CN105895265A - High-voltage cable terminal processing process - Google Patents
High-voltage cable terminal processing process Download PDFInfo
- Publication number
- CN105895265A CN105895265A CN201610328799.6A CN201610328799A CN105895265A CN 105895265 A CN105895265 A CN 105895265A CN 201610328799 A CN201610328799 A CN 201610328799A CN 105895265 A CN105895265 A CN 105895265A
- Authority
- CN
- China
- Prior art keywords
- core
- high pressure
- cable
- pressure belt
- fingerstall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01B—CABLES; CONDUCTORS; INSULATORS; SELECTION OF MATERIALS FOR THEIR CONDUCTIVE, INSULATING OR DIELECTRIC PROPERTIES
- H01B13/00—Apparatus or processes specially adapted for manufacturing conductors or cables
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Removal Of Insulation Or Armoring From Wires Or Cables (AREA)
- Processing Of Terminals (AREA)
Abstract
The invention discloses a high-voltage cable terminal processing process. The high-voltage cable terminal processing process is implemented by the steps of insulation testing, marking and cutting, thermal shrinkage and cooling, marking and winding, copper connector connecting, polishing and dust removing, comprehensively winding and post processing in sequence. The process is simple and reasonable, rapid and convenient to operate, and suitable for wide popularization; and the produced cable is good in transfer effect, relatively good in insulation property, relatively long in service life, and can be applied to many fields.
Description
Technical field
The present invention relates to field of cable technology, particularly a kind of hv cable termination processes technique.
Background technology
The manufacture of electric wire is diverse with the mode of production of most of electronic products.Electronic product generally uses
Another part is assembled into parts, multiple parts refill and are made into separate unit product, and product measures with number of units or number of packages.Electric wire is with length
Degree is basic measurement unit.All electric wires are all from the beginning of conductor is processed, in the periphery of conductor layer by layer plus absolutely
Edge, shielding, stranding, sheath etc. and make electric wire product.Product structure is the most complicated, and the level of superposition is the most.
Summary of the invention
It is an object of the invention to provide a kind of hv cable termination easy and simple to handle, in hgher efficiency and process technique.
The technical solution used in the present invention is:
A kind of hv cable termination processes technique, and its innovative point is: sequentially pass through Insulation test, labelling cutting, pyrocondensation cooling,
Labelling is wound around, connect copper sleeve, polishing dedusting, comprehensive be wound around and post processing processes technique to complete hv cable termination, and it is concrete
Step is as follows:
1) Insulation test: before making, need to carry out Insulation test, testing sequence with the megger of the 2500 volts cable to making
For the insulation between phase and phase and between phase and ground, any one of palpus is more than 2500 megaohms and can make, such as any one
Insulation less than 2500 megaohms or lower, then to cut out 1 meter of this cable, then retest, qualified after can make;
2) labelling cutting: first measure required size, carry out labelling, before moving knife, first adjust razor blade for carving tool, make the point of a knife exposed
Maintain an equal level mutually with the thinnest part of skin at this cable, from mark, draw two cuttves in 45 degree of angle modes, make sure to keep in mind not hinder core diagonal cutting pliers
The glass layer peelling off cable sheath and the inside is coordinated with cutter;
3) pyrocondensation cooling: clean the part of set point fingerstall with ethanol cloth, is inserted in a point fingerstall according to the order of core, and strikes tight.
