CN105909916B - The safty shield and its installation method of a kind of pipeline - Google Patents

The safty shield and its installation method of a kind of pipeline Download PDF

Info

Publication number
CN105909916B
CN105909916B CN201610453406.4A CN201610453406A CN105909916B CN 105909916 B CN105909916 B CN 105909916B CN 201610453406 A CN201610453406 A CN 201610453406A CN 105909916 B CN105909916 B CN 105909916B
Authority
CN
China
Prior art keywords
pipeline
protection department
elastic
main protection
lid portion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610453406.4A
Other languages
Chinese (zh)
Other versions
CN105909916A (en
Inventor
黎富勇
曾金发
刘松涛
罗国荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Sanshui Gas Co ltd
Original Assignee
Foshan Sanshui Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Sanshui Gas Co Ltd filed Critical Foshan Sanshui Gas Co Ltd
Priority to CN201610453406.4A priority Critical patent/CN105909916B/en
Publication of CN105909916A publication Critical patent/CN105909916A/en
Application granted granted Critical
Publication of CN105909916B publication Critical patent/CN105909916B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L57/00Protection of pipes or objects of similar shape against external or internal damage or wear
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L57/00Protection of pipes or objects of similar shape against external or internal damage or wear
    • F16L57/04Protection of pipes or objects of similar shape against external or internal damage or wear against fire or other external sources of extreme heat
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L58/00Protection of pipes or pipe fittings against corrosion or incrustation
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L59/00Thermal insulation in general
    • F16L59/02Shape or form of insulating materials, with or without coverings integral with the insulating materials
    • F16L59/021Shape or form of insulating materials, with or without coverings integral with the insulating materials comprising a single piece or sleeve, e.g. split sleeve, two half sleeves
    • F16L59/024Shape or form of insulating materials, with or without coverings integral with the insulating materials comprising a single piece or sleeve, e.g. split sleeve, two half sleeves composed of two half sleeves

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Body Structure For Vehicles (AREA)
  • Supports For Pipes And Cables (AREA)

Abstract

The safty shield and its installation method of a kind of pipeline, the safty shield are used to be set in pipeline(7)Outside play heat-insulated protective action, including can merge composition cylinder the main protection department as larger discount vibram outlet section cylinder(8)With the lid portion as smaller discount vibram outlet section cylinder(4), wherein, the main protection department(8)Bottom and the lid portion(4)Top be symmetrically arranged it is flexible to roof panel pipe fitting(81、41), the main protection department(8)Diametrically opposed both sides be symmetrically provided with elastic clip assembly(82), thus two elasticity are to roof panel pipe fitting(81、41)It can be formed for the pipeline(7)Vertical direction clamping.

