CN105986567A - Quick resonance compacting method for island-reef coral filled fragment sandy soil - Google Patents

Quick resonance compacting method for island-reef coral filled fragment sandy soil Download PDF

Info

Publication number
CN105986567A
CN105986567A CN201510053459.2A CN201510053459A CN105986567A CN 105986567 A CN105986567 A CN 105986567A CN 201510053459 A CN201510053459 A CN 201510053459A CN 105986567 A CN105986567 A CN 105986567A
Authority
CN
China
Prior art keywords
vibration head
quickly
vibration
resonate
sandy soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510053459.2A
Other languages
Chinese (zh)
Inventor
王建平
徐士龙
徐望
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Harbor Infrastructure (group) Co Ltd
Original Assignee
Shanghai Harbor Infrastructure (group) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Harbor Infrastructure (group) Co Ltd filed Critical Shanghai Harbor Infrastructure (group) Co Ltd
Priority to CN201510053459.2A priority Critical patent/CN105986567A/en
Publication of CN105986567A publication Critical patent/CN105986567A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a quick resonance compacting method for island-reef coral filled fragment sandy soil. The method includes: under coordination of high-pressure water flushing, inserting vibration heads of a plurality of vibrating impacters into treated sandy soil to a required depth, gradually lifting the vibration heads, filling sandy soil or coral reef fragments into holes formed by vibrating impact on the spot in each-time lifting of 0.5-2m, staying for vibration for appropriate time, continuing to lift, and repeating the steps of filling the sandy soil or the coral reef fragments and staying for vibration until reaching the top of the treated soil, wherein the vibration heads are arranged at intervals of 1-8m, and motor power of the vibration heads is 75-320KW. Due to the fact of on-spot adoption of the coral reef fragments as filler, quickness in construction and environment friendliness are realized, and construction cost is saved by about 30% as compared with that of an existing method.

