CN105863218B - Non-curing rubber asphalt spraying construction equipment - Google Patents

Non-curing rubber asphalt spraying construction equipment Download PDF

Info

Publication number
CN105863218B
CN105863218B CN201610330714.8A CN201610330714A CN105863218B CN 105863218 B CN105863218 B CN 105863218B CN 201610330714 A CN201610330714 A CN 201610330714A CN 105863218 B CN105863218 B CN 105863218B
Authority
CN
China
Prior art keywords
coating
heat conduction
conduction oil
temperature
heating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610330714.8A
Other languages
Chinese (zh)
Other versions
CN105863218A (en
Inventor
许宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongke Jiantong Engineering Technology Co ltd
Original Assignee
Beijing Oriental Yuhong Waterproof Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Oriental Yuhong Waterproof Engineering Co ltd filed Critical Beijing Oriental Yuhong Waterproof Engineering Co ltd
Priority to CN201610330714.8A priority Critical patent/CN105863218B/en
Publication of CN105863218A publication Critical patent/CN105863218A/en
Application granted granted Critical
Publication of CN105863218B publication Critical patent/CN105863218B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/02Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
    • E04F21/06Implements for applying plaster, insulating material, or the like
    • E04F21/08Mechanical implements
    • CCHEMISTRY; METALLURGY
    • C10PETROLEUM, GAS OR COKE INDUSTRIES; TECHNICAL GASES CONTAINING CARBON MONOXIDE; FUELS; LUBRICANTS; PEAT
    • C10CWORKING-UP PITCH, ASPHALT, BITUMEN, TAR; PYROLIGNEOUS ACID
    • C10C3/00Working-up pitch, asphalt, bitumen
    • C10C3/002Working-up pitch, asphalt, bitumen by thermal means
    • CCHEMISTRY; METALLURGY
    • C10PETROLEUM, GAS OR COKE INDUSTRIES; TECHNICAL GASES CONTAINING CARBON MONOXIDE; FUELS; LUBRICANTS; PEAT
    • C10CWORKING-UP PITCH, ASPHALT, BITUMEN, TAR; PYROLIGNEOUS ACID
    • C10C3/00Working-up pitch, asphalt, bitumen
    • C10C3/10Melting

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • General Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Materials Engineering (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Organic Chemistry (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Road Paving Machines (AREA)
  • Coating Apparatus (AREA)

Abstract

The invention relates to a construction device for heating and spraying non-cured rubber asphalt, which comprises a storage barrel, wherein the storage barrel is an important component of the device, is an area for heating, temperature adjusting and heat insulating asphalt paint and is divided into two areas: the upper part is a heating zone, and the lower part is a cooling and heat-preserving zone. A first heat-conducting oil heating system is arranged in the heating area and used for heating and melting the non-solidified asphalt coating, the coating enters a cooling and heat-preserving area after being heated, a second heating system is arranged in the cooling and heat-preserving area, and the two pairs of heating systems perform temperature adjustment and heat preservation treatment on the heated and melted coating; the spraying machine is connected with the temperature adjusting and preserving area to carry out spraying operation. The invention adjusts and controls the temperature of the coating in the cooling and heat preservation area, so that the coating is constructed in a low-temperature state, the mechanical index of the material is ensured not to be damaged, and the phenomenon of pinholes on a coating layer caused by high temperature of the coating is avoided, or the phenomenon of smog during field construction of the coating in a high-temperature state is avoided.

Description

Non-curing rubber asphalt spraying construction equipment
Technical Field
The invention belongs to the field of waterproof engineering construction, and particularly relates to an integrated thermal spraying construction device for heating and constructing asphalt waterproof paint, which is divided into a heating high-temperature area, a storage cooling area and a heat preservation area.
Background
The method of the existing construction equipment and the defects thereof are as follows:
(1) the method comprises the steps of heating a pot by using fixed metal asphalt, placing a heater (with open fire) at the bottom of the heating pot, heating the asphalt in the pot, filling hot asphalt into an iron bucket by using a long-handle iron ladle, and conveying the hot asphalt to a construction site through the iron bucket for manual blade coating construction. The heating mode has the disadvantages of slow heating, incapability of freely moving, naked fire, poor safety and environmental protection performance of exposed heating, long heating time, manual stirring of the coating, only manual scraping and coating in construction, low efficiency,
(2): a set of heat conduction oil pipe circulation system is arranged in the equipment, after the heat conduction oil in the heat conduction oil pipe is heated by adopting electromagnetic heating or a burner, the heat conduction oil with high temperature circularly flows in the heat conduction oil pipe, and the asphalt coating is melted by circular heating and has the heat preservation effect on the non-solidified rubber asphalt coating. The heating process is as follows: the non-solidified asphalt coating is placed on a heating coil (the coil is in a shape of a disc formed by heat conducting oil pipes), the non-solidified rubber asphalt block coating is melted under the high-temperature action of the coil, then the melted non-solidified asphalt material is stirred in equipment, and the asphalt coating is kept at a certain construction temperature in the equipment. Install a light equipment additional on equipment, make non-curing coating export by the gear pump behind several layers of readily removable filter screens that wash, carry to heatable spray gun blowout through high-efficient reliable electrical heating hose, can select multiple nozzle, reach required spraying effect. When the spraying construction is not adopted, the external outlet tap of the device can be directly opened, and the coating directly flows into the construction barrel for blade coating construction.
The existing equipment has the following defects:
(1) the automatic walking and moving device cannot automatically walk and move, and can only be fixed at a certain position or moved by a crane on a construction site, so that the transportation distance is long and the working efficiency is influenced when workers carry out construction on the site; meanwhile, the existing equipment is only provided with a set of heat conduction oil circulating system, when the asphalt coating is heated, the temperature in the equipment can only be kept in the same high-temperature state, and temperature conversion and low-temperature storage of the asphalt coating cannot be carried out, so that the temperature is high during asphalt coating construction, safety accidents of workers are easy to occur, and a coating layer is easy to have a pinhole phenomenon when the temperature of the asphalt is high;
(2) the existing equipment adopts an asphalt pump for construction when spray construction is carried out, but the asphalt pump has low efficiency and the weight of the equipment is increased;
(3) the existing heating equipment can not control the temperature of the non-cured rubber asphalt coating, and no measure is taken to monitor the material temperature in the equipment;
(4) the spraying pipe of the existing equipment is dragged without a support rod after being connected out of the equipment, so that the phenomenon of serious abrasion of the spraying pipe is caused.
SUMMERY OF THE UTILITY MODEL
The invention mainly solves the defects that the equipment can not automatically travel, can not store the non-solidified asphalt coating at low temperature after being heated and can not monitor the temperature of the rubber asphalt coating in the equipment, and simultaneously solves the defects that the spraying construction efficiency is low and the spraying pipeline is worn due to overlong connection. In order to solve the above defects, the technical solution of the present invention is as follows: the utility model provides a non-curing rubber asphalt spraying construction equipment, is including storing the bucket, its characterized in that: the upper part of the storage barrel is a heating area, the lower part of the storage barrel is a cooling and heat preservation area, a heat conduction oil heating system is placed in the heating area of the storage barrel and used for heating the non-solidified coating, the coating enters the cooling and heat preservation area after being heated, a second heating system is installed in the cooling and heat preservation area, and the two pairs of heating systems heat the molten coating to carry out temperature regulation and heat preservation treatment; the spraying machine is connected with the cooling and heat preservation area to carry out spraying operation. A cooling device and a heat preservation system can be arranged in the cooling and heat preservation area.
Preferably, the heat conduction oil heating system comprises a disc-shaped heat conduction oil pipe, the disc-shaped heat conduction oil pipe is arranged below the inner spiral of the storage barrel, the heat conduction oil pipe on each horizontal plane is also in a horizontal spiral structure, two ends of the heat conduction oil pipe are respectively communicated with a first circulating pump, heat conduction oil is placed in the heat conduction oil pipe, and the heat conduction oil in the heat conduction oil pipe circulates in the heat conduction oil pipe through the first circulating pump; one end of the first circulating pump is communicated with the first container, heat conduction oil is contained in the first container, one end of the first container is connected with the heater, the heater is electrically connected with the first container, the heater is used for heating the heat conduction oil, and the heated heat conduction oil enters the heat conduction oil pipe through the first circulating pump to flow in a circulating mode.
Preferably, a heat conduction oil temperature detector is inserted into the heat conduction oil pipe close to one end of the circulating pump.
Preferably, the heating system II comprises a heat conduction oil pipe, an oil inlet pipe and an oil outlet pipe are respectively arranged at two ends of the heat conduction oil pipe, the free ends of the oil inlet pipe and the oil outlet pipe are communicated with a heating oil tank, meanwhile, the oil outlet pipe is also communicated with a second circulating pump, heat conduction oil in the heating oil tank circularly flows in the heat conduction oil pipe through the second circulating pump, one end of the second circulating pump is communicated with a second container, the second container contains heat conduction oil, one end of the second container is connected with a heater, the heater is electrically connected with the second container, the heater is used for heating the heat conduction oil, and the heated heat conduction oil enters the heat conduction pipe; wherein the spraying machine is communicated with the heat conducting oil pipe.
Preferably, a heat conduction oil temperature detector is inserted into the heat conduction oil pipe close to two ends of the circulating pump.
Preferably, a support is installed on the side wall of the storage barrel, a plurality of fixing rings arranged at intervals are arranged on the support, and the spraying pipe penetrates through the fixing rings.
Preferably, a coating temperature controller is arranged in the cooling and heat preservation area and is in signal connection with a heater of the heating container II, the coating temperature controller is used for monitoring the temperature of the coating at the cooling and heat preservation area, when the temperature of the coating is high, the temperature of the heat conduction oil is independently reduced, and when the temperature of the material is high, the temperature of the heat conduction oil is independently increased, and the temperature of the coating is increased.
Preferably, the lower part of the storage barrel is also provided with a discharge opening;
or a coating temperature meter is also arranged in the heating area and the cooling and heat-preserving area in the storage barrel.
Preferably, the bottom of the storage barrel is provided with a walking system, the walking system comprises a roller and a motor, the roller is arranged at the bottom of the storage barrel, the motor is connected with the roller through a wire, and the motor drives the roller to rotate.
When the device works, firstly, the non-solidified coating is placed on the heating system, when the temperature of the heating system rises to a temperature above the softening point of the non-solidified coating, the non-solidified coating starts to be melted, the melted non-solidified coating enters the heating system II, the non-solidified coating entering the heating system II is subjected to temperature adjustment in the area, and when the temperature of the non-solidified coating is adjusted to a preset temperature, the spraying machine is started to perform spraying operation. By adopting the method, the temperature of the coating can be flexibly adjusted according to actual needs, so that the coating is more suitable for operation in various environments.
According to the technical scheme, the coating is heated in the heating area and is insulated in the cooling area of the storage area, so that low-temperature construction of the coating is facilitated, mechanical indexes of materials are not damaged, and the phenomenon of pinholes on a coating layer caused by high temperature of the coating is avoided.
Drawings
FIG. 1 is a schematic view of the present invention
Description of the figures: storage bucket 1, flush coater 2, spray pipe 3, heat conduction oil pipe 4, circulating pump 5, conduction oil temperature detector 6, oil inlet pipe 7, oil outlet pipe 8, heating oil tank 9, circulating pump two 10, coating temperature controller 11, fixed ring 12, rope 13, cross bar 14 and montant 15, couple 16, bottom heating device 17, discharge opening 19, gyro wheel 20, motor 21, feed inlet 22, handrail 23, electrically controlled device 24
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings.
In the figure, the non-curing rubber asphalt spraying construction equipment comprises a storage barrel 1, wherein the storage barrel is an important component of the equipment and is an area for heating, temperature adjusting and heat preserving asphalt paint.
The upper part of the storage barrel 1 is a heating area, the lower part of the storage barrel 1 is a cooling and heat preservation area, and a heat conduction oil heating system is arranged in the heating area of the storage barrel 1 and is used for heating and melting non-solidified coatings, preferably heating and melting non-solidified asphalt coatings or non-solidified rubber asphalt coatings. Heating the coating and then entering a cooling and heat preservation area, wherein a heating system II is arranged in the cooling and heat preservation area, and the heating system carries out temperature regulation and heat preservation treatment on the coating after being heated and melted by two pairs of heating systems so as to control the temperature of the coating; and the coating machine 2 is arranged in the cooling and heat preservation area and is connected with the cooling and heat preservation area to carry out coating operation, the coating machine 2 coats the coating processed by the heating system II through the coating pipe 3, and the coating machine is an airless coating machine.
The structure of the present invention is described in detail below:
the heat conducting oil heating system comprises a disc-shaped heat conducting oil pipe 4, the disc-shaped heat conducting oil pipe 4 forms a coil pipe, the disc-shaped heat conducting oil pipe 4 is arranged in the storage barrel 1 in a spiral mode, and the heat conducting oil pipe 4 on each horizontal plane is also of a horizontal spiral structure. Preferably, the interval between the heat conduction oil pipes in the vertical direction is 4-5cm, and the diameter of each heat conduction oil pipe is 6 cm.
The two ends of the heat conduction oil pipe 4 are respectively communicated with a first circulating pump 5, heat conduction oil flows in the heat conduction oil pipe 3, and the heat conduction oil in the heat conduction oil pipe 3 circulates in the heat conduction oil pipe through the first circulating pump 5; one end of the first circulating pump 5 is communicated with a first container (not shown in the figure), heat conduction oil is contained in the first container, one end of the first container is connected with a heater (not shown in the figure), the heater is electrically connected with the first container and is used for heating the heat conduction oil, and the heated heat conduction oil enters the heat conduction oil pipe through the first circulating pump 5 to flow in a circulating mode. In order to control the temperature of the heat conduction oil pipe, a heat conduction oil temperature detector 6 is inserted into the heat conduction oil pipe close to the end 5 of the first circulating pump.
The non-solidified asphalt coating is thrown into the surface of the coil pipe of the heating area, the flame thrower is adopted to heat the heat conducting oil in the heat conducting oil pipe, the hot heat conducting oil circularly flows in the coil pipe, when the temperature of the surface of the coil pipe rises to a temperature above the softening point of the non-solidified asphalt coating, the non-solidified asphalt coating starts to melt, and in order to accelerate the melting speed, the temperature of the heat conducting oil in the heating pipe can be increased.
After the coating is melted in the heating area, the coating flows into the lower part of the storage barrel 1 and enters the cooling and heat preservation area of the storage barrel 1. The temperature of the paint after heating cannot be too high and must enter a storage area with a lower temperature, in which the temperature of the paint is lowered, but not too low or the viscosity of the paint increases and construction is impossible. Therefore, a set of heat conduction oil heat preservation system, namely a heating system II is independently arranged in the area, and in order to avoid overhigh temperature, the heat conduction oil in the heat conduction oil pipe is electrically heated and preserved with low power.
The heating system II comprises a heat conduction oil pipe, an oil inlet pipe 7 and an oil outlet pipe 8 are respectively arranged at two ends of the heat conduction oil pipe, the free ends of the oil inlet pipe 7 and the oil outlet pipe 8 are jointly communicated with a heating oil tank 9, meanwhile, the oil outlet pipe 8 is also communicated with a second circulating pump 10, heat conduction oil in the heating oil tank 8 circularly flows in the heat conduction oil pipe through the second circulating pump 10, one end of the second circulating pump 10 is communicated with a second container (not shown in the figure), the second container is filled with the heat conduction oil, one end of the second container is connected with a heater (not shown in the figure), the heater is electrically connected with the second container and is used for heating the heat conduction oil, the temperature of the heater can be controlled, the heated heat conduction oil enters the heat conduction oil pipe; wherein the spraying machine 2 is communicated with a heat conducting oil pipe. In order to control the temperature of the heat conduction oil pipe, a heat conduction oil temperature detector 6 is inserted into the heat conduction oil pipe close to the end 10 of the circulating pump II. And meanwhile, a coating temperature controller 11 is arranged in the cooling and heat preservation area, the coating temperature controller 11 is in signal connection with a heater of the heating container II, the coating temperature controller 11 is used for monitoring the temperature of the coating at the cooling and heat preservation area, when the temperature of the coating is high, the temperature of heat conduction oil is independently reduced, when the temperature of the coating is low, the temperature of the heat conduction oil is independently increased, the temperature of the coating is increased, and the optimum construction temperature of the material is kept in the storage barrel after the non-solidified asphalt coating after being heated and melted is cooled.
The side wall of storage bucket 1 installs the support, sets up the solid fixed ring 12 that the several interval set up on the support, and spray tube 3 passes in solid fixed ring 12, perhaps links rod or rope 13 are connected on solid fixed ring 12, and solid fixed ring 12 is fixed again to the free end of rope 13, and spray tube 3 passes in solid fixed ring 12. With this structure, the spray pipe 3 is not dragged due to the support of the fixing ring 12, and thus the spray pipe 3 is not worn. The support can be that an solitary horizontal pole 14 directly inserts on storing bucket 1, also can be one and be right angled support, right angled support has horizontal pole 14 and montant 15, and montant 15 is installed on storing bucket 1, and horizontal pole 14 can be the telescopic link, can shrink when not needing to use the support and accomodate, also can install couple 16 on montant 15, for the intensity of strengthening the support, sets up the stiffener between horizontal pole 14 and montant 15. The connecting part of the cross rod 14 and the vertical rod 15 of the right-angle bracket can be movably connected, the cross rod 14 can be folded at the connecting part, so that the folded cross rod can be parallel to the vertical rod, or the cross rod can rotate along the connecting part of the cross rod and the vertical rod, the direction of the fixing ring 12 can be adjusted by the rotating structure, and the height of the spraying pipe 3 can be adjusted.
The lower part of the storage barrel is also provided with a discharge opening 19, and when the storage barrel is provided with excess paint and is not needed for use temporarily, the excess paint flows out from the discharge opening 19.
The storage barrel is also provided with a coating thermometer or a coating temperature controller in the heating area and the cooling and heat preservation area, and the temperature of the asphalt coating is monitored through the thermometer so as to regulate and control the temperature of the heat-conducting oil and achieve the purpose of adjusting the temperature of the asphalt coating.
Store the bottom installation traveling system of bucket, traveling system includes gyro wheel 20 and motor 21, and gyro wheel 20 is the universal wheel, and the gyro wheel is installed in the bottom of storing the bucket, and the motor passes through the wire and is connected with the gyro wheel, and motor drive gyro wheel rotates. The walking system can enable the equipment to move on the construction site.
According to the invention, the storage barrel 1 is a container with an opening, a barrel cover is arranged on the opening, a feed inlet 22 is reserved on the barrel cover, a sealing cover is arranged on the feed inlet 22, a handrail 23 is arranged on the sealing cover, an electric control device 24 is arranged on the barrel cover, the electric control device 24 controls the walking of the device, or controls the heating and temperature adjustment of the heat conducting oil heating system of the device, namely the heat conducting oil heating system and the heat conducting oil heating system, the electric control device is selected from the prior art, and the electric control device 24 can be remotely controlled by a remote controller, so that the work of.
When the paint spraying device is used, the heat conducting oil in the heat conducting oil heating system is heated firstly, when the paint is melted and enters a cooling and heat preservation area, the temperature of the paint is adjusted through the hot oil heating system II, and then the paint is sprayed out through the spraying machine.
The invention adjusts and controls the temperature of the coating in the cooling and heat preservation area, so that the coating is constructed in a low-temperature state, the mechanical index of the material is ensured not to be damaged, and the phenomenon of pinholes on a coating layer caused by high temperature of the coating or the phenomenon of smog during the field construction of the coating in a high-temperature state is avoided.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not intended to limit the embodiments of the present invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the embodiments of the present invention should be included in the scope of the embodiments of the present invention.

Claims (9)

1. The utility model provides a non-curing rubber asphalt spraying construction equipment, is including storing the bucket, its characterized in that: the upper part of the storage barrel is a heating area, the lower part of the storage barrel is a cooling and heat preservation area, a heat conduction oil heating system is placed in the heating area of the storage barrel and used for heating the non-solidified coating, the coating enters the cooling and heat preservation area after being heated, a second heating system is installed in the cooling and heat preservation area, and the two pairs of heating systems heat the molten coating to carry out temperature regulation and heat preservation treatment; the spraying machine is connected with the cooling and heat preservation area to carry out spraying operation;
the coating temperature controller is used for monitoring the temperature of the coating at the cooling and heat preservation area, independently reduces the temperature of the heat conduction oil when the temperature of the coating is high, independently increases the temperature of the heat conduction oil when the temperature of the coating is low, and improves the temperature of the coating.
2. The non-curing rubberized asphalt spray coating construction equipment according to claim 1, wherein: the heat conduction oil heating system comprises a disc-shaped heat conduction oil pipe, the disc-shaped heat conduction oil pipe is arranged below the inner spiral of the storage barrel, the heat conduction oil pipe on each horizontal plane is also in a horizontal spiral structure, two ends of the heat conduction oil pipe are respectively communicated with a first circulating pump, heat conduction oil is placed in the heat conduction oil pipe, and the heat conduction oil in the heat conduction oil pipe circulates in the heat conduction oil pipe through the first circulating pump; one end of the first circulating pump is communicated with the first container, heat conduction oil is contained in the first container, one end of the first container is connected with the heater, the heater is electrically connected with the first container, the heater is used for heating the heat conduction oil, and the heated heat conduction oil enters the heat conduction oil pipe through the first circulating pump to flow in a circulating mode.
3. The non-curing rubberized asphalt spray coating construction equipment according to claim 2, wherein: a heat conducting oil temperature detector is inserted into the heat conducting oil pipe near one end of the circulating pump.
4. The non-curing rubberized asphalt spray coating construction equipment according to claim 1, wherein: the heating system II comprises a heat conduction oil pipe, an oil inlet pipe and an oil outlet pipe are respectively arranged at two ends of the heat conduction oil pipe, the free ends of the oil inlet pipe and the oil outlet pipe are jointly communicated with a heating oil tank, meanwhile, a circulating pump II is also communicated with the oil outlet pipe, heat conduction oil in the heating oil tank circularly flows in the heat conduction oil pipe through the circulating pump II, one end of the circulating pump II is communicated with a container II, the container II contains heat conduction oil, one end of the container II is connected with a heater, the heater is electrically connected with the container II and is used for heating the heat conduction oil, and the heated heat conduction oil enters the heat conduction pipe; wherein the spraying machine is communicated with the heat conducting oil pipe.
5. The non-curing rubber asphalt spraying construction equipment as claimed in claim 4, wherein: a heat conducting oil temperature detector is inserted into the heat conducting oil pipe close to two ends of the circulating pump.
6. The non-curing rubberized asphalt spray coating construction equipment according to claim 1, wherein: the side wall of the storage barrel is provided with a support, the support is provided with a plurality of fixing rings arranged at intervals, and the spraying pipe penetrates through the fixing rings.
7. The non-curing rubberized asphalt spray coating construction equipment according to claim 1, wherein: wherein the lower part of the storage barrel is also provided with a discharge opening;
or a coating temperature meter is also arranged in the heating area and the cooling and heat-preserving area in the storage barrel.
8. The non-curing rubberized asphalt spray coating construction equipment according to claim 1, wherein: wherein, store the bottom installation traveling system of bucket, traveling system includes gyro wheel and motor, and the gyro wheel is installed in the bottom of storing the bucket, and the motor passes through the wire and is connected with the gyro wheel, and motor drive gyro wheel rotates.
9. The processing method of the non-solidified rubber asphalt spraying construction equipment adopts the non-solidified rubber asphalt spraying construction equipment as claimed in any one of claims 1 to 8, and is characterized in that: firstly, placing the non-solidified coating on a heating system, when the temperature of the heating system rises to a temperature above the softening point of the non-solidified coating, the non-solidified coating starts to be melted, the melted non-solidified coating enters a heating system II, the non-solidified coating entering the heating system II is subjected to temperature regulation in the area, and when the temperature of the non-solidified coating is regulated to a preset temperature, a spraying machine is started to carry out spraying operation.
CN201610330714.8A 2016-05-18 2016-05-18 Non-curing rubber asphalt spraying construction equipment Active CN105863218B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610330714.8A CN105863218B (en) 2016-05-18 2016-05-18 Non-curing rubber asphalt spraying construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610330714.8A CN105863218B (en) 2016-05-18 2016-05-18 Non-curing rubber asphalt spraying construction equipment

Publications (2)

Publication Number Publication Date
CN105863218A CN105863218A (en) 2016-08-17
CN105863218B true CN105863218B (en) 2020-01-14

Family

ID=56634342

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610330714.8A Active CN105863218B (en) 2016-05-18 2016-05-18 Non-curing rubber asphalt spraying construction equipment

Country Status (1)

Country Link
CN (1) CN105863218B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107747273B (en) * 2017-10-10 2023-07-07 黄河科技学院 Marking paint heat conduction oil double-circulation hot melting tank
CN108504286A (en) * 2018-06-14 2018-09-07 秦皇岛市地维建材有限公司 Multifunctional mobile aqueous rubber asphalt waterproofing paint equipment
CN108756161B (en) * 2018-06-20 2024-02-23 中山晶诚机电设备有限公司 Melt flush coater
CN109894292A (en) * 2019-03-19 2019-06-18 江阴市绿畅路面新材料有限公司 A kind of hand-hold type asphalt flush coater
RU2742426C1 (en) * 2020-08-05 2021-02-05 Олег Александрович Скворцов Device for melting of briquetted amorphous substance and method implemented by it

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4661684A (en) * 1978-10-16 1987-04-28 Sellers William W Asphalt heating system
CN2187628Y (en) * 1992-09-28 1995-01-18 李克义 Pitch heating and thermal-insulating device for vehicle conveying and construction in situs
CN2317241Y (en) * 1998-01-22 1999-05-05 常智 Heat pipe type asphalt fast heating device
CN201343268Y (en) * 2009-01-09 2009-11-11 唐山德生防水材料有限公司 Fast heating device of asphalt storage tank
CN202672006U (en) * 2012-07-05 2013-01-16 福建铁拓机械有限公司 Bituminous mixture stirring equipment with heating and heat preservation system
CN103015293A (en) * 2012-12-04 2013-04-03 山东泰德新能源有限公司 Asphalt heating tank
CN205742924U (en) * 2016-05-18 2016-11-30 东方雨虹民用建材有限责任公司 A kind of uncured rubber asphalt spraying application equipment

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4661684A (en) * 1978-10-16 1987-04-28 Sellers William W Asphalt heating system
CN2187628Y (en) * 1992-09-28 1995-01-18 李克义 Pitch heating and thermal-insulating device for vehicle conveying and construction in situs
CN2317241Y (en) * 1998-01-22 1999-05-05 常智 Heat pipe type asphalt fast heating device
CN201343268Y (en) * 2009-01-09 2009-11-11 唐山德生防水材料有限公司 Fast heating device of asphalt storage tank
CN202672006U (en) * 2012-07-05 2013-01-16 福建铁拓机械有限公司 Bituminous mixture stirring equipment with heating and heat preservation system
CN103015293A (en) * 2012-12-04 2013-04-03 山东泰德新能源有限公司 Asphalt heating tank
CN205742924U (en) * 2016-05-18 2016-11-30 东方雨虹民用建材有限责任公司 A kind of uncured rubber asphalt spraying application equipment

Also Published As

Publication number Publication date
CN105863218A (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN105863218B (en) Non-curing rubber asphalt spraying construction equipment
US20170165691A1 (en) Paint spraying device
CN202549501U (en) Submarine cable anticorrosion asphalt coating device
BR102015026842B1 (en) machine to spray a section of pipe and process to spray a section of pipe
CN105562276A (en) Automatic spraying equipment
CN110306142B (en) Automatic feeding system for half flexible cable hot tinning procedure and automatic feeding thereof
CN112358166B (en) Automatic control system for regulating and controlling unloading amount of glass kiln
CN205742924U (en) A kind of uncured rubber asphalt spraying application equipment
CN106391395A (en) Cable asphalt coating system
CN206345784U (en) A kind of 3D glass melters glass metal excess flow accurate control device
CN215695140U (en) Controllable mortar spraying equipment of stroke and spraying volume
US8807149B2 (en) System, method and apparatus for recycling quenching medium
CN111829178B (en) Heating and heat-preserving method for asphalt paint bucket
CN209675019U (en) Ice coating removal equipment and deicing vehicle
JP6042141B2 (en) Snow melting equipment
CN110846601B (en) Zinc liquid treatment device
CN208742834U (en) The control device of painting spraying device
CN207188048U (en) Solventless coatings paint finishing with reflux
CN105819046A (en) Ton bag unpacking device
CN204769425U (en) Coating heating device
CN210420111U (en) Automatic feeding system for semi-flexible cable hot tinning process
CN204662209U (en) Pitch slip casting a complete set of equipment
CN207210528U (en) A kind of pipe fitting copper facing equipment
CN209906817U (en) Automatic lead discharging device at bottom of blast furnace
CN201684705U (en) Far infrared heating multi-gun automatic spraying production line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220523

Address after: No. A2, Shaling section, Shunping Road, Yang Town, Shunyi District, Beijing 101309

Patentee after: Zhongke Jiantong Engineering Technology Co.,Ltd.

Address before: 101309 Sha Ling section 2, Shunping Road, Shunyi District, Beijing

Patentee before: BEIJING ORIENTAL YUHONG WATERPROOF ENGINEERING Co.,Ltd.