Before this step, must be by earth lead 23# high pressure belt overstriking, to ensure the sealing after dividing fingerstall pyrocondensation, with heat gun to dividing
Fingerstall heats so that it is pyrocondensation.It should be noted that heat from centre to two during heating so that it is air can be got rid of completely, complete with cable
Seal, after point fingerstall cooling and shaping, according to required size, core is blocked;
4) labelling is wound around: from the head of core to a point fingerstall direction, the distance measuring 27 centimetres performs labelling, 23# high pressure belt
Winding position to point upper 2 to the 3 centimetres of end of finger of point fingerstall, during winding, should use half lap from the beginning of 27 centimetres of positions backward
The mode of bag is carried out, back and forth each the most once, two-layer altogether, determine phase sequence according to the color of core, use form and aspect band to be wound around, its method with
It is wound around 23# high pressure belt the same, covers on 23# high pressure belt, but should be noted at 27 centimetres of marks position backward, form and aspect band
With the distance that 3# high pressure belt should have 5-10 millimeter, after form and aspect band is wrapped, must wrap with adhesive tape, the position when the form and aspect end of tape
Put and be wound around to both sides, each 1 centimetre, terminate after returning to centre, peel off the semiconductor layer of core head, to the position of 27 centimetres;
5) connect copper sleeve: according to the size of core, select suitable copper sleeve, when stripping the major insulation of core, should connect than copper
Long 5 millimeters, earth lead then need not, use hydraulic tongs that copper sleeve is crimped, the copper sleeve after pressing must be put forth one's strength with hands and be drawn
Once, check whether steel joint crimps firmly;
6) polishing dedusting: roughly grind with the 80# rubber in special 211K rubber, polishes the semiconductor layer on core dry
Only, then with 320# rubber, this line is carried out fine grinding, by line ground smooth, use 3MCC-3 cable cleaning paper, the line that will have polished
Core scrub;
7) be comprehensively wound around: the core junction that online die semiconductor layer is clean with polishing, use 13# quasiconductor band from centre to
Both sides are wound around, half pressure half, two centimeters, left and right, and the silicone oil edge in cold-shrinkable terminal should be wound by end point in centre
13# semiconductor layer is coated with a circle, and cold-shrinkable terminal, on core, is then inserted in core by remaining uniform application, and position is then at 13# half
The position of conductor layer 3-4 cm backward extracts the support in shrinkage end out, in core front end, with 23# high pressure belt in shrinkage
Terminal is wound with core junction, method same half pressure half, needs in the gap of copper sleeve Yu major insulation to use
23# high pressure belt fills up, thickness as phase line major insulation, on the 23# high pressure belt wrapped, twines with 70# high pressure belt
Around, the same half pressure half that uses, the method covering of two-layer is on 23# high level belt the most altogether;
8) the ready-made cable termination leftover of bolt of cloth is wrapped up, and prevents from making a mess of, making dirty, clears up rubbish, keeps place cleaning.
Beneficial effects of the present invention is as follows:
Present invention process advantages of simple, simple operation, it is suitable for being widely popularized, the cable of production not only transmission effect is good, insulating properties
Preferably, and service life is the longest, it is possible to apply to a lot of field.
Detailed description of the invention
A kind of hv cable termination processes technique, sequentially pass through Insulation test, labelling cutting, pyrocondensation cooling, labelling winding,
Connecing copper sleeve, polishing dedusting, comprehensive winding and post processing and process technique to complete hv cable termination, it specifically comprises the following steps that
1) Insulation test: before making, need to carry out Insulation test, testing sequence with the megger of the 2500 volts cable to making
For the insulation between phase and phase and between phase and ground, any one of palpus is more than 2500 megaohms and can make, such as any one
Insulation less than 2500 megaohms or lower, then to cut out 1 meter of this cable, then retest, qualified after can make;
2) labelling cutting: first measure required size, carry out labelling, before moving knife, first adjust razor blade for carving tool, make the point of a knife exposed
Maintain an equal level mutually with the thinnest part of skin at this cable, from mark, draw two cuttves in 45 degree of angle modes, make sure to keep in mind not hinder core diagonal cutting pliers
The glass layer peelling off cable sheath and the inside is coordinated with cutter;
3) pyrocondensation cooling: clean the part of set point fingerstall with ethanol cloth, is inserted in a point fingerstall according to the order of core, and strikes tight.
Before this step, must be by earth lead 23# high pressure belt overstriking, to ensure the sealing after dividing fingerstall pyrocondensation, with heat gun to dividing
Fingerstall heats so that it is pyrocondensation.It should be noted that heat from centre to two during heating so that it is air can be got rid of completely, complete with cable
Seal, after point fingerstall cooling and shaping, according to required size, core is blocked;
4) labelling is wound around: from the head of core to a point fingerstall direction, the distance measuring 27 centimetres performs labelling, 23# high pressure belt
Winding position to point upper 2 to the 3 centimetres of end of finger of point fingerstall, during winding, should use half lap from the beginning of 27 centimetres of positions backward
The mode of bag is carried out, back and forth each the most once, two-layer altogether, determine phase sequence according to the color of core, use form and aspect band to be wound around, its method with
It is wound around 23# high pressure belt the same, covers on 23# high pressure belt, but should be noted at 27 centimetres of marks position backward, form and aspect band
With the distance that 3# high pressure belt should have 5-10 millimeter, after form and aspect band is wrapped, must wrap with adhesive tape, the position when the form and aspect end of tape
Put and be wound around to both sides, each 1 centimetre, terminate after returning to centre, peel off the semiconductor layer of core head, to the position of 27 centimetres;
5) connect copper sleeve: according to the size of core, select suitable copper sleeve, when stripping the major insulation of core, should connect than copper
Long 5 millimeters, earth lead then need not, use hydraulic tongs that copper sleeve is crimped, the copper sleeve after pressing must be put forth one's strength with hands and be drawn
Once, check whether steel joint crimps firmly;
6) polishing dedusting: roughly grind with the 80# rubber in special 211K rubber, polishes the semiconductor layer on core dry
Only, then with 320# rubber, this line is carried out fine grinding, by line ground smooth, use 3MCC-3 cable cleaning paper, the line that will have polished
Core scrub;
7) be comprehensively wound around: the core junction that online die semiconductor layer is clean with polishing, use 13# quasiconductor band from centre to
Both sides are wound around, half pressure half, two centimeters, left and right, and the silicone oil edge in cold-shrinkable terminal should be wound by end point in centre
13# semiconductor layer is coated with a circle, and cold-shrinkable terminal, on core, is then inserted in core by remaining uniform application, and position is then at 13# half
The position of conductor layer 3-4 cm backward extracts the support in shrinkage end out, in core front end, with 23# high pressure belt in shrinkage
Terminal is wound with core junction, method same half pressure half, needs in the gap of copper sleeve Yu major insulation to use
23# high pressure belt fills up, thickness as phase line major insulation, on the 23# high pressure belt wrapped, twines with 70# high pressure belt
Around, the same half pressure half that uses, the method covering of two-layer is on 23# high level belt the most altogether;
8) the ready-made cable termination leftover of bolt of cloth is wrapped up, and prevents from making a mess of, making dirty, clears up rubbish, keeps place cleaning.
