CN105955752A - Method and system for controlling system online change - Google Patents
Method and system for controlling system online change Download PDFInfo
- Publication number
- CN105955752A CN105955752A CN201610318034.4A CN201610318034A CN105955752A CN 105955752 A CN105955752 A CN 105955752A CN 201610318034 A CN201610318034 A CN 201610318034A CN 105955752 A CN105955752 A CN 105955752A
- Authority
- CN
- China
- Prior art keywords
- change
- workflow activities
- unit
- relation
- perform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F8/00—Arrangements for software engineering
- G06F8/70—Software maintenance or management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F8/00—Arrangements for software engineering
- G06F8/60—Software deployment
- G06F8/65—Updates
Landscapes
- Engineering & Computer Science (AREA)
- Software Systems (AREA)
- General Engineering & Computer Science (AREA)
- Theoretical Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Computer Security & Cryptography (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention provides a method and a system for controlling system online change. The method comprises the steps of importing a change control table; generating a workflow activity graph according to the change control table; executing change items based on a sequential execution relationship among the change items from the first change item according to the workflow activity graph; after the execution of one change item is finished, executing a check script corresponding to the change item and displaying a check result on a display interface; if the check result displays that the change succeeds, executing the remaining change items based on the sequential execution relationship among the change items according to the workflow activity graph; and if the check result displays that the change fails, performing exception prompting on the display interface, pausing the influenced rear change items, and after exception processing succeeds, executing the subsequent change items based on the sequential execution relationship among the change items according to the workflow activity graph. The system change items are automatically executed by utilizing a computer and whether errors exist or not in the system change is checked, so that the manual operation errors can be reduced and the labor can be saved.
Description
Technical field
The present invention relates to computer control field, the change more particularly, it relates to a kind of control system is reached the standard grade
Method and system.
Background technology
Along with the development of financial business, Financial Information construction is constantly brought forth new ideas, and banking core business
System Construction occupy an important position especially, be mainly concerned with the change of reaching the standard grade of sorts of systems, in system
Line change needs to tackle safety upgrade production system, shorten system downtime, control Change risk etc. respectively
The problem of kind.
At present, online implementing change mode is relatively simple, prepares Variation control table in initial go-live period, reaches the standard grade
Item in period manual operation Variation control table, uses double review mechanism to reduce risk after change.
And manual operation easily makes mistakes, substantial amounts of human cost can be wasted simultaneously, therefore, need one badly and subtract
Few manual operation makes mistakes, saves artificial online implementing variation.
Summary of the invention
In view of this, the present invention provides a kind of control system to reach the standard grade variation and system, artificial to solve
Processing ease is made mistakes, the problem that simultaneously can waste substantial amounts of human cost.
For solving above-mentioned technical problem, present invention employs following technical scheme:
A kind of control system is reached the standard grade variation, and the method includes:
Import Variation control table, wherein, described Variation control table includes: change, change it
Before and after between perform relation, perform main frame, perform user, change perform script, the time started and
The inspection script that change is corresponding;
Generating workflow activities figure according to described Variation control table, wherein, described workflow activities figure is to use
The oriented flow chart that change is linked together by directed arc;
Start according to before and after between change from Section 1 change according to described workflow activities figure
Execution relation performs change;
After a change has performed, perform inspection script corresponding to described change and aobvious
Show that interface display checks result;
If check result display change successfully, then according to described workflow activities figure according to change between
Before and after perform relation perform remaining change;
If checking, result display change is unsuccessful, then carry out abnormal prompt at display interface, suspend rearmounted being subject to
Impact change, abnormality processing success after, according to described workflow activities figure according to change it
The relation that performs before and after between performs follow-up change.
Preferably, described change includes: preposition item and follow-up item, wherein, and described preposition thing
Item is for being positioned at one section of directed arc change in front, and described follow-up item is for being positioned at described one section of directed arc
The change of back.
Preferably, described generate after workflow activities figure according to Variation control table, described according to described work
Make stream activity diagram to start to perform change according to performing relation before and after between change from Section 1 change
Before more item, also include:
Start node and terminal node is inserted in described workflow activities figure.