Description

The safty shield and its installation method of a kind of pipeline
Technical field
The present invention relates to the safty shield and its installation method in pipeline protection field, specially a kind of pipeline.
Background technology
Pipeline in use, may face physical shock, corrosivity working environment or the hot operation of outside Environment;This may have a negative impact the structure of pipeline even causes security risk so as to influence the service life of pipeline. , can be using protective cover come protective conduit in order to overcome this defect.
Have in the prior art and protective cover is formed to pipeline using in pipeline workshop, damaged against the external world.But It is that in existing industry spot, the various pipelines for needing to protect often have installed.And the feelings of installation are not completed at some In shape, the production of pipeline is also over and is not easy to be again introduced into factory's progress secondary operation.Therefore, it is necessary to one kind for pipe Road carries out the protective cover that subsidiarity is installed in the protective cover that line is installed or after dispatching from the factory, it can flexibly realize the protection for pipeline Need, to be adapted to the needs of various application scenarios.
The content of the invention
The object of the present invention is to provide the safty shield and its installation method of a kind of pipeline, it can overcome existing skill The defects of art.
Heat-insulated protective action is played in the safty shield of pipeline according to the present invention, the outside for being set in pipeline, Including can merge the main protection department as larger discount vibram outlet section cylinder of composition cylinder with as smaller discount vibram outlet section cylinder Lid portion, wherein, be symmetrically arranged at the top of the bottom of the main protection department and the lid portion it is flexible to roof panel pipe fitting, The diametrically opposed both sides of the main protection department are symmetrically provided with elastic clip assembly, and thus two elasticity are to top Platform pipe fitting can form the clamping of the vertical direction for the pipeline, diametrically opposed two elastic clip groups Part can form the clamping of the horizontal direction for the pipeline, wherein, the left and right sides of the opening of the main protection department is right Claim to be provided with the convex extension part extended towards one another, circular arc head is provided with the medial end of each convex extension part, with favourable Tentatively cover and be set on the pipeline from the bottom of the pipeline in by the opening main protection department, and temporarily will Main protection department is carried on the pipeline and is dropped with preventing from loosening;Being provided with two on the top surface of each convex extension part has The cylindrical fixing groove of top-slitting is to two elastic deformations at corresponding one in two end faces with the lid portion Cylinder bracket coordinates, wherein, elastic deformation appearance is provided with the plane of symmetry position of each elastic deformation cylinder bracket Perhaps gap;Wherein, the pipeline engagement arm and auxiliary support arm that each elasticity includes being oppositely arranged to roof panel pipe fitting, institute State plateau elastic bending section that pipeline engagement arm includes being connected with the body of main protection department, be connected with the plateau elastic bending section Platform part to the support engagement angled portion for engaging the pipeline and being connected with the platform part, the auxiliary support arm It is connected including the sub-arm elastic bend part being connected with the body of the main protection department and with the sub-arm elastic bend part And to the inclined shore portion being slidably matched with the support engagement angled portion, thus, when described when mounted elastic to top When platform pipe fitting is subject to the top pressure active force of the pipeline and elastic deformation occurs, the support engagement angled portion can be relative to institute State inclined shore portion and opposite slide occurs;Wherein, every side of the main protection department in the diametrically opposed both sides On be provided with multiple elastic clip assemblies along the longitudinal direction, each elastic clip assembly includes symmetrical on diametric(al) Two elastic clips set, one in described two elastic clips is V-type elastic bending piece, the one of the V-type elastic bending piece A support arm is connected with the main body of the main protection department, another support arm and another the corresponding support arm in described two elastic clips Arranged crosswise supports engagement so as to fulfill for the staggered form of the pipeline;It is fixedly mounted on two end faces in the lid portion There is sheet metal, the sheet metal outboard end is provided with draw ring, when the lid portion needs to dismantle from the main protection department, borrows Help the draw ring to dismantle the lid portion;The end of described two elastic clips is mounted on scroll wheel, and the scroll wheel is used Contacted with the outer surface with the pipeline, so as to avoid described two elastic clips from scratching the pipeline.
According to the present invention, the installation method of above-mentioned protective cover, first, by the opening court of the main protection department On, make the convex extension part that bullet occur by the gap of the cylindrical fixing groove from the bottom of the pipeline by the opening Property deformation so that the main protection department be installed and be carried on the pipeline, then, by the way that the elastic deformation cylinder is tight Gu bar is inserted into and is coupled in the cylindrical fixing groove and the lid portion is fixed on the main protection department, so as to utilize Two elasticity of the main protection department form roof panel pipe fitting the clamping of the vertical direction for the pipeline, profit The clamping of the horizontal direction for the pipeline is formed with the diametrically opposed elastic clip assembly.
By the present invention, due to there is provided the main protection department with upper opening, enabling to protective cover at the scene Installed and be carried on pipeline.And in assembling, since shield is divided into two parts not of uniform size, larger portion The opening of the main protection department divided is missing the opening round, it is easy to temporarily be carried on pipeline protective cover and be not easy to drop;By setting Convex extension part setting in the opening and using circular groove, elastic deformation can occur in installation process and temporarily will shield Cover blocks, this for the shield that is loaded axially along the pipe and gradually during it is especially advantageous.After assembling, court of lid portion On, enable to the convex extension part to be subject to the gravity spare supporting part of pressure-bearing downwards as shield, avoid making in long-term installation During the self gravitation of shield for shield caused by the long-term biased deformation of the elastomeric platform pipe portion of shield it is excessive under It is heavy, so that peripheral circular air space occurs extruding and influences heat insulation.Whole guard apparatus has easy for installation, peace Fill firmly and service-strong advantage.It can effectively solve the problem that the problems of the prior art.
Brief description of the drawings
Fig. 1 is the overall structure diagram of the main protection department of the safty shield of the pipeline of the present invention;
Fig. 2 is the overall structure diagram in the lid portion of the present invention;
Fig. 3 is the overall structure diagram of the safty shield of the pipeline of the invention after assembling installation;
Fig. 4 is described elastic to the close-up schematic view at roof panel pipe fitting in Fig. 1.
Embodiment
With reference to Fig. 1-4, the present invention is described in detail.
Heat-insulated protective action is played in the safty shield of pipeline according to the embodiment, the outside for being set in pipeline 7, Including can merge the main protection department 8 as larger discount vibram outlet section cylinder of composition cylinder with as smaller discount vibram outlet section cylinder Lid portion 4, wherein, the bottom of the main protection department 8 is symmetrically arranged flexible to roof panel pipe with the top in the lid portion 4 Part 81,41, the diametrically opposed both sides of the main protection department 8 are symmetrically provided with elastic clip assembly 82, thus two The elasticity can form roof panel pipe fitting 81,41 clamping of the vertical direction for the pipeline 7, diametrically opposed Two elastic clip assemblies 82 can form the horizontal direction of clamping to(for) the pipeline 7, wherein, the main protection department The convex extension part 83 extended towards one another is symmetrically arranged with left and right sides of 8 opening, the medial extremity of each convex extension part 83 Circular arc head 84 is provided with portion, be conducive to by the opening main protection department 8 from the bottom of the pipeline 7 and Preliminary set is set on the pipeline 7, and temporarily main protection department 8 is carried on the pipeline 7 and is dropped with preventing from loosening;Each institute State be provided with the top surface of convex extension part 83 two have top-slitting cylindrical fixing grooves 830 to the lid portion 4 Two end faces in correspondence one at two elastic deformation cylinder brackets 43 coordinate, wherein, each elastic deformation Elastic deformation, which is provided with, at the plane of symmetry position of cylinder bracket 43 allows gap 431;Wherein, each elasticity is to roof panel Pipe fitting 81,41 includes the pipeline engagement arm 2 and auxiliary support arm 3 being oppositely arranged, and the pipeline engagement arm 2 includes and main protection The plateau elastic bending section 21 of the body connection in portion 8, the platform part 22 that is connected with the plateau elastic bending section 21 are engaging The pipeline 7 and the support engagement angled portion 23 being connected with the platform part 22, the auxiliary support arm 3 include with it is described The sub-arm elastic bend part 31 and be connected and use with the sub-arm elastic bend part 31 that the body of main protection department 8 connects With the inclined shore portion 32 being slidably matched with the support engagement angled portion 23, thus, when when mounted, the elasticity is flat to pushing up When platform pipe fitting 81,41 is subject to the top pressure active force of the pipeline 7 and elastic deformation occurs, the support engagement angled portion 23 can phase Opposite slide occurs for the inclined shore portion 32;Wherein, the main protection department 8 is in the diametrically opposed both sides In every side on be provided with multiple elastic clip assemblies 82 along the longitudinal direction, each elastic clip assembly 82 include on Symmetrically arranged two elastic clips 821 of diametric(al), one in described two elastic clips 821 is V-type elastic bending piece, described One support arm of V-type elastic bending piece is connected with the main body of the main protection department 8, another support arm and described two elastic clips Another correspondence support arm arranged crosswise in 821 supports engagement so as to fulfill for the staggered form of the pipeline 7;The lid Sheet metal 47 is installed with two end faces in portion 4,47 outboard end of sheet metal is provided with draw ring 46, when the lid When portion 4 needs to dismantle from the main protection department 8, the lid portion 4 is dismantled by means of the draw ring 46;Described two elasticity The end of folder 821 is mounted on scroll wheel 822, and the scroll wheel 822 with the outer surface of the pipeline 7 to contact, so as to keep away Exempt from described two elastic clips 821 to scratch the pipeline 7.
According to embodiment, the installation method of above-mentioned protective cover, first, by the opening court of the main protection department 8 On, make gap of the convex extension part 83 by the cylindrical fixing groove 830 from the bottom of the pipeline 7 by the opening Generation elastic deformation by the main protection department 8 so as to install and be carried on the pipeline 7, then, by the way that the elasticity is become Shape cylinder bracket 43 is inserted into and is coupled in the cylindrical fixing groove 830 and prevents in the lid portion 4 fixed to the master In shield portion 8, so as to be formed roof panel pipe fitting 81,41 for described using two elasticity of the main protection department 8 The clamping of the vertical direction of pipeline 7, is formed for the pipeline 7 using the diametrically opposed elastic clip assembly 82 The clamping of horizontal direction.
Exemplarily, main protection department 8 can be integrally formed, and the lid portion 4 can also be integrally formed.
Due to there is provided the main protection department with upper opening, enabling to protective cover to be installed and held at the scene It is loaded on pipeline.And in assembling, since shield is divided into two parts not of uniform size, the main protection department of major part Opening be missing the opening round, protective cover easy to being temporarily carried on pipeline and be not easy to drop by it;It is located at the opening by setting The convex extension part at place and using circular groove, can occur elastic deformation in installation process and temporarily block shield, this is right It is especially advantageous during the shield that is loaded axially along the pipe and gradually.After assembling, lid portion upward, enables to The convex extension part is subject to the gravity spare supporting part of pressure-bearing downwards as shield, avoids the shield during long-term install and use Self gravitation for shield excessive convergence caused by the long-term biased deformation of the elastomeric platform pipe portion of shield so that all Annular air space is enclosed extruding occurs and influences heat insulation.Entirely guard apparatus has easy for installation, firmly installs and uses The advantages of reliable.
In the above manner, those skilled in the art can be made within the scope of the invention according to operating mode it is various Change.

Claims (2)

  1. A kind of 1. safty shield of pipeline, for being set in pipeline(7)Outside play heat-insulated protective action, including can close And form the main protection department as larger discount vibram outlet section cylinder of cylinder(8)With the lid portion as smaller discount vibram outlet section cylinder (4), wherein, the main protection department(8)Bottom and the lid portion(4)Top be symmetrically arranged it is flexible to roof panel pipe Part(81、41), the main protection department(8)Diametrically opposed both sides be symmetrically provided with elastic clip assembly(82), by This two elasticity are to roof panel pipe fitting(81、41)It can be formed for the pipeline(7)Vertical direction clamping, diameter The opposite two elastic clip assemblies on direction(82)It can be formed for the pipeline(7)Horizontal direction clamping, its In, the main protection department(8)Opening(80)The convex extension part extended towards one another is symmetrically arranged with left and right sides of place(83), often A convex extension part(83)Medial end at be provided with circular arc head(84), to be conducive to by the opening master Protection department(8)From the pipeline(7)Bottom and tentatively cover and be set to the pipeline(7)On, and temporarily by main protection department(8)Carrying In the pipeline(7)On dropped with preventing from loosening;Each convex extension part(83)Top surface on be provided with two there is top The cylindrical fixing groove of fluting(830)To with the lid portion(4)Two end faces in correspondence one at two elasticity Deform cylinder bracket(43)Coordinate, wherein, each elastic deformation cylinder bracket(43)Plane of symmetry position at set Gap is allowed in flexible deformation(431);Wherein, each elasticity is to roof panel pipe fitting(81、41)Including the pipe being oppositely arranged Road engagement arm(2)And auxiliary support arm(3), the pipeline engagement arm(2)Including with main protection department(8)Body connection it is flat Platform elastic bend part(21)And the plateau elastic bending section(21)The platform part of connection(22)To engage the pipeline(7)、 And with the platform part(22)The support engagement angled portion of connection(23), the auxiliary support arm(3)Including preventing with the master Shield portion(8)Body connection sub-arm elastic bend part(31)And with the sub-arm elastic bend part(31)Connect and To support engagement angled portion with described(23)The inclined shore portion being slidably matched(32), thus, when the elasticity when mounted To roof panel pipe fitting(81、41)It is subject to the pipeline(7)Top pressure active force and when elastic deformation occurs, the support engagement is inclined Inclined portion(23)Can be relative to the inclined shore portion(32)Opposite slide occurs;Wherein, the main protection department(8)In the diameter Multiple elastic clip assemblies are provided with every side on direction in opposite both sides along the longitudinal direction(82), each elasticity Clip assembly(82)Include on symmetrically arranged two elastic clips of diametric(al)(821), described two elastic clips(821)In One is V-type elastic bending piece, a support arm and the main protection department of the V-type elastic bending piece(8)Main body be connected, separately One support arm and described two elastic clips(821)In another correspondence support arm arranged crosswise so as to fulfill for the pipeline (7)Staggered form support engagement;The lid portion(4)Two end faces on be installed with sheet metal(47), the metal Piece(47)Outboard end is provided with draw ring(46), when the lid portion(4)Need from the main protection department(8)During upper dismounting, by In the draw ring(46)By the lid portion(4)Dismounting;Described two elastic clips(821)End be mounted on scroll wheel (822), the scroll wheel(822)To with the pipeline(7)Outer surface contact, so as to avoid described two elastic clips (821)By the pipeline(7)Scratch.
  2. A kind of 2. installation method of the safty shield of pipeline as claimed in claim 1, first, by the main protection department (8)It is described opening up, from the pipeline(7)Bottom and by it is described opening make the convex extension part(83)By the circle Cylindricality fixing groove(830)Gap elastic deformation occurs so as to by the main protection department(8)Install and be carried on the pipeline(7) On, then, by by the elastic deformation cylinder bracket(43)It is inserted into and is coupled to the cylindrical fixing groove(830)In and By the lid portion(4)Fixed to the main protection department(8)On, so as to utilize the main protection department(8)Two described in Elasticity is to roof panel pipe fitting(81、41)Formed for the pipeline(7)Vertical direction clamping, utilization is diametrically opposed The elastic clip assembly(82)Formed for the pipeline(7)Horizontal direction clamping.
CN201610453406.4A 2016-06-22 2016-06-22 The safty shield and its installation method of a kind of pipeline Active CN105909916B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610453406.4A CN105909916B (en) 2016-06-22 2016-06-22 The safty shield and its installation method of a kind of pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610453406.4A CN105909916B (en) 2016-06-22 2016-06-22 The safty shield and its installation method of a kind of pipeline

Publications (2)

Publication Number Publication Date
CN105909916A CN105909916A (en) 2016-08-31
CN105909916B true CN105909916B (en) 2018-05-11

Family

ID=56759299

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610453406.4A Active CN105909916B (en) 2016-06-22 2016-06-22 The safty shield and its installation method of a kind of pipeline

Country Status (1)

Country Link
CN (1) CN105909916B (en)

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE9210771U1 (en) * 1992-08-12 1992-11-05 Rehau Ag + Co, 8673 Rehau, De
CN102155587A (en) * 2010-02-11 2011-08-17 喜利得(中国)商贸有限公司 Cable clamp
CN202972206U (en) * 2012-12-11 2013-06-05 吴健 Anti-dropping pipe clamp with cushion layer
CN204533964U (en) * 2015-04-15 2015-08-05 刘明 A kind of air conditioner connecting pipe outside protective pipe

Also Published As

Publication number Publication date
CN105909916A (en) 2016-08-31

Similar Documents

Publication Publication Date Title
CN106015755B (en) The pipeline protection closure assembly and its installation method of a kind of stabilized structure
CN106090533B (en) A kind of protectiveness strong pipeline protection closure assembly and its installation method
CN105909916B (en) The safty shield and its installation method of a kind of pipeline
CN105864582B (en) A kind of easy pipeline protection closure assembly and its installation method
CN105895219A (en) Anti-corrosion cable equipped with thermal-insulating protection cover and assembling and mounting method for anti-corrosion cable
CN105864571B (en) A kind of protective cover and its installation method for pipeline
CN105889701B (en) A kind of pipe insulation protective cover and its installation method
CN105864572B (en) The novel protective closure assembly and its installation method of a kind of pipeline
CN105972383B (en) A kind of pipe safety protective cover and its installation method
CN105864573B (en) One kind mounts and dismounts convenient pipeline protection closure assembly and its installation method
CN105864576B (en) The pipe safety protective roof structure and its installation method of a kind of convenient disassembly
CN105840952B (en) The abrasion-proof pipe protective roof structure and its installation method of a kind of easy disassembly
CN105864574B (en) A kind of firm pipeline protection closure assembly and its installation method
CN105889689B (en) A kind of wear-resisting pipeline protection cover structure and its installation method
CN105972386B (en) The protective cover and its installation method of a kind of pipeline
CN105889702B (en) A kind of pipeline protection cover structure and its installation method
CN105840953B (en) A kind of pipeline protection closure assembly and its installation method firmly installed
CN105864577B (en) A kind of reliability high pipeline protection closure assembly and its installation method
CN106090532B (en) A kind of easily pipeline protection closure assembly and its installation method
CN105840954B (en) A kind of corrosion resistant pipe safety safeguard structure and its installation method
CN105972382B (en) The anticorrosion pipeline protective cover and its installation method of a kind of easy disassembly
CN105972385B (en) The pipeline protection closure assembly and its installation method of a kind of easy disassembly
CN106090531B (en) A kind of wear Protection closure assembly and its installation method for pipeline
CN105889705B (en) A kind of heat-insulating shield device and its installation method for pipeline
CN106015834B (en) A kind of pipeline protection closure assembly and its installation method easy to maintenance

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: Zhuji City, Zhejiang province 311819 city of Shaoxing Town Road 136, Zhao Qinghua

Applicant after: Wu Xiaoxiao

Address before: 312399 Zhejiang city of Shaoxing province Shangyu City Baiguan Street New Village Temple No. 3 tablets

Applicant before: Wu Xiaoxiao

CB02 Change of applicant information
CB03 Change of inventor or designer information

Inventor after: Li Fuyong

Inventor after: Zeng Jinfa

Inventor after: Liu Songtao

Inventor after: Luo Guorong

Inventor before: Wu Xiaoxiao

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20180413

Address after: 528100 21 Kang Road, southwest Street, Sanshui District, Foshan, Guangdong

Applicant after: FOSHAN SANSHUI GAS Co.,Ltd.

Address before: Zhuji City, Zhejiang province 311819 city of Shaoxing Town Road 136, Zhao Qinghua

Applicant before: Wu Xiaoxiao

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant