CN106013045A - Fast drainage method for shallow soil body - Google Patents

Fast drainage method for shallow soil body Download PDF

Info

Publication number
CN106013045A
CN106013045A CN201610379534.9A CN201610379534A CN106013045A CN 106013045 A CN106013045 A CN 106013045A CN 201610379534 A CN201610379534 A CN 201610379534A CN 106013045 A CN106013045 A CN 106013045A
Authority
CN
China
Prior art keywords
soil body
pipe
well
shallow
draining board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610379534.9A
Other languages
Chinese (zh)
Inventor
张禹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cabr Foundation Engineering Co Ltd
Original Assignee
Cabr Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cabr Foundation Engineering Co Ltd filed Critical Cabr Foundation Engineering Co Ltd
Priority to CN201610379534.9A priority Critical patent/CN106013045A/en
Publication of CN106013045A publication Critical patent/CN106013045A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0053Production methods using suction or vacuum techniques

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention relates to a fast drainage method for a shallow soil body. The fast drainage method for the shallow soil body is characterized by including the following steps that firstly, a trench is excavated in a reinforcement region, and a drainage plate horizontally arranged in the trench direction is laid in the trench; one end of the drainage plate is connected with a well point pipe in a sealed manner through a variable-diameter connector so that an integrated well point plastic drainage pipe can be formed, and the outer end of the well point pipe is exposed out of the trench; and finally, the outer end of the well point pipe is connected with a vacuumizing header pipe through a connecting pipe, the vacuumizing header pipe is connected with a vacuum pump to start vacuumizing, and fast water lowering of the shallow soil body is achieved. The fast drainage method for the shallow soil body has the beneficial effects of being easy to operate, low in cost and good in construction effect.

Description

Shallow-layer soil body Quick drainage method
Technical field
The present invention relates to a kind of Treatment Methods of Soft Ground, particularly relate to a kind of shallow-layer soil body Quick drainage method.
Background technology
Specifying according to " Code for design of building " (GB5007-2011) 7.1.1, soft foundation means the ground being mainly made up of mud, muck soil, rinse fill, miscellaneous fill or other high-compressibility soil layer.Before soft foundation carries out construction, need first soft foundation to be carried out consolidation process.
The first step of traditional basement process is levelling of the land, is then treating that reinforcing area surrounding excavates gutter draining;For the place that some operating modes are complicated, simple excavation gutter draining is oversize due to the drainage path long natural drainage efficiency the lowest time.
Summary of the invention
It is an object of the invention to overcome above-mentioned deficiency, it is provided that a kind of simple to operate, with low cost, shallow-layer soil body Quick drainage method that construction effect is good.
The object of the present invention is achieved like this:
Compared with prior art, the invention has the beneficial effects as follows:
1, simple to operate, speed of application is fast, and construction unit can complete in one day to excavate groove, lay integral type well point plastic strip pipe, backfilling working;
2, changing nature seepage flow draining is to force vacuum drainage, and speed is fast, efficiency is high;
3, vacuum-dewatering good sealing effect, in the well-point pipe underground length of integral type well point plastic strip pipe or depth bounds, the soil body is seal, good sealing effect;
4, the well-point pipe of integral type well point plastic strip can be pulled out, and the degraded of plastic strip filter membrane, central layer are retained the soil body and played level to reinforced action;
5, cheap, excavation cost is the highest, integral type well point plastic strip level interval about 10 ~ 30 meters, saves tubing and does not reduce drainage effect simultaneously.
Therefore the present invention has advantage simple to operate, with low cost, that construction effect is good.
Accompanying drawing explanation
Fig. 1 is the elevation of embodiments of the invention one.
Fig. 2 is the top view at the draining board of Fig. 1.
Fig. 3 is the A-A sectional view of Fig. 1.
Fig. 4 is the elevation of embodiments of the invention two.
Fig. 5 is the top view at the draining board of Fig. 4.
Fig. 6 is the B-B sectional view of Fig. 4.
Fig. 7 is the sectional view of draining board.
Fig. 8 is the axonometric chart of draining board.
Wherein:
Draining board 1, central layer 1.1, main gusset 1.11, secondary gusset 1.12, filter membrane 1.2, drainage channel 1.3
Reducer union 2
Well-point pipe 3
Connecting tube 4
Evacuation house steward 5
Vacuum pump 6.
Detailed description of the invention
See Fig. 1 ~ Fig. 8, for backfilling ground or subsoil, the shallow-layer soil body Quick drainage method that the present invention relates to, it comprises the following steps:
Step one, reinforcing area excavation groove, gash depth 3 ~ 5m, groove pitch 10 ~ 30m
Yellow ground or the gravel filtering material of 5 ~ 10cm thickness 30cm width laid by step 2, groove bottom;
The draining board horizontally disposed along groove direction is laid in step 3, groove;
Step 4, using reducer union to be tightly connected well-point pipe to form integral type well point plastic strip pipe in one end of draining board, the outer end of well-point pipe is exposed outside groove;
Step 5, the yellow ground laying 5 ~ 10cm thickness 30cm width on draining board surface or gravel filtering material, then trench backfill clay seals, and as required, can lay multilamellar integral type well point plastic strip pipe;
Step 6, the outer end of well-point pipe use connecting tube to connect evacuation house steward, and evacuation house steward connects vacuum pump and starts evacuation, it is achieved the fast rainfall of the shallow-layer soil body.
Wherein:
Draining board 1 includes central layer 1.1 and the filter membrane 1.2 of central layer 1.1 periphery of inside, drainage channel 1.3 is formed between described central layer 1.1 and filter membrane 1.2, described central layer 1.1 is made for non-degradable material or difficult degradation material, and described filter membrane 1.2 is made for degradation material.
Preferred as one, central layer 1.1 is made for plastic material, and filter membrane 1.2 is made for Caulis et Folium Lini material.
Preferred as one, central layer 1.1 includes the main gusset 1.11 of a lateral arrangement and the many longitudinally spaced secondary gussets 1.12 being arranged in before and after main gusset 1.11, and main ribs plate 1.11, the space formed between secondary gusset 1.12 and filter membrane 1.2 are drainage channel 1.3.
Draining board 1 is in the soil body, as time goes by, owing to filter membrane 1.2 uses degradation material to make, filter membrane 1.2 realizes fast degradation, filter membrane 1.2 degraded after in ground the most remaining central layer 1.1, the soil in ground can fill former filter membrane 1.2 and the space of former drainage channel 1.3 so that soil fits tightly with central layer 1.1, therefore the most there is not space and make ground continue sedimentation in central layer 1.1 in ground, but also serves the effect of reinforcement.
The tail end of described draining board 1 is provided with draining board end socket, and draining board end socket uses plastic adhesive tape paper to be wrapped to form.
Described connecting tube 4 is wired hose, and connecting tube 4 includes the spiral wire of flexible pipe and Lining Hose.
Described well-point pipe 3 is pvc pipe, PPR pipe, and well-point pipe 3 and connecting tube 4 junction are wrapped up by diaphragm seal or steel wire winding, after using diaphragm seal parcel, produces negative-pressure dense sealer when evacuation and is inhaled tighter and tighter.Well-point pipe 3 can also use with connecting tube 4 as wired hose so that well-point pipe 3 and connecting tube 4 form integrative-structure.
Embodiment one
Seeing Fig. 1 ~ Fig. 2, intend disposal field and backfilled 3 meters of thick clays, water content is higher, it is necessary to leading draining could launch subsequent construction;
Step one, reinforcing area excavation groove, gash depth 3m to original place table, groove pitch 25m, groove width 0.8m;Groove right-hand member stays about the 4 meters soil bodys not dig, it is ensured that draining board right-hand member is air tight, and left side is dug through and is easy to lay well-point pipe and lifts one's head connection vacuum pump
The yellow ground of 5cm thickness 30cm width laid by step 2, groove bottom;Groove left section 5 meters long does not lay yellow ground
The draining board horizontally disposed along groove direction is laid in step 3, groove;
Step 4, using reducer union to be tightly connected 5.1m well-point pipe at the left end of draining board to form integral type well point plastic strip pipe, well-point pipe exposes outer about the 10cm of groove to be easy to connect, and well-point pipe and draining board are that yi word pattern is arranged;
Step 5, the yellow ground laying 5 ~ 10cm thickness 30cm width on draining board surface or gravel filtering material, then trench backfill clay seals;
Step 6, the integral type well point plastic strip pipe section of being unearthed use connecting tube to connect evacuation house steward, and evacuation house steward connects vacuum pump and starts evacuation, the fast rainfall completing the shallow-layer soil body in 1 ~ 3 day.
Embodiment two
Seeing Fig. 3 and Fig. 4, plan disposal field is subsoil, and topsoil body water content is higher
Step one, reinforcing area excavation groove, gash depth 4m, groove pitch 15m, groove width 1m;Groove right-hand member stays about the 4 meters soil bodys not dig, it is ensured that draining board right-hand member is air tight, and groove left end also stays the part soil body not dig,
The yellow ground of 8cm thickness 30cm width laid by step 2, groove bottom;
The plastic draining board horizontally disposed along groove direction is laid in step 3, groove;
Step 4, using reducer union to be tightly connected 4.1m well-point pipe at the left end of draining board to form integral type well point plastic strip pipe, well-point pipe exceeds to be easy to about trench top 10cm connect, well-point pipe and draining board is L-shaped is arranged vertically;
Step 5, the yellow ground laying 5 ~ 10cm thickness 30cm width on draining board surface or gravel filtering material, then trench backfill clay seals;
Step 6, the integral type well point plastic strip pipe section of being unearthed use connecting tube to connect evacuation house steward, and evacuation house steward connects vacuum pump and starts evacuation, the fast rainfall completing the shallow-layer soil body in 1 ~ 3 day.

Claims (3)

1. a shallow-layer soil body Quick drainage method, it is characterised in that it comprises the following steps:
First, reinforcing area excavation groove, then lay the draining board horizontally disposed along groove direction in groove;Using in one end of draining board reducer union to be tightly connected well-point pipe and form integral type well point plastic strip pipe, the outer end of well-point pipe is exposed outside groove;The outer end of last well-point pipe uses connecting tube to connect evacuation house steward, and evacuation house steward connects vacuum pump and starts evacuation, it is achieved the fast rainfall of the shallow-layer soil body.
A kind of shallow-layer soil body Quick drainage method the most according to claim 1, it is characterized in that draining board includes the central layer of inside and the filter membrane that central layer is peripheral, drainage channel is formed between described central layer and filter membrane, described central layer is non-degradable material or difficult degradation material is made, and described filter membrane is that degradation material is made.
A kind of shallow-layer soil body Quick drainage method the most according to claim 1, it is characterised in that well-point pipe and draining board are that yi word pattern is arranged or L-type is arranged.
CN201610379534.9A 2016-06-01 2016-06-01 Fast drainage method for shallow soil body Pending CN106013045A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610379534.9A CN106013045A (en) 2016-06-01 2016-06-01 Fast drainage method for shallow soil body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610379534.9A CN106013045A (en) 2016-06-01 2016-06-01 Fast drainage method for shallow soil body

Publications (1)

Publication Number Publication Date
CN106013045A true CN106013045A (en) 2016-10-12

Family

ID=57092233

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610379534.9A Pending CN106013045A (en) 2016-06-01 2016-06-01 Fast drainage method for shallow soil body

Country Status (1)

Country Link
CN (1) CN106013045A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106930304A (en) * 2017-03-24 2017-07-07 中冶建工集团有限公司 Drift sand base pit dewatering construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101225657A (en) * 2008-01-08 2008-07-23 上海大学 Low-position belt type vacuum sealing-water lowering new method
CN101614006A (en) * 2009-07-09 2009-12-30 宜兴市鑫泰土工材料有限公司 Silt consolidation is with band drain and filter cloth and band drain core
KR20110026550A (en) * 2009-09-08 2011-03-16 지에스건설 주식회사 Two-way suction drain consolidation method for porewater drainage of soft ground
CN102322054A (en) * 2011-06-30 2012-01-18 中交四航工程研究院有限公司 Method for processing ultra-soft soil through combining shallow-surface-layer intermittent strong water-pumping/draining with short-term air-curing
CN104831703A (en) * 2015-04-29 2015-08-12 中交上海三航科学研究院有限公司 Horizontal drainage board structure and construction process

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101225657A (en) * 2008-01-08 2008-07-23 上海大学 Low-position belt type vacuum sealing-water lowering new method
CN101614006A (en) * 2009-07-09 2009-12-30 宜兴市鑫泰土工材料有限公司 Silt consolidation is with band drain and filter cloth and band drain core
KR20110026550A (en) * 2009-09-08 2011-03-16 지에스건설 주식회사 Two-way suction drain consolidation method for porewater drainage of soft ground
CN102322054A (en) * 2011-06-30 2012-01-18 中交四航工程研究院有限公司 Method for processing ultra-soft soil through combining shallow-surface-layer intermittent strong water-pumping/draining with short-term air-curing
CN104831703A (en) * 2015-04-29 2015-08-12 中交上海三航科学研究院有限公司 Horizontal drainage board structure and construction process

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106930304A (en) * 2017-03-24 2017-07-07 中冶建工集团有限公司 Drift sand base pit dewatering construction method

Similar Documents

Publication Publication Date Title
CN102587352B (en) Hot-water draining consolidation processing device and hot-water draining consolidating processing method for soft soil foundation
CN206385531U (en) A kind of pile tube device of reinforcing soft ground
CN102330424B (en) Vacuum preloading consolidation method for duplex vacuum tube well of blowing filling soft soil
CN105064383B (en) Pipe-inserting negative pressure air jet deep-well dewatering device
CN104120711B (en) A kind of piling prepressing united vacuum precompressed soft foundation consolidation process structure and method
CN103628915A (en) Dewatering and drainage method for large-section water-rich saturation fine-silt tunnel
CN105780754A (en) Sand-bed-free vacuum preloading and water bag heaped loading combined reinforcing device and method for soft soil foundation
CN103821135A (en) Stereo airtight independent vacuum preloading foundation processing method
CN106013045A (en) Fast drainage method for shallow soil body
CN204919528U (en) A go out membrane structure for detecting vacuum pre -compaction in -process reinforcement effect
CN105862716B (en) Integral type well point plastic strip pipe
CN105821829B (en) Quasi- backfill ground shallow soil body Quick drainage method
CN105970910B (en) Well point plastic strip overlay film vacuum pre-pressed joint precipitating, pre-pressing dynamic consolidation method
CN105970909B (en) Well point plastic strip vacuum preloading seepage consolidation joint precipitating, pre-pressing dynamic consolidation method
CN105926577B (en) Vacuum preloading seepage consolidation method
CN205917709U (en) Integral type well dotted arranges house steward vacuum system
CN205917685U (en) Integral type well dotted arranges vacuum system
CN205917684U (en) Integral type well dotted calandria
CN106013046A (en) Grading loading method for variable-stress path well point plastic drainage vacuum preloading seepage consolidation
CN105862714A (en) Soft foundation water cover type integrated well point plastic strip vacuum system
CN206736888U (en) A kind of novel evacuated pre-pressing system of Soft Ground
CN105862719A (en) Reinforced foundation
CN109797762A (en) A kind of excavation slope built-in pipe, which is cut, seeps structure and its construction method
CN204875827U (en) Intubate formula negative pressure air -spray deep well precipitation device
CN105887902B (en) Well point plastic strip vacuum pre-pressed joint precipitating, pre-pressing dynamic consolidation method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161012