CN105821766A - Steel arch bridge river crossing installation technology - Google Patents

Steel arch bridge river crossing installation technology Download PDF

Info

Publication number
CN105821766A
CN105821766A CN201510010220.7A CN201510010220A CN105821766A CN 105821766 A CN105821766 A CN 105821766A CN 201510010220 A CN201510010220 A CN 201510010220A CN 105821766 A CN105821766 A CN 105821766A
Authority
CN
China
Prior art keywords
bridge
steel
construction
bow
river
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510010220.7A
Other languages
Chinese (zh)
Inventor
朱连吉
季雪娇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Renqiu Yongji Construction and Installation Engineering Co Ltd
Original Assignee
Renqiu Yongji Construction and Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Renqiu Yongji Construction and Installation Engineering Co Ltd filed Critical Renqiu Yongji Construction and Installation Engineering Co Ltd
Priority to CN201510010220.7A priority Critical patent/CN105821766A/en
Publication of CN105821766A publication Critical patent/CN105821766A/en
Pending legal-status Critical Current

Links

Abstract

The invention belongs to the field of bridge engineering, and particularly relates to a steel arch bridge river crossing installation technology. The steel arch bridge river crossing installation technology is mainly used for a steel arch bridge. According to the technology, pier steel structures of the steel arch bridge are prefabricated and produced in a workshop and transported to a construction site, meanwhile, bridge boards of the steel arch bridge are prefabricated and produced in the workshop and transported to the construction site, construction is conducted from the two sides of the river to the middle of the river till the two ends are assembled, and therefore construction of the steel arch bridge is finished. By the adoption of the technology, construction of auxiliary facilities in the construction process can be reduced, the construction amount is reduced, time and manpower are saved, cost is reduced, and the project schedule can be guaranteed as well.

Description

Steel bow spanning gets over river mounting technique
Technical field
The invention belongs to science of bridge building field, particularly apply and get over river mounting technique in steel bow spanning.
Background technology
Bridge crosses over river, mountain valley or other traffic line, the road is clear in realization, in recent years in order to make the traffic of two sides, river more convenient, economic development is rapider, and a large amount of crossing bridges, in construction, the invention provides steel bow spanning and get over river mounting technique, both can guarantee that the progress of engineering, time and manpower can be saved again, reduce cost, increase economic efficiency.
Summary of the invention
It is an object of the present invention to provide steel bow spanning and get over river mounting technique, be mainly used for steel bow bridge, engineering construction amount can be reduced by the present invention, save time and manpower, and can guarantee that project progress, and reduce cost, increase economic efficiency.
The technical solution used in the present invention is: producing steel bow bridge bridge pier steel construction in shop-fabricated, be transported to construction site, steel bow bridge bridge plate produces in shop-fabricated simultaneously, it is transported to job site, constructing in the middle of river two is lateral simultaneously, until joining in two ends, completing steel bow bridge construction.
Described steel bow bridge bridge plate, is made up of basic body steel construction.
Described construct in the middle of river two is lateral simultaneously, after i.e. steel bow bridge bridge plate is connected with bridge pier, lateral middle construct from two simultaneously, until two ends junction.
The present invention is applicable to steel bow bridge, by producing bridge pier steel construction and steel bow bridge bridge plate in shop-fabricated, after being transported to construction site, constructing in the middle of river two is lateral simultaneously, until joining in two ends, both can reduce the construction of auxiliary equipment in work progress, reduce construction volume, saving time and manpower, reduce cost, ensure that again project progress.
Accompanying drawing explanation
Fig. 1 is that steel bends bridge construction schematic diagram.
Fig. 2 is that steel bends bridge bridge plate structural representation.
Fig. 3 is basic body steel construction schematic diagram.
Reference: 1, steel bow bridge bridge;2, steel bow bridge bridge pier;3, seamless steel pipe;4, H profile steel;5, H profile steel diagonal brace.
Detailed description of the invention
Describe the present invention below with reference to accompanying drawing.But embodiments of the present invention are not limited to that.
Prefabrication steel bow bridge bridge pier 2 in workshop, prefabricated complete after be transported to construction site, and be fixed on the corresponding position, both sides, river of steel bow bridge design;Prefabrication steel bow bridge bridge plate as shown in Figure 2 in workshop, and it is transported to construction site, steel is bent that bridge bridge plate and steel bow bridge bridge pier 2 is fixing to be connected, the bow bridge bridge plate of basic body steel structure connection steel as shown in Figure 3 consisted of seamless steel pipe 3, H profile steel 4 and H profile steel diagonal brace 5, completes the extension of radial direction, constructs in the both sides in river simultaneously, until joining in steel Gong Qiao two ends, complete the construction of steel bow bridge bridge.
The present invention is not limited to above-mentioned embodiment, and anyone can obtain steel bow spanning under the enlightenment of the present invention and get over the installation method in river.All impartial changes done according to scope of the present invention patent and modification, all should belong to the covering scope of the present invention.

Claims (3)

1. steel bow spanning gets over river mounting technique, including steel bow bridge bridge, steel bow bridge bridge pier, it is characterized in that: produce steel bow bridge bridge pier steel construction in shop-fabricated, it is transported to construction site, steel bow bridge bridge plate produces in shop-fabricated simultaneously, is transported to job site, constructs in the middle of river two is lateral simultaneously, until joining in two ends, complete steel bow bridge construction.
Steel the most according to claim 1 bow spanning gets over river mounting technique, it is characterised in that: described steel bow bridge bridge plate is made up of basic body steel construction.
Steel the most according to claim 1 bow spanning gets over river mounting technique, it is characterised in that: described after in the middle of river two is lateral, the i.e. steel of construction simultaneously bow bridge bridge plate is connected with bridge pier, middle construct from two simultaneously, until two ends junction.
CN201510010220.7A 2015-01-09 2015-01-09 Steel arch bridge river crossing installation technology Pending CN105821766A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510010220.7A CN105821766A (en) 2015-01-09 2015-01-09 Steel arch bridge river crossing installation technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510010220.7A CN105821766A (en) 2015-01-09 2015-01-09 Steel arch bridge river crossing installation technology

Publications (1)

Publication Number Publication Date
CN105821766A true CN105821766A (en) 2016-08-03

Family

ID=56514879

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510010220.7A Pending CN105821766A (en) 2015-01-09 2015-01-09 Steel arch bridge river crossing installation technology

Country Status (1)

Country Link
CN (1) CN105821766A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1904210A (en) * 2006-07-28 2007-01-31 中铁工程设计咨询集团有限公司 Installing and closure method of steel arched bridge arch rib large segment and lifting system
CN101054791A (en) * 2007-05-09 2007-10-17 华东交通大学 Joist type cable arch bridge structure and its construction method
CN101581074A (en) * 2009-06-09 2009-11-18 中国第一冶金建设有限责任公司 Large-span steel truss arch construction method
CN102808382A (en) * 2012-08-28 2012-12-05 中铁七局集团第五工程有限公司 Method for constructing arch bridge in V-shaped valley without tower
CN103882798A (en) * 2014-04-03 2014-06-25 四川省交通运输厅公路规划勘察设计研究院 Reinforced concrete arch bridge of concrete filled steel tube stiff skeleton and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1904210A (en) * 2006-07-28 2007-01-31 中铁工程设计咨询集团有限公司 Installing and closure method of steel arched bridge arch rib large segment and lifting system
CN101054791A (en) * 2007-05-09 2007-10-17 华东交通大学 Joist type cable arch bridge structure and its construction method
CN101581074A (en) * 2009-06-09 2009-11-18 中国第一冶金建设有限责任公司 Large-span steel truss arch construction method
CN102808382A (en) * 2012-08-28 2012-12-05 中铁七局集团第五工程有限公司 Method for constructing arch bridge in V-shaped valley without tower
CN103882798A (en) * 2014-04-03 2014-06-25 四川省交通运输厅公路规划勘察设计研究院 Reinforced concrete arch bridge of concrete filled steel tube stiff skeleton and construction method thereof

Similar Documents

Publication Publication Date Title
JP5698359B2 (en) Composite decorative concrete and its construction method
CN102154992B (en) Dislocation installation method of corrugated steel web
CN204185755U (en) A kind of Wavelike steel webplate post-stressed concrete T beam
CN205205654U (en) Seam construction of precast concrete festival segmentation bridge
CN103924505A (en) Prefabricated steel-concrete combination T beam with corrugated steel web and construction method
CN105256723A (en) Multi-girder section steel-doublelayer concrete bridge deck composite beam implementing technology
CN104047225B (en) The precast segment assembly girder construction of steel thimble elasticity shear tenon is set
CN104988951B (en) Straddle monorail underground section track wall construction and construction method thereof
CN105714681B (en) Implementation method of suspension type monorail traffic rigid frame system
CN103485270A (en) Setting technology of second-phase pre-stressed tendons in straddle type single-traffic-track girder bridge
CN105714668A (en) Multifunctional concrete box-girder bridge for double-deck traffic
CN104047223B (en) Light assembling structure bridge and construction method thereof
CN206091355U (en) Post structure is taken out to concrete plant's pillars of a house
CN204825963U (en) Stride single track ground of formula hypomere track wall structure
CN204435675U (en) A kind of lattice salomonica structure
CN104018427A (en) All-welded box girder combination section constructing method
CN103726440A (en) Round tube web girder and manufacturing method thereof
CN204212043U (en) Prefabricated ultra-high performance concrete π ellbeam unit
CN105821766A (en) Steel arch bridge river crossing installation technology
CN203891066U (en) Underground structure prefabricated ribbed-plate type component
CN203960729U (en) A kind of precast segment spliced girder body structure that steel sleeve elasticity shear tenon is set
CN214993221U (en) Corrugated steel plate-concrete composite structure suitable for culvert reinforcement and transformation
CN202324155U (en) Adjustable corrugated prestress anti-pollution drainage culvert
CN205576761U (en) Prestressing force carbon fiber plate consolidates bridge
CN103669193A (en) Laterally spliced combination T beam with wavy steel webs and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160803

WD01 Invention patent application deemed withdrawn after publication