CN105926534A - Intelligent hinge type protection slope, slope protection method and protection slope construction method - Google Patents

Intelligent hinge type protection slope, slope protection method and protection slope construction method Download PDF

Info

Publication number
CN105926534A
CN105926534A CN201610299706.1A CN201610299706A CN105926534A CN 105926534 A CN105926534 A CN 105926534A CN 201610299706 A CN201610299706 A CN 201610299706A CN 105926534 A CN105926534 A CN 105926534A
Authority
CN
China
Prior art keywords
protection
slope
hinge type
building block
main body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610299706.1A
Other languages
Chinese (zh)
Inventor
任伟
董伟智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Water Resources Ecological Environment Technology Co Ltd
Original Assignee
Shaanxi Water Resources Ecological Environment Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Water Resources Ecological Environment Technology Co Ltd filed Critical Shaanxi Water Resources Ecological Environment Technology Co Ltd
Priority to CN201610299706.1A priority Critical patent/CN105926534A/en
Publication of CN105926534A publication Critical patent/CN105926534A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G9/00Cultivation in receptacles, forcing-frames or greenhouses; Edging for beds, lawn or the like
    • A01G9/02Receptacles, e.g. flower-pots or boxes; Glasses for cultivating flowers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/14Preformed blocks or slabs for forming essentially continuous surfaces; Arrangements thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental Sciences (AREA)
  • Revetment (AREA)

Abstract

The invention relates to the field of slope protection, in particular to an intelligent hinge type protection slope, a slope protection method and a protection slope construction method. A building block combined body is included. The building block combined body comprises a plurality of building block main bodies. The multiple building block main bodies are connected into a whole through a connecting line. Each building block main body is a prefabricated concrete block. The connecting line is a galvanized steel cable or a polyester rope. The galvanized steel cable or the polyester rope is used for mutually connecting the building block main bodies to form a lock type matrix. The building block main bodies are provided with rope holes. The galvanized steel cable or the polyester rope penetrates through the rope holes. The building block main bodies comprise planting holes. Plants are arranged in the planting holes. The protection slope is high in deformation capacity, so that the protection slope can adapt to various terrains, suspension cavities cannot be caused by too close connection, accordingly potential safety hazards cannot be further caused, and the protection slop cannot be overall torn either. Due to the fact that the protection slope is a prepared main body, direct conveying and placing can also be achieved, and the construction speed is high.