The above is the preferred embodiment of the present invention, it is impossible to limit the interest field of the present invention with this.Should refer to
Go out, for those skilled in the art, technical scheme is modified or equivalent, all
Without departing from protection scope of the present invention.
Claims (3)
1. a hv cable termination processes technique, it is characterised in that: sequentially pass through Insulation test, labelling cutting, pyrocondensation cooling,
Labelling is wound around, connect copper sleeve, polishing dedusting, comprehensive be wound around and post processing processes technique to complete hv cable termination, and it is concrete
Step is as follows:
Insulation test: before making, need to carry out Insulation test with the megger of the 2500 volts cable to making, and testing sequence is phase
With the insulation between phase and between phase and ground, any one of palpus is more than 2500 megaohms and can make, such as the insulation of any one
Less than 2500 megaohms or lower, then to cut out 1 meter of this cable, then retest, qualified after can make;
Labelling cuts: first measures required size, carries out labelling, before moving knife, first adjusts razor blade for carving tool, makes the point of a knife exposed and is somebody's turn to do
At cable, the thinnest part of skin maintains an equal level mutually, from mark, draws two cuttves in 45 degree of angle modes, makes sure to keep in mind not hinder core diagonal cutting pliers with beautiful
Work cutter coordinates the glass layer peelling off cable sheath and the inside;
Pyrocondensation cools down: clean the part of set point fingerstall with ethanol cloth, is inserted in by a point fingerstall according to the order of core, and strikes tight.
The most before this step, earth lead 23# high pressure belt overstriking, to ensure the sealing after dividing fingerstall pyrocondensation, must be used hot blast
Rifle is to a point fingerstall heating so that it is pyrocondensation.
3. it should be noted that heat from centre to two during heating so that it is air can be got rid of completely, fully seal with cable, fingerstall to be divided
After cooling and shaping, according to required size, core is blocked;
Labelling is wound around: from the head of core to a point fingerstall direction, the distance measuring 27 centimetres performs labelling, twining of 23# high pressure belt
From the beginning of 27 centimetres of positions backward, to point upper 2 to the 3 centimetres of end of finger of point fingerstall, when winding, half-stack package should be used around position
Mode carry out, back and forth each the most once, two-layer altogether, determine phase sequence according to the color of core, use form and aspect band to be wound around, its method with twine
The same around 23# high pressure belt, cover on 23# high pressure belt, but should be noted in 27 centimetres of marks position backward, form and aspect band with
3# high pressure belt should have the distance of 5-10 millimeter, after form and aspect band is wrapped, must wrap with adhesive tape, the position when the form and aspect end of tape
It is wound around to both sides, each 1 centimetre, terminates after returning to centre, peel off the semiconductor layer of core head, to the position of 27 centimetres;
Connect copper sleeve: according to the size of core, select suitable copper sleeve, when stripping the major insulation of core, copper sleeve should be compared
Long 5 millimeters, earth lead then need not, use hydraulic tongs that copper sleeve is crimped, the copper sleeve after pressing must be put forth one's strength with hands and be drawn one
Under, check whether steel joint crimps firmly;
Polishing dedusting: roughly grind with the 80# rubber in special 211K rubber, polishes the semiconductor layer on core clean,
Then with 320# rubber, this line is carried out fine grinding, by line ground smooth, use 3MCC-3 cable cleaning paper, the core polished is wiped
Wash clean;
Comprehensive winding: the core junction that online die semiconductor layer is clean with polishing, uses 13# quasiconductor band from centre to both sides
Being wound around, half pressure half, two centimeters, left and right, end point should be in centre, by the silicone oil in cold-shrinkable terminal along the 13# wound partly
Conductor layer is coated with a circle, and cold-shrinkable terminal, on core, is then inserted in core by remaining uniform application, and position is then at 13# quasiconductor
The position of layer 3-4 cm backward extracts the support in shrinkage end out, in core front end, with 23# high pressure belt at cold-shrinkable terminal
It is wound with core junction, method same half pressure half, needs in the gap of copper sleeve Yu major insulation with 23# high
Pressure zone fills up, thickness as phase line major insulation, on the 23# high pressure belt wrapped, is wound with 70# high pressure belt, with
Sample uses half pressure half, and the method for two-layer covers on 23# high level belt the most altogether;
8) the ready-made cable termination leftover of bolt of cloth is wrapped up, and prevents from making a mess of, making dirty, clears up rubbish, keeps place cleaning.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610328799.6A CN105895265A (en) | 2016-05-18 | 2016-05-18 | High-voltage cable terminal processing process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610328799.6A CN105895265A (en) | 2016-05-18 | 2016-05-18 | High-voltage cable terminal processing process |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105895265A true CN105895265A (en) | 2016-08-24 |
Family
ID=56716542
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610328799.6A Pending CN105895265A (en) | 2016-05-18 | 2016-05-18 | High-voltage cable terminal processing process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105895265A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109768456A (en) * | 2018-12-04 | 2019-05-17 | 国网山东省电力公司汶上县供电公司 | Shorten the method for 110kV cable outdoor terminal Production Time |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07192557A (en) * | 1993-12-27 | 1995-07-28 | Furukawa Electric Co Ltd:The | Forming method for oil seal molding of terminal of power cable |
CN104113019A (en) * | 2014-05-30 | 2014-10-22 | 南通贝斯特船舶与海洋工程设计有限公司 | Manufacture method of multi-core high-voltage cable terminal |
-
2016
- 2016-05-18 CN CN201610328799.6A patent/CN105895265A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07192557A (en) * | 1993-12-27 | 1995-07-28 | Furukawa Electric Co Ltd:The | Forming method for oil seal molding of terminal of power cable |
CN104113019A (en) * | 2014-05-30 | 2014-10-22 | 南通贝斯特船舶与海洋工程设计有限公司 | Manufacture method of multi-core high-voltage cable terminal |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109768456A (en) * | 2018-12-04 | 2019-05-17 | 国网山东省电力公司汶上县供电公司 | Shorten the method for 110kV cable outdoor terminal Production Time |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104113019B (en) | A kind of preparation method of multicore hv cable termination | |
CN108666844B (en) | Full-automatic multicore wire crimp tin sticky terminal machine | |
CN105281260A (en) | 35kV heat shrink power cable intermediate connector manufacturing technology method | |
CN102903505B (en) | Transformer production process | |
CN101252266B (en) | Mounting process of three-core cable shrink terminal | |
CN208521482U (en) | A kind of rural power grids distribution business work skill operation training cabinet | |
CN103855652A (en) | Special manufacturing process for heat-shrinkable cable terminal head | |
CN105895265A (en) | High-voltage cable terminal processing process | |
CN114336438A (en) | Method for repairing mineral insulated cable copper sheath | |
US9997885B2 (en) | Method and device for producing a cable and cable produced by the method | |
CN104377527A (en) | High-voltage cable network installation method | |
CN104184078A (en) | Manufacturing of intermediate joint of high-voltage cable | |
CN205140617U (en) | Apparatus for producing of flexible fireproof cable | |
CN111740355A (en) | High-voltage cable joint repairing method | |
CN107899924B (en) | GIS shielding piece and silver-plated conductor paint spraying process | |
CN107196242A (en) | 110kV cross-linked power cable insulation transition joint manufacture crafts | |
CN111193226B (en) | V-shaped bracket type elastic clamp heat stripping tool | |
CN208033516U (en) | Secondary connection bending fixture | |
CN112350224A (en) | Wiring harness insulation layer stripping device | |
CN114227162A (en) | Hot melting connection process for 25 type passenger car box body and pipeline heat tracing band | |
CN106571218A (en) | Automatic processing equipment and method of electronic transformer lead | |
CN110556749A (en) | seismic exploration acquisition chain cable repairing method | |
CN109599227A (en) | A kind of harness production method suitable for medical treatment detection device | |
CN105070350A (en) | Manufacture process of low-flourine mica tape | |
CN205764488U (en) | Flux-cored wire forming machine group |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160824 |