CN106013669A - Wallboard installation structure and method - Google Patents
Wallboard installation structure and method Download PDFInfo
- Publication number
- CN106013669A CN106013669A CN201610507418.0A CN201610507418A CN106013669A CN 106013669 A CN106013669 A CN 106013669A CN 201610507418 A CN201610507418 A CN 201610507418A CN 106013669 A CN106013669 A CN 106013669A
- Authority
- CN
- China
- Prior art keywords
- wallboard
- wall
- installing tache
- installation
- installation portion
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0889—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements characterised by the joints between neighbouring elements, e.g. with joint fillings or with tongue and groove connections
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0801—Separate fastening elements
- E04F13/0832—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements
- E04F13/0833—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements not adjustable
- E04F13/0851—Hooking means on the back side of the covering elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F2201/00—Joining sheets or plates or panels
- E04F2201/02—Non-undercut connections, e.g. tongue and groove connections
- E04F2201/026—Non-undercut connections, e.g. tongue and groove connections with rabbets, e.g. being stepped
Abstract
The invention relates to a wallboard installation structure and method. The structure comprises a wallboard, a wall body and a wallboard installation buckle. The wallboard is in a long-strip shape. The lower end of the wallboard installation direction is a plug-in end. The upper end of the wallboard installation direction is a bell end. A downward-protruding first protruding strip is arranged at the plug-in end. The inner side of the first protruding strip is provided with a first gap which extends upwards and is adjacent to the wall body. A positioning groove is formed in the bell end of the wallboard. The wallboard installation buckle comprises a supporting portion, an installation portion and a connecting portion for connecting the installation portion with the supporting portion. The supporting portion is located below the installation portion, a supporting groove is formed in the supporting portion, and a connecting hole is formed in the installation portion; the supporting portion is matched with the positioning groove, the first protruding strip is matched with the supporting groove, and the connecting portion of the wallboard installation buckle is fixed to the wall body through a self-tapping screw. Before an adhesive achieves the best adhesive strength, reliable connection of the wallboard is achieved.
Description
Technical field
The present invention relates to the realm of building construction, particularly relate to mounting structure and the installation method of wallboard.
Background technology
When wallboard is installed, bonding with metope by adhesive, and owing to adhesive solidification reaches optimal bonding force
Needing the regular hour, in the process, wallboard can be slid down by effect of weight.Therefore when wallboard is installed,
Typically install from the bottom up, and need etc. the wallboard of bottom paste completely fixing after be further continued for up installing phase
Adjacent wallboard.Installation period is longer.
Summary of the invention
In order to solve the problems referred to above, it is an object of the invention to provide a kind of reliable wallboard of mounting structure and install
Structure and installation method.
In order to realize above-mentioned purpose, present invention employs following technical scheme:
The mounting structure of wallboard, including wallboard, body of wall and wallboard installing tache;Wallboard is strip;Wallboard is pacified
Dress direction on lower end be plug-in unit end, the upper end on wallboard installation direction is bell end, plug-in unit end be provided with to
Lower the first prominent raised line, the inner side of the first raised line is provided with and upwardly extends and first breach adjacent with body of wall,
Described first breach is made up of a lateral wall and a diapire, and the lateral wall of the first breach is i.e. the first raised line
Medial wall;The bell end of wallboard is provided with locating slot;
Wallboard installing tache includes supporting part, installation portion and for connecting the connecting portion of installation portion and supporting part;?
Support part is positioned at the lower section of installation portion, and supporting part is provided with support slot, and installation portion is provided with connecting hole;
Described supporting part coordinates with described locating slot, and described first raised line coordinates with described support slot, and wallboard is pacified
Dress is buckled in connecting portion and is fixed on body of wall by tapping screw.
Described wallboard installing tache passes through metal sheet bending forming;
Described wallboard installing tache is strip, and connecting portion is evenly distributed with multiple connecting hole.
