A kind of Novel steel wire rope grid transmission mechanism
CN106654985B (en) A kind of straight line pole fall block
CN110775901B (en) Combined hanging basket special for equipotential operation of multi-loop vertical arrangement wires

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 210000, Jiangsu, Jiangning Development Zone, Nanjing, the source of the road, No. 58, -5

Co-patentee after: STATE GRID JIANGSU ELECTRIC POWER COMPANY

Patentee after: National network Jiangsu Electric Power Co., Ltd. maintenance branch

Co-patentee after: State Grid Corporation of China

Address before: 210000, Jiangsu, Jiangning Development Zone, Nanjing, the source of the road, No. 58, -5

Co-patentee before: STATE GRID JIANGSU ELECTRIC POWER COMPANY

Patentee before: State Grid Jiangsu Electric Power Company Maintenance Branch Company

Co-patentee before: State Grid Corporation of China