CN105887657A - Soft foundation road and bridge connecting slope two-dimensional prestressing elastic shell plate application technology - Google Patents

Soft foundation road and bridge connecting slope two-dimensional prestressing elastic shell plate application technology Download PDF

Info

Publication number
CN105887657A
CN105887657A CN201410422738.7A CN201410422738A CN105887657A CN 105887657 A CN105887657 A CN 105887657A CN 201410422738 A CN201410422738 A CN 201410422738A CN 105887657 A CN105887657 A CN 105887657A
Authority
CN
China
Prior art keywords
bridge
prestressing
road
shell plate
connecting slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410422738.7A
Other languages
Chinese (zh)
Inventor
钱久军
刘珍昆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410422738.7A priority Critical patent/CN105887657A/en
Publication of CN105887657A publication Critical patent/CN105887657A/en
Pending legal-status Critical Current

Links

Abstract

A novel two-dimensional prestressing elastic shell plate connecting slope technology can solve the normal vehicle bumping problems in soft foundation road and bridge projects; two-dimensional prestressing ribs are novelly introduced in the connecting slope section of the road and bridge; the elastic plate with two-dimensional prestressing ribs can effectively disperse stresses so as to reduce and control settlement deformation of bridgehead back filled soil; and deformation coordinating with the soil body can effectively prevent bridgehead vehicle jumping phenomenon; the novel two-dimensional prestressing elastic shell plate connecting slope technology is novel and unique in design, simple in construction technology, safe and reliable, and has very wide application values.

Description

Soft soil foundation road and bridge connect slope two dimension prestressing elasticity coverboard application technology
Art
The invention belongs to a kind of urban municipal road science of bridge building field, be specifically related to a kind of solve soft soil foundation Bridge with in road engineering common jumping car problem connect slope technology.
Background technology
In urban construction, the problem of bumping at bridge-head on soft soil foundation not only can reduce driving comfort level but also serious harm traffic safety.At present, the problem of bumping at bridge-head or the property difficult problem in a world are the most effectively solved.
Owing to bridge has navigation and many requirement the such as drain off floodwaters to limit, therefore floor elevation is usually above road surface, and the factor such as construction and excavation inevitably results in end of the bridge and there is fairly large banketing in addition.Retraining again the soil body in the middle part of comparing because of the end of the bridge soil body few, so the produced deformation of base compress that bankets is the biggest, in general Practical Project, end of the bridge absolute altitude is commonplace compared with general road raising about two meters.During indivedual relatively medium-and-large-sized river course, improve 4-5 rice and also calculate normally.The sedimentation and deformation of its bridge pier in actual use, often within 5cm, the soil body at end of the bridge rear portion compression and being deposited in then up to 20~50cm.
Nowadays in the soft soil foundation of the coastal area such as China Jiangsu and Zhejiang Provinces, prevent nose from jumping difficult point place that car is also engineering design and construction technology.And currently technical measures is also placed on the control of compression, soil solidifying and loaded deformation to end of the bridge backfill soil.Existing design, construction have mainly been taken the concrete measures a variety of, such as: strengthen end of the bridge and return quality of filling soil, take to select good backfill soil and layering rammer to fill out, use retaining wall to close end of the bridge both sides, be also adopted by the new techniques such as relevant geotextiles;Under the precondition controlling back quality of filling soil, the soil body after end of the bridge is progressively taked concrete mixing pile to reinforce the soil body after end of the bridge;At end of the bridge buttress with backfill soil thereafter, use a kind of attachment strap of suitable length, so that the impact of sedimentation is eased by the gradient;Take what Roofing slab connected to connect slope process etc. in end of the bridge proper range.
But, different schemes all achieves certain effect in its specific environment, but for soft soil foundation using the extremely rare of two dimension prestressing elastic thin shell, this kind of scheme to have can effectively to solve car problem of jumping, there is good feasibility and therefore have important realistic meaning simultaneously.
Summary of the invention
Fully analyzing the deficiency of the technical scheme of the pre-anti-jump car of existing end of the bridge and this programme is used the feature of elasticity coverboard, the invention provides a kind of novel soft soil foundation road and bridge connects slope two dimension prestressing elasticity coverboard application technology.
This technology is when solving the jumping car problem in Practical Project, herein in connection with in view of the slope retaining etc. reinforcing end of the bridge.The present invention is made can not only effectively to overcome the problem of bumping at bridge-head also to have the effect of end of the bridge bank protection concurrently.Material, equipment and technique used by the present invention is to be commonly used in current case history, has the best feasibility.Its solve its technical problem technical scheme just be:
1, by having the two dimension prestressing plate of certain rigidity, make the compressive stress on road surface obtain a range of diffusion, and directly reduce soil pressure, thus the sedimentation reducing the bridgehead soil body reached and the effect of compression.
2, it is applied with two dimension prestressing reinforcing bar due to end of the bridge, the bridgehead soil body is had the cohesiveness of level, the soil body is formed operative constraint, thus produces the effect of a kind of similar cuff.It is effectively increased the resistance to compression of the soil body, makes the soil body effectively reduce sedimentation and deformation and compression.
3, owing to this technology have employed, to have the two dimension prestressing coverboard of Reasonable Rigidity be a kind of can to allow its elastic plate with the common compatible deformation of the bottom soil body, deformation is that reduced overall is formed, it is similar to a kind of overlength elasticity attachment strap technology, therefore sudden change sedimentation will not be produced at end of the bridge thus be substantially improved bumping at bridge-head situation.
4, another factor that bumping at bridge-head produces is also in that left and right, bridgehead two ends retaining wall is under soil body thrust, the side-move distortion of retaining wall is to the sedimentation produced, this technology, because stress has been delivered to road line direction, also deforms effectively alleviating produced by the horizontal thrust on both sides retaining wall and impact.
5 additionally, for some special foundation conditions, also reserve grout hole, it can be carried out slip casting pressurization under flexographic plate as a kind of arbitrary way.
The present invention connects slope to soft soil foundation Bridge and provides the benefit that, conveniently end of the bridge can be connect in engineering construction slope construction, can effectively be avoided because local settles problem of bumping at bridge-head that is excessive and that cause by common compatible deformation in actual use.
Accompanying drawing explanation
The present invention is further described with embodiment below in conjunction with the accompanying drawings.
Fig. 1 be in the present invention attachment strap in the complete layout of end of the bridge
Fig. 2 is the present invention schematic diagram at the vertical section in certain hypothesis section
Fig. 3 is layering schematic diagram
Detailed description of the invention
In FIG, two dimension prestressing flexible board rests on abutment bent cap (2) and concrete sleeper beam (3) as overall (1) two ends respectively with other appendages.In order to reach to accept rational purpose, two dimension prestressing flexible board (1) length L is usually about 7 times of bridge floor and superelevation of highway surface h, can make arch camber depending on practical situation in addition and process.
Fig. 2 certain assume section connect in the example of slope, prestressing force typically can use pre-tensioning system technique, backfill soil (5) at end of the bridge retaining wall (4) rear portion is successively tamped, its top remakes prestressing force elasticity coverboard (6), wherein carry out arrangement of reinforcement, and stretch-draw two dimension prestressing reinforcing bar (9).And solidifying soil stabilization layer (7) is laid in upper back, then topmost is road structure layer and road surface (8).Reserved pore (11) is to banket Compression Settlement in order to compensate rammer as later stage grouting under pressure hole.
In Specific construction, effectively guaranteeing that the flexible armoured concrete slab that thickness is 6cm~12cm reaches lucky elastic stage, be the guardian technique requirement of this technology, all structural flexibilities also can have the compatibility after being reflected in foundation soil deformation, i.e. synchronizes deformation.This function is mainly produced by two dimension prestressing with effect, additionally must conscientiously carry out roadbed stable layer, it is ensured that bridge pier avris returns the safeguard that quality of filling soil is also the most important thing.
In the planar layer schematic diagram of Fig. 3, as presstressed reinforcing steel (9), bar-mat reinforcement (12), stabilized zone (7), structure sheaf and the horizontal layout schematic diagram of road surface (8) of configuration in the roadbase soil body, major part two dimension prestressing elasticity coverboard (6) of the present invention from lower-left to upper right.Prestressing force typically can use pre-tensioning system technique, owing to presstressed reinforcing steel is as a kind of frame mode and the technique alleviating stress, arrangement pitch is often relatively dredged, typically can arrange between@500~@1000, and longitudinally can also select respectively by designing according to the practical situation of engineering with horizontal spacing.Presstressed reinforcing steel end anchorage (10) is separately fixed on abutment bent cap (2), concrete sleeper beam (3) and side retaining wall capping beam (13).

Claims (8)

1. an engineering scheme for innovation, mainly solves jumping car problem common in the science of bridge building of soft soil foundation.
Technical scheme the most according to claim 1, is characterized in that: use a kind of overall structure (1) with novel two dimension prestressing elastic plate that end of the bridge is connect slope.
The most according to claim 2 connect slope structure (1), it is characterized in that mainly being collectively constituted by compacted fill (5), two dimension prestressing elastic plate (6), concrete stabilized zone (7) and road structure aspect layer (11).
Prestressing force flexible board the most according to claim 2, it is characterized in that more practical engineering calculation can rationally arch camber, reach to accept rational purpose.
Prestressing force flexible board the most according to claim 2, is characterized in that having reserved grout hole (13) can carry out special grouting pressurized treatments according to Practical Project situation.
Two dimension prestressing elastic plate (6) the most according to claim 3, it is characterized in that there is two dimension prestressing stretch-draw, surrounding contacts with the retaining wall capping beam (13) of end of the bridge bent cap (2), afterbody sleeper beam (3) and both sides respectively, and is effectively anchored by anchorage (10) etc..
Two dimension prestressing muscle (9) the most according to claim 6, its stretching mode is according to being pre-tensioning system or post stretching depending on practical situation, have bonding or soap-free emulsion polymeization mode.
8. all scantlings of the present invention determine all in accordance with Practical Project appropriate design.
CN201410422738.7A 2014-08-22 2014-08-22 Soft foundation road and bridge connecting slope two-dimensional prestressing elastic shell plate application technology Pending CN105887657A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410422738.7A CN105887657A (en) 2014-08-22 2014-08-22 Soft foundation road and bridge connecting slope two-dimensional prestressing elastic shell plate application technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410422738.7A CN105887657A (en) 2014-08-22 2014-08-22 Soft foundation road and bridge connecting slope two-dimensional prestressing elastic shell plate application technology

Publications (1)

Publication Number Publication Date
CN105887657A true CN105887657A (en) 2016-08-24

Family

ID=57000740

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410422738.7A Pending CN105887657A (en) 2014-08-22 2014-08-22 Soft foundation road and bridge connecting slope two-dimensional prestressing elastic shell plate application technology

Country Status (1)

Country Link
CN (1) CN105887657A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638291A (en) * 2017-02-14 2017-05-10 上海市城市建设设计研究总院(集团)有限公司 Structure of arc-shaped lap-joint slab capable of reducing bridge circulation control joint swelling and shrinking
CN106638277A (en) * 2017-02-14 2017-05-10 上海市城市建设设计研究总院(集团)有限公司 Expansible bridge abutment approach slab structure
CN106758782A (en) * 2017-02-14 2017-05-31 上海市城市建设设计研究总院(集团)有限公司 The construction of bridge hazard to bridge's pier end horizontal active force can be reduced