Preferably, described in described workflow activities figure, insert start node and terminal node after, institute
State and start to hold before and after between change from Section 1 change according to described workflow activities figure
Before row relation performs change, also include:
Select the change in critical path;
When the change in critical path changes unsuccessful, while display interface carries out abnormal prompt
Control phonation unit and send tweeting sound.
Preferably, select the change in critical path, specifically include:
From the beginning of start node, before and after between described change, perform relation to described workflow
Activity diagram carries out topological sorting traversal, calculates the earliest start time of each change;
Elect the path of the change that free float is 0 included with last change as pass
Key path;
Select the change in critical path.
A kind of control system is reached the standard grade altering system, and this system includes:
Import unit, is used for importing Variation control table;
Workflow activities figure forms unit, for generating workflow activities figure according to described Variation control table;
Change performance element, for according to described workflow activities figure from Section 1 change start according to
After before and after between change, execution relation execution change, inspection result display are changed successfully, depend on
Before and after between change, the relation remaining change of execution is performed according to described workflow activities figure
And after abnormality processing success, perform before and after between change according to described workflow activities figure
Relation performs follow-up change;
Inspection unit, for after a change has performed, performs described change corresponding
Check script;
Display unit, for checking result in display interface display;
Abnormal prompt and time-out unit, be used for checking when result display change is unsuccessful, enter at display interface
Row abnormal prompt, suspends rearmounted affected change.
Preferably, described system also includes:
Insert unit, for forming unit according to described Variation control table generation work at workflow activities figure
Stream activity diagram after, change performance element according to described workflow activities figure from the beginning of Section 1 change
Before performing change according to the relation that performs before and after between change, at described workflow activities figure
Middle insertion start node and terminal node.
Preferably, described system also includes:
Select unit, be used for inserting unit in described workflow activities figure, insert start node and terminal node
After Dian, change performance element starts according to change from Section 1 change according to described workflow activities figure
Before the relation that performs before and after between more item performs change, select the change thing in critical path
?;
Phonation unit, for when the change in critical path changes unsuccessful, abnormal prompt and temporarily
Stop unit and send tweeting sound while display interface carries out abnormal prompt.
Preferably, described selection unit includes:
Computing unit, for from the beginning of start node, performs pass before and after between described change
System carries out topological sorting traversal to described workflow activities figure, when calculating the early start of each change
Between;
Critical path selects unit, and being used for including the free float with last change is 0
The path of change elect critical path as;
In critical path, change selects unit, for selecting the change in critical path.
Compared to prior art, the method have the advantages that
By above it can be seen that the invention provides a kind of control system and reach the standard grade variation and system, tool
Body, import Variation control table, generate workflow activities figure according to Variation control table, live according to workflow
Cardon starts to perform relation execution change thing before and after between change from Section 1 change
, after a change has performed, perform inspection script corresponding to described change and aobvious
Show that interface display checks result;If check result display change successfully, then foundation workflow activities figure according to
The relation that performs before and after between change performs remaining change;If checking result display change not
Success, then carry out abnormal prompt at display interface, suspend rearmounted affected change, abnormality processing
After success, before and after between change, perform the relation follow-up change of execution according to workflow activities figure
Item.So can utilize computer automatic execution system variation item and check whether system variation exists
Mistake, it is possible to reduce manual operation and make mistakes saving simultaneously manually.
Accompanying drawing explanation
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to reality
Execute the required accompanying drawing used in example or description of the prior art to be briefly described, it should be apparent that below,
Accompanying drawing in description is only embodiments of the invention, for those of ordinary skill in the art, not
On the premise of paying creative work, it is also possible to obtain other accompanying drawing according to the accompanying drawing provided.
Fig. 1 reaches the standard grade for the control system that the embodiment of the present invention one provides the flow chart of variation;
Fig. 2 reaches the standard grade for the control system that the embodiment of the present invention two provides the flow chart of variation;
Fig. 3 reaches the standard grade altering system for the control system that the embodiment of the present invention three provides;
Fig. 4 reaches the standard grade altering system for the control system that the embodiment of the present invention four provides;
Fig. 5 reaches the standard grade flow chart for cost system 20150613 version that the embodiment of the present invention five provides.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the present invention, and
It is not all, of embodiment.Based on the embodiment in the present invention, those of ordinary skill in the art are not doing
Go out the every other embodiment obtained under creative work premise, broadly fall into the scope of protection of the invention.
