CN105807456B - Lighting test method and device - Google Patents

Lighting test method and device Download PDF

Info

Publication number
CN105807456B
CN105807456B CN201610304688.1A CN201610304688A CN105807456B CN 105807456 B CN105807456 B CN 105807456B CN 201610304688 A CN201610304688 A CN 201610304688A CN 105807456 B CN105807456 B CN 105807456B
Authority
CN
China
Prior art keywords
examining system
test
lighting test
time
lighting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610304688.1A
Other languages
Chinese (zh)
Other versions
CN105807456A (en
Inventor
马志鹏
张文静
常琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
InfoVision Optoelectronics Kunshan Co Ltd
Original Assignee
InfoVision Optoelectronics Kunshan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by InfoVision Optoelectronics Kunshan Co Ltd filed Critical InfoVision Optoelectronics Kunshan Co Ltd
Priority to CN201610304688.1A priority Critical patent/CN105807456B/en
Publication of CN105807456A publication Critical patent/CN105807456A/en
Application granted granted Critical
Publication of CN105807456B publication Critical patent/CN105807456B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G02OPTICS
    • G02FOPTICAL DEVICES OR ARRANGEMENTS FOR THE CONTROL OF LIGHT BY MODIFICATION OF THE OPTICAL PROPERTIES OF THE MEDIA OF THE ELEMENTS INVOLVED THEREIN; NON-LINEAR OPTICS; FREQUENCY-CHANGING OF LIGHT; OPTICAL LOGIC ELEMENTS; OPTICAL ANALOGUE/DIGITAL CONVERTERS
    • G02F1/00Devices or arrangements for the control of the intensity, colour, phase, polarisation or direction of light arriving from an independent light source, e.g. switching, gating or modulating; Non-linear