The installation method of wallboard, including wallboard as above, body of wall and wallboard installing tache, wallboard from lower toward
Upper installation, comprises the following steps: 1) lower section wallboard with bell end upward, plug-in unit end pass down through adhesive glue
It is attached on body of wall;2) support slot of wallboard installing tache is inserted in the locating slot of lower section wallboard bell end, by wall
The installation portion of plate installing tache is affixed with body of wall, and fixes with self-tapping screw;3) by the of top wallboard plug-in unit end
One raised line inserts in the support slot of wallboard installing tache, and is pasted onto on body of wall by adhesive by top wallboard;4)
Repeat step 2) and step 3) wallboard is installed from the bottom up to all wallboard installations;
In above-mentioned steps, after two neighbouring wallboards and wallboard installing tache installation, wallboard installing tache
Installation portion and the self-tapping screw that is fixed on installation portion nut wallboard above the first breach in.
The mounting structure of above-mentioned wallboard, sets up, between two neighbouring wallboards, the wall being fixed on body of wall
Plate installing tache, supports top wallboard by wallboard installing tache when adhesive is not fixed, it is ensured that wallboard is in peace
Dress overall process does not haves position skew, connects reliable.Meanwhile, structure and the wallboard of wall panel ends are set
The structure matching of installing tache, after wallboard installation, attachment structure and wallboard installing tache between wallboard all can not
Being seen, structure is attractive in appearance.
Accompanying drawing explanation
Fig. 1 is the cross-sectional view of the present invention.
Fig. 2 is enlarged drawing at the A in Fig. 1.
Fig. 3 is the structural representation of the wallboard installing tache in the present invention.
Wherein: 1, wallboard, 2, body of wall, 3, wallboard installing tache, 4, self-tapping screw, the 11, first raised line, 12,
First breach, 13, locating slot, 31, support slot, 32, connecting portion, 33, installation portion, 331, installing hole.
Detailed description of the invention
Below in conjunction with the accompanying drawings the preferred embodiment of this patent is described in further detail.In the application
Wallboard is buckled wallboard, and wallboard is vertically pasted onto on body of wall, therefore, and the retouching about orientation of the application
Stating after being arranged on body of wall with wallboard as reference standard, the wallboard side bonding with body of wall is inner side, with inner side
Relative side is outside.
The mounting structure of a kind of wallboard as depicted in figs. 1 and 2, installs including wallboard 1, body of wall 2 and wallboard
Button 3.Wallboard 1 is strip, and the long limit of wallboard 1 is horizontally arranged on body of wall 2.One end of wallboard 1 is slotting
Part end, the other end of wallboard 1 is bell end, is provided with downward projection of first raised line 11 at plug-in unit end, first
The inner side of raised line 11 is provided with and upwardly extends and first breach 12 adjacent with body of wall 2.Described first breach 12
Being made up of a lateral wall and a diapire, lateral wall is perpendicular to diapire, and the lateral wall of the first breach 12 is i.e.
The medial wall of the first raised line 11.The bell end of wallboard 1 is provided with locating slot 13.When mounted, the holding of wallboard 1
Upward, plug-in unit end is down for spigot end.
Being connected by wallboard installing tache 3 between two neighbouring wallboards 1, wallboard installing tache 3 is for upper
The wallboard 1 of side play supporting role.As it is shown on figure 3, wallboard installing tache 3 includes support slot 31, installation portion 33
And for connecting the connecting portion 32 of installation portion 33 and support slot 31.The two ends of connecting portion 32 connect installation respectively
The lower end in portion 33 and the upper end of support slot 31.Support slot 31 is placed at the locating slot of lower section wallboard 1 bell end
In 13, the first raised line 11 of top wallboard inserted terminal inserts in support slot 31.Installation portion 33 is provided with installation
Hole 331, wallboard installing tache 3 is fixed on body of wall 2 by self-tapping screw 4 at installation portion 33.In phase up and down
Installing wallboard installing tache 3 between two adjacent wallboards 1, the adhesive between body of wall 2 and wallboard 1 is uncured
The position of prelocalization wallboard 1, prevents from causing not due to stickiness in the curing process top wall due to adhesive
There is position skew in plate.
The installation of wallboard comprises the following steps: 1) by lower section wallboard 1 with bell end upward, plug-in unit end leads to down
Cross adhesive to be pasted onto on body of wall 2;2) support slot 31 of wallboard installing tache 3 is inserted lower section wallboard 1 hold
In the locating slot 13 of spigot, the installation portion 33 of wallboard installing tache 3 is affixed with body of wall 2, and uses self tapping spiral shell
Silk 4 is fixed;3) the first raised line 11 of top wallboard plug-in unit end is inserted lower section wallboard installing tache 3
In support groove 31, and top wallboard is pasted onto on body of wall by adhesive, the now installation portion of wallboard installing tache
33 and be fixed on installation portion self-tapping screw 4 nut wallboard above the first breach 12 in;4) weight
Multiple step 2) and step 3) wallboard is installed from the bottom up to all wallboard installations.
The installation method of above-mentioned wallboard, solves in wallboard work progress, adhesive between body of wall 2 and wallboard 1
The difficult problem that uncured front wallboard is installed.During construction, wallboard 1 is bonding with body of wall 2, on demand by adhesive
Insert wallboard installing tache 3 with a determining deviation, and wallboard installing tache 3 fixed with body of wall 2 by self-tapping screw 4,
This structure and construction method may insure that and reach the fixing reliable of optimal bonding force front wallboard in adhesive solidification
Property.
Claims (4)
1. the mounting structure of wallboard, it is characterised in that include wallboard, body of wall and wallboard installing tache;
Wallboard is strip;Lower end on wallboard installation direction is plug-in unit end, and the upper end on wallboard installation direction is bell end, is provided with downward projection of first raised line at plug-in unit end, and the inner side of the first raised line is provided with and upwardly extends and first breach adjacent with body of wall;Described first breach is made up of a lateral wall and a diapire, and the lateral wall of the first breach is i.e. the medial wall of the first raised line;The bell end of wallboard is provided with locating slot;
Wallboard installing tache includes supporting part, installation portion and for connecting the connecting portion of installation portion and supporting part;Support zone is in the lower section of installation portion, and supporting part is provided with support slot, and installation portion is provided with connecting hole;
Described supporting part coordinates with described locating slot, and described first raised line coordinates with described support slot, and wallboard installing tache is fixed on body of wall by tapping screw at connecting portion.
The mounting structure of wallboard the most according to claim 1, it is characterised in that described wallboard installing tache passes through metal sheet bending forming.
The mounting structure of wallboard the most according to claim 1, it is characterised in that described wallboard installing tache is strip, and connecting portion is evenly distributed with multiple connecting hole.
4. the installation method of wallboard, it is characterised in that including the wallboard as according to any one of claims 1 to 3, body of wall and wallboard installing tache, wallboard is installed from lower to upper, comprises the following steps:
1) lower section wallboard with bell end upward, plug-in unit end passes down through adhesive and is pasted onto on body of wall;
2) support slot of wallboard installing tache is inserted in the locating slot of lower section wallboard bell end, the installation portion of wallboard installing tache is affixed with body of wall, and fixes with self-tapping screw;
3) the first raised line of top wallboard plug-in unit end is inserted in the support slot of wallboard installing tache, and top wallboard is pasted onto on body of wall by adhesive;
4) step 2 is repeated) and step 3) wallboard is installed from the bottom up to all wallboard installations;
In above-mentioned steps, after two neighbouring wallboards and wallboard installing tache installation, in the first breach of the nut wallboard above of the installation portion of wallboard installing tache and the self-tapping screw that is fixed on installation portion.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610507418.0A CN106013669B (en) | 2016-06-27 | 2016-06-27 | The mounting structure and installation method of wallboard |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610507418.0A CN106013669B (en) | 2016-06-27 | 2016-06-27 | The mounting structure and installation method of wallboard |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106013669A true CN106013669A (en) | 2016-10-12 |
CN106013669B CN106013669B (en) | 2019-02-19 |
Family
ID=57105716
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610507418.0A Active CN106013669B (en) | 2016-06-27 | 2016-06-27 | The mounting structure and installation method of wallboard |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106013669B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836707A (en) * | 2017-03-23 | 2017-06-13 | 机械科学研究总院先进制造技术研究中心 | A kind of plasterboard bank closes locking method |
