CN105887678A - Construction method of epoxy asphalt concrete of steel bridge floor - Google Patents

Construction method of epoxy asphalt concrete of steel bridge floor Download PDF

Info

Publication number
CN105887678A
CN105887678A CN201510035306.5A CN201510035306A CN105887678A CN 105887678 A CN105887678 A CN 105887678A CN 201510035306 A CN201510035306 A CN 201510035306A CN 105887678 A CN105887678 A CN 105887678A
Authority
CN
China
Prior art keywords
asphalt concrete
epoxy asphalt
construction
width
paves
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510035306.5A
Other languages
Chinese (zh)
Inventor
朱连吉
钱博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Renqiu Yongji Construction and Installation Engineering Co Ltd
Original Assignee
Renqiu Yongji Construction and Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Renqiu Yongji Construction and Installation Engineering Co Ltd filed Critical Renqiu Yongji Construction and Installation Engineering Co Ltd
Priority to CN201510035306.5A priority Critical patent/CN105887678A/en
Publication of CN105887678A publication Critical patent/CN105887678A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the field of bridges, in particular to a construction method of epoxy asphalt concrete of a steel bridge floor. The construction method comprises the following steps: step S101, performing cleaning treatment on the bridge floor; step S102, performing shot blasting and rust removal on the bridge floor; step S103, performing lacquer spraying operation; step S104, treating jointing parts; step S105, spreading epoxy asphalt concrete; step S106, milling the epoxy asphalt concrete; step S107, performing maintenance of the epoxy asphalt concrete. The construction method disclosed by the invention has the advantages that an epoxy asphalt mixture has the advantages of being high in intensity and large in rigidity; under high temperature, the epoxy asphalt mixture is powerful in plasticity resistance and permanent deformation resistance, and good in low temperature crack resistance, and has excellent fatigue resistance, and the fatigue life of the epoxy asphalt mixture is 10-30 times of that of common asphalt concrete; in addition, the construction technology is simple and convenient, the cycle is short, and influence on road traffics is small.

Description

A kind of Steel Bridge Deck epoxy asphalt concrete construction
Technical field
The present invention relates to a kind of bridge field, particularly to a kind of Steel Bridge Deck epoxy asphalt concrete construction.
Background technology
Design that steel structure bridge is rich in creativeness with it and extraordinary refined moulding are bursted forth strange light extraordinary splendor in world's bridge construction history, mating formation also along with the unremitting effort of builder with pursue and obtain remarkable achievement of Steel Bridge Deck.For big-span steel bridge, bridge asphalt pavement layer directly influences the safety of driving, comfortableness, bridge durability as the important component part of bridge vehicle-driving, its quality.Therefore, except the intensity to bridge asphalt pavement layer.Deformation stability, fatigability etc. all have outside higher requirement, also require that it meets the particular/special requirements such as lightweight, high-adhesion, impermeability in serviceability, the asphalt concrete that past steel bridge uses is mated formation, or uses modified pitch to mat formation and still can not meet its needs.
Summary of the invention
Invention provides a kind of Steel Bridge Deck epoxy asphalt concrete construction, solve above-mentioned produced problem.
The present invention adopts the technical scheme that: a kind of Steel Bridge Deck epoxy asphalt concrete construction, comprises the following steps: step S101, and bridge floor cleaning processes;Step S102, bridge floor impeller blasting;Step S103, spray painting operation;Step S104, connects batch position and processes;Step S105, epoxy asphalt concrete paves;Step S106, epoxy asphalt concrete rolls;Step S107, epoxy asphalt concrete maintenance.
Described bridge floor cleaning processes, and before operation, first cleans surface of steel plate comprehensively with the instrument such as giant, hairbrush, rinses, the place dispersant work local cleaning that greasy dirt is serious, then wide scouring;Treat that bridge surface armor plate is dried, surface of steel plate has the welding thing that construction overlap, the crator etc. of protrusion remain on steel plate, and removing of polishing one by one with electric grinding machine, in bruting process, being careful not to too much erosion floorings, the steel plate after polishing should ensure that the smooth, clean of surface.
Described bridge floor impeller blasting, each width work strip to have the lap width of 50~100mm, and when the fineness after ball blast reaches more than 2.5 grades, roughness, in the range of 60~80 m, can carry out next procedure construction;The surface of steel plate of impeller blasting must blow off surface floating dust by the compressed air being dried, clean in time; and in 4h, spray epoxy zinc rich primer; fail timely operation for some reason, suitable protective measure will be taked, to stop the moisture in air and other materials reoxidation to steel plate.
Described spray painting operation, epoxy zinc rich primer to mix the most in proportion and to join, if special messenger detects wet-film thickness with wet film card and calibrator, accomplish coating be evenly distributed, thickness moderate;Testing oneself continuously wet-film thickness with wet film card in construction, wet-film thickness should be 100~140 m, to obtain the build required.
The described batch position of connecing processes, and construction operation every day region to be left and certain to spray after the 200mm width layer of paint sand papering reserved being fallen hair stubble when connecing the operation next time of batch position again, is still to ensure the cleaning of the scope of operation before spraying.
Described epoxy asphalt concrete paves, S2100 or S1800 paver is used to pave, paver automaticity is high, simple to operation, the paver 1h before work that paves every day preheats, and controls preheating temperature between 110~121 DEG C, after the first width paves, has been compacted, next width utilizes previous width to make datum level when paving, before the second width paves, will be cut by the longitudinal joint being connected with the first width after bituminous epoxy bonding oil is smeared on inclined-plane at 45 ° and carry out the construction that paves again.
Described epoxy asphalt concrete rolls, and rolls and carries out immediately following paver, rolls all static pressure, if special messenger is responsible for keeping an eye on compacting work, it is ensured that final pressure finishing temperature is not less than 55 DEG C.
Described epoxy asphalt concrete maintenance, uses and stands maintenance method, and curing period must not < 45d forbids all vehicle pass-throughs during this period.
The advantage of the present invention is: epoxy asphalt mixture has the advantage that intensity is high, rigidity is big, during high temperature, anti-plasticity and permanent deformation are strong, crack resistance at low-temperature is good, there is fabulous anti-fatigue performance, it it is 10~30 times of asphalt concrete fatigue life, and its construction technology is simple and convenient, and the cycle is short, the impact on road traffic is little.
Accompanying drawing explanation
Accompanying drawing is Steel Bridge Deck epoxy asphalt concrete construction process figure.
Detailed description of the invention
It is described further below in conjunction with construction process figure.
As shown in the figure, a kind of Steel Bridge Deck epoxy asphalt concrete construction, comprise the following steps: step S101, bridge floor cleaning processes, before operation, first surface of steel plate is cleaned comprehensively with the instrument such as giant, hairbrush, rinses, the place dispersant work local cleaning that greasy dirt is serious, then wide scouring;Treat that bridge surface armor plate is dried, surface of steel plate has the welding thing that construction overlap, the crator etc. of protrusion remain on steel plate, and removing of polishing one by one with electric grinding machine, in bruting process, being careful not to too much erosion floorings, the steel plate after polishing should ensure that the smooth, clean of surface.
Step S102, bridge floor impeller blasting, each width work strip to have the lap width of 50~100mm, and when the fineness after ball blast reaches more than 2.5 grades, roughness, in the range of 60~80 m, can carry out next procedure construction;The surface of steel plate of impeller blasting must blow off surface floating dust by the compressed air being dried, clean in time; and in 4h, spray epoxy zinc rich primer; fail timely operation for some reason, suitable protective measure will be taked, to stop the moisture in air and other materials reoxidation to steel plate.
Step S103, spray painting operation, epoxy zinc rich primer to mix the most in proportion and to join, if special messenger detects wet-film thickness with wet film card and calibrator, accomplish coating be evenly distributed, thickness moderate;Testing oneself continuously wet-film thickness with wet film card in construction, wet-film thickness should be 100~140 m, to obtain the build required.
Step S104, connects batch position and processes, and construction operation every day region to be left and certain to spray after the 200mm width layer of paint sand papering reserved being fallen hair stubble when connecing the operation next time of batch position again, is still to ensure the cleaning of the scope of operation before spraying.
Step S105, epoxy asphalt concrete paves, using S2100 or S1800 paver to pave, paver automaticity is high, simple to operation, the paver 1h before work that paves every day preheats, control preheating temperature is between 110~121 DEG C, and after the first width paves, has been compacted, next width utilizes previous width to make datum level when paving, before second width paves, the longitudinal joint being connected with the first width to be cut after bituminous epoxy bonding oil is smeared on inclined-plane at 45 ° and carry out the construction that paves again.
Step S106, epoxy asphalt concrete rolls, and rolls and carries out immediately following paver, rolls all static pressure, if special messenger is responsible for keeping an eye on compacting work, it is ensured that final pressure finishing temperature is not less than 55 DEG C.
Step S107, epoxy asphalt concrete maintenance, use and stand maintenance method, curing period, must not < 45d forbids all vehicle pass-throughs during this period.

Claims (8)

1. a Steel Bridge Deck epoxy asphalt concrete construction, it is characterised in that: comprising the following steps: step S101, bridge floor cleaning processes;Step S102, bridge floor impeller blasting;Step S103, spray painting operation;Step S104, connects batch position and processes;Step S105, epoxy asphalt concrete paves;Step S106, epoxy asphalt concrete rolls;Step S107, epoxy asphalt concrete maintenance.
A kind of Steel Bridge Deck epoxy asphalt concrete construction, it is characterized in that: described bridge floor cleaning processes, before operation, first surface of steel plate is cleaned comprehensively with the instrument such as giant, hairbrush, rinses, the place dispersant work local cleaning that greasy dirt is serious, then wide scouring;Treat that bridge surface armor plate is dried, surface of steel plate has the welding thing that construction overlap, the crator etc. of protrusion remain on steel plate, and removing of polishing one by one with electric grinding machine, in bruting process, being careful not to too much erosion floorings, the steel plate after polishing should ensure that the smooth, clean of surface.
A kind of Steel Bridge Deck epoxy asphalt concrete construction, it is characterized in that: described bridge floor impeller blasting, each width work strip to have the lap width of 50~100mm, when the fineness after ball blast reaches more than 2.5 grades, roughness, in the range of 60~80 m, can carry out next procedure construction;The surface of steel plate of impeller blasting must blow off surface floating dust by the compressed air being dried, clean in time; and in 4h, spray epoxy zinc rich primer; fail timely operation for some reason, suitable protective measure will be taked, to stop the moisture in air and other materials reoxidation to steel plate.
A kind of Steel Bridge Deck epoxy asphalt concrete construction, it is characterized in that: described spray painting operation, epoxy zinc rich primer to be mixed the most in proportion and to join, if special messenger detects wet-film thickness with wet film card and calibrator, accomplish coating be evenly distributed, thickness moderate;Testing oneself continuously wet-film thickness with wet film card in construction, wet-film thickness should be 100~140 m, to obtain the build required.
A kind of Steel Bridge Deck epoxy asphalt concrete construction, it is characterized in that: described in connect batch position and process, construction operation every day region to be left and certain to spray after the 200mm width layer of paint sand papering reserved being fallen hair stubble when connecing the operation next time of batch position again, is still to ensure the cleaning of the scope of operation before spraying.
A kind of Steel Bridge Deck epoxy asphalt concrete construction, it is characterized in that: described epoxy asphalt concrete paves, S2100 or S1800 paver is used to pave, paver automaticity is high, simple to operation, the paver 1h before work that paves every day preheats, control preheating temperature between 110~121 DEG C, when the first width paves, after being compacted, next width utilizes previous width to make datum level when paving, before second width paves, the longitudinal joint being connected with the first width is cut after bituminous epoxy bonding oil is smeared on inclined-plane at 45 ° and carry out the construction that paves again.
7. a kind of Steel Bridge Deck epoxy asphalt concrete construction according to claim 1 described in, it is characterized in that: described epoxy asphalt concrete rolls, roll and carry out immediately following paver, roll all static pressure, if special messenger is responsible for keeping an eye on compacting work, it is ensured that final pressure finishing temperature is not less than 55 DEG C.
A kind of Steel Bridge Deck epoxy asphalt concrete construction, it is characterised in that: described epoxy asphalt concrete maintenance, use and stand maintenance method, curing period, must not < 45d forbids all vehicle pass-throughs during this period.
CN201510035306.5A 2015-01-26 2015-01-26 Construction method of epoxy asphalt concrete of steel bridge floor Pending CN105887678A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510035306.5A CN105887678A (en) 2015-01-26 2015-01-26 Construction method of epoxy asphalt concrete of steel bridge floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510035306.5A CN105887678A (en) 2015-01-26 2015-01-26 Construction method of epoxy asphalt concrete of steel bridge floor

Publications (1)

Publication Number Publication Date
CN105887678A true CN105887678A (en) 2016-08-24

Family

ID=56999117

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510035306.5A Pending CN105887678A (en) 2015-01-26 2015-01-26 Construction method of epoxy asphalt concrete of steel bridge floor

Country Status (1)

Country Link
CN (1) CN105887678A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111827117A (en) * 2020-06-24 2020-10-27 中铁北京工程局集团(天津)工程有限公司 Concrete pouring method for bridge deck of steel-concrete composite beam
CN112030761A (en) * 2020-09-01 2020-12-04 浙江世润建创科技发展有限公司 Steel bridge full-section cleaning, paint spraying and stone scattering assembly and disassembly integrated machine and use method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1928243A (en) * 2006-09-20 2007-03-14 山东省路桥集团有限公司 Method for constructing epoxy resin pitch concrete steel bridge surface
JP2010095849A (en) * 2008-10-14 2010-04-30 Toray Ind Inc Method for reinforcing steel floor slab
CN102635047A (en) * 2012-04-17 2012-08-15 中交二公局第三工程有限公司 Large-span bridge deck composite structure layer construction technology

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1928243A (en) * 2006-09-20 2007-03-14 山东省路桥集团有限公司 Method for constructing epoxy resin pitch concrete steel bridge surface
JP2010095849A (en) * 2008-10-14 2010-04-30 Toray Ind Inc Method for reinforcing steel floor slab
CN102635047A (en) * 2012-04-17 2012-08-15 中交二公局第三工程有限公司 Large-span bridge deck composite structure layer construction technology

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张南: "《桥梁结构质量控制技术与工程实例》", 31 March 2011 *
张挺: "环氧沥青混凝土铺装施工质量控制-以西堠门大桥为例", 《中国水运》 *
陈岱杰: "西堠门大桥钢桥面环氧沥青混凝土铺装方案", 《中国水运》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111827117A (en) * 2020-06-24 2020-10-27 中铁北京工程局集团(天津)工程有限公司 Concrete pouring method for bridge deck of steel-concrete composite beam
CN112030761A (en) * 2020-09-01 2020-12-04 浙江世润建创科技发展有限公司 Steel bridge full-section cleaning, paint spraying and stone scattering assembly and disassembly integrated machine and use method thereof

Similar Documents

Publication Publication Date Title
CN102226330B (en) Method for micro-treatment of cement concrete road surface
CN110735371B (en) Weather-resistant colored resin cover and preparation method thereof
CN201280677Y (en) Improved ultrathin antiskid paving structure of epoxy resins
CN103938513B (en) Construction process of colored pavement epoxy non-slip wearing layer structure
CN108343213A (en) A kind of underground parking garage epoxy resin mortar abrasion-proof terrace and construction method
CN101914886A (en) Construction method of wear-resistant non-slip ramp
CN105887678A (en) Construction method of epoxy asphalt concrete of steel bridge floor
CN103410071A (en) Construction method for paving stable sealing layer on steel bridge deck for realizing preventive maintenance
CN110184933A (en) A kind of steel box girder bridge floor paving construction method
CN101935971A (en) Steel bridge deck protecting device and production method thereof
CN103321447A (en) Method for repairing metal fluorocarbon paint outer wall coating defects
CN102777015A (en) Integrally-cast steel rib millstone terrace and construction process thereof
CN108581363A (en) A kind of Vertical Mill wheel hub restorative procedure
CN107905096A (en) A kind of road/wearing floor construction method
CN106638295A (en) Pavement method of steel bridge deck made from epoxy asphalt
KR100724163B1 (en) Repairing method of bridge or road using waste tire chip
CN106903477A (en) A kind of taper roll-in machine bearing position renovation technique
CN101929127B (en) Method for preparing overlay of bridge expansion joint
KR101344735B1 (en) Water-soluble waterproof composition for asphalt and water-soluble waterproof method using the water-soluble waterproof material made by the same
CN106223153B (en) Modified by tar epoxy pavement structure and construction technology under a kind of low temperature environment
CN203285046U (en) Static plastic spraying profile steel formwork
CN109629842A (en) A kind of restorative procedure of status concrete structure breakage
CN109082967B (en) Superfine powder spraying layer structure for tunnel anti-skid pavement and preparation and construction processes thereof
KR102614304B1 (en) New surface coating method of structures using starfish nano-bio coating composition and solvent-free eco-friendly double coating material for surface repair protection of steel bridges and steel structures
CN1292137C (en) Integral seamless floor on grade prepared from environmental protection type epoxy resin grindstones in high intensity

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160824

WD01 Invention patent application deemed withdrawn after publication