CN106013207A - Fully-symmetrical prestress assembled type tower crane foundation connected to pile foundation - Google Patents

Fully-symmetrical prestress assembled type tower crane foundation connected to pile foundation Download PDF

Info

Publication number
CN106013207A
CN106013207A CN201610406155.4A CN201610406155A CN106013207A CN 106013207 A CN106013207 A CN 106013207A CN 201610406155 A CN201610406155 A CN 201610406155A CN 106013207 A CN106013207 A CN 106013207A
Authority
CN
China
Prior art keywords
bar blocks
tower crane
stake
strip
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610406155.4A
Other languages
Chinese (zh)
Inventor
彭宝安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Lantian Chuangxian Technology Services Limited
Original Assignee
Wuhan Chuangxian Patent Technology Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Chuangxian Patent Technology Service Co Ltd filed Critical Wuhan Chuangxian Patent Technology Service Co Ltd
Priority to CN201610406155.4A priority Critical patent/CN106013207A/en
Publication of CN106013207A publication Critical patent/CN106013207A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a fully-symmetrical prestress assembled type tower crane foundation connected to a pile foundation and mainly applied to tower crane foundations in constructional engineering field. The fully-symmetrical prestress assembled type tower crane foundation mainly comprises strip-shaped blocks A (1), strip-shaped blocks (2) with pre-embedded bolts, strip-shaped blocks B (13), steel strands (3), anchor tools (5), connection steel plates (8) and piles (11). A construction process of the fully-symmetrical prestress assembled type tower crane foundation connected to the pile foundation mainly comprises the following steps: firstly constructing the piles (11), then lifting the strip-shaped blocks A (1), and inserting pile main bars (9) of the piles (11) into holes C (15) of the strip-shaped blocks A (1); subsequently lifting other strip-shaped blocks, inserting U-shaped steel plates (7) of the strip-shaped blocks into arc-shaped grooves (14) of the adjacent strip-shaped blocks, then enabling the steel strands (3) to successively pass through holes A (6) of the strip-shaped blocks, applying prestress and fixing via the anchor tools (5); and finally enabling the pile main bars (9) to pass through holes B (10) of the connection steel plates (8), fixing the whole tower crane foundation to the piles (11) through nuts, and finishing mounting the tower crane foundation.

Description

A kind of holohedral symmetry prestressed assembly formula foundation for tower crane connecting pile foundation
Technical field
Present invention is mainly used for building engineering field tower crane foundation.
Background technology
The patent of invention that I has authorized: a kind of holohedral symmetry prestressed assembly formula foundation for tower crane, the patent No.: ZL201210114414.8, pile foundation is not combined, runs into soft foundation inapplicable by this patent.
Summary of the invention
Pin-connected panel foundation for tower crane is combined by the present invention with pile foundation, greatly strengthen the resistance to capsizing of tower crane, is simultaneously suitable for soft foundation, expands the range of pin-connected panel foundation for tower crane.
It is an advantage of the current invention that: 1. Flat shape is holosymmetric, overcomes weak axle problem. 2. Plane combination is simple, only split basic plane in a direction, Shi Hanzhang is also a direction, need the most two-way Shi Hanzhang like that not necessarily like beam and slab type or beam type assembly tower crane and cause basic plane deformation after assembly, particularly fix the relative change in location of four groups of pre-embedded bolts of tower crane and the relative position error of producing. 3. The present invention is after Shi Hanzhang anchoring, and the basic stress after assembly is reasonable, and the frictional force between bar blocks and bar blocks can resist the shear stress suffered by basis;The steel strand wires arranged up and down ( 3 ) moment of flexure suffered by basis can be resisted 4. Prefabricated components are simple, and shape is single, the most prefabricated, are not easy to damage and substitute easily during lifting and assembly. 5. Relatively for beam foundation, the present invention is more reliable and more stable, and joins reinforcing bar amount and reduce, and saves amount of reinforcement, although multiplex concrete amount, but adds basis weight, and when work to overcoming tower crane, the vibrations load of generation is helpful, adds security reliability. 6. For fix four groups of pre-embedded bolts of tower crane support be embedded in respectively two bar blocks ( 2 On), make to be embedded in two bar blocks two groups of pre-embedded bolt groups along bar blocks long side direction and do not have assembled error. 7. Pin-connected panel foundation for tower crane is combined by the present invention with pile foundation, greatly strengthen the resistance to capsizing of tower crane, can be suitably used for again soft foundation simultaneously, expands the range of pin-connected panel foundation for tower crane.
The present invention is mainly by bar blocks A ( 1 ), with pre-embedded bolt bar blocks ( 2 ), bar blocks B ( 13 ), steel strand wires ( 3 ), anchorage ( 5 ), junction steel plate ( 8 ), stake ( 11 ) composition;Bar blocks A ( 1 ) porose C ( 15 ), with pre-embedded bolt bar blocks ( 2 ) have pre-embedded bolt group ( 4 ), bar blocks A ( 1 ), with pre-embedded bolt bar blocks ( 2 ), bar blocks B ( 13 ) be all embedded with U Shape steel plate ( 7 ) and all have arcuate groove ( 14 ) and multiple hole A ( 6 ), junction steel plate ( 8 ) porose B ( 10 ), stake ( 11 ) be embedded with the main muscle of stake ( 9 );The main muscle of stake ( 9 ) sequentially pass through bar blocks A ( 1 ) hole C ( 15 ) and junction steel plate ( 8 ) hole B ( 10 ) and with nut by stake ( 11 ) and bar blocks A ( 1 ) fixing;Steel strand wires ( 3 ) through multiple bar blocks A ( 1 ), multiple bar blocks with pre-embedded bolt ( 2 ), multiple bar blocks B ( 13 ) hole A ( 6 ), two ends with anchorage ( 5 ) fixing;Work progress and the operation principle of the present invention be: first construction stake ( 11 ), then lift bar blocks A ( 1 ), by stake ( 11 ) the main muscle of stake ( 9 ) insert bar blocks A ( 1 ) hole C ( 15 In), then lift bar blocks with pre-embedded bolt ( 2 ) and bar blocks B ( 13 ), make bar blocks U Shape steel plate ( 7 ) insert adjacent bar blocks arcuate groove ( 14 ) in, then by steel strand wires ( 3 ) sequentially pass through the hole of each bar blocks A ( 6 ), steel strand wires ( 3 ) two ends Shi Hanzhang after, with anchorage ( 5 ) fixing, form holosymmetric tower crane form, finally by junction steel plate ( 8 ) hole B ( 10 ) through the main muscle of stake ( 9 ), with nut by whole tower crane and stake ( 11 ) fixing, tower crane installs, with rear pre-embedded bolt group ( 4 Tower crane is installed on).
Accompanying drawing explanation
Description of reference numerals: 1- Bar blocks A , 2- With the bar blocks of pre-embedded bolt, 3- Steel strand wires, 4- Pre-embedded bolt group, 5- Anchorage, 6- Hole A , 7-U Shape steel plate, 8- Junction steel plate, 9- The main muscle of stake, 10- Hole B , 11- Stake, 12- Ground, 13- Bar blocks B , 14- Arcuate groove, 15- Hole C
Figure 1 It it is the square composite plane graph of the present invention.
Figure 2 It it is the octagon combination view of the present invention.
Figure 3 It is the present invention C-C Profile.
Figure 4 It is the present invention D-D Profile.
Figure 5 Be the present invention junction steel plate ( 8 ) drawing.
Figure 6 It it is the transverse section drawing of bar blocks of the present invention.
Figure 7 It it is bar blocks of the present invention A ( 1 ) longitudinal sectional drawing.
Detailed description of the invention
Summary of the invention has been described in detail the detailed description of the invention of the present invention, is not repeated herein, and need to be described as follows: see figure 1 , figure 2 , first should select different basic arrangement forms according to parameters such as tower crane foundation bearing capacity situation and the tower crane biggest lifting capacities, the plane on basis can be square can also be octagon, circle or other any holosymmetric shapes.See figure 3 , steel strand wires ( 3 ) arrange up and down and can resist the moment of flexure suffered by basis;Bar blocks U Shape steel plate ( 7 ) embed adjacent bar blocks arcuate groove ( 14 In), the anti-shear ability between adjacent bar block can be greatly increased, enhance the globality on basis.

Claims (1)

1. connect a holohedral symmetry prestressed assembly formula foundation for tower crane for pile foundation, it is characterized in that: it is mainly by bar blocks A(1), the bar blocks (2) with pre-embedded bolt, bar blocks B(13), steel strand wires (3), anchorage (5), junction steel plate (8), stake (11) form;Bar blocks A(1) porose C(15), bar blocks (2) with pre-embedded bolt has pre-embedded bolt group (4), bar blocks A(1), the bar blocks (2) with pre-embedded bolt, bar blocks B(13) be all embedded with U-shaped steel plate (7) and all have arcuate groove (14) and multiple hole A(6), junction steel plate (8) porose B(10), stake (11) is embedded with the main muscle of stake (9);Stake main muscle (9) sequentially pass through bar blocks A(1) hole C(15) and the hole B(10 of junction steel plate (8)) and with nut by stake (11) and bar blocks A(1) fix;Steel strand wires (3) pass multiple bar blocks A(1), multiple bar blocks with pre-embedded bolt (2), multiple bar blocks B(13) hole A(6), two ends with anchorage (5) fix;Work progress and the operation principle of the present invention be: first construction stake (11), lift bar blocks A(1 again), bar blocks A(1 is inserted in the main muscle of the stake (9) of stake (11)) hole C(15) in, then the bar blocks (2) with pre-embedded bolt and bar blocks B(13 are lifted), the U-shaped steel plate (7) making bar blocks inserts in the arcuate groove (14) of adjacent bar blocks, steel strand wires (3) are sequentially passed through the hole A(6 of each bar blocks again), after the two ends Shi Hanzhang of steel strand wires (3), fix with anchorage (5), form holosymmetric tower crane form, finally by the hole B(10 of junction steel plate (8)) through the main muscle of stake (9), with nut, whole tower crane is fixed with stake (11), tower crane installs, with on rear pre-embedded bolt group (4), tower crane is installed;Need explanation: the twisted wire (3) of the present invention is arranged up and down;The plane form on basis can select the multiple whole symmetrical shapes such as square, regular hexagon, octagon, circle.
CN201610406155.4A 2016-06-12 2016-06-12 Fully-symmetrical prestress assembled type tower crane foundation connected to pile foundation Pending CN106013207A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610406155.4A CN106013207A (en) 2016-06-12 2016-06-12 Fully-symmetrical prestress assembled type tower crane foundation connected to pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610406155.4A CN106013207A (en) 2016-06-12 2016-06-12 Fully-symmetrical prestress assembled type tower crane foundation connected to pile foundation

Publications (1)

Publication Number Publication Date
CN106013207A true CN106013207A (en) 2016-10-12

Family

ID=57090934

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610406155.4A Pending CN106013207A (en) 2016-06-12 2016-06-12 Fully-symmetrical prestress assembled type tower crane foundation connected to pile foundation

Country Status (1)

Country Link
CN (1) CN106013207A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106894437A (en) * 2017-02-15 2017-06-27 同济大学建筑设计研究院(集团)有限公司 Limited prestressing precast concrete foundation, communication tower building and construction method
CN112878354A (en) * 2021-02-23 2021-06-01 北京银泰建构预应力技术股份有限公司 Beam-slab assembled prestressed concrete foundation for onshore wind turbine generator
CN112900480A (en) * 2021-02-23 2021-06-04 北京银泰建构预应力技术股份有限公司 Assembled prestressed concrete foundation for onshore wind turbine generator
CN113668596A (en) * 2021-09-05 2021-11-19 弓健 Prefabricated iron tower basis of assembled
CN115369910A (en) * 2022-06-29 2022-11-22 安徽华电工程咨询设计有限公司 Assembly type column lower independent foundation of post-tensioned pre-stressed assembled transformer substation and design method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2701914Y (en) * 2004-10-18 2005-05-25 从卫民 Concrete prefabricated and assembled multipurpose tower crane foundation
CN2734716Y (en) * 2003-11-10 2005-10-19 陈宽诚 Assembling steel structure tower type crane foundation
CN102767190A (en) * 2012-07-18 2012-11-07 北京金风科创风电设备有限公司 Tower foundation and method for manufacturing same
CN202969409U (en) * 2012-12-10 2013-06-05 霍宏斌 Anchor rod gravity type onshore/offshore wind turbine foundation
CN103374924A (en) * 2012-04-18 2013-10-30 彭宝安 Full-symmetry prestressed assembled tower crane foundation
CN103774687A (en) * 2014-01-22 2014-05-07 深圳市海能通信股份有限公司 Single-pipe tower prefabricated spiral steel pipe pile foundation
WO2016043406A1 (en) * 2014-09-17 2016-03-24 한국전력공사 Transmission tower foundation using micropile

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2734716Y (en) * 2003-11-10 2005-10-19 陈宽诚 Assembling steel structure tower type crane foundation
CN2701914Y (en) * 2004-10-18 2005-05-25 从卫民 Concrete prefabricated and assembled multipurpose tower crane foundation
CN103374924A (en) * 2012-04-18 2013-10-30 彭宝安 Full-symmetry prestressed assembled tower crane foundation
CN102767190A (en) * 2012-07-18 2012-11-07 北京金风科创风电设备有限公司 Tower foundation and method for manufacturing same
CN202969409U (en) * 2012-12-10 2013-06-05 霍宏斌 Anchor rod gravity type onshore/offshore wind turbine foundation
CN103774687A (en) * 2014-01-22 2014-05-07 深圳市海能通信股份有限公司 Single-pipe tower prefabricated spiral steel pipe pile foundation
WO2016043406A1 (en) * 2014-09-17 2016-03-24 한국전력공사 Transmission tower foundation using micropile

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106894437A (en) * 2017-02-15 2017-06-27 同济大学建筑设计研究院(集团)有限公司 Limited prestressing precast concrete foundation, communication tower building and construction method
CN112878354A (en) * 2021-02-23 2021-06-01 北京银泰建构预应力技术股份有限公司 Beam-slab assembled prestressed concrete foundation for onshore wind turbine generator
CN112900480A (en) * 2021-02-23 2021-06-04 北京银泰建构预应力技术股份有限公司 Assembled prestressed concrete foundation for onshore wind turbine generator
CN113668596A (en) * 2021-09-05 2021-11-19 弓健 Prefabricated iron tower basis of assembled
CN115369910A (en) * 2022-06-29 2022-11-22 安徽华电工程咨询设计有限公司 Assembly type column lower independent foundation of post-tensioned pre-stressed assembled transformer substation and design method thereof

Similar Documents

Publication Publication Date Title
CN106013207A (en) Fully-symmetrical prestress assembled type tower crane foundation connected to pile foundation
US8881485B2 (en) Wind turbine tower system
CN104294753B (en) A kind of hollow pier stud syndeton of bridge prefabrication and construction
KR101027393B1 (en) Longitudinal and/or transverse seismic reinforcing method for masonry walls
CN203923924U (en) No. 0 section bracket prepressing device
CN103290786A (en) System and method for rapidly reinforcing railway bridge by external prestressing
SG175868A1 (en) Half precast slab and method for structuring half precast slab
CN103966953B (en) Based on the post-tensioned prestressed large-span concrete beam construction method of non-bending steel cable
CN102979221A (en) Shear wall structure configured with crossed slant internal prestress and construction method of shear wall structure
CN102409619B (en) Method for improving cross integrity of bridge deck structure of multi-girder type combined small box girder bridge
KR101328045B1 (en) Reinforced concrete composite columns using precast high-performance fiber-reinforced cement
CN106930436B (en) Reinforced concrete shear wall with built-in prestressed steel diagonal bracing
CN104631436A (en) Method for improving integral type bridge abutment sustaining pile stress performance by H-shaped concrete pile
CN106836645B (en) Thin wall concrete column in prefabricated cavity formula
CN103374924A (en) Full-symmetry prestressed assembled tower crane foundation
KR101086643B1 (en) Prestressed concrete girder with plural steel wires disposed at shear surface of tension port
CN203097040U (en) Antifatigue prestressing force steel-concrete combination beam
CN111379436A (en) Masonry filler wall with reinforcing structure and masonry filler wall reinforcing method
CN218622790U (en) Antidetonation coincide wall
CN202610695U (en) Corrugated steel web type pre-tensioned prestressed concrete I-type beam
CN201794215U (en) Pretensioning method prestress reinforced concrete prefabricated beam
EP1705313B1 (en) Reinforced console column and the method of its production
JP5439016B2 (en) Buried formwork
CN103498573B (en) Set up the existing frame strengthening method of band frame bracing members
JP5982143B2 (en) Reinforcing structure and reinforcing method for existing structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
C41 Transfer of patent application or patent right or utility model
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20161017

Address after: Room 2, building 457, Huangpu Road, Huangdao, Shandong, Qingdao, 266555, China

Applicant after: Qingdao Lantian Chuangxian Technology Services Limited

Address before: 430064, Wuhan, Hubei province Hongshan District lion mountain street, school 84, 73, 7, 2 room

Applicant before: WUHAN CHUANGXIAN PATENT TECHNOLOGY SERVICE CO., LTD.

CB03 Change of inventor or designer information

Inventor after: Xiong Jing

Inventor after: Peng Baoan

Inventor before: Peng Baoan

COR Change of bibliographic data
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161012