CN109025144A (en) * | 2018-09-19 | 2018-12-18 | 浙江华夏杰高分子建材有限公司 | The mounting structure of wallboard |
CN109208850A (en) * | 2017-07-07 | 2019-01-15 | 霍高文建筑系统(广州)有限公司 | Combined wall board installation method and its assembling assembly |
CN111352331A (en) * | 2018-12-21 | 2020-06-30 | 伊塔瑞士钟表制造股份有限公司 | Assembly comprising a support, a main plate and a fastening device, in particular for a timepiece |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202064584U (en) * | 2011-03-28 | 2011-12-07 | 湖州立方新材料有限公司 | Wallboard connecting piece |
EP2644478A1 (en) * | 2012-03-27 | 2013-10-02 | UPM-Kymmene Wood Oy | A panel comprising plywood |
CN104179321A (en) * | 2014-08-18 | 2014-12-03 | 山东阁林板建材科技有限公司 | Wallboard mounting system and mounting method thereof |
CN205329932U (en) * | 2016-01-19 | 2016-06-22 | 多维联合集团有限公司 | Battenboard interface adhesive tape and application node structure thereof |
CN205742832U (en) * | 2016-06-27 | 2016-11-30 | 浙江华夏杰高分子建材有限公司 | The mounting structure of wallboard |
-
2016
- 2016-06-27 CN CN201610507418.0A patent/CN106013669B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202064584U (en) * | 2011-03-28 | 2011-12-07 | 湖州立方新材料有限公司 | Wallboard connecting piece |
EP2644478A1 (en) * | 2012-03-27 | 2013-10-02 | UPM-Kymmene Wood Oy | A panel comprising plywood |
CN104179321A (en) * | 2014-08-18 | 2014-12-03 | 山东阁林板建材科技有限公司 | Wallboard mounting system and mounting method thereof |
CN205329932U (en) * | 2016-01-19 | 2016-06-22 | 多维联合集团有限公司 | Battenboard interface adhesive tape and application node structure thereof |
CN205742832U (en) * | 2016-06-27 | 2016-11-30 | 浙江华夏杰高分子建材有限公司 | The mounting structure of wallboard |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836707A (en) * | 2017-03-23 | 2017-06-13 | 机械科学研究总院先进制造技术研究中心 | A kind of plasterboard bank closes locking method |
CN109208850A (en) * | 2017-07-07 | 2019-01-15 | 霍高文建筑系统(广州)有限公司 | Combined wall board installation method and its assembling assembly |
CN109208850B (en) * | 2017-07-07 | 2024-03-12 | 霍高文建筑系统(广州)有限公司 | Composite wallboard mounting method and assembly component thereof |
CN109025144A (en) * | 2018-09-19 | 2018-12-18 | 浙江华夏杰高分子建材有限公司 | The mounting structure of wallboard |
CN111352331A (en) * | 2018-12-21 | 2020-06-30 | 伊塔瑞士钟表制造股份有限公司 | Assembly comprising a support, a main plate and a fastening device, in particular for a timepiece |
Also Published As
Publication number | Publication date |
---|---|
CN106013669B (en) | 2019-02-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106013669A (en) | Wallboard installation structure and method | |
JP6816050B2 (en) | Bracket for fixing electronic devices and fixed structure for electronic devices | |
CN103206065A (en) | Novel detachable skirting line and assembly thereof | |
US20170012421A1 (en) | Self-Measuring Wall Box Bracket | |
CN205742832U (en) | The mounting structure of wallboard | |
JP6227367B2 (en) | Fastening bracket and exterior material construction method | |
CN206917165U (en) | A kind of mounting structure of wallboard | |
RU175224U1 (en) | The fastening device for the cladding element at the junction of two surfaces | |
CN101970934B (en) | Mounting device for recessed ceiling lights and/or surface-mounted ceiling lights | |
CN203213541U (en) | Novel detachable skirting line and assembly thereof | |
CN207063401U (en) | The decorating structure of wallboard | |
US8309849B2 (en) | Attachable supporting spacer for electrical boxes | |
CN102937823A (en) | Fixing device for power supply unit (PSU) | |
CN204876445U (en) | Indoor shingle nail mounting structure | |
CN214169614U (en) | Adjusting plate installation modeling structure | |
CN109025144A (en) | The mounting structure of wallboard | |
CN103883861B (en) | Curved surface television set wall hanging components | |
CN103899894A (en) | Flat-panel television set supporting device | |
CN104895280B (en) | Improved anchoring part device | |
CN206784675U (en) | For connecting the connection component of domes and metal curtain wall | |
CN217840718U (en) | Assembled skirting structure with lamp strip | |
CN210530226U (en) | Installation component of cloth-coated wallboard | |
CN206448851U (en) | Impeller bracket | |
JP6496811B2 (en) | Edge profile elements for ceiling substructures | |
CN205577491U (en) | Shower room sclausura mounting structure and possess its shower room |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |