CN105930984A - Project dynamic management method and system - Google Patents

Project dynamic management method and system Download PDF

Info

Publication number
CN105930984A
CN105930984A CN201610375724.3A CN201610375724A CN105930984A CN 105930984 A CN105930984 A CN 105930984A CN 201610375724 A CN201610375724 A CN 201610375724A CN 105930984 A CN105930984 A CN 105930984A
Authority
CN
China
Prior art keywords
subtask
engineering
tasks carrying
dynamic management
serial number
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610375724.3A
Other languages
Chinese (zh)
Inventor
曾开发
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Chenxi Information Technology Co Ltd
Original Assignee
Fujian Chenxi Information Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Chenxi Information Technology Co Ltd filed Critical Fujian Chenxi Information Technology Co Ltd
Priority to CN201610375724.3A priority Critical patent/CN105930984A/en
Publication of CN105930984A publication Critical patent/CN105930984A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention belongs to the construction project field and relates to a project dynamic management method and a project dynamic management system. According to the project dynamic management method and system, when a project task is created, the execution order of sub tasks is determined; in the execution process of the project task, the executor of each sub task only needs to be responsible for the corresponding task and can skip without being responsible for selecting the executor of a next sub task; and as for a special field where the construction period of a construction project is long, the project dynamic management method provided by the invention can make project management be more convenient. Unified management is carried out by the background. When unexecuted sub tasks are needed to be changed, the sub tasks can be replaced through the serial numbers of the sub tasks, and therefore, project dynamic management can be realized.

Description

A kind of engineering dynamic management approach and system
Technical field
The present invention relates to building engineering field, particularly relate to a kind of engineering dynamic management approach and system.
Background technology
At building engineering field, initiateing to completion of an architectural engineering needs through ten several steps or links, Traditional way to manage uses workflow management, and the OA flow process that similar office is used, when first link is held Row is complete, the executor of this link select the executor of next link, and after completing, flow process jumps to next ring The executor of joint, now the executor of current link starts to perform, by that analogy, until last link Executor complete, represent that this engineering completes.
But traditional management method in use there are the following problems:
1, the cycle of architectural engineering is longer, and the time interval between each link is longer, usually occurs flow process When going to next link executor, this executor has left office or by transfer of personnel, causes flow process to continue Continue down;
2, when needing follow-up link is changed during architectural engineering performs, it is impossible to change.
Summary of the invention
The technical problem to be solved is: provide one to be applicable to building engineering field and motility is strong Engineering dynamic management approach and system.
In order to solve above-mentioned technical problem, the technical solution used in the present invention is:
A kind of engineering dynamic management approach, including:
Creating engineering duty, described engineering duty includes list and multiple subtask;Described list storage has many The numbering of the execution sequence of individual subtask;
According to list successively subtasking;
When receiving the change request of unenforced subtask during engineering duty performs, record is current The numbering corresponding to subtask performed;
The numbering of the subtask according to request change updates behind subtask, continue executing with described in be currently executing Subtask.
The another kind of technical scheme that the present invention provides is:
A kind of engineering dynamic management system, including: creation module, execution module, logging modle and renewal mould Block;
Described creation module, is used for creating engineering duty, and described engineering duty includes list and multiple subtask; Described list storage has the numbering of the execution sequence of multiple subtask;
Described execution module, for according to list successively subtasking;
Described logging modle, receiving the change of unenforced subtask when engineering duty during performing please When asking, the numbering corresponding to subtask that record is currently executing;
Described more new module, after updating subtask according to the numbering of the subtask of request change, continues executing with institute State the subtask being currently executing.
The beneficial effects of the present invention is: during by establishment engineering duty, determine that the execution sequence of subtask, During engineering duty performs, the executor of each subtask only need to be responsible for task itself, it is not necessary to is responsible for choosing The executor selecting next subtask can redirect, this special dimension longer for the architectural engineering duration and Speech, the engineering dynamic management approach that the present invention provides makes engineering management become convenient, backstage carry out unifying pipe Reason.When unenforced subtask is changed by needs, can be substituted by subtask numbering, it is achieved work Journey dynamically manages.
Accompanying drawing explanation
Fig. 1 is the flow chart of steps of a kind of engineering dynamic management approach of the present invention;
Fig. 2 is the structural representation of a kind of engineering dynamic management system of the present invention;
Label declaration:
1, creation module;2, module is performed;3, logging modle;4, more new module.
Detailed description of the invention
By describing the technology contents of the present invention in detail, being realized purpose and effect, below in conjunction with embodiment also Accompanying drawing is coordinated to be explained.
The design of most critical of the present invention is: determine that the execution sequence of subtask during by establishment engineering duty, During engineering duty performs, the executor of each subtask only need to be responsible for task itself, for building For this special dimension that duration of a project is longer, the engineering dynamic management approach that the present invention provides makes engineering pipe Reason becomes convenient, backstage be managed collectively.
Refer to Fig. 1, a kind of engineering dynamic management approach that the present invention provides, including:
Creating engineering duty, described engineering duty includes list and multiple subtask;Described list storage has many The numbering of the execution sequence of individual subtask;
According to list successively subtasking;
When receiving the change request of unenforced subtask during engineering duty performs, record is current The numbering corresponding to subtask performed;
The numbering of the subtask according to request change updates behind subtask, continue executing with described in be currently executing Subtask.
Knowable to foregoing description, the beneficial effects of the present invention is: by determining that when creating engineering duty that son is appointed The execution sequence of business, during engineering duty performs, the executor of each subtask only need to be responsible for task Itself, it is not necessary to it is responsible for selecting the executor of next subtask to redirect, longer for the architectural engineering duration This special dimension for, the present invention provide engineering dynamic management approach make engineering management become convenient, It is managed collectively by backstage.When unenforced subtask is changed by needs, numbered by subtask Can substitute, it is achieved engineering dynamically manages.
Further, described subtask includes task names, tasks carrying content and tasks carrying department.
Further, described " according to list successively subtasking " particularly as follows:
When tasks carrying department receives described subtask, appoint according to task names and tasks carrying content choice Business executor;
When tasks carrying people has performed described subtask, jump to next height according to the execution sequence in list Tasks carrying department corresponding to task.
Seen from the above description, for subtasking, the list in the engineering duty that the present invention creates is concrete Being the numbering of the execution sequence storing multiple tasks carrying departments, for engineering, tasks carrying department is Will not change, the personnel in department change often, thus jump to according to the execution sequence in list Next tasks carrying department corresponding to subtask, is specified executor to go to perform by this tasks carrying department again This task so that the engineering duty of establishment can continuously carry out down.
Further, the step of described renewal subtask includes:
Determine the Base Serial Number of the subtask that need to change, according to described Base Serial Number and default finish number meter Calculate the subtask quantity obtaining currently can substituting;Described Base Serial Number is the numbering of unenforced subtask;
Whether the subtask quantity that judgement need to be changed is beyond the subtask quantitative range that currently can substitute, if exceeding, Then it is calculated number differences;
Behind the subtask of described finish number, the subtask of respective amount is increased according to described number differences;
Subtask is updated by described Base Serial Number.
Further, if the subtask quantity that need to change is without departing from the subtask quantitative range that currently can substitute, Subtask is updated by described Base Serial Number.
Seen from the above description, first judge that space, original subtask is the most enough deposited new before updating subtask Subtask (includes replacing subtask and increasing subtask), when the subtask quantity that need to change is without departing from currently may be used During the subtask quantitative range substituted, can directly start to update, if exceeding, then according to calculating from Base Serial Number The number differences obtained increases the subtask of respective amount behind the subtask of described finish number, then updates. Can disposably update during renewal, it is not necessary to when updating to half, find that original inadequate resource goes to apply for resource again, Cause timeliness low.
Refer to Fig. 2, a kind of engineering dynamic management system that the present invention provides, including: creation module 1, hold Row module 2, logging modle 3 and more new module 4;
Described creation module 1, is used for creating engineering duty, and described engineering duty includes list and multiple subtask; Described list storage has the numbering of the execution sequence of multiple subtask;
Described execution module 2, for according to list successively subtasking;
Described logging modle 3, receiving the change of unenforced subtask when engineering duty during performing please When asking, the numbering corresponding to subtask that record is currently executing;
Described more new module 4, after updating subtask according to the numbering of the subtask of request change, continues executing with institute State the subtask being currently executing.
Knowable to foregoing description, the beneficial effects of the present invention is: by determining that when creating engineering duty that son is appointed The execution sequence of business, during engineering duty performs, the executor of each subtask only need to be responsible for task Itself, it is not necessary to it is responsible for selecting the executor of next subtask to redirect, longer for the architectural engineering duration This special dimension for, the present invention provide engineering dynamic management approach make engineering management become convenient, It is managed collectively by backstage.When unenforced subtask is changed by needs, numbered by subtask Can substitute, it is achieved engineering dynamically manages.
Further, described subtask includes task names, tasks carrying content and tasks carrying department.
Further, described execution module 2 also includes selecting unit and jump-transfer unit;
Described selection unit, when tasks carrying department receives described subtask, according to task names and Tasks carrying content choice tasks carrying people;
Described jump-transfer unit, when tasks carrying people has performed described subtask, according to the execution in list Order jumps to next tasks carrying department corresponding to subtask.
Seen from the above description, for subtasking, the list in the engineering duty that the present invention creates is concrete Being the numbering of the execution sequence storing multiple tasks carrying departments, for engineering, tasks carrying department is Will not change, the personnel in department change often, thus jump to according to the execution sequence in list Next tasks carrying department corresponding to subtask, is specified executor to go to perform by this tasks carrying department again This task so that the engineering duty of establishment can continuously carry out down.
Further, described more new module 4 also includes computing unit, judging unit, increase unit and renewal Unit;
Described computing unit, for determining the Base Serial Number of the subtask that need to change, according to described Base Serial Number The subtask quantity that currently can substitute it is calculated with default finish number;Described Base Serial Number is for being not carried out The numbering of subtask;
Described judging unit, for judging whether the subtask quantity that need to change appoints beyond the son that currently can substitute Business quantitative range, if exceeding, is then calculated number differences;
Described increase unit, right for increasing behind the subtask of described finish number according to described number differences Answer the subtask of quantity;
Described updating block, for updating subtask by described Base Serial Number.
Further, described judging unit, if the subtask quantity being additionally operable to change can be more without departing from currently During the subtask quantitative range replaced, by described Base Serial Number, update subtask.
Seen from the above description, first judge that space, original subtask is the most enough deposited new before updating subtask Subtask (includes replacing subtask and increasing subtask), when the subtask quantity that need to change is without departing from currently may be used During the subtask quantitative range substituted, can directly start to update, if exceeding, then according to calculating from Base Serial Number The number differences obtained increases the subtask of respective amount behind the subtask of described finish number, then updates. Can disposably update during renewal, it is not necessary to when updating to half, find that original inadequate resource goes to apply for resource again, Cause timeliness low.
Refer to Fig. 1-2, embodiments of the invention one are:
A kind of engineering dynamic management approach that the present invention provides, including:
Creating engineering duty, described engineering duty includes list and multiple subtask;Described list storage has many The numbering of the execution sequence of individual subtask;Described subtask includes task names, tasks carrying content and task Executive arm.
According to list successively subtasking;Particularly as follows:
When tasks carrying department receives described subtask, appoint according to task names and tasks carrying content choice Business executor;
When tasks carrying people has performed described subtask, jump to next height according to the execution sequence in list Tasks carrying department corresponding to task.
For subtasking, the list in the engineering duty that the present invention creates specifically stores multiple task and holds The numbering of the execution sequence of row department, for engineering, tasks carrying department will not change, department Interior personnel change often, thus it is right to jump to next subtask institute according to the execution sequence in list The tasks carrying department answered, is specified executor to go to perform this task by this tasks carrying department again so that create Engineering duty can continuously carry out down.
When receiving the change request of unenforced subtask during engineering duty performs, record is current The numbering corresponding to subtask performed;
The numbering of the subtask according to request change updates behind subtask, continue executing with described in be currently executing Subtask.
The step of described renewal subtask includes:
Determine the Base Serial Number of the subtask that need to change, according to described Base Serial Number and default finish number meter Calculate the subtask quantity obtaining currently can substituting;Described Base Serial Number is the numbering of unenforced subtask;
Whether the subtask quantity that judgement need to be changed is beyond the subtask quantitative range that currently can substitute, if exceeding, Then it is calculated number differences;
Behind the subtask of described finish number, the subtask of respective amount is increased according to described number differences;
Subtask is updated by described Base Serial Number.
Wherein, if the subtask quantity that need to change is without departing from the subtask quantitative range that currently can substitute, by Described Base Serial Number starts to update subtask.
First judge before updating subtask that space, original subtask is the most enough deposited new subtask and (included replacing Subtask and increase subtask), when the subtask quantity that need to change is without departing from the subtask quantity that currently can substitute During scope, can directly starting to update from Base Serial Number, if exceeding, then existing according to calculated number differences Increase the subtask of respective amount behind the subtask of described finish number, then update.Can the most more during renewal Newly, it is not necessary to when updating to half, find that original inadequate resource goes to apply for resource again, cause timeliness low.
In sum, a kind of engineering dynamic management approach of present invention offer and system, by creating engineering duty Time determine that the execution sequence of subtask, during engineering duty performs, the executor of each subtask Only need to be responsible for task itself, it is not necessary to be responsible for selecting the executor of next subtask can redirect, for building For this special dimension that duration of a project is longer, the engineering dynamic management approach that the present invention provides makes engineering pipe Reason becomes convenient, backstage be managed collectively.When unenforced subtask is changed by needs, logical Cross subtask numbering can substitute, it is achieved engineering dynamically manages.
The foregoing is only embodiments of the invention, not thereby limit the scope of the claims of the present invention, every profit The equivalents made by description of the invention and accompanying drawing content, or directly or indirectly it is used in relevant technology Field, is the most in like manner included in the scope of patent protection of the present invention.

Claims (10)

1. an engineering dynamic management approach, it is characterised in that including:
Creating engineering duty, described engineering duty includes list and multiple subtask;Described list storage has many The numbering of the execution sequence of individual subtask;
According to list successively subtasking;
When receiving the change request of unenforced subtask during engineering duty performs, record is current The numbering corresponding to subtask performed;
The numbering of the subtask according to request change updates behind subtask, continue executing with described in be currently executing Subtask.
Engineering dynamic management approach the most according to claim 1, it is characterised in that described subtask is wrapped Include task names, tasks carrying content and tasks carrying department.
Engineering dynamic management approach the most according to claim 2, it is characterised in that described " according to row Table subtasking successively " particularly as follows:
When tasks carrying department receives described subtask, appoint according to task names and tasks carrying content choice Business executor;
When tasks carrying people has performed described subtask, jump to next height according to the execution sequence in list Tasks carrying department corresponding to task.
Engineering dynamic management approach the most according to claim 1, it is characterised in that described renewal is appointed The step of business includes:
Determine the Base Serial Number of the subtask that need to change, according to described Base Serial Number and default finish number meter Calculate the subtask quantity obtaining currently can substituting;Described Base Serial Number is the numbering of unenforced subtask;
Whether the subtask quantity that judgement need to be changed is beyond the subtask quantitative range that currently can substitute, if exceeding, Then it is calculated number differences;
Behind the subtask of described finish number, the subtask of respective amount is increased according to described number differences;
Subtask is updated by described Base Serial Number.
Engineering dynamic management approach the most according to claim 4, it is characterised in that if the son that need to change When task quantity is without departing from the subtask quantitative range that currently can substitute, by described Base Serial Number, update son Task.
6. an engineering dynamic management system, it is characterised in that including: creation module, execution module, note Record module and more new module;
Described creation module, is used for creating engineering duty, and described engineering duty includes list and multiple subtask; Described list storage has the numbering of the execution sequence of multiple subtask;
Described execution module, for according to list successively subtasking;
Described logging modle, receiving the change of unenforced subtask when engineering duty during performing please When asking, the numbering corresponding to subtask that record is currently executing;
Described more new module, after updating subtask according to the numbering of the subtask of request change, continues executing with institute State the subtask being currently executing.
Engineering dynamic management system the most according to claim 6, it is characterised in that described subtask is wrapped Include task names, tasks carrying content and tasks carrying department.
Engineering dynamic management system the most according to claim 7, it is characterised in that described execution module Also include selecting unit and jump-transfer unit;
Described selection unit, when tasks carrying department receives described subtask, according to task names and Tasks carrying content choice tasks carrying people;
Described jump-transfer unit, when tasks carrying people has performed described subtask, according to the execution in list Order jumps to next tasks carrying department corresponding to subtask.
Engineering dynamic management system the most according to claim 6, it is characterised in that described more new module Also include computing unit, judging unit, increase unit and updating block;
Described computing unit, for determining the Base Serial Number of the subtask that need to change, according to described Base Serial Number The subtask quantity that currently can substitute it is calculated with default finish number;Described Base Serial Number is for being not carried out The numbering of subtask;
Described judging unit, for judging whether the subtask quantity that need to change appoints beyond the son that currently can substitute Business quantitative range, if exceeding, is then calculated number differences;
Described increase unit, right for increasing behind the subtask of described finish number according to described number differences Answer the subtask of quantity;
Described updating block, for updating subtask by described Base Serial Number.
Engineering dynamic management system the most according to claim 9, it is characterised in that described judgement list Unit, if be additionally operable to the subtask quantity that need to change without departing from the subtask quantitative range that currently can substitute, by Described Base Serial Number starts to update subtask.
CN201610375724.3A 2016-05-31 2016-05-31 Project dynamic management method and system Pending CN105930984A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610375724.3A CN105930984A (en) 2016-05-31 2016-05-31 Project dynamic management method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610375724.3A CN105930984A (en) 2016-05-31 2016-05-31 Project dynamic management method and system

Publications (1)

Publication Number Publication Date
CN105930984A true CN105930984A (en) 2016-09-07

Family

ID=56832783

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610375724.3A Pending CN105930984A (en) 2016-05-31 2016-05-31 Project dynamic management method and system

Country Status (1)

Country Link
CN (1) CN105930984A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107784448A (en) * 2017-11-07 2018-03-09 中国银行股份有限公司 Task management method and system under a kind of waterfall model
CN108108895A (en) * 2017-12-19 2018-06-01 上海携程商务有限公司 Method, system, equipment and the storage medium of task status dynamic management and control

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101770616A (en) * 2010-02-09 2010-07-07 北京航空航天大学 Multi-level collaborative project plan management method
CN101866458A (en) * 2010-06-23 2010-10-20 用友软件股份有限公司 Method and system for obtaining schedule data of task
CN102542379A (en) * 2010-12-20 2012-07-04 中国移动通信集团公司 Method, system and device for processing scheduled tasks

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101770616A (en) * 2010-02-09 2010-07-07 北京航空航天大学 Multi-level collaborative project plan management method
CN101866458A (en) * 2010-06-23 2010-10-20 用友软件股份有限公司 Method and system for obtaining schedule data of task
CN102542379A (en) * 2010-12-20 2012-07-04 中国移动通信集团公司 Method, system and device for processing scheduled tasks

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107784448A (en) * 2017-11-07 2018-03-09 中国银行股份有限公司 Task management method and system under a kind of waterfall model
CN108108895A (en) * 2017-12-19 2018-06-01 上海携程商务有限公司 Method, system, equipment and the storage medium of task status dynamic management and control
CN108108895B (en) * 2017-12-19 2021-01-26 上海携程商务有限公司 Method, system, equipment and storage medium for dynamically controlling task state

Similar Documents

Publication Publication Date Title
JP6122967B2 (en) Plan linkage system and plan linkage method
CN102592198B (en) A kind of workflow engine supporting composite service
CN103714414A (en) Process node returning method used for intelligent power grid dispatching
Anisimov et al. Model and algorithm for substantiating solutions for organization of high-rise construction project
Chua et al. PDM++: Planning framework from a construction requirements perspective
CN105930984A (en) Project dynamic management method and system
CN103729742B (en) A kind of Data Resources Management System based on SOA framework and executing model drive structure
US11341292B2 (en) Production plan supporting apparatus and method
CN101695080A (en) Execution method of BPMN composition service and execution device thereof
CN112465451A (en) Optimization method for project parallel and multi-resource supporting scheme
Li et al. Single machine scheduling with two-agent for total weighted completion time objectives
CN114169801A (en) Workflow scheduling method and device
JP2007148635A (en) Production scheduling program and production scheduling device
CN104731695A (en) Unit testing system and method supporting table-driven underlying input
CN110532311A (en) A kind of distributed data deriving method and system based on queue
CN105160475A (en) Three-dimensional visualization system of nuclear power project progress
CN115496373A (en) Task allocation method and device applied to agile management platform
Xiao et al. A constraint-driven human resource scheduling method in software development and maintenance process
CN101101551A (en) Method for automatically establishing procedure body
JP7247051B2 (en) Planning support device and method
Nisar et al. Resource-Dependent Critical Path Method for Identifying the Critical Path and the “Real Floats” in Resource-Constrained Project Scheduling
Liu et al. Semi-Automatic Hybrid Software Deployment Workflow in a Research Computing Center
Zhao et al. An extended process model supporting software evolution
CN104572304A (en) Method for intelligently maintaining and managing cluster rendering tasks in balance manner
CN104184632A (en) Method for analyzing performance of communication protocol router

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160907