Description

The densification process that quickly resonates of islands and reefs Corallium Japonicum Kishinouye hydraulic reclamation fragment sand
Technical field
The present invention relates to Sandy Soil Foundation processing technology field, be specifically related to a kind of occasions such as islands and reefs that are applicable to The densification process that quickly resonates of islands and reefs Corallium Japonicum Kishinouye hydraulic reclamation fragment sand.
Background technology
For the process of Sandy Soil Foundation, the method that prior art is the most a lot, conventional such as water pendant sand changes Fill out, strong rammer, cement mixing pile, lime-soil compaction pile, be applicable to process clay content be not more than 10% medium sand, The vibrocompaction etc. of coarse sand ground etc..But, owing to the geology of Sandy Soil Foundation has the following characteristics that one Being that top aeolian sand is the loosest, bearing capacity is relatively low and uneven, and engineering property is poor;Two is that sand cosmid contains Measuring glutinous poly-property between less, sand granule poor, void ratio is big, seepage of water is strong;Three is internal friction between unsaturated sand grains Power is bigger;Four to be that phreatic water is contained abundant etc..Thus, use above-mentioned conventional method for processing foundation to sand When property soil base processes, have that input cost is higher the most to some extent, complicated construction technique, construction Inefficient, stiffening basic ground effect is poor, be not suitable for number of drawbacks and the deficiencies such as deep foundation base reinforcing. Thus, the above-mentioned geological characteristics of Sandy Soil Foundation makes the at present conventional all kinds of method for processing foundation all can not be complete Complete applicable.
CN103215944B Chinese patent discloses a kind of several vibrating impacters resonance ground processing equipment and side Method, construction equipment disclosed in this patent is several vibrators, is suspended on equipment body cantilever including by hoist cable On crossbeam (channel-section steel), crossbeam two ends arrange 2 vibration head (vibrating device), vibration head further through cable wire On be provided with water inlet and be connected to high-pressure hydraulic pump.The step of corresponding construction method is included in high pressure water flushing Under cooperation, shaker arm is inserted the processed soil body and carries out vibratory compaction to the required degree of depth, promote the most step by step, The reasonable time that all pauses after every time promoting certain altitude is to carry out vibratory compaction, so until promoting and being unearthed Body.Apparatus and method for disclosed in this patent is preferable for common Sandy Soil Foundation treatment effect, but for island The sandy soil of the occasions such as reef is the most inapplicable, and the problem being primarily present is as follows:
1, the soil body of islands and reefs constitutes more complicated, the most often with a lot of rubbles and coral reef fragment, Coral reef therein again because of the difference of its Formed age and there is bigger difference, such as shatter value, hardness, Buried depth etc..
2, need to fill in the pore-forming of shaker arm vibrations formation to blow during several vibrating impacter resonance constructions Banketing, and often lack this soil of filling on islands and reefs, this also results in construction cost and is significantly increased.
3, the environment on islands and reefs is the moistest, adds in sea water more containing salinity, causes construction equipment The more wet and slippery thickness of appearance, is unfavorable for the heat radiation of equipment, is frequently encountered by construction equipment mistake during practice of construction The situation of heat, serious meeting causes motor to be burned.
Accordingly, it would be desirable to the processing method of existing Sandy Soil Foundation is improved, to be adapted for islands and reefs etc. The closely knit process construction of the Sandy Soil Foundation of occasion.
Summary of the invention
The primary and foremost purpose of the present invention is that and overcomes existing Sandy Soil Foundation processing method not to be suitable for islands and reefs Etc. the shortcoming of occasion, thus provide the densification process that quickly resonates of a kind of islands and reefs Corallium Japonicum Kishinouye hydraulic reclamation fragment sand.
The densification process that quickly resonates of the islands and reefs Corallium Japonicum Kishinouye hydraulic reclamation fragment sand of the present invention, the construction that the method uses Equipment is several vibrators, and including the crossbeam being suspended on equipment body cantilever by hoist cable, crossbeam two ends are again Arranging two vibration head by cable wire, vibration head is provided with water inlet, this water inlet is connected to by pipeline High-pressure hydraulic pump, wherein, described rapid densification method is included under the cooperation of high pressure water flushing, by several vibrating impacters Vibration head insert in processed sandy soil to the most required degree of depth, promote vibration head the most step by step, often promote 0.5~2 meter, insert in the pore-forming that vibroflotation is formed, when stop vibration is suitable with sand or coral reef fragment on the spot Continue to lift up after between, repeat back-up sand soil or coral reef fragment and stop the step of vibration until rising to and being located Reason soil body top, wherein, the spacing of described vibration head is set to 1~8 meter, the motor merit of described vibration head Rate is 75~320KW.
According to embodiments of the invention, described several vibrators are provided with multiple crossbeam.
According to the present invention, the crossbeam two ends balance of described several vibrators is provided with multiple vibration head.
According to a preferred embodiment of the invention, the inside of the shell wall of the motor of described vibration head is entered from top to bottom One step offers several through holes, and leader High-Pressure Water is through this through hole.
According to the present invention, in the motor of described vibration head, it is provided with temperature sensor, for the temperature to motor It is monitored;Accordingly, described vibrator is provided with controller, and is provided with frequency modulation and voltage modulation temperature-limiting device, with Motor overheating is prevented by the way of frequency modulation and voltage modulation.
According to the present invention, described vibrator is provided with controller, and in record work progress automatically, each shakes The size of dynamic compact electric current corresponding to the degree of depth, to be further ensured that construction quality.
According to the present invention, the closely knit degree of depth of described processed hydraulic reclamation thing is 3~50 meters.
Preferred according to the present invention, during described vibration head inserts processed sandy soil, high-pressure hydraulic pump carries The pressure of confession is 5~15MPa, and its output is 100L/min~900L/min.
Preferred according to the present invention, during described vibration head promotes, the pressure that high-pressure hydraulic pump provides is 2.5~15MPa, and its output is 150L/min~650L/min.
Further, the time paused in described work progress is 2~40 seconds.
The present invention compared with prior art has the advantage that
1, take full advantage of the own characteristic that on islands and reefs, coral reef fragment is many, gather materials on the spot, guarantee construction Cost has significantly been saved on the basis of quality.
2, through hole has been offered in the initiative inside at motor housing wall, is introduced by water under high pressure in through hole with right Motor is lowered the temperature, and what the motor overheating that well solving constructs on islands and reefs is frequently encountered by even burnt out asks Topic.
3, speed of application is fast, and more environmentally-friendly, and construction cost compares existing method can also save about 30%.
Accompanying drawing explanation
Fig. 1 is the structural representation of several vibrating impacters of embodiment 1.
Fig. 2 shows that motor housing pars intramuralis offers the close-up schematic view of through hole.
Detailed description of the invention
Below in conjunction with specific embodiment, the quickly resonance to the islands and reefs Corallium Japonicum Kishinouye hydraulic reclamation fragment sand of the present invention is closely knit Method is described in further detail.Should be understood that following example are merely to illustrate the present invention not for restriction The scope of the present invention.
Embodiment 1
The densification process that quickly resonates of the islands and reefs Corallium Japonicum Kishinouye hydraulic reclamation fragment sand of the present invention, the equipment used is permissible With reference to CN103215944B Chinese patent.As it is shown in figure 1, several the vibrating impacters of the present embodiment include leading to Crossing the crossbeam 2 that hoist cable 1 is suspended on the cantilever 9 of equipment body 8, the two ends of this crossbeam 2 are further through cable wire 3 arrange two vibration head 4, and vibration head 4 is provided with water under high pressure water inlet 6, this water under high pressure water inlet 6 Being connected to high-pressure hydraulic pump 7 by pipeline, wherein, the vibration head 4 of cable wire 3 and correspondence thereof is on crossbeam 2 Position is adjustable, i.e. can move in the longitudinal direction along crossbeam 2.
In the present embodiment, described equipment body 8 can arrange multiple crossbeam 2, to configure more vibration head 4, this will be apparent to the person skilled in the art;It addition, can set on a crossbeam 2 Putting more vibration head 4, such as three or four, arranging as long as balancing on crossbeam 2, this for Also it is apparent from for those skilled in the art.
Further, since the air humidity on islands and reefs is relatively big and more containing salinity, cause construction equipment appearance ratio More wet and slippery thickness, is unfavorable for the heat radiation of equipment, is frequently encountered by the feelings that construction equipment is overheated during practice of construction Condition, serious meeting causes motor to be burned.Overheated situation is easily there is in order to solve motor, as in figure 2 it is shown, The inside at motor housing wall 10 of present invention initiative offers several through holes 11 from top to bottom, and draws Lead partial high pressure water and flow through this through hole 11, motor to be lowered the temperature by water under high pressure.
Further, described vibrator is provided with controller, can use common single-chip microcomputer, and be provided with frequency modulation tune Pressure temperature-limiting device, accordingly, is provided with temperature sensor in the motor of described vibration head, for motor Temperature is monitored, and coordinates frequency modulation and voltage modulation temperature-limiting device, to pass through frequency modulation and voltage modulation when motor temperature is too high Mode, reduces motor temperature, prevents motor from damaging because of overheated.Additionally, described controller record also automatically The size of each vibration compact electric current corresponding to the degree of depth in work progress, to be further ensured that construction matter Amount.Said temperature sensor and frequency modulation and voltage modulation temperature-limiting device itself are all that prior art is existing, non-invention Inventive point place, be not described in detail the most here.
Embodiment 2
Certain islands and reefs Corallium Japonicum Kishinouye hydraulic reclamation fragment sand foundation, thickness is 3~18 meters, rubble and coral reef fragment content 3~42wt%, infiltration coefficient 10-3cm/s.Design requires: the bearing capacity of 18 meters of Sandy Soil Foundations reaches 120KPa。
Before construction, conventionally, the Sandy Soil Foundation that need to construct is carried out the closely knit degree of depth of layer of sand to survey Amount, the closely knit degree of depth of described layer of sand is 18 meters.
Using several vibrating impacters described in embodiment 1 to construct, power of motor 320KW, vibrating impacter is horizontal The two ends of beam are provided with two vibration head by cable wire, and the spacing adjusted between two vibration head is 5 meters, often Individual vibrating device is connected with high-pressure hydraulic pump respectively, and on the Sandy Soil Foundation constructed, selected several need construction Position, described needs construction location suitable with the distributing position of vibration head, each construction party needing construction location Method is the most identical, and for any one needs construction location, its work progress is as follows:
The first step, is directed at the position that need to construct by the vibration head of several vibrators;
Second step, under the cooperation of high pressure water flushing, controls vibration head below cable wire vertically into constructing In Sandy Soil Foundation, until dropping to the closely knit degree of depth of described layer of sand;During vibration head moves down, described height The pressure that water pump provides is 10MPa, and its output is 400L/min;
3rd step, controls the vibration head below cable wire and is progressively lifted up, the distance control that vibration head promotes every time Make at 1.5~2 meters, the pause time of 40 seconds after every time promoting;So step up until vibration head promotes Top to the processed soil body;After vibration head promotes each time, take rubble on the spot and coral reef fragment is inserted and shaken In the dynamic pit formed;In vibration head lifting process, described high-pressure hydraulic pump provide Stress control at 2.5MPa, And output controls at 150L/min, wherein partial high pressure water offer from motor housing pars intramuralis several Through hole flows through, so that motor is lowered the temperature.
According to design requirement, repeat the step 3 time of above to three, then shift position, other need to be executed Station is put and is carried out vibration construction.
Detecting after construction, the bearing capacity of Sandy Soil Foundation reaches to design requirement.
Through measuring and calculating, construct as stated above, due to take on the spot rubble and coral reef fragment as filler etc. because of Element, not only speed of application is fast, and more environmentally-friendly, and construction cost is compared existing method and can also be saved about 30%.
Embodiment 3
Certain islands and reefs Corallium Japonicum Kishinouye hydraulic reclamation fragment sand foundation, thickness is 8~40 meters, rubble and coral reef fragment content 10~50wt%, infiltration coefficient 10-4cm/s.Design requires: the bearing capacity of 40 meters of Sandy Soil Foundations reaches 120KPa。
Before construction, conventionally, the Sandy Soil Foundation that need to construct is carried out the closely knit degree of depth of layer of sand to survey Amount, the closely knit degree of depth of described layer of sand is 40 meters.
Using several vibrating impacters described in embodiment 1 to construct, power of motor 220KW, vibrating impacter is horizontal The two ends of beam are provided with two vibration head by cable wire, and the spacing adjusted between two vibration head is 1 meter, often Individual vibrating device is connected with high-pressure hydraulic pump respectively, and on the Sandy Soil Foundation constructed, selected several need construction Position, described needs construction location suitable with the distributing position of vibration head, each construction party needing construction location Method is the most identical, and for any one needs construction location, its work progress is as follows:
The first step, is directed at the position that need to construct by the vibration head of several vibrators;
Second step, under the cooperation of high pressure water flushing, controls vibration head below cable wire vertically into constructing In Sandy Soil Foundation, until dropping to the closely knit degree of depth of described layer of sand;During vibration head moves down, described height The pressure that water pump provides is 5.0MPa, and its output is 100L/min;
3rd step, controls the vibration head below cable wire and is progressively lifted up, the distance control that vibration head promotes every time Make at 1.0~1.5 meters, the pause time of 2 seconds after every time promoting;So step up until vibration head promotes Top to the processed soil body;After vibration head promotes each time, take rubble on the spot and coral reef fragment is inserted and shaken In the dynamic pit formed;In vibration head lifting process, described high-pressure hydraulic pump provide Stress control at 10MPa, And output controls at 500L/min, wherein partial high pressure water offer from motor housing pars intramuralis several Through hole flows through, so that motor is lowered the temperature.
According to design requirement, repeat the step secondary of above to three, then shift position, other need to be executed Station is put and is carried out vibration construction.
Detecting after construction, the bearing capacity of Sandy Soil Foundation reaches to design requirement.
Through measuring and calculating, construct as stated above, due to take on the spot rubble and coral reef fragment as filler etc. because of Element, not only speed of application is fast, and more environmentally-friendly, and construction cost is compared existing method and can also be saved about 30%.
Embodiment 4
Certain islands and reefs Corallium Japonicum Kishinouye hydraulic reclamation fragment sand foundation, thickness is 15~50 meters, and rubble and coral reef fragment contain Amount 8~45wt%, infiltration coefficient 10-3cm/s.Design requires: the bearing capacity of 50 meters of Sandy Soil Foundations reaches 110KPa。
Before construction, conventionally, the Sandy Soil Foundation that need to construct is carried out the closely knit degree of depth of layer of sand to survey Amount, the closely knit degree of depth of described layer of sand is 50 meters.
Several vibrating impacters described in embodiment 1 are used to construct, power of motor 75KW, vibrating impacter crossbeam Two ends cable wire is provided with two vibration head, the spacing adjusted between two vibration head is 8 meters, each Vibrating device is connected with high-pressure hydraulic pump respectively, several positions of need to constructing selected on the Sandy Soil Foundation constructed Put, described need construction location suitable with the distributing position of vibration head, each construction method needing construction location The most identical, for any one needs construction location, its work progress is as follows:
The first step, is directed at the position that need to construct by the vibration head of several vibrators;
Second step, under the cooperation of high pressure water flushing, controls vibration head below cable wire vertically into constructing In Sandy Soil Foundation, until dropping to the closely knit degree of depth of described layer of sand;During vibration head moves down, described height The pressure that water pump provides is 15MPa, and its output is 900L/min;
3rd step, controls the vibration head below cable wire and is progressively lifted up, the distance control that vibration head promotes every time Make at 0.5~1 meter, the pause time of 30 seconds after every time promoting;So step up until vibration head promotes Top to the processed soil body;After vibration head promotes each time, take rubble on the spot and coral reef fragment is inserted and shaken In the dynamic pit formed;In vibration head lifting process, described high-pressure hydraulic pump provide Stress control at 15MPa, And output controls at 650L/min, wherein partial high pressure water offer from motor housing pars intramuralis several Through hole flows through, so that motor is lowered the temperature.
According to design requirement, repeat the step 3 time of above to three, then shift position, other need to be executed Station is put and is carried out vibration construction.
Detecting after construction, the bearing capacity of Sandy Soil Foundation reaches to design requirement.
Through measuring and calculating, construct as stated above, due to take on the spot rubble and coral reef fragment as filler etc. because of Element, not only speed of application is fast, and more environmentally-friendly, and construction cost is compared existing method and can also be saved about 30%.