This application provides a kind of control system to reach the standard grade variation, referring in particular to Fig. 1, the method includes
Following steps:
S11, importing Variation control table;
It should be noted that Variation control table is typically preset by technical staff and control at needs
Manually being filled in by technical staff during online implementing processed, Variation control table includes: change, change thing
Before and after between Xiang perform relation, perform main frame, perform user, change perform script, the time started,
And the inspection script that change is corresponding.Time started is for estimating the change time started.
S12, according to Variation control table generate workflow activities figure;
It should be noted that workflow activities figure be with directed arc change is linked together oriented
Flow chart, wherein, each node on workflow activities figure is each change, and directed arc represents change
Dependence before and after more item.
S13, start according to before between change from Section 1 change according to workflow activities figure
Rear execution relation performs change i;
It should be noted that master control machine is issued an order, execution main frame and the execution user of correspondence perform change
Perform script.
S14, after change i has performed, perform inspection script corresponding to described change and
Display interface display checks result;
S15, according to checking that result judges change whether success, if successfully, then performing S17;If it is unsuccessful
Then perform S16;
S16, carry out abnormal prompt at display interface, suspend rearmounted affected change, treat exception
After processing successfully, perform S17;
S17, foundation workflow activities figure perform relation i-th change of execution before and after between change
More item, wherein i=i+1.
After S17 has performed, return to S14, perform inspection script corresponding to described change also
Result is checked in display interface display.
It should be noted that after all of change successfully changes, this change terminates.
The control system provided for the embodiment of the present invention one above is reached the standard grade variation, by this embodiment party
Formula, it is possible to utilize computer automatic execution system variation item and check whether system variation exists mistake,
Manual operation can be reduced and make mistakes saving simultaneously manually.
This application provides another control system to reach the standard grade variation, referring in particular to Fig. 2.The method
Comprise the following steps:
S21, importing Variation control table;
Wherein, Variation control table includes: performs relation before and after between change, change, hold
The inspection foot that row main frame, execution user, time started, change execution script and change are corresponding
This.Change includes: preposition item and follow-up item, and wherein, preposition item is oriented for being positioned at one section
Arc change in front, follow-up item is to be positioned at the change of this section of directed arc back.
S22, according to Variation control table generate workflow activities figure;
S23, in workflow activities figure, insert start node and terminal node;
Wherein, start node and terminal node are intended merely to indicate beginning and the end of workflow activities figure,
Do not affect the change of change.
S24, from the beginning of start node, according to performing relation before and after between change, workflow is lived
Cardon carries out topological sorting traversal, calculates the earliest start time of each change;
Wherein, the computational methods of earliest start time are the (earliest start time of preposition item+preposition thing
Change required time) maximum.
S25, the path of the change that free float is 0 that will include with last change
Elect critical path as;
S26, the change selected in critical path;
S27, start according to before between change from Section 1 change according to workflow activities figure
Rear execution relation performs change i;
S28, after change i has performed, perform inspection script corresponding to described change and
Display interface display checks result;
S29, according to checking that result judges change whether success, if successfully, then performing S213;If not becoming
Merit then performs S210;
S210, judge whether it is that the change in critical path does not changes successfully, if in critical path
Change do not change successfully, then perform S211, if not the change in critical path does not changes
Success, then perform S212;
S211, carry out abnormal prompt at display interface and control phonation unit and send tweeting sound, suspending rearmounted
Affected change, after abnormality processing success, performs S213;
S212, carry out abnormal prompt at display interface, suspend rearmounted affected change, exception
After managing successfully, perform S213;
S213, foundation workflow activities figure perform relation execution i-th before and after between change
Change, wherein, i=i+1.
After S213 has performed, return to S28, perform inspection script corresponding to described change also
Result is checked in display interface display.
