CN105855671A - Butting process of large-diameter rolled steel pipe for building structure - Google Patents

Butting process of large-diameter rolled steel pipe for building structure Download PDF

Info

Publication number
CN105855671A
CN105855671A CN201610410787.8A CN201610410787A CN105855671A CN 105855671 A CN105855671 A CN 105855671A CN 201610410787 A CN201610410787 A CN 201610410787A CN 105855671 A CN105855671 A CN 105855671A
Authority
CN
China
Prior art keywords
welding
steel pipe
weld
voltage
butting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610410787.8A
Other languages
Chinese (zh)
Inventor
吴宏根
彭静
郑家胜
张保宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Ziking Pipe Inc
Original Assignee
Henan Ziking Pipe Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Ziking Pipe Inc filed Critical Henan Ziking Pipe Inc
Priority to CN201610410787.8A priority Critical patent/CN105855671A/en
Publication of CN105855671A publication Critical patent/CN105855671A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • B23K9/18Submerged-arc welding
    • B23K9/186Submerged-arc welding making use of a consumable electrodes
    • B23K9/188Submerged-arc welding making use of a consumable electrodes making use of several electrodes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • B23K9/16Arc welding or cutting making use of shielding gas
    • B23K9/173Arc welding or cutting making use of shielding gas and of a consumable electrode
    • B23K9/1735Arc welding or cutting making use of shielding gas and of a consumable electrode making use of several electrodes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • B23K9/235Preliminary treatment

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Plasma & Fusion (AREA)
  • Mechanical Engineering (AREA)
  • Butt Welding And Welding Of Specific Article (AREA)
  • Arc Welding In General (AREA)

Abstract

The invention discloses a butting process of a large-diameter rolled steel pipe for a building structure, comprising the following steps: (1), fattening pipe ends; (2), chamfering the pipe ends: chamfering to obtain dull edges 7-9 mm in size through a chamfering apparatus and a groove angle 22-25 degrees, and butting pipe segments to form a Y-shaped groove; (3), butting steel pipes; (4), pre-welding: applying mixed gas shielded welding and gas shielded welding wires, a gas being 80% of Ar and 20% of CO2, current being 140-160 A, voltage being 25-27 V and welding speed being 0.5-0.6 m/min; (5) welding inside and outside: carrying submerged arc welding for inside prior to outside, both using four-wire submerged arc auto-welding, and wires being 3.5-4.0 mm in diameter, welding speed being 1.0-1.2 m/min; (6), grinding for redundant height of a weld; (7), carrying circumferential weld UT detection; (8), carrying X-ray detection. The butting process of the rolled steel pipe enables greatly improved butting quality and efficiency of the steel pipe and reduced cost and can guarantee good appearance quality.

Description

A kind of building structure heavy caliber rolls the butt-joint process of steel pipe
Technical field
The present invention relates to a kind of building structure heavy caliber and roll the butt-joint process of steel pipe, belong to steel pipe manufacture processing Technical field.
Background technology
Rolling steel pipe is to be welded in the gap that steel plate carries out the docking of helical buckling tailing edge steel plate by certain curvature Making together, the advantage rolling steel pipe is low cost, and production efficiency is fast, it is wide in variety to produce.Building structure is used Steel pipe usually needs various length, rolls steel pipe at present and limits or other reasons due to production equipment, will necessarily Producing pup joint, and welding mostly is monofilament submerged-arc welding at present, the steel pipe for overlength need to dock after producing, but mesh Front butt-joint process is inefficient, and joint quality is low, and cost is very big, and after steel pipe docking, the weldering of formation Seam is higher than tube surfaces, and outward appearance physical dimension, flatness are low, cause presentation quality low.
Summary of the invention
It is an object of the invention to overcome the deficiencies in the prior art, it is provided that a kind of building structure heavy caliber rolls steel pipe Butt-joint process, substantially increase joint quality and the efficiency of steel pipe, reduce cost, and can guarantee that good Presentation quality.
To achieve these goals, the present invention adopts the following technical scheme that
A kind of building structure heavy caliber rolls the butt-joint process of steel pipe, comprises the following steps:
(1) pipe end leveling: treat docking steel pipe and carry out end full circle;
(2) pipe end chamfered edge: pour out root face a size of 7-9mm by chamfering device, bevel angle is 22-25 Degree, forms Y type groove after pipeline section docking;
(3) steel pipe docking;
(4) prewelding: using mixed gas arc welding and gas shield welding wire, gas is 80%Ar+20%CO2, its electricity Stream is 140-160A, and voltage is 25-27V, and speed of welding is 0.5-0.6m/min;
(5) interior outside weld: submerged arc welding outer after in carrying out first, interior outside weld all uses four Lincoln welds to enter Row welding, gage of wire is 3.5-4.0mm, and speed of welding is 1.0-1.2m/min;
(6) weld reinforcement grinding: use weld reinforcement milling drum butt welded seam reinforcement to carry out grinding leveling.
(7) circumferential weld UT flaw detection;
(8) x-ray inspection.
Described inside and outside welder's sequence all uses four Lincoln welds to weld, and first is DC reverse connection, electricity Stream is 1050-1150A, and voltage is 30-33V;Second is exchange, and electric current is 850-950A, and voltage is 32-34V;3rd is exchange, and electric current is 650-750A, and voltage is 38-40V;4th is exchange, electricity Stream is 550-650A, and voltage is 40-42V.
Compared with the prior art, beneficial effects of the present invention is as follows:
The building structure heavy caliber of the present invention rolls the butt-joint process of steel pipe, substantially increases the docking matter of steel pipe Amount and efficiency, reduce cost, and can guarantee that good presentation quality;Pipe end slope-mouth in the present invention ensures weldering In termination process can through welding, and improve speed of welding, improve seam center, reduce sealing wire ability, reduce weldering Connect heat input to welding heat affected zone tissue and the impact of performance, the performance of raising weld heat-affected zone;After docking Prewelding effectively reduces heat input and ensures the straight degree of docking steel pipe to reduce welding deformation amount;Interior outside weld all uses four Silk Lincoln weld is welded, it is ensured that good presentation quality, it is ensured that weld seam stabilizing welding quality and work effect Rate, substantially increases the docking efficiency of steel pipe;Carry out welding reinforcement grinding equating at inside and outside postwelding to process, it is possible to Ensureing that the commissure of steel pipe is smooth, presentation quality is good.
Detailed description of the invention
Below in conjunction with embodiment, the present invention is further illustrated, but the present invention is not limited only to these embodiments, On the premise of without departing from present inventive concept, within any improvement made all falls within protection scope of the present invention.
Embodiment 1:
A kind of building structure heavy caliber rolls the butt-joint process of steel pipe, comprises the following steps:
(1) pipe end leveling: treat docking steel pipe and carry out end full circle;
(2) pipe end chamfered edge: pour out root face a size of 7-9mm by chamfering device, bevel angle is 22-25 Degree, forms Y type groove after pipeline section docking;
(3) steel pipe docking;
(4) prewelding: using mixed gas arc welding and gas shield welding wire, gas is 80%Ar+20%CO2, its electricity Stream is 140-160A, and voltage is 25-27V, and speed of welding is 0.5-0.6m/min;
(5) interior outside weld: submerged arc welding outer after in carrying out first, interior outside weld all uses four Lincoln welds to enter Row welding, gage of wire is 3.5-4.0mm, and speed of welding is 1.0-1.2m/min;Described inside and outside welder's sequence All using four Lincoln welds to weld, first is DC reverse connection, and electric current is 1050-1150A, electricity Pressure is 30-33V;Second is exchange, and electric current is 850-950A, and voltage is 32-34V;3rd is exchange, Electric current is 650-750A, and voltage is 38-40V;4th is exchange, and electric current is 550-650A, and voltage is 40-42V。
(6) weld reinforcement grinding: use weld reinforcement milling drum butt welded seam reinforcement to carry out grinding leveling.
(7) circumferential weld UT flaw detection;
(8) x-ray inspection.
The building structure heavy caliber of the present invention rolls the butt-joint process of steel pipe, substantially increases the docking matter of steel pipe Amount and efficiency, reduce cost, and can guarantee that good presentation quality;Pipe end slope-mouth in the present invention ensures weldering In termination process can through welding, and improve speed of welding, improve seam center, reduce sealing wire ability, reduce weldering Connect heat input to welding heat affected zone tissue and the impact of performance, the performance of raising weld heat-affected zone;After docking Prewelding effectively reduces heat input and ensures the straight degree of docking steel pipe to reduce welding deformation amount;Interior outside weld all uses four Silk Lincoln weld is welded, it is ensured that good presentation quality, it is ensured that weld seam stabilizing welding quality and work effect Rate, substantially increases the docking efficiency of steel pipe;Carry out welding reinforcement grinding equating at inside and outside postwelding to process, it is possible to Ensureing that the commissure of steel pipe is smooth, presentation quality is good.

Claims (2)

1. a building structure heavy caliber rolls the butt-joint process of steel pipe, it is characterised in that: include following step Rapid:
(1) pipe end leveling: treat docking steel pipe and carry out end full circle;
(2) pipe end chamfered edge: pour out root face a size of 7-9mm by chamfering device, bevel angle is 22-25 Degree, forms Y type groove after pipeline section docking;
(3) steel pipe docking;
(4) prewelding: using mixed gas arc welding and gas shield welding wire, gas is 80%Ar+20%CO2, its electricity Stream is 140-160A, and voltage is 25-27V, and speed of welding is 0.5-0.6m/min;
(5) interior outside weld: submerged arc welding outer after in carrying out first, interior outside weld all uses four Lincoln welds to enter Row welding, gage of wire is 3.5-4.0mm, and speed of welding is 1.0-1.2m/min;
(6) weld reinforcement grinding: use weld reinforcement milling drum butt welded seam reinforcement to carry out grinding leveling;
(7) circumferential weld UT flaw detection;
(8) x-ray inspection.
Building structure heavy caliber the most according to claim 1 rolls the butt-joint process of steel pipe, its feature Being: described inside and outside welder's sequence all uses four Lincoln welds to weld, first is DC reverse connection, Electric current is 1050-1150A, and voltage is 30-33V;Second is exchange, and electric current is 850-950A, and voltage is 32-34V;3rd is exchange, and electric current is 650-750A, and voltage is 38-40V;4th is exchange, electricity Stream is 550-650A, and voltage is 40-42V.
CN201610410787.8A 2016-06-03 2016-06-03 Butting process of large-diameter rolled steel pipe for building structure Pending CN105855671A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610410787.8A CN105855671A (en) 2016-06-03 2016-06-03 Butting process of large-diameter rolled steel pipe for building structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610410787.8A CN105855671A (en) 2016-06-03 2016-06-03 Butting process of large-diameter rolled steel pipe for building structure

Publications (1)

Publication Number Publication Date
CN105855671A true CN105855671A (en) 2016-08-17

Family

ID=56650053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610410787.8A Pending CN105855671A (en) 2016-06-03 2016-06-03 Butting process of large-diameter rolled steel pipe for building structure

Country Status (1)

Country Link
CN (1) CN105855671A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110722279A (en) * 2019-09-11 2020-01-24 珠海东方重工有限公司 Steel pipe butt welding process
CN111570977A (en) * 2020-05-26 2020-08-25 中国水利水电第九工程局有限公司 Butt welding connection method for building supporting circular tube steel column
CN113385787A (en) * 2021-05-06 2021-09-14 江苏鼎嘉机械设备科技有限公司 Submerged-arc welding process for small-diameter tank body

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103008999A (en) * 2012-12-17 2013-04-03 华油钢管有限公司 Spiral seam submerged-arc welded pipe butt joint process
CN103433604A (en) * 2013-08-20 2013-12-11 首钢总公司 Multiple-wire submerged-arc welding technology for guaranteeing subsea pipeline steel pipe connector comprehensive performance
CN104475941A (en) * 2014-12-03 2015-04-01 宝鸡石油钢管有限责任公司 Multiple-wire submerged arc welding process suitable for thick-wall straight-seam steel pipes X70
CN104511720A (en) * 2013-09-27 2015-04-15 中国石油天然气集团公司 Reducing production method of deepwater submerged arc welding large-caliber steel pipes

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103008999A (en) * 2012-12-17 2013-04-03 华油钢管有限公司 Spiral seam submerged-arc welded pipe butt joint process
CN103433604A (en) * 2013-08-20 2013-12-11 首钢总公司 Multiple-wire submerged-arc welding technology for guaranteeing subsea pipeline steel pipe connector comprehensive performance
CN104511720A (en) * 2013-09-27 2015-04-15 中国石油天然气集团公司 Reducing production method of deepwater submerged arc welding large-caliber steel pipes
CN104475941A (en) * 2014-12-03 2015-04-01 宝鸡石油钢管有限责任公司 Multiple-wire submerged arc welding process suitable for thick-wall straight-seam steel pipes X70

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110722279A (en) * 2019-09-11 2020-01-24 珠海东方重工有限公司 Steel pipe butt welding process
CN111570977A (en) * 2020-05-26 2020-08-25 中国水利水电第九工程局有限公司 Butt welding connection method for building supporting circular tube steel column
CN113385787A (en) * 2021-05-06 2021-09-14 江苏鼎嘉机械设备科技有限公司 Submerged-arc welding process for small-diameter tank body

Similar Documents

Publication Publication Date Title
CN102653022B (en) Method for welding narrow-gap butt-joint connector of pipeline with large pipe diameter and thick wall
CN101797600B (en) Method for manufacturing high-strength X100 steel grade spiral seam submerged arc welded pipe
CN102330034B (en) X65MS steel-grade spiral welded tube for acidic corrosion environment and manufacturing method thereof
CN101886222B (en) Method for manufacturing high-strength X90 steel grade spiral submerged arc welded pipe
CN103008999B (en) Spiral seam submerged-arc welded pipe butt joint process
CN102172814B (en) Method for manufacturing longitudinal submerged arc welded pipe
CN102383049B (en) Method for manufacturing low-cost high-toughness X70 steel spiral submerged arc welded pipe
CN105345235A (en) Cylindrical no-root full-penetration union melt welding method
WO2017215525A1 (en) Double-sided welding and double-sided shaping method for large-diameter aluminum alloy tube-making helical friction stir welding (fsw) equipment
CN108526662B (en) Back-surface-free argon-filling welding method for X groove of large-diameter nickel-based composite pipe
CN105855671A (en) Butting process of large-diameter rolled steel pipe for building structure
CN103495795A (en) Gas protection bottoming automatic welding process of carbon steel pipeline consumable electrode
CN105195872A (en) Double-sided submerged arc back-chipping-free welding technology for pipeline steel
CN108723557A (en) A kind of welding method of cylinder
WO2021114686A1 (en) Circular seam welding method for low-alloy steel low temperature pressure vessel tank body
CN108500559B (en) Manufacturing method of extra-large-pipe-diameter thick-wall X80 steel-grade spiral submerged arc welded pipe
CN105728911A (en) Process for welding steel pipes of pipelines
CN104384678A (en) Novel welding technology of SSAW (Spirally Submerged Arc Welding) pipe
KR20130120735A (en) Flux cored wire and manufacturing method thereof and manufacturing device thereof
CN102330032A (en) Acid-proof X70MS steel-grade spiral welded pipe and manufacturing method thereof
CN202701575U (en) Double-faced dual-arc welding device of pipe root layer
CN108620448B (en) Method for manufacturing large-diameter and high-strength spiral welded pipe
CN106624614B (en) A kind of manufacturing process of the high-strength welded tube of heavy caliber thick wall
CN104439672A (en) High frequency prewelding technology of longitudinal submerged arc welded pipe
CN109807438A (en) A method of for water heater porcelain enamel steel liner girth welding

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160817

RJ01 Rejection of invention patent application after publication