Claims (10)

1. the densification process that quickly resonates of islands and reefs Corallium Japonicum Kishinouye hydraulic reclamation fragment sand, the construction that the method uses Equipment is several vibrators, and including the crossbeam being suspended on equipment body cantilever by hoist cable, crossbeam two ends are again Arranging two vibration head by cable wire, vibration head is provided with water inlet, this water inlet is connected to by pipeline High-pressure hydraulic pump, it is characterised in that described rapid densification method is included under the cooperation of high pressure water flushing, by several heads The vibration head of vibrating impacter is inserted in processed sandy soil to the required degree of depth, promotes vibration head the most step by step, Often promote 0.5~2 meter, insert in the pore-forming that vibroflotation is formed with sand or coral reef fragment on the spot, stop vibration Continue to lift up after appropriate time, repeat back-up sand soil or coral reef fragment and stop the step of vibration until promoting To processed soil body top, wherein, the spacing of described vibration head is set to 1~8 meter, described vibration head Power of motor is 75~320KW.
2. quickly resonate densification process as claimed in claim 1, it is characterised in that described several vibrations Device is provided with multiple crossbeam.
3. quickly resonate densification process as claimed in claim 1 or 2, it is characterised in that described several heads The crossbeam two ends balance of vibrator is provided with multiple vibration head.
4. quickly resonate densification process as claimed in claim 1, it is characterised in that described vibration head The inside of the shell wall of motor offers several through holes, and leader High-Pressure Water the most further Through this through hole.
5. quickly resonate densification process as claimed in claim 1, it is characterised in that described vibration head It is provided with temperature sensor in motor, is monitored for the temperature of motor;Accordingly, described vibrator It is provided with controller, and is provided with frequency modulation and voltage modulation temperature-limiting device, in the way of by frequency modulation and voltage modulation, prevent motor mistake Heat.
6. quickly resonate densification process as claimed in claim 1, it is characterised in that described vibrator sets Having controller, in record work progress automatically, each vibration compact electric current corresponding to the degree of depth is big Little, to be further ensured that construction quality.
7. quickly resonate densification process as claimed in claim 1, it is characterised in that described being processed is blown The closely knit degree of depth filling out thing is 3~50 meters.
8. quickly resonate densification process as claimed in claim 1, it is characterised in that described vibration head is inserted During entering treated object, the pressure that high-pressure hydraulic pump provides is 5~15MPa, and its output is 100L/min~900L/min.
9. quickly resonate densification process as claimed in claim 1, it is characterised in that described vibration head carries During Shenging, high-pressure hydraulic pump provide pressure be 2.5~15MPa, and its output be 150L/min~ 650L/min。
10. quickly resonate densification process as claimed in claim 1, it is characterised in that described work progress The time of middle pause is 2~40 seconds.
CN201510053459.2A 2015-02-02 2015-02-02 Quick resonance compacting method for island-reef coral filled fragment sandy soil Pending CN105986567A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510053459.2A CN105986567A (en) 2015-02-02 2015-02-02 Quick resonance compacting method for island-reef coral filled fragment sandy soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510053459.2A CN105986567A (en) 2015-02-02 2015-02-02 Quick resonance compacting method for island-reef coral filled fragment sandy soil

Publications (1)

Publication Number Publication Date
CN105986567A true CN105986567A (en) 2016-10-05

Family

ID=57037268

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510053459.2A Pending CN105986567A (en) 2015-02-02 2015-02-02 Quick resonance compacting method for island-reef coral filled fragment sandy soil

Country Status (1)

Country Link
CN (1) CN105986567A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2238328Y (en) * 1995-11-26 1996-10-23 蔡贞辉 Self-cooling floating water electric pump
JP4014403B2 (en) * 2001-12-25 2007-11-28 鹿島建設株式会社 Ground improvement method
CN102465523A (en) * 2010-11-19 2012-05-23 葛辉 Dry and dense resonance method for reinforcing soft soil foundation of new hydraulic-fill sand
CN103215944A (en) * 2013-04-10 2013-07-24 上海港湾基础建设(集团)有限公司 Multi-vibroflot resonance ground treatment equipment and method
CN203808040U (en) * 2014-01-29 2014-09-03 上海港湾基础建设(集团)有限公司 Detection and automatic recording multi-point resonator

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2238328Y (en) * 1995-11-26 1996-10-23 蔡贞辉 Self-cooling floating water electric pump
JP4014403B2 (en) * 2001-12-25 2007-11-28 鹿島建設株式会社 Ground improvement method
CN102465523A (en) * 2010-11-19 2012-05-23 葛辉 Dry and dense resonance method for reinforcing soft soil foundation of new hydraulic-fill sand
CN103215944A (en) * 2013-04-10 2013-07-24 上海港湾基础建设(集团)有限公司 Multi-vibroflot resonance ground treatment equipment and method
CN203808040U (en) * 2014-01-29 2014-09-03 上海港湾基础建设(集团)有限公司 Detection and automatic recording multi-point resonator

Similar Documents

Publication Publication Date Title
US3865501A (en) Method and device for soil compacting
CN103628463B (en) The construction method of the ultra-deep vibro replacement stone column of bad ground
CN110387896B (en) Foundation pit dewatering well design method
US4230425A (en) Method and installation for producing cast-in-situ piles
CN105040692B (en) A kind of construction method of precast concrete pile body carrier pile
CN104264655A (en) Preformed hole deep-layer underwater tamping method
CN106192981A (en) A kind of Dewatering dynamic compaction integrated device and using method thereof
CN106320340A (en) Vibrating sleeve for pile extracting and high-pressure water-jetting and pile-extracting process
US2555359A (en) Pile structure and method of making same
CN105113478A (en) Dynamic compaction treatment method of deep foundation displacement
CN108642987A (en) A kind of sandy soil liquefied foundation processing method
US9512586B2 (en) Soil densification system and method
CN103215944B (en) Multi-vibroflot resonance ground treatment equipment and method
CN107100160B (en) A kind of construction technology for lower storage reservoir check dam vibro-replacement stone column
CN102296588B (en) Construction process of underwater sand compaction pile
CN111305250A (en) Collapsible loess foundation structure treated by T-shaped compaction piles and construction method
JP2019007133A (en) Ground improvement method
CN110144872B (en) Horizontal dynamic consolidation drainage device and construction method
CN106869153B (en) A kind of method of the quick soft soil foundation treatment of well-points dewatering
CN106192980B (en) A kind of method of the closely knit sandstone ground of dither
JP6748235B2 (en) Method for compacting foundations consisting of soft mineral soil
CN105986567A (en) Quick resonance compacting method for island-reef coral filled fragment sandy soil
CN116289862A (en) Construction method of soft soil vibroflotation gravel pile composite foundation with upper open mountain layer and lower horizontal soft soil
CN210439273U (en) Vibration and impact device for vibration and impact treatment of overwater foundation
CN207003405U (en) Pneumatics ruggedized equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 201507 Shanghai Jinshan District, Caojing Town, Ting Wei Road, 3316, 1, two, 207 rooms.

Applicant after: Shanghai Bay infrastructure construction (Group) Limited by Share Ltd

Address before: 201507 eight Caojing Town, Jinshan District, Shanghai

Applicant before: Shanghai harbor infrastructure (Group) Co., Ltd.

CB02 Change of applicant information
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161005

WD01 Invention patent application deemed withdrawn after publication