It should be noted that after all of change successfully changes, this change terminates
In the present embodiment, generate after workflow activities figure, insert in workflow activities figure start node and
Terminal node can be used to beginning and the end of mark change, selects key according to earliest start time
Path, and when the change in critical path changes unsuccessful, control phonation unit sends and pipes
Sound, in such manner, it is possible to process the change fault in critical path in time, reduces the change thing in critical path
Item changes the unsuccessful impact bringing the whole change time.
This application provides a kind of control system to reach the standard grade altering system, refer to Fig. 3, specifically include importing
Unit 11, workflow activities figure form unit 12, change performance element 13, inspection unit 14, display
Unit 15, abnormal prompt and time-out unit 16.
Concrete, import unit 11, it is used for importing Variation control table;
Workflow activities figure forms unit 12, for generating workflow activities figure according to Variation control table;
Change performance element 13, for starting according to change from Section 1 change according to workflow activities figure
After before and after between more item, execution relation execution change, inspection result display are changed successfully, foundation
Workflow activities figure performs remaining change and different according to the relation that performs before and after between change
After often processing successfully, according to workflow activities figure according to execution relation execution before and after between change after
Continuous change;
Inspection unit 14, for after a change has performed, performs described change corresponding
Inspection script;
Display unit 15, for checking result in display interface display;
Abnormal prompt and time-out unit 16, be used for checking when result display change is unsuccessful, at display interface
Carry out abnormal prompt, suspend rearmounted affected change.
It should be noted that when, after abnormality processing success, change performance element 13 performs remaining change
After item and a change have performed, it is corresponding that inspection unit 14 performs described change
Check script.
Control system disclosed in the present embodiment is reached the standard grade altering system, and import unit 11 imports Variation control
Table, workflow activities figure forms unit 12 and generates workflow activities figure according to Variation control table, and change is held
Row unit 13 starts according to before between change from Section 1 change according to workflow activities figure
Rear execution relation performs change, and after a change has performed, inspection unit 14 performs
Inspection script and display unit 15 that described change is corresponding check result in display interface display;If
Check that result display is changed successfully, then change performance element 13 according to workflow activities figure according to change thing
The relation that performs before and after between Xiang performs remaining change;If checking, result display change is unsuccessful,
Then abnormal prompt and time-out unit 16 carry out abnormal prompt at display interface, suspend rearmounted affected change
More item, after abnormality processing success, changes performance element 13 according to workflow activities figure according to change thing
The relation that performs before and after between Xiang performs follow-up change.So can utilize computer automatic execution system
System change also checks whether system variation exists mistake, it is possible to minimizing manual operation makes mistakes and saves simultaneously
Manually.
The tool of unit in altering system it should be noted that control system disclosed in the present embodiment is reached the standard grade
Body running process, refers to the content of embodiment 1, and here is omitted.
This application provides another control system to reach the standard grade altering system, refer to Fig. 4.Specifically include
Import unit 11, workflow activities figure formed unit 12, change performance element 13, inspection unit 14,
Display unit 15, abnormal prompt and time-out unit 16, insertion unit 17, selection unit 18, sounding list
Unit 19.Unit 18 is wherein selected to include that computing unit 181, critical path select unit 182, critical path
On footpath, change selects unit 183.
Wherein, import unit 11, workflow activities figure form unit 12, change performance element 13, inspection
The concrete function of verification certificate unit 14, display unit 15, abnormal prompt and time-out unit 16 is with reference to embodiment
Three, do not repeat them here.
Insert unit 17, generate work for forming unit 12 at workflow activities figure according to Variation control table
After making stream activity diagram, change performance element 13 is opened from Section 1 change according to workflow activities figure
Before beginning to perform change according to the relation that performs before and after between change, in workflow activities figure
Insert start node and terminal node;
Select unit 18, be used for inserting unit 17 in workflow activities figure, insert start node and termination
After node, change performance element 13 according to workflow activities figure from Section 1 change start according to
Before the relation that performs before and after between change performs change, select the change in critical path
Item;
Computing unit 181, for from the beginning of start node, performs pass before and after between change
System carries out topological sorting traversal to workflow activities figure, calculates the earliest start time of each change;
Critical path selects unit 182, for including the free float with last change
It is that critical path is elected in the path of the change of 0 as;
In critical path, change selects unit 183, for selecting the change thing in critical path
?;
Phonation unit 19, for when in critical path change change unsuccessful time, abnormal prompt and
Suspend unit 16 and send tweeting sound while display interface carries out abnormal prompt.
It should be noted that when, after abnormality processing success, change performance element 13 performs remaining change
After item and a change have performed, it is corresponding that inspection unit 14 performs described change
Check script.
In the present embodiment, after workflow activities figure formation unit 12 generates workflow activities figure, insert single
Unit 17 inserts start node and terminal node in workflow activities figure, can be used to opening of mark change
Begin and terminate, selecting unit 18 to select critical path according to earliest start time, and at critical path
When change on footpath changes unsuccessful, phonation unit 19 sends tweeting sound, in such manner, it is possible in time
Process the change fault in critical path, reduce the change change in critical path unsuccessful to whole
The impact that the change time brings.
The tool of unit in altering system it should be noted that control system disclosed in the present embodiment is reached the standard grade
Body running process, refers to the content of embodiment 2, and here is omitted.
In order to those skilled in the art clearer can understand this programme, name cost system
The example that 20150613 versions are reached the standard grade illustrates, and refers to Fig. 5, and wherein Variation control table includes change
Perform relation before and after between item, change, perform main frame, execution user, change execution foot
The inspection script that basis, time started and change are corresponding.As shown in the table.
Wherein the time started is point 13 days 14 June in 2015, during by the beginning of each change
Between and the end time may determine that execution sequence before and after change.It should be noted that each change
One time of the time started of item and end time simply prediction, when a change has performed it
After, it is possible to perform the change of back.Wherein, change is 101-108 item change.
Variation control table is imported and generates workflow activities figure by main control computer, and workflow activities figure sees figure
5。
According to performing relation before and after between change, workflow activities figure is carried out topological sorting traversal,
Calculate the earliest start time of each change.Concrete, during the early start of 101 changes
Between be 14:30, the earliest start time of 102 changes is 14:30, and 107 changes are
Early the time started is 14:30, and the earliest start time of 103 changes is 14:50,104 changes
The earliest start time of item is 15:10, and the earliest start time of 105 changes is 15:40,106
The earliest start time of item change is 15:50, and the earliest start time of 108 changes is
14:40.Because the earliest start time of 106 changes is the most the latest, so by 106 change things
Item, as last change, will comprise 102,103,104,105,106 these several change things
Critical path is elected in the path of item as.
It is first begin to 101,102,107 changes of executed in parallel, when one of which has performed it
After, start perform inspection script corresponding to this change and on computer desktop, show inspection result.Example
As, after 101 changes have performed, perform to check script cis_check_ap81.sh, if not going out
It is normal that mistake, i.e. script return inspection value, after treating that 102 changes have performed and checked correctly, holds
103 changes of row, if there is mistake, then at computer desktop during performing in 101 changes
On carry out abnormal prompt, the most do not perform 103 changes, when abnormality processing success after, treat 102
After item change has performed and checked correctly, perform 103 changes.When 102 are changed thing
Item checks after having performed when there is mistake, because 102 changes are changes in critical path
Item, then, while computer desktop display abnormal prompt, computer sends tweeting sound.When abnormality processing becomes
After merit, perform 103 changes.
In like manner, the execution tandem of 103,104,105,106,108 changes is with reference to figure
5, the concrete execution process performing same 101,102 changes of process.When 106 changes become
When merit performs change, system variation terminates.
Described above to the disclosed embodiments, makes professional and technical personnel in the field be capable of or uses
The present invention.Multiple amendment to these embodiments will be aobvious and easy for those skilled in the art
Seeing, generic principles defined herein can be in the situation without departing from the spirit or scope of the present invention
Under, realize in other embodiments.Therefore, the present invention is not intended to be limited to these realities shown in this article
Execute example, and be to fit to the widest scope consistent with principles disclosed herein and features of novelty.
Claims (9)
1. a control system is reached the standard grade variation, it is characterised in that the method includes:
Import Variation control table, wherein, described Variation control table includes: change, change it
Before and after between perform relation, perform main frame, perform user, change perform script, the time started and
The inspection script that change is corresponding;
Generating workflow activities figure according to described Variation control table, wherein, described workflow activities figure is to use
The oriented flow chart that change is linked together by directed arc;
Start according to before and after between change from Section 1 change according to described workflow activities figure
Execution relation performs change;
After a change has performed, perform inspection script corresponding to described change and aobvious
Show that interface display checks result;
If check result display change successfully, then according to described workflow activities figure according to change between
Before and after perform relation perform remaining change;
If checking, result display change is unsuccessful, then carry out abnormal prompt at display interface, suspend rearmounted being subject to
Impact change, abnormality processing success after, according to described workflow activities figure according to change it
The relation that performs before and after between performs follow-up change.
Online implementing variation the most according to claim 1, it is characterised in that described change
Item includes: preposition item and follow-up item, wherein, before described preposition item is for being positioned at one section of directed arc
The change on limit, described follow-up item is to be positioned at the change of described one section of directed arc back.
Online implementing variation the most according to claim 1, it is characterised in that described basis
Variation control table generates after workflow activities figure, described becomes from Section 1 according to described workflow activities figure
Before more item starts to perform change according to the relation that performs before and after between change, also include:
Start node and terminal node is inserted in described workflow activities figure.
Online implementing variation the most according to claim 3, it is characterised in that described in institute
State after workflow activities figure inserts start node and terminal node, described according to described workflow activities
Figure from Section 1 change start according to the relation that performs before and after between change perform change it
Before, also include:
Select the change in critical path;
When the change in critical path changes unsuccessful, while display interface carries out abnormal prompt
Control phonation unit and send tweeting sound.
Online implementing variation the most according to claim 4, it is characterised in that select pass
Change on key path, specifically includes:
From the beginning of start node, before and after between described change, perform relation to described work
Stream activity diagram carries out topological sorting traversal, calculates the earliest start time of each change;
Elect the path of the change that free float is 0 included with last change as pass
Key path;
Select the change in critical path.
6. a control system is reached the standard grade altering system, it is characterised in that this system includes:
Import unit, is used for importing Variation control table;
Workflow activities figure forms unit, for generating workflow activities figure according to described Variation control table;
Change performance element, for according to described workflow activities figure from Section 1 change start according to
After before and after between change, execution relation execution change, inspection result display are changed successfully, depend on
Before and after between change, the relation remaining change of execution is performed according to described workflow activities figure
And after abnormality processing success, perform before and after between change according to described workflow activities figure
Relation performs follow-up change;
Inspection unit, for after a change has performed, performs described change corresponding
Check script;
Display unit, for checking result in display interface display;
Abnormal prompt and time-out unit, be used for checking when result display change is unsuccessful, enter at display interface
Row abnormal prompt, suspends rearmounted affected change.
System the most according to claim 6, it is characterised in that described system also includes:
Insert unit, for forming unit according to described Variation control table generation work at workflow activities figure
Stream activity diagram after, change performance element according to described workflow activities figure from the beginning of Section 1 change
Before performing change according to the relation that performs before and after between change, at described workflow activities figure
Middle insertion start node and terminal node.
System the most according to claim 7, it is characterised in that described system also includes:
Select unit, be used for inserting unit in described workflow activities figure, insert start node and terminal node
After Dian, change performance element starts according to change from Section 1 change according to described workflow activities figure
Before the relation that performs before and after between more item performs change, select the change thing in critical path
?;
Phonation unit, for when the change in critical path changes unsuccessful, abnormal prompt and temporarily
Stop unit and send tweeting sound while display interface carries out abnormal prompt.
System the most according to claim 8, it is characterised in that described selection unit includes:
Computing unit, for from the beginning of start node, performs pass before and after between described change
System carries out topological sorting traversal to described workflow activities figure, when calculating the early start of each change
Between;
Critical path selects unit, and being used for including the free float with last change is 0
The path of change elect critical path as;
In critical path, change selects unit, for selecting the change in critical path.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610318034.4A CN105955752B (en) | 2016-05-13 | 2016-05-13 | A kind of online variation of control system and system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610318034.4A CN105955752B (en) | 2016-05-13 | 2016-05-13 | A kind of online variation of control system and system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105955752A true CN105955752A (en) | 2016-09-21 |
CN105955752B CN105955752B (en) | 2019-01-25 |
Family
ID=56911786
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610318034.4A Active CN105955752B (en) | 2016-05-13 | 2016-05-13 | A kind of online variation of control system and system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105955752B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110471821A (en) * | 2019-08-07 | 2019-11-19 | 深圳市腾讯计算机系统有限公司 | Abnormal alteration detection method, server and computer readable storage medium |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101403965A (en) * | 2008-11-18 | 2009-04-08 | 四川赛文纳克软件有限公司 | Integration type iteration software development process control system and method |
CN101403964A (en) * | 2008-11-18 | 2009-04-08 | 四川赛文纳克软件有限公司 | Integration type software configuration management method based on transaction management |
CN102486730A (en) * | 2010-12-06 | 2012-06-06 | 上海协讯软件有限公司 | Workflow realization method and workflow system capable of customizing flow in user-defined manner |
CN105302542A (en) * | 2014-07-14 | 2016-02-03 | 柯尼卡美能达株式会社 | Workflow system, workflow executing device, workflow executing method |
-
2016
- 2016-05-13 CN CN201610318034.4A patent/CN105955752B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101403965A (en) * | 2008-11-18 | 2009-04-08 | 四川赛文纳克软件有限公司 | Integration type iteration software development process control system and method |
CN101403964A (en) * | 2008-11-18 | 2009-04-08 | 四川赛文纳克软件有限公司 | Integration type software configuration management method based on transaction management |
CN102486730A (en) * | 2010-12-06 | 2012-06-06 | 上海协讯软件有限公司 | Workflow realization method and workflow system capable of customizing flow in user-defined manner |
CN105302542A (en) * | 2014-07-14 | 2016-02-03 | 柯尼卡美能达株式会社 | Workflow system, workflow executing device, workflow executing method |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110471821A (en) * | 2019-08-07 | 2019-11-19 | 深圳市腾讯计算机系统有限公司 | Abnormal alteration detection method, server and computer readable storage medium |
CN110471821B (en) * | 2019-08-07 | 2023-10-13 | 深圳市腾讯计算机系统有限公司 | Abnormality change detection method, server, and computer-readable storage medium |
Also Published As
Publication number | Publication date |
---|---|
CN105955752B (en) | 2019-01-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106506283B (en) | Business test method and device of bank and enterprise docking system | |
US20140325480A1 (en) | Software Regression Testing That Considers Historical Pass/Fail Events | |
US9734045B2 (en) | Generating test cases | |
CN108121543B (en) | Software code compiling processing method and device | |
US8214245B2 (en) | Method and system for synchronizing inclusive decision branches | |
Derezinska et al. | Experimental evaluation of mutation testing approaches to python programs | |
KR102160780B1 (en) | Bug fixing system and bug fixing method | |
JP2021525914A5 (en) | ||
CN110599341A (en) | Transaction calling method and system | |
TW201616377A (en) | Reorganizing and presenting data fields with erroneous inputs | |
CN106022912A (en) | Evaluation model updating method and evaluation model updating system | |
CN113448380A (en) | Method and device for synchronously switching accounting dates | |
CN104158905B (en) | The creation method of web container | |
CN105930226A (en) | Data processing method and apparatus | |
CN105955752A (en) | Method and system for controlling system online change | |
CN110597688A (en) | Monitoring information acquisition method and system | |
CN103034553B (en) | Intelligent verification algorithm, method and device for report designer | |
JP2016143134A (en) | Relevant information distribution method, relevant information distribution system and relevant information distribution program | |
CN114064012B (en) | Dynamic and static combined interface code generation method and system and electronic equipment | |
JP2014106912A (en) | Constraint extraction program, constraint extraction device and constraint extraction method | |
CN110912743B (en) | Method and device for executing configuration instruction | |
CN115080382A (en) | Code testing method, device, equipment and medium | |
US8510342B1 (en) | Automatic conversion of build processes to use streaming input | |
CN110992448A (en) | Animation processing method and device, electronic equipment and storage medium | |
CN106815034A (en) | A kind of data updating method and device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |