CN105838835A - Blast furnace blowing-in iron notch device and blast furnace blowing-in iron notch method - Google Patents

Blast furnace blowing-in iron notch device and blast furnace blowing-in iron notch method Download PDF

Info

Publication number
CN105838835A
CN105838835A CN201610455652.3A CN201610455652A CN105838835A CN 105838835 A CN105838835 A CN 105838835A CN 201610455652 A CN201610455652 A CN 201610455652A CN 105838835 A CN105838835 A CN 105838835A
Authority
CN
China
Prior art keywords
blast furnace
steel pipe
ferrum
iron notch
ferrum mouth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610455652.3A
Other languages
Chinese (zh)
Inventor
王玉莲
杜敏庆
卢保军
薛燕
孔凡朔
齐婳
陈霞
张熙玮
邓勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Iron and Steel Group Co Ltd SISG
Original Assignee
Shandong Iron and Steel Group Co Ltd SISG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Iron and Steel Group Co Ltd SISG filed Critical Shandong Iron and Steel Group Co Ltd SISG
Priority to CN201610455652.3A priority Critical patent/CN105838835A/en
Publication of CN105838835A publication Critical patent/CN105838835A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • C21B7/12Opening or sealing the tap holes

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Vertical, Hearth, Or Arc Furnaces (AREA)

Abstract

The invention relates to a blast furnace blowing-in iron notch device and a blast furnace blowing-in iron notch method and belongs to the technical field of steel production. The blast furnace blowing-in iron notch device comprises a furnace wall iron notch combined brick, an iron notch channel and a mud drum covering the iron notch channel, wherein at least one steel pipe is embedded in the mud drum and the iron notch channel; one end of the steel pipe is positioned in a blast furnace, and the other end of the steel pipe sequentially passes through the mud drum and the iron notch channel and is positioned outside the blast furnace; the part, which is positioned outside the blast furnace, of the steel pipe is provided with a three-way valve; the three-way valve is respectively connected with a compressed air tank and a high-pressure oxygen tank by virtue of pipelines; the three-way valve is electrically connected with an electric control device; the electric control device is electrically connected with the blast furnace. The blast furnace blowing-in iron notch device has the advantages of ensuring smooth first furnace iron notch during blowing of the blast furnace, saving manpower and material resources and avoiding environmental pollution.

Description

A kind of blast furnace opening ferrum mouth device and method
Technical field
The present invention relates to a kind of blast furnace opening ferrum mouth device and method, belong to technical field of steel production, be particularly suited for during blast furnace opening opening the ferrum mouth of the first stove ferrum.
Background technology
Blast furnace ironmaking is the main method of modern ironmaking, is the important step during iron and steel produces.During blast fumance, from furnace roof loading iron ore, coke, slag making with flux (limestone), it is blown into preheated air from being positioned at the lower furnace air port along stove week.The carbon monoxide that at high temperature carbon in coke generates with the oxygen burning blasted in air, removes the oxygen in iron ore in stove, thus reduction obtains ferrum in uphill process.The molten iron produced, from flux combination generation slags such as the releasing of ferrum mouth, the impurity not reduced in iron ore and limestone, is discharged from cinder notch, and the coal gas of generation is derived from furnace roof, after removing dust, as the fuel of air stove, heating furnace, coke oven, boiler etc..
In iron and steel enterprise the big-and-middle maintenance of blast furnace terminate after, carry out blowing-in operation operation time, bed rearrangement blast furnace is in room temperature state, ferrum mouth passage iron port gun mud is blocked, light a fire to from blow-on and form the slag ferrum of liquid, time interval is up to ten several hours, when opening the first stove ferrum after accumulating a certain amount of slag ferrum in cupola well, the stemming in ferrum mouth passage is the most sintered hardening, and the tapping machine of stokehold is beaten motionless.Existing solution way is typically, and flushing and casting work oxygen burns tapping outlet discharge slag ferrum, but there is problems in that one, operating time length, workload big;Two, there will be substantial amounts of tobacco and airborne dust during burning ferrum mouth, pollute environment;Three, can not quickly beat tapping outlet in the short time, can cause and suppress wind, cause hanging, time serious, even can burn out air port.
Summary of the invention
For solving above technical deficiency, the invention provides a kind of blast furnace opening ferrum mouth device and method, can make during blast furnace opening, to open the first stove ferrum mouth smooth, use manpower and material resources sparingly, it is to avoid pollute environment.
Technical scheme is as follows: a kind of blast furnace opening ferrum mouth device, including furnace wall ferrum mouth modular tile, ferrum mouth passage and the mud drum covering ferrum mouth passage, it is embedded with at least steel pipe in described mud drum and ferrum mouth passage, one end of described steel pipe is positioned at blast furnace, the other end of steel pipe passes sequentially through mud drum and ferrum mouth passage is positioned at outside blast furnace, the position being positioned at outside blast furnace on described steel pipe is provided with three-way valve, described three-way valve is connected to compressed air cylinder and hyperbaric oxygen gas tank by pipeline, three-way valve is electrically connected with electric control gear, and described electric control gear electrically connects with blast furnace.
Technical scheme also includes: described blast furnace is provided with piezometer and thermometer, and described piezometer and thermometer electrically connect with electric control gear.
Technical scheme also includes: the quantity of described steel pipe is two, and two steel pipes are arranged side by side.
Technical scheme also includes: the quantity of described steel pipe is three, and three steel pipes are triangularly arranged.
Technical scheme also includes: described steel pipe is positioned at the end of blast furnace part and is provided with blind plate, and steel pipe is positioned at blast furnace position and is provided with one group of perforate.
Technical scheme also includes: described perforate is positioned at the bottom of steel pipe, and the diameter of perforate is 10mm, and the spacing between adjacent apertures is 100~200mm.
Technical scheme also includes: described steel pipe is positioned at blast furnace end partly and is positioned at 1/3 position of blast furnace diameter.
A kind of blast furnace opening ferrum mouth method, mainly comprises the steps that
Step one, at the pre-buried at least steel pipe of ferrum mouth passage and mud drum, steel pipe mud drum to be stretched out certain length, reaches 1/3 position of blast furnace diameter;
Step 2, steel pipe is positioned at inside blast furnace to set up separately puts perforate, and perforate is positioned at steel pipe at lower half circumferential position, and perforate is the circular hole of diameter 10mm, and adjacent apertures blocks along steel pipe length direction spacing 100~200mm, steel pipe front end blind plate;
Step 3, steel pipe is positioned at blast furnace outer portion connecting tee valve, and three-way valve connects compressed air cylinder and hyperbaric oxygen gas tank respectively by pipeline, and oxygen pressure is 1.0MPa;
Step 4, compressed air it is passed through after blast furnace opening, compressed-air actuated pressure is equal to cold blast pressure+100~300KPa, decline and the carrying out of reduction reaction with furnace charge, generate liquid slag ferrum and enter cupola well, now, electric control gear action control is opened the hyperbaric oxygen air valve of hyperbaric oxygen gas tank, is closed the compressed air valve of compressed air cylinder;
Step 5, with the raising of accumulation slag ferrum temperature in blast furnace, in ferrum mouth passage, steel pipe all melts, and now, electric control gear action control closes three-way valve, stops sending oxygen;
Step 6, steel pipe forms slag Tie Tong road after all melting, and melted slag ferrum emits from slag Tie Tong road, and the first stove outspoken speed of ferrum ferrum is opened.
The invention has the beneficial effects as follows: by steel pipe reserved in ferrum mouth passage and mud drum, and use electric control gear to carry out auto-action control, compressed air is passed first into after blast furnace opening, decline and the carrying out of reduction reaction with furnace charge, generate liquid slag ferrum and enter cupola well, now open hyperbaric oxygen air valve, close compressed air valve, heat is released by oxygen combustion, the temperature of slag ferrum is accumulated in improving cupola well, improve slag ferrum mobility, in cylinder, steel pipe in ferrum mouth passage is all melted by slag ferrum accumulation to a certain extent, steel pipe fusing thus a Ge Zha Tie Tong road is formed by the liquid slag ferrum generated, avoid stemming in slag Tie Tong road to sinter the hardening ferrum mouth difficulty caused for a long time to open, ensure that blast furnace opening is smoothed out, save manpower and materials.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of the present invention.
In figure: 1, furnace wall ferrum mouth modular tile, 2, mud drum, 3, ferrum mouth passage, 4, steel pipe, 41, perforate, 42, blind plate, 5, three-way valve, 6, electric control gear, 7, compressed air cylinder, 8, hyperbaric oxygen gas tank.
Detailed description of the invention
Below in conjunction with accompanying drawing, by embodiment, the invention will be further described.
As it is shown in figure 1, a kind of blast furnace opening ferrum mouth device of the present invention, including furnace wall ferrum mouth modular tile 1, ferrum mouth passage 3 and the mud drum 2 covering ferrum mouth passage 3, in mud drum 2 and ferrum mouth passage 3, it is embedded with at least steel pipe 4.One end of steel pipe 4 is positioned at blast furnace, the other end of steel pipe 4 passes sequentially through mud drum 2 and ferrum mouth passage 3 is positioned at outside blast furnace, the position being positioned at outside blast furnace on steel pipe 4 is provided with three-way valve 5, three-way valve 5 is connected to compressed air cylinder 7 and hyperbaric oxygen gas tank 8 by pipeline, and three-way valve 5 and blast furnace electrically connect with electric control gear.
By steel pipe reserved in ferrum mouth passage and mud drum, and use electric control gear to carry out auto-action control, compressed air is passed first into after blast furnace opening, decline and the carrying out of reduction reaction with furnace charge, generate liquid slag ferrum and enter cupola well, now open hyperbaric oxygen air valve, close compressed air valve, heat is released by oxygen combustion, the temperature of slag ferrum is accumulated in improving cupola well, improve slag ferrum mobility, in cylinder, steel pipe in ferrum mouth passage is all melted by slag ferrum accumulation to a certain extent, steel pipe fusing thus a Ge Zha Tie Tong road is formed by the liquid slag ferrum generated, avoid stemming in slag Tie Tong road to sinter the hardening ferrum mouth difficulty caused for a long time to open, ensure that blast furnace opening is smoothed out, save manpower and materials.
In embodiments of the invention, blast furnace is provided with piezometer and thermometer, and this piezometer and thermometer electrically connect with electric control gear 6, to improve control accuracy.Steel pipe 4 is positioned at the end of blast furnace part and is provided with blind plate 42, and steel pipe 4 is positioned at blast furnace position and is provided with one group of perforate 41, and specifically, perforate 41 is positioned at the bottom of steel pipe 4, and the diameter of perforate 41 is 10mm, and the spacing between adjacent apertures 41 is 100~200mm.Steel pipe 4 is positioned at blast furnace end partly and is positioned at 1/3 position of blast furnace diameter.So design is advantageous in that, it is possible to increase the formation speed in slag Tie Tong road and quality, and then is easily opened ferrum mouth.
In embodiments of the invention one, the quantity of embedded steel tube 4 is two, and two steel pipes 4 are arranged side by side, it is possible to increase the reliability that device uses, it is to avoid the problem that can not open ferrum mouth that the error of one of them steel pipe occurs.
In embodiments of the invention two, the quantity of embedded steel tube 4 is three, and three steel pipes 4 are triangularly arranged, so design is advantageous in that, it is possible to form the size in slag Tie Tong road, and setting triangular in shape after adding big steel pipe fusing, the velocity of liquid assets of slag ferrum can be improved, and then improve ferrum mouth opening speed.
A kind of blast furnace opening ferrum mouth method of the present invention, mainly comprises the steps that
Step one, at the pre-buried at least steel pipe of ferrum mouth passage and mud drum, steel pipe mud drum to be stretched out certain length, reaches 1/3 position of blast furnace diameter;
Step 2, steel pipe is positioned at inside blast furnace to set up separately puts perforate, and perforate is positioned at steel pipe at lower half circumferential position, and perforate is the circular hole of diameter 10mm, and adjacent apertures blocks along steel pipe length direction spacing 100~200mm, steel pipe front end blind plate;
Step 3, steel pipe is positioned at blast furnace outer portion connecting tee valve, and three-way valve connects compressed air cylinder and hyperbaric oxygen gas tank respectively by pipeline, and oxygen pressure is 1.0MPa;
Step 4, compressed air it is passed through after blast furnace opening, compressed-air actuated pressure is equal to cold blast pressure+100~300KPa, decline and the carrying out of reduction reaction with furnace charge, generate liquid slag ferrum and enter cupola well, now, electric control gear action control is opened the hyperbaric oxygen air valve of hyperbaric oxygen gas tank, is closed the compressed air valve of compressed air cylinder;
Step 5, with the raising of accumulation slag ferrum temperature in blast furnace, in ferrum mouth passage, steel pipe all melts, and now, electric control gear action control closes three-way valve, stops sending oxygen;
Step 6, steel pipe forms slag Tie Tong road after all melting, and melted slag ferrum emits from slag Tie Tong road, and the first stove outspoken speed of ferrum ferrum is opened.
The above, be only presently preferred embodiments of the present invention, the present invention not does any pro forma restriction, done all any amendment, equivalent and improvement etc., should be included within the scope of the present invention.

Claims (8)

1. a blast furnace opening ferrum mouth device, including furnace wall ferrum mouth modular tile (1), ferrum mouth passage (3) and the mud drum (2) of covering ferrum mouth passage (3), it is characterized in that: in described mud drum (2) and ferrum mouth passage (3), be embedded with at least steel pipe (4), one end of described steel pipe (4) is positioned at blast furnace, the other end of steel pipe (4) passes sequentially through mud drum (2) and ferrum mouth passage (3) is positioned at outside blast furnace, the position being positioned at outside blast furnace on described steel pipe (4) is provided with three-way valve (5), described three-way valve (5) is connected to compressed air cylinder (7) and hyperbaric oxygen gas tank (8) by pipeline, three-way valve (5) is electrically connected with electric control gear (6), described electric control gear (6) electrically connects with blast furnace.
2. a kind of blast furnace opening ferrum mouth device as claimed in claim 1, it is characterised in that: described blast furnace is provided with piezometer and thermometer, described piezometer and thermometer and electrically connects with electric control gear (6).
3. a kind of blast furnace opening ferrum mouth device as claimed in claim 1, it is characterised in that: the quantity of described steel pipe (4) is two, and two steel pipes (4) are arranged side by side.
4. a kind of blast furnace opening ferrum mouth device as claimed in claim 1, it is characterised in that: the quantity of described steel pipe (4) is three, and three steel pipes (4) are triangularly arranged.
5. a kind of blast furnace opening ferrum mouth device as described in Claims 1-4 is arbitrary, it is characterised in that: described steel pipe (4) is positioned at the end of blast furnace part and is provided with blind plate (42), and steel pipe (4) is positioned at blast furnace position and is provided with one group of perforate (41).
6. a kind of blast furnace opening ferrum mouth device as claimed in claim 5, it is characterised in that: described perforate (41) is positioned at the bottom of steel pipe (4), and the diameter of perforate (41) is 10mm, and the spacing between adjacent apertures (41) is 100~200mm.
7. a kind of blast furnace opening ferrum mouth device as claimed in claim 5, it is characterised in that: described steel pipe (4) is positioned at blast furnace end partly and is positioned at 1/3 position of blast furnace diameter.
8. a blast furnace opening ferrum mouth method, mainly comprises the steps that
Step one, at ferrum mouth passage (3) and the pre-buried at least steel pipe of mud drum (2) (4), steel pipe (4) mud drum to be stretched out (2) certain length, reaches 1/3 position of blast furnace diameter;
Step 2, steel pipe (4) is positioned at inside blast furnace to set up separately puts perforate (41), perforate (41) is positioned at steel pipe (4) at lower half circumferential position, perforate (41) is the circular hole of diameter 10mm, adjacent apertures (41) blocks along steel pipe length direction spacing 100~200mm, steel pipe (4) front end blind plate (42);
Step 3, steel pipe (4) is positioned at blast furnace outer portion connecting tee valve (5), and three-way valve (5) connects compressed air cylinder (7) and hyperbaric oxygen gas tank (8) respectively by pipeline, and oxygen pressure is 1.0MPa;
Step 4, compressed air it is passed through after blast furnace opening, compressed-air actuated pressure is equal to cold blast pressure+100~300KPa, decline and the carrying out of reduction reaction with furnace charge, generate liquid slag ferrum and enter cupola well, now, electric control gear (6) action control is opened the hyperbaric oxygen air valve of hyperbaric oxygen gas tank (8), is closed the compressed air valve of compressed air cylinder (7);
Step 5, with the raising of accumulation slag ferrum temperature in blast furnace, ferrum mouth passage (3) interior steel pipe (4) all melts, and now, electric control gear (6) action control closes three-way valve (5), stops sending oxygen;
Step 6, forms slag Tie Tong road after steel pipe (4) all fusings, and melted slag ferrum emits from slag Tie Tong road, and the first stove outspoken speed of ferrum ferrum is opened.
CN201610455652.3A 2016-06-22 2016-06-22 Blast furnace blowing-in iron notch device and blast furnace blowing-in iron notch method Pending CN105838835A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610455652.3A CN105838835A (en) 2016-06-22 2016-06-22 Blast furnace blowing-in iron notch device and blast furnace blowing-in iron notch method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610455652.3A CN105838835A (en) 2016-06-22 2016-06-22 Blast furnace blowing-in iron notch device and blast furnace blowing-in iron notch method

Publications (1)

Publication Number Publication Date
CN105838835A true CN105838835A (en) 2016-08-10

Family

ID=56576307

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610455652.3A Pending CN105838835A (en) 2016-06-22 2016-06-22 Blast furnace blowing-in iron notch device and blast furnace blowing-in iron notch method

Country Status (1)

Country Link
CN (1) CN105838835A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109468422A (en) * 2018-12-15 2019-03-15 江苏盛耐新材料有限公司 A kind of blast furnace entirety tapping hole brick
CN110358882A (en) * 2019-08-27 2019-10-22 广东韶钢松山股份有限公司 Blast furnace taphole angle acquisition methods and blast furnace taphole angle regulation method
CN111607674A (en) * 2020-06-29 2020-09-01 盐城市联鑫钢铁有限公司 Method and device for promoting rapid temperature rise of blast furnace hearth
CN111705176A (en) * 2020-05-21 2020-09-25 南京钢铁股份有限公司 Method for discharging slag iron by using oxygen lance during blow-in of blast furnace and oxygen lance thereof
CN112575135A (en) * 2020-12-25 2021-03-30 北京金泰烁昌科技有限公司 Blast furnace taphole dredging and blockage removing equipment and using method thereof
CN114908206A (en) * 2022-06-08 2022-08-16 广东韶钢松山股份有限公司 Blast furnace opening iron notch device and operation method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201190165Y (en) * 2008-04-30 2009-02-04 山东泰山钢铁集团有限公司 Taphole of blowing-on of blast furnace with wind pressure tube
CN202157080U (en) * 2011-07-12 2012-03-07 武汉钢铁(集团)公司 Wind leading device for blow-in
CN203559066U (en) * 2013-11-19 2014-04-23 四川省川威集团有限公司 Blow-in taphole structure of blast furnace
CN103757167A (en) * 2014-01-14 2014-04-30 攀钢集团成都钢钒有限公司 Iron notch pretreatment method used during blowing in of blast furnace

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201190165Y (en) * 2008-04-30 2009-02-04 山东泰山钢铁集团有限公司 Taphole of blowing-on of blast furnace with wind pressure tube
CN202157080U (en) * 2011-07-12 2012-03-07 武汉钢铁(集团)公司 Wind leading device for blow-in
CN203559066U (en) * 2013-11-19 2014-04-23 四川省川威集团有限公司 Blow-in taphole structure of blast furnace
CN103757167A (en) * 2014-01-14 2014-04-30 攀钢集团成都钢钒有限公司 Iron notch pretreatment method used during blowing in of blast furnace

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109468422A (en) * 2018-12-15 2019-03-15 江苏盛耐新材料有限公司 A kind of blast furnace entirety tapping hole brick
CN110358882A (en) * 2019-08-27 2019-10-22 广东韶钢松山股份有限公司 Blast furnace taphole angle acquisition methods and blast furnace taphole angle regulation method
CN111705176A (en) * 2020-05-21 2020-09-25 南京钢铁股份有限公司 Method for discharging slag iron by using oxygen lance during blow-in of blast furnace and oxygen lance thereof
CN111705176B (en) * 2020-05-21 2022-03-22 南京钢铁股份有限公司 Method for discharging slag iron by using oxygen lance during blow-in of blast furnace and oxygen lance thereof
CN111607674A (en) * 2020-06-29 2020-09-01 盐城市联鑫钢铁有限公司 Method and device for promoting rapid temperature rise of blast furnace hearth
CN112575135A (en) * 2020-12-25 2021-03-30 北京金泰烁昌科技有限公司 Blast furnace taphole dredging and blockage removing equipment and using method thereof
CN114908206A (en) * 2022-06-08 2022-08-16 广东韶钢松山股份有限公司 Blast furnace opening iron notch device and operation method
CN114908206B (en) * 2022-06-08 2024-01-05 广东韶钢松山股份有限公司 Blast furnace tapping device and operation method

Similar Documents

Publication Publication Date Title
CN105838835A (en) Blast furnace blowing-in iron notch device and blast furnace blowing-in iron notch method
CN102912051B (en) Method for exchanging cooling wall of blast furnace taphole online
CN108866270A (en) A kind of steelmaking equipment
CN111705176B (en) Method for discharging slag iron by using oxygen lance during blow-in of blast furnace and oxygen lance thereof
CN107385145A (en) It is a kind of to heat steel scrap and improve the method for smelting scrap ratio
CN208472142U (en) A kind of steelmaking equipment
CN103725817A (en) Blast-furnace tuyere blocking device
CN205774645U (en) A kind of bell feeding device of refining furnace
CN209210845U (en) A kind of blast furnace taphole oxygen rifle
CN203238278U (en) Air guide device for blowing-in preheating furnace hearth of blast furnace
CN104006658B (en) The method for repairing and mending of metallurgical furnace exhaust fume collecting hood top interior wall
CN202643724U (en) Blast furnace oven baking tuyere air guide tube device
CN201190165Y (en) Taphole of blowing-on of blast furnace with wind pressure tube
CN209802102U (en) Scrap steel preheating device
CN202361780U (en) Furnace body of cupola furnace
CN205088275U (en) Cowper stove lower part short circuit prosthetic devices
CN211079208U (en) Blast furnace tuyere opening device
CN204881226U (en) A device for getting rid of rotary kiln ring formation
CN207845724U (en) A kind of combustion gas blowing device
CN104089476A (en) Method for using induction furnace for smelting iron alloy and dedicated induction furnace
CN111996317A (en) Method for heating furnace hearth during furnace-closing period of blast furnace
CN103924016B (en) A kind of method changing the large cover of cinder monkey
CN206014983U (en) Blast furnace opening iron mouth gas export control device
CN105400916A (en) Uniform charging device of blast furnace
CN201974038U (en) Improved structure of heat accumulating type gas aluminum melting furnace

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160810

RJ01 Rejection of invention patent application after publication