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2533153Y (en) * 2002-03-20 2003-01-29 宁波市城市建设设计院 Bridge approach capable of preventing car from skipping
CN2627053Y (en) * 2003-05-30 2004-07-21 长安大学 Pile form abutment soft patch
CN1540100A (en) * 2003-10-30 2004-10-27 湖南大学 Complete seamless bridge in road
KR100503867B1 (en) * 2005-02-23 2005-07-26 (주)신광건설 A water interception apparatus of the bridge slab
CN102051861A (en) * 2009-11-02 2011-05-11 郑州优特基础工程维修有限公司 Bridgehead vehicle bump prevention and control high polymer grouting technique and construction method thereof
CN103741595A (en) * 2014-01-21 2014-04-23 浙江省交通规划设计研究院 Bridge head structure for controlling bump at bridge head
CN203716051U (en) * 2014-01-21 2014-07-16 浙江省交通规划设计研究院 Soft soil foundation based bridgehead structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2533153Y (en) * 2002-03-20 2003-01-29 宁波市城市建设设计院 Bridge approach capable of preventing car from skipping
CN2627053Y (en) * 2003-05-30 2004-07-21 长安大学 Pile form abutment soft patch
CN1540100A (en) * 2003-10-30 2004-10-27 湖南大学 Complete seamless bridge in road
KR100503867B1 (en) * 2005-02-23 2005-07-26 (주)신광건설 A water interception apparatus of the bridge slab
CN102051861A (en) * 2009-11-02 2011-05-11 郑州优特基础工程维修有限公司 Bridgehead vehicle bump prevention and control high polymer grouting technique and construction method thereof
CN103741595A (en) * 2014-01-21 2014-04-23 浙江省交通规划设计研究院 Bridge head structure for controlling bump at bridge head
CN203716051U (en) * 2014-01-21 2014-07-16 浙江省交通规划设计研究院 Soft soil foundation based bridgehead structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638291A (en) * 2017-02-14 2017-05-10 上海市城市建设设计研究总院(集团)有限公司 Structure of arc-shaped lap-joint slab capable of reducing bridge circulation control joint swelling and shrinking
CN106638277A (en) * 2017-02-14 2017-05-10 上海市城市建设设计研究总院(集团)有限公司 Expansible bridge abutment approach slab structure
CN106758782A (en) * 2017-02-14 2017-05-31 上海市城市建设设计研究总院(集团)有限公司 The construction of bridge hazard to bridge's pier end horizontal active force can be reduced
CN106758782B (en) * 2017-02-14 2021-05-11 上海市城市建设设计研究总院(集团)有限公司 Structure capable of reducing horizontal acting force at end part of bridge abutment butt strap
CN106638291B (en) * 2017-02-14 2021-08-31 上海市城市建设设计研究总院(集团)有限公司 Arc-shaped lapping plate structure capable of reducing expansion and contraction amount of bridge circulation control joint

Similar Documents

Publication Publication Date Title
CN101838998B (en) Prestressed anchor cable pile sliding wall along river road shoulder and construction method thereof
CN203174453U (en) Light-mass embankment structure for managing bump at bridge head
CN204418003U (en) A kind of bridge platform post processing combined system
CN108999045A (en) A kind of subgrade strengthening structure and its construction method preventing and treating bumping at bridge-head
CN109853381B (en) Transitional structure for preventing bridge head from jumping and construction method thereof
CN204849851U (en) Retaining pile combines anti structure of floating in subway station of anti floating block
CN107805987A (en) The hassock layer Foam lightweight soil road structure and construction method in deep soft foundation section
CN104612120B (en) A kind of integral construction method setting up platform about steel-pipe pile in water
CN108842523A (en) In-strong expansive rock or expansive soils ballastless track of high-speed railway foundation stabilization construction and construction method
CN102966048B (en) Reinforcing method for increasing bearing force of spandrel-filled arch bridge
CN105887657A (en) Soft foundation road and bridge connecting slope two-dimensional prestressing elastic shell plate application technology
CN104674645A (en) Integral plate type small bridge and culvert combination applicable to soft soil foundations
CN104612142B (en) Integral abutment bridge structure based on composite flexible piles and construction method thereof
CN106917358B (en) A kind of cable-stayed bridge main-beam combination constructing method thereof and its counter weight construction system
CN203393609U (en) Seamless bridge head structure
CN211080254U (en) Structure for increasing backfill height of existing high-fill tunnel
CN105804101B (en) Reduce off-loading supporting and retaining system system and construction method and the application of retaining structure stress
KR101160186B1 (en) Pile slab construction technique for railroad land subsidence reduction
CN104499425A (en) Structure and construction process for reducing power impact response at back of seamless bridge abutment
CN208251156U (en) It is a kind of to reduce the grand heavy device of underground structure using building enclosure
CN209039963U (en) A kind of platform back preventing car jump between high road bed and bridge
CN105113384A (en) Z-shaped bridge end transition slab structure and construction method thereof
CN205775811U (en) A kind of structure being applied to abutment roadbed
CN105544334B (en) One kind is used for vehicle jumping at bridge head of highway Treatment Methods
CN211872447U (en) Side wide roadbed structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160824