Description

Intelligence hinge type bank protection and bank protecting method and slope protection construction method
Technical field
The present invention relates to bank protection field, particularly relate to intelligence hinge type bank protection and bank protecting method and slope protection construction method.
Background technology
Existing protective slope structure and bank protecting method have the drawback that
Card is with too closely each other, is easily torn overall landing river levee local collapse when;
Card is with too closely each other, and dangerous hidden danger is caused in easily cavity, lower section;
Speed of application is slow, since it is desired that one piece one piece construction.
Summary of the invention
The purpose of invention: in order to provide a kind of effect preferably intelligence hinge type bank protection and bank protecting method and slope protection construction Method, specific purposes are shown in the multiple substantial technological effects being embodied as part.
In order to reach as above purpose, the present invention adopts the following technical scheme that:
Scheme one:
Intelligence hinge type bank protection, it is characterised in that comprising building block association, building block association comprises multiple block main body, multiple Block main body is connected line to be worn is an entirety, and block main body is precast concrete block, and connecting line is zinc-plated wirerope or polyester Hawser, is interconnected to form linked matrix with zinc-plated wirerope or polyester hawser, block main body comprises string holes, zinc-plated Wirerope or polyester hawser, through this string holes, block main body comprise implantation hole, comprise plant in implantation hole.
The further technical scheme of the present invention is, so block main body is hypotenuse, the interface between block main body can be kissed Incompatible reply slope descent.
The further technical scheme of the present invention is, comprises filter reticulated or the filtration of classification below described building block association Pad, is stratum below the filter pad of filter reticulated or classification.
The further technical scheme of the present invention is, described plant is Caulis Miscanthis floriduli, after building block association plantation Caulis Miscanthis floriduli is Caulis Miscanthis floriduli-hinge type slope protection ecologic dummy.
The further technical scheme of the present invention is, comprises middle lock dog in described connecting line, and middle lock dog is by block main body Relative localization is in building block association.
The further technical scheme of the present invention is, comprises cavity, also have cavity in the middle part of middle lock body in the middle part of described connecting line And cavity and cavity connect, and cavity comprises hole.
The further technical scheme of the present invention is, described inside cavity comprises moisture transducer, and moisture transducer passes through line Road externally protrudes, and circuit is walked in the cavity in connecting line.
The further technical scheme of the present invention is, described in stretch out the circuit external connection alarming device of connecting line.
Scheme two:
Intelligence hinge type bank protecting method, it is characterised in that utilize as above the most described bank protection, be laid on bank protection on gradient face.
Scheme three:
The construction method of intelligence hinge type bank protection, it is characterised in that comprise the steps of:
River proposes main body compacting and carries out based process, and after unwrapping wire, artificial accurately process is domatic, makes slope leveling;
Laying geotextiles, geotextile laying must accomplish that domatic nothing jams on, smooth aptychus;
Hinge type revetment brick is laid, and uses slide type specific purpose tool to be transported to brick lay near sites, carries out wirerope perforation peace Dress, perforation installation need to wear wirerope from top to bottom;Or building block association is directly transported and lays;
Wirerope joint processes, and needs every two wireropes to be fixed process.
Use the present invention of as above technical scheme, have the advantages that relative to prior art: the deformation energy of this patent Power is strong, further such that this patent adapts to various landform, too closely unsettled cavity will be caused further because of connecting Causing dangerous hidden danger, also will not overall tear, owing to this patent is the main body prepared, directly transport placement can also realize, real Existing speed is fast.
Accompanying drawing explanation
In order to further illustrate the present invention, it is further illustrated below in conjunction with the accompanying drawings:
Fig. 1 is the local detail schematic diagram that the present invention implements;
Fig. 2 is present invention partial schematic diagram after basic unit subsides;
Fig. 3 is the partial schematic diagram that the present invention is coated with in basic unit;
Fig. 4 is the structural representation of the present invention;
Fig. 5 is the structural representation under visual angle, side of the present invention;
Fig. 6 is one of structure realization figure of steel strand wires;
Fig. 7 is the process chart of the present invention;
Fig. 8 is the structural representation of transportation of the present invention;
Fig. 9 is the structural representation that the present invention lays;
Figure 10 is that the paving groove of the present invention realizes one of process;
Figure 11 is the structural representation after the present invention lays;
Wherein: 1. block main body;2. plant;3. building block plateau;4. implantation hole;5. string holes;6. connecting line;Middle lock dog; 8. hole;9. building block association;10. grass layer;11. stratum.
Detailed description of the invention
Illustrating embodiments of the invention below in conjunction with the accompanying drawings, embodiment is not construed as limiting the invention:
Scheme one:
Intelligence hinge type bank protection, it is characterised in that comprising building block association, building block association comprises multiple block main body, multiple Block main body is connected line to be worn is an entirety, and block main body is precast concrete block, and connecting line is zinc-plated wirerope or polyester Hawser, is interconnected to form linked matrix with zinc-plated wirerope or polyester hawser, block main body comprises string holes, zinc-plated Wirerope or polyester hawser, through this string holes, block main body comprise implantation hole, comprise plant in implantation hole.The technical side at this place Technique effect and the process that realizes thereof of the essence that case is played are as follows: compare with prior art, at least following benefit, The most not block fixing, in conjunction with Fig. 2 and Fig. 3 so that the deformability of this patent is strong, further such that this patent adapts to respectively Plant landform, unsettled cavity will not be caused because of connecting too closely to further result in dangerous hidden danger, also will not overall tear, by Being the main body prepared in this patent, directly transport placement can also realize, and sees Fig. 8 and Fig. 9.The further technical scheme of the present invention Being, so block main body is hypotenuse, the interface between block main body can coincide and tackle slope descent.As further Improvement and realization, as further improving and realizing, hinge type slope-protection block with wirerope interconnect, when domatic occur sedimentation After, need bottom hinge block to settle with domatic simultaneously, prevent that big space occurs bottom block main body, form swirling water current to domatic Carry out erosion damage, cause bigger potential safety hazard.Hinge type bank protection is domatic consolidating settlement occurs after, for preventing block main body heavy Mutually extrude and can not effectively follow domatic bulk settling during fall and cause domatic destruction, so block main body is designed as trapezoidal side, Clearance distance is 8.6mm, has the biggest motility between adjacent block main body.The tangent plane of block main body is designed to faced by two Cut, identical slope descent of tackling that can be good between block main body, and the most malfunctioning activity.
Filter reticulated or the filter pad of classification, filter reticulated or the filtration of classification is comprised below described building block association It it is stratum below pad.By placing filter reticulated or the filter pad of classification, increase the permeability of shore protection system, thus weaken The fluid pressure to roadbed.And system decreases soil losses, the subsoil of leaching can not pass through system, and such hinge type protects Slope guard system will more be stablized.
As the most preferably, using Germany's import equipment, product middle part, without obvious groove breach, makes block exist Fracture is not had when being clashed into.Equipment uses the vibration of frequency conversion batch (-type), makes cement fully liquefy in aggregate, subtracts The porosity of few concrete, thus reach freeze thawing resistance requirement.
Production dispensing is accurate, uses numerical control proportioning machine to carry out dispensing, error≤0.5KG per ton.Use and add dry type fibre Dimension element and concrete additive effectively strengthen bulk strength and toughness, reduce concrete moisture content simultaneously.Conventional concrete is aqueous Measure bigger inapplicable long-term immersion, by alternation of wetting and drying or the construction site of freeze-thaw cycle.
Using steam curing, steam curing provides the necessary suitable temperature of cement aquation. damp condition, and to ensure Normal hydration.Product is not likely to produce contraction fissure. increase intensity. and the durability of Concrete Structure and other various property Energy.
As further preferably:
Can grass planting:
Perforating hinge type bank protection provides perfect environment for vegetation.Hinge type bank protection uses low alkali cement to add the wooden fibre of acetic acid Dimension improves the raw environment of planting of concrete, and the open-celled structure of hinge type bank protection provides for grass and undershrub grows up and more faster Add stable living environment.Vegetation can grow in hole, and absorption, on ground, which increases the coagulation of hinge type bank protection The absorption affinity of soil block.If need not grass planting, the hinge type bank protection of atresia can be installed or use rubble filling pore.
Use safety:
Calculating through hinge type revetment block wirerope aperture pull test, aperture diameter is 23mm, and what block can be stable bears steel Cable pulling force is without breakage.Aperture is crossed conference and is formed wirerope and block excesssive gap, causes wirerope excessive wear, and block ruptures.Aperture Too small can increase difficulty of construction.Hinge type bank protection the most firmly, safety, therefore pedestrian, animal, car and little Ship can be at freedom of movement above.
Durable:
As an outstanding guard system, hinge type bank protection can weaken the destructive strength of water, thus gives riverbank, river Dike, river course etc. provide continuous print to corrode protection.According to the design hydraulics of measuring and calculating, select the hinge type bank protection class being suitable for Type.
Hinge type bank protection system uses dry concrete, and in order to reach F50 freeze thawing resistance requirement, equipment uses frequency conversion interval Formula is vibrated, and makes cement fully liquefy in aggregate, reduces the porosity of concrete.Add nano-scale rice starch mixing simultaneously Additive, makes concrete density improve further, thus reaches freeze thawing resistance requirement.
Further preferably parameter is as follows:
Concrete specification: C30 grating dry concrete, antiacid, durable, good freezing and thawing performance.
Radial type slope-protection block size: 420*420*150mm
More than 20% voidage: the domatic resistance to flowing water can be reduced, it is simple to slope drainage.
Domestic test
Size of product is: 420*400*150mm
Test: rule ripple and irregular wave carry out wave flume test, utilize wave flume to carry out the serial mould of typical building block Type is tested, and has obtained the block thickness computing formula under regular ripple and irregular wave action according to result of the test.Result of the test Showing, block thickness and wave height are directly proportional, and relevant with factors such as breaker parameter, block relative densities under water.By with coagulation The comparison of several usual thickness computing formula of earth building blocks and concrete slab, demonstrates the reasonability of computing formula.
Conclusion (of pressure testing): after comparing the data such as the soil temperature field of freeze-thaw cycle process, domatic displacement deformation, to concrete Hinge block protective slope structure is applied in channel side slopes protection works, has obtained that " concrete hinge block protective slope structure form is defeated on hada mountain Water trunk canal frost heave adaptability model test shows, this kind of version well adapts to ability to frost heave and thaw collapse." knot Opinion.After experimental project is built up, through the operation in winter, demonstrate the reliability of experimental result.
(1) hinge type bank protection static ice pressure model test;
Conclusion (of pressure testing): cold district winter continue for a long time average low temperature be-27 DEG C time, hinge bank protection structure is at static ice pressure work Being less than 1% with lower along domatic displacement deformation rate, spring, residual displacement deformation rate was less than 0.1%, bank protection structure monolithic stability, work Journey is safe.
(2) frozen soil mechanics model test of hinge block protective slope structure
Experiment conclusion: the model test of the hinge block protective slope structure pattern by carrying out, at the soil comparing freeze-thaw cycle process After the data such as temperature field, domatic displacement deformation, hinge block protective slope structure is applied in channel side slopes protection works, obtains To draw a conclusion: hinge block protective slope structure form shows in water delivery trunk canal, hada mountain frost heave adaptability model test, this kind of structure shape Formula well adapts to ability to frost heave and thaw collapse.
(3) impact of concrete flap frictional behaviour is tested by freeze-thaw cycle;
Experiment conclusion: use bevel friction instrument to record the concrete flap of each 3 groups of Different Weight after room temperature and freeze-thaw cycle And the frictional behavior between clay, is concluded that in cold regions engineering, uses concrete flap protection system, should note The impact of freeze-thaw cycle Upon Slope Stability of meaning base soil also takes appropriate measures.
Taihu Lake, Suzhou Caulis Miscanthis floriduli-hinge type slope protection ecologic is repaired system and is tested:
Experiment conclusion: Caulis Miscanthis floriduli-hinge type slope protection ecologic is repaired the anti-floating capacity of system, anti-started ability and anti-coasting energy Power is the most significantly strengthened.As functional grass seeds, it is unquestionable in the suitability of shore protection anti-scour system.Caulis Miscanthis floriduli-hinge type As time goes on slope protection ecologic repairs system, and the root system of Caulis Miscanthis floriduli will develop further, and more firm suction protects soil Earth, makes the stability of barricade improve further;Strong and dense hedgerow band is formed on the surface of hinge type slope-protection block;Caulis Miscanthis floriduli In eutrophication water can normal growth, and can effectively remove N, P, COD, BOD etc. in water body, therefore Caulis Miscanthis floriduli is one The good plant of kind of purifying eutrophication water body. simultaneously as Caulis Miscanthis floriduli is again a kind of to integrate raw material, feedstuff, fuel Economic plants, can not only repair aquatic ecological environment in the plantation of the eutrophication water surface, and can produce certain economic worth. institute With, Vetiver Grass Technology is the new way of the phytoremediation eutrophic water of collection three benefits economic, social, ecological, will tool Have broad application prospects. make green embankment, ecological embankment.Described plant is Caulis Miscanthis floriduli, and building block association plants It it is Caulis Miscanthis floriduli-hinge type slope protection ecologic dummy after Caulis Miscanthis floriduli.
As further improving, in conjunction with Fig. 6, comprising middle lock dog in described connecting line, middle lock dog is by block main body Relative localization is in building block association.This place provides a kind of concrete prescriptive procedure, and similar fixing means is also at this patent Protection domain in.
As further improving, comprise cavity in the middle part of described connecting line, in the middle part of middle lock body, also have cavity and sky Chamber and cavity connect, and cavity comprises hole.Therefore, needs are reseeded sub-when, directly allow seed Kong Zhongliu from cavity Going out and just can sow in implantation hole, not employment goes to mend.
Described inside cavity comprises moisture transducer, and moisture transducer is externally protruded by circuit, and circuit is walked and connected In cavity in line.Therefore, for the height of water level of river levee, can detect at any time, described in stretch out outside the circuit of connecting line Portion connects alarming device.Alarming device can also be reported to the police, and such as indicates, by buzzer or warning lamp, the water level that river carries Highly.
Scheme two:
Intelligence hinge type bank protecting method, it is characterised in that utilize as above the most described bank protection, be laid on gradient face in order to protect Slope.
Scheme three:
The construction method of intelligence hinge type bank protection, it is characterised in that comprise the steps of:
River proposes main body compacting and carries out based process, and after unwrapping wire, artificial accurately process is domatic, makes slope leveling;
Laying geotextiles, geotextile laying must accomplish that domatic nothing jams on, smooth aptychus;
Hinge type revetment brick is laid, and uses slide type specific purpose tool to be transported to brick lay near sites, carries out wirerope perforation peace Dress, perforation installation need to wear wirerope from top to bottom;Or building block association is directly transported and lays;
Wirerope joint processes, and needs every two wireropes to be fixed process.
It is below more specifically implementation:
Hinge type bank protection mechanical erection way:
Hinge type slope-protection block is transported to factory material and assembles ground, and be connected to pad with hawser.Hinge type bank protection is placed in advance On the roadbed completed, and by routine building apparatus measures to ensure precision.
Pay and unloading
Hinge type slope protection bedding course need to be with the trailer loader of 40 feet, and every truck useful load is 1600 square feet.If respectively constructed Layout scenarios allows, and unloading should be carried out according to certain step, in order to hinge type slope protection bedding course can directly be taped against from road vehicle On pre-prepd roadbed.
Place hinge type slope protection bedding course
Hinge type slope protection bedding course can be with cable wire from two ends pull-up.
Fixed hinge formula slope protection bedding course
Hinge type slope protection bedding course can be fixed with knitmesh.Interim fixing need along two inches of center place punching above mat. Can certainly be permanently fixed.
Finishing radial type slope protection bedding course
Hinge type slope protection bedding course should pad with sandy soil mixture facing upward the water surface.Hinge type slope protection bedding course can be in pad holes on normal waterline Green vegetation is planted between gap.
The selection of steel strand wires:
Steel strand wires selection 1 × 7 galvanized strand wires, a diameter of 7.8, every hundred meters of weight are 29.51KG.Use rare earth alloy and plating Zinc steel strand wires two kinds, anti-corrosive properties and distortion performance are 2 times of conventional steel twisted wire, it is ensured that construction quality.
The manually installed way of hinge type bank protection:
1. river carry main body compacting reach requirement height after, carry out brusher slope and carry out compaction treatment.
2. river proposes based process, common use stone masonry or the process of lattice guest's gabion two ways
3. after unwrapping wire, artificial accurately process is domatic, is that slope leveling degree reaches to design requirement
4. laying geotextiles, geotextile laying must accomplish that domatic nothing jams on, smooth aptychus
5. hinge type revetment brick is laid, and uses slide type specific purpose tool to be transported to brick lay near sites, workman spreads If installing.When workman lays installation, I company technique personnel can carry out laying installation guide at the scene.As domatic in run into big radian Hinge type slope-protection block cutting need to be carried out, then install.
When 6. laying to dyke design height, carrying out wirerope perforation and install, perforation installation need to wear wirerope from top to bottom, installs Time my company technique personnel instruct the erection skills such as how personnel's cooperation to workman, it is ensured that can reach convenient and swift.
7. wirerope joint processes, and needs every two wireropes to be fixed process.Carry out according to design requirement after having fixed Concreting.
8., after concrete belt has poured up and down, carry out ploughing soil and puddle the greening constructions such as grass seed landfill.
In a creative way, each effect above is individually present, moreover it is possible to complete the combination of the above results with a nested structure.
Part details not shown in figure.
It should be noted that multiple schemes that this patent provides comprise the basic scheme of itself, separate, the most mutually Restriction, but it can also be mutually combined in the case of not conflicting, and reaches multiple effect and jointly realizes.
The ultimate principle of the present invention, principal character and advantages of the present invention have more than been shown and described.The technology of this area Personnel, it should be recognized that the present invention is not restricted to the described embodiments, simply illustrate this described in above-described embodiment and description Bright principle, without departing from the spirit and scope of the present invention, the present invention also has various changes and modifications, these changes Both fall within claimed scope with improving.

Claims (10)

1. intelligence hinge type bank protection, it is characterised in that comprising building block association, building block association comprises multiple block main body, many Individual block main body is connected line to be worn is an entirety, and block main body is precast concrete block, and connecting line is zinc-plated wirerope or poly- Ester hawser, is interconnected to form linked matrix with zinc-plated wirerope or polyester hawser, block main body comprises string holes, zinc-plated Wirerope or polyester hawser through this string holes, block main body comprises implantation hole, implantation hole comprises plant.
2. intelligence hinge type bank protection as claimed in claim 1, it is characterised in that so block main body is hypotenuse, block main body Between interface can coincide and tackle slope descent.
3. intelligence hinge type bank protection as claimed in claim 1, it is characterised in that comprise filter screen shape below described building block association Fabric or the filter pad of classification, be stratum below the filter pad of filter reticulated or classification.
4. intelligence hinge type bank protection as claimed in claim 1, it is characterised in that described plant is Caulis Miscanthis floriduli, and building block is combined It is Caulis Miscanthis floriduli-hinge type slope protection ecologic dummy after body plantation Caulis Miscanthis floriduli.
5. intelligence hinge type bank protection as claimed in claim 1, it is characterised in that comprise middle lock dog in described connecting line, in Between lock dog by block main body relative localization in building block association.
6. intelligence hinge type bank protection as claimed in claim 5, it is characterised in that comprise cavity in the middle part of described connecting line, middle Also there are cavity and cavity and cavity to connect in the middle part of lock body, cavity comprises hole.
7. intelligence hinge type bank protection as claimed in claim 6, it is characterised in that described inside cavity comprises moisture transducer, Moisture transducer is externally protruded by circuit, and circuit is walked in the cavity in connecting line.
8. intelligence hinge type bank protection as claimed in claim 7, it is characterised in that described in stretch out the circuit external connection of connecting line Alarming device.
9. intelligence hinge type bank protecting method, it is characterised in that utilize the bank protection that claim 1 to 8 is the most described, be laid on the gradient Bank protection on face.
10. the construction method of intelligence hinge type bank protection, it is characterised in that comprise the steps of:
River proposes main body compacting and carries out based process, and after unwrapping wire, artificial accurately process is domatic, makes slope leveling;
Laying geotextiles, geotextile laying must accomplish that domatic nothing jams on, smooth aptychus;
Hinge type revetment brick is laid, and uses slide type specific purpose tool to be transported to brick lay near sites, carries out wirerope perforation peace Dress, perforation installation need to wear wirerope from top to bottom;Or building block association is directly transported and lays;
Wirerope joint processes, and needs every two wireropes to be fixed process.
CN201610299706.1A 2016-05-09 2016-05-09 Intelligent hinge type protection slope, slope protection method and protection slope construction method Pending CN105926534A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610299706.1A CN105926534A (en) 2016-05-09 2016-05-09 Intelligent hinge type protection slope, slope protection method and protection slope construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610299706.1A CN105926534A (en) 2016-05-09 2016-05-09 Intelligent hinge type protection slope, slope protection method and protection slope construction method

Publications (1)

Publication Number Publication Date
CN105926534A true CN105926534A (en) 2016-09-07

Family

ID=56834392

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610299706.1A Pending CN105926534A (en) 2016-05-09 2016-05-09 Intelligent hinge type protection slope, slope protection method and protection slope construction method

Country Status (1)

Country Link
CN (1) CN105926534A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111455931A (en) * 2020-04-20 2020-07-28 上海市水利工程设计研究院有限公司 Cold region flexible integral ecological slope protection structure and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110099846A (en) * 2010-03-03 2011-09-09 (주)동영조경 Revetment block
CN203096692U (en) * 2013-03-18 2013-07-31 连云港市市区水工程管理处 Hinge type concrete block ecological slope protection system
CN103758084A (en) * 2014-01-27 2014-04-30 浙江水利水电学院 Ecological river interlocking type building blocks and construction method for building protection ridge through building blocks
CN103774617A (en) * 2013-12-06 2014-05-07 浙江水利水电学院 Mutually-embedded type slope protection building block and construction method thereof
CN203947448U (en) * 2012-03-19 2014-11-19 北京东方利禾景观设计有限公司 A kind of novel ecological landscape type shore protection system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110099846A (en) * 2010-03-03 2011-09-09 (주)동영조경 Revetment block
CN203947448U (en) * 2012-03-19 2014-11-19 北京东方利禾景观设计有限公司 A kind of novel ecological landscape type shore protection system
CN203096692U (en) * 2013-03-18 2013-07-31 连云港市市区水工程管理处 Hinge type concrete block ecological slope protection system
CN103774617A (en) * 2013-12-06 2014-05-07 浙江水利水电学院 Mutually-embedded type slope protection building block and construction method thereof
CN103758084A (en) * 2014-01-27 2014-04-30 浙江水利水电学院 Ecological river interlocking type building blocks and construction method for building protection ridge through building blocks

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111455931A (en) * 2020-04-20 2020-07-28 上海市水利工程设计研究院有限公司 Cold region flexible integral ecological slope protection structure and construction method thereof

Similar Documents

Publication Publication Date Title
US5160215A (en) Ground surfacing and erosion control device
CN102011394B (en) Method for reinforcing aeolian sandy soil by polypropylene fibers
CN110306565B (en) Road ecological slope protection system and construction method
CN113774917B (en) Safe construction method for earth and rockfill excavation and side slope supporting engineering
CN104234061A (en) Reinforced ecological concrete revetment and construction method thereof
CN106149625A (en) A kind of ecological self-purification type landscape revetment reconstruction structure and construction method thereof
CN106542769A (en) A kind of composite of laying porous pavement
CN106759397A (en) Ecological lattice guest method to set up
CN106917410A (en) A kind of downstream slope slope shoulder safeguard structure and its construction method
CN106702845B (en) One kind preventing saline and alkaline permeable pavement structure
CN107032660B (en) Preparation method of composite material for paving permeable pavement
CN206110149U (en) Intelligence hinge type bank protection
CN105926534A (en) Intelligent hinge type protection slope, slope protection method and protection slope construction method
Ali Manual RC box culvert analysis and designing
CN203905032U (en) Large pond cutting protection structure
CN216514911U (en) High fill roadbed structure
CN209307794U (en) Low-level bog area hydraulic reclamation ultra fine sand road structure
CN206298869U (en) A kind of concrete guard wall structure of free drainage
CN204959774U (en) Ecological brick flexible protection structure of immerseable embankment high slope interlocking formula
CN109355990A (en) Low-level bog area hydraulic reclamation ultra fine sand road structure
RU104195U1 (en) DRAINAGE STRUCTURE ON PERMANENT WATERWATERS
Permanent International Association of Navigation Congresses. Permanent Technical Committee I. Working Group 4 Guidelines for the Design and Construction of Flexible Revetments Incorporating Geotextiles for Inland Waterways: Report of Working Group 4 of the Permanent Technical Committee I.
KR20010016170A (en) Anti-Scouring and Erosion Fabric Form
RU2270900C2 (en) Slope consolidation method
RU2176700C1 (en) Method for protecting territory from flooding

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160907