CN105862931A - Construction method for underground waterproof coil material of large deep foundation pit - Google Patents
Construction method for underground waterproof coil material of large deep foundation pit Download PDFInfo
- Publication number
- CN105862931A CN105862931A CN201610212126.4A CN201610212126A CN105862931A CN 105862931 A CN105862931 A CN 105862931A CN 201610212126 A CN201610212126 A CN 201610212126A CN 105862931 A CN105862931 A CN 105862931A
- Authority
- CN
- China
- Prior art keywords
- construction
- construction method
- foundation pit
- deep foundation
- coiled material
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 36
- 239000000463 material Substances 0.000 title claims abstract description 22
- 239000010410 layer Substances 0.000 claims abstract description 12
- 238000000034 method Methods 0.000 claims abstract description 12
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 9
- 239000010959 steel Substances 0.000 claims abstract description 9
- 239000011241 protective layer Substances 0.000 claims abstract description 7
- 229920001903 high density polyethylene Polymers 0.000 claims description 6
- 239000004700 high-density polyethylene Substances 0.000 claims description 6
- 230000002787 reinforcement Effects 0.000 claims description 6
- 239000012790 adhesive layer Substances 0.000 claims description 3
- 238000004140 cleaning Methods 0.000 claims description 3
- 238000007789 sealing Methods 0.000 claims description 3
- 230000009286 beneficial effect Effects 0.000 abstract 1
- 230000003014 reinforcing effect Effects 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 3
- 230000007547 defect Effects 0.000 description 2
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- VEMKTZHHVJILDY-UHFFFAOYSA-N resmethrin Chemical compound CC1(C)C(C=C(C)C)C1C(=O)OCC1=COC(CC=2C=CC=CC=2)=C1 VEMKTZHHVJILDY-UHFFFAOYSA-N 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
The invention discloses a construction method for an underground waterproof coil material of a large deep foundation pit. The large deep foundation pit comprises a supporting structure, wherein a treatment layer is arranged on the outer side of the supporting structure; the waterproof coil material is arranged on the outer side of the treatment layer; the waterproof coil material is fixed through a steel nail; and a gasket is mounted on the steel nail in a sleeving manner. The construction method achieves the beneficial effects that procedures of binding reinforcing bars, arranging a template, pouring structural concrete, and the like, can be directly carried out without the requirement of laying a protective layer, the operation is easy and convenient, the construction procedures are less, the construction progress is fast, the construction quality is improved, and the construction cost is reduced.
Description
Technical field
The present invention relates to a kind of large deep foundation pit underground waterproof coiled material construction method.
Background technology
In building trade, especially large-and-medium size cities high-rise civil building and commercial building, the most all use support deep pit Large Underground Parking Space form, increased available space as far as possible and reduce cost.But at present, China's overwhelming majority underground engineering all uses traditional material, traditional construction construction technology waterproof layer, and the defect of this way is when waterproof layer is destroyed, and subsoil water can form crossfire between waterproof layer and structure.The ratio that Chinese large-sized deep basal pit has supporting underground waterproof engineering pre-installed and inverted adhered new waterproofing techniques to use at present is the lowest, and it has bigger development and application prospect in China, promotes the development of this technology will to produce huge economic benefit and social benefit energetically.
Summary of the invention
The technical problem to be solved in the present invention is the defect overcoming prior art, it is provided that a kind of large deep foundation pit underground waterproof coiled material construction method, it is not necessary to lay any protective layer and can directly carry out assembling reinforcement; install template; the operations such as pouring structure concrete, it is achieved that less operation, reduce the duration.
In order to solve above-mentioned technical problem, the invention provides following technical scheme:
One large deep foundation pit underground waterproof coiled material construction method of the present invention, including supporting construction, the outside of described supporting construction is provided with process layer, and the outside of described process layer is provided with waterproof roll, described waterproof roll is fixed by steel nail, and described steel nail is set with pad;
Its construction method is: carries out campshed, diaphram wall according to design, inverse makees the construction of arch wall enclosed structure, carries out base cleaning, put waterproof roll location line and fixing point bit line.
Further, paving waterproof roll, when coiled material is used in plane, high density polyethylene (HDPE) is carried out empty paving facing to bed course;When coiled material is used in facade, using mechanical means that waterproof roll is fixed on building enclosure wall supporting surface, adhesive layer is towards structure sheaf.
Further, after fixing end, use Special seal material to carry out adhering and sealing in minor face lap-joint or fixing point, be not required to after having checked and accepted lay protective layer, can directly carry out assembling reinforcement, install template, pouring structure concrete subsequent handling.
The present invention is reached to provide the benefit that: can directly carry out assembling reinforcement without laying any protective layer, install the operations such as template, pouring structure concrete, the most easy and simple to handle, working procedure is few, and construction speed is fast, and improves construction quality, reduces construction cost.
Accompanying drawing explanation
Accompanying drawing is for providing a further understanding of the present invention, and constitutes a part for description, is used for together with embodiments of the present invention explaining the present invention, is not intended that limitation of the present invention.In the accompanying drawings:
Fig. 1 is the structural representation of the present invention;
In figure: 1, steel nail;2, pad;3, layer is processed;4, waterproof roll;5, supporting construction.
Detailed description of the invention
Below in conjunction with accompanying drawing, the preferred embodiments of the present invention are illustrated, it will be appreciated that preferred embodiment described herein is merely to illustrate and explains the present invention, is not intended to limit the present invention.
Embodiment 1
As it is shown in figure 1, a kind of large deep foundation pit underground waterproof coiled material construction method, including supporting construction 5, the outside of described supporting construction 5 is provided with process layer 3, the outside of described process layer 3 is provided with waterproof roll 4, and described waterproof roll 4 is fixed by steel nail 1, described steel nail 1 is set with pad 2;
Its construction method is: carries out campshed, diaphram wall according to design, inverse makees the construction of arch wall enclosed structure, carries out base cleaning, put waterproof roll location line and fixing point bit line.
Paving waterproof roll, when coiled material is used in plane, carries out empty paving by high density polyethylene (HDPE) facing to bed course;When coiled material is used in facade, using mechanical means that waterproof roll is fixed on building enclosure wall supporting surface, adhesive layer is towards structure sheaf.
After fixing end, use Special seal material to carry out adhering and sealing in minor face lap-joint or fixing point, be not required to after having checked and accepted lay protective layer, can directly carry out assembling reinforcement, install template, pouring structure concrete subsequent handling.
Can directly carry out assembling reinforcement without laying any protective layer, install the operations such as template, pouring structure concrete, the most easy and simple to handle, working procedure is few, and construction speed is fast, and improves construction quality, reduces construction cost.
Last it is noted that the foregoing is only the preferred embodiments of the present invention, it is not limited to the present invention, although the present invention being described in detail with reference to previous embodiment, for a person skilled in the art, technical scheme described in foregoing embodiments still can be modified by it, or wherein portion of techniques feature is carried out equivalent.All within the spirit and principles in the present invention, any modification, equivalent substitution and improvement etc. made, should be included within the scope of the present invention.
Claims (3)
1. a large deep foundation pit underground waterproof coiled material construction method, it is characterized in that, including supporting construction (5), the outside of described supporting construction (5) is provided with process layer (3), the outside of described process layer (3) is provided with waterproof roll (4), described waterproof roll (4) is fixed by steel nail (1), and described steel nail (1) is set with pad (2);
Its construction method is: carries out campshed, diaphram wall according to design, inverse makees the construction of arch wall enclosed structure, carries out base cleaning, put waterproof roll location line and fixing point bit line.
A kind of large deep foundation pit underground waterproof coiled material construction method the most according to claim 1, it is characterised in that paving waterproof roll, when coiled material is used in plane, carries out empty paving by high density polyethylene (HDPE) facing to bed course;When coiled material is used in facade, using mechanical means that waterproof roll is fixed on building enclosure wall supporting surface, adhesive layer is towards structure sheaf.
A kind of large deep foundation pit underground waterproof coiled material construction method the most according to claim 2; it is characterized in that; after fixing end; Special seal material is used to carry out adhering and sealing in minor face lap-joint or fixing point; examination is not required to after completing lay protective layer; assembling reinforcement be can directly carry out, template, pouring structure concrete subsequent handling installed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610212126.4A CN105862931A (en) | 2016-04-07 | 2016-04-07 | Construction method for underground waterproof coil material of large deep foundation pit |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610212126.4A CN105862931A (en) | 2016-04-07 | 2016-04-07 | Construction method for underground waterproof coil material of large deep foundation pit |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105862931A true CN105862931A (en) | 2016-08-17 |
Family
ID=56636145
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610212126.4A Pending CN105862931A (en) | 2016-04-07 | 2016-04-07 | Construction method for underground waterproof coil material of large deep foundation pit |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105862931A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106284430A (en) * | 2016-08-26 | 2017-01-04 | 中国十七冶集团有限公司 | A kind of structural concrete for large deep foundation pit with waterproofing protection |
CN109322325A (en) * | 2018-09-06 | 2019-02-12 | 海南大学 | A freezing oil storage device through a freezing tube and its construction method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20090006361A (en) * | 2007-07-11 | 2009-01-15 | (주)리뉴시스템 | Waterproof construction method of concrete station pouring section |
CN201826858U (en) * | 2010-10-09 | 2011-05-11 | 卢桂才 | Reaction bonding type sealing waterproof roll material for tunnel pre-paving |
CN203145055U (en) * | 2013-01-06 | 2013-08-21 | 广州禹神建筑防水材料有限公司 | Underground construction pre-laid reversely-adhered waterproof structure |
CN104695488A (en) * | 2015-03-17 | 2015-06-10 | 深圳大学建筑设计研究院 | Underground composite wall external water-proofing structure |
CN204982977U (en) * | 2015-09-24 | 2016-01-20 | 中建四局第一建筑工程有限公司 | Basement bottom plate and waterproofing membrane integration waterproof construction |
-
2016
- 2016-04-07 CN CN201610212126.4A patent/CN105862931A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20090006361A (en) * | 2007-07-11 | 2009-01-15 | (주)리뉴시스템 | Waterproof construction method of concrete station pouring section |
CN201826858U (en) * | 2010-10-09 | 2011-05-11 | 卢桂才 | Reaction bonding type sealing waterproof roll material for tunnel pre-paving |
CN203145055U (en) * | 2013-01-06 | 2013-08-21 | 广州禹神建筑防水材料有限公司 | Underground construction pre-laid reversely-adhered waterproof structure |
CN104695488A (en) * | 2015-03-17 | 2015-06-10 | 深圳大学建筑设计研究院 | Underground composite wall external water-proofing structure |
CN204982977U (en) * | 2015-09-24 | 2016-01-20 | 中建四局第一建筑工程有限公司 | Basement bottom plate and waterproofing membrane integration waterproof construction |
Non-Patent Citations (1)
Title |
---|
叶军 等: "天津站交通枢纽后广场工程地下结构防水技术", 《中国建筑防水》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106284430A (en) * | 2016-08-26 | 2017-01-04 | 中国十七冶集团有限公司 | A kind of structural concrete for large deep foundation pit with waterproofing protection |
CN109322325A (en) * | 2018-09-06 | 2019-02-12 | 海南大学 | A freezing oil storage device through a freezing tube and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5529892B2 (en) | Device for starting and reaching a shield machine in a sealed state | |
CN204326566U (en) | A kind of structure utilizing carbon fiber reinforcement reinforced concrete post | |
CN104088298A (en) | Municipal road prefabricated concrete inspection well and construction method thereof | |
CN107268688B (en) | Construction method for reinforcing and sealing I-shaped steel joint of underground continuous wall | |
CN202300445U (en) | Super-shallow underpass tunnel support structure with long pipe shed for crossing road | |
CN105862931A (en) | Construction method for underground waterproof coil material of large deep foundation pit | |
CN110552378A (en) | Underground space roof subsides post-cast strip and seals structure in advance | |
CN203188225U (en) | Novel dewatering-well sealing structure | |
CN105951985A (en) | Precast concrete frame beam joint | |
CN206801581U (en) | A kind of tunnel lining structure defect reinforcing device | |
CN202431281U (en) | Waterproof structure outside side wall of subway station main body | |
CN204139413U (en) | A kind of cast-in-place hollow slab of zonal cooling formula anti-floating | |
CN102720275B (en) | Flexible coiled material for deformation joint and construction method of flexible coiled material | |
CN206299392U (en) | A kind of high osmosis water-rich sand layer shield end reinforcement system | |
CN108385686A (en) | A kind of cast-in-situ bored pile exempts from stripping and exempts from ring cutting to cut pile crown technique | |
CN210086033U (en) | Quick-positioning high-waterproof ultrahigh-performance concrete combined permanent formwork | |
CN103334771A (en) | Concrete pouring method of side wall and joint of middle plate and vault by means of underground excavation reverse construction method | |
CN104343204B (en) | Sectional continuous floating-resistant cast-in-situ hollow slab | |
CN206607675U (en) | A kind of basement composite external wall anti-cracking and seepage control structure construction | |
CN102518458B (en) | Construction method of top beam part of underground bus stop | |
CN206090823U (en) | Precast concrete frame girder segment point | |
CN205776327U (en) | A kind of slip casting bag buried pipeline basis of band pipe pillow | |
CN204126094U (en) | A kind of cast-in-place hollow slab of segmentation dislocation type anti-floating | |
CN202170705U (en) | Window frame fixing seat | |
CN205444910U (en) | Can have enough to meet need structure firmware with PVC plastic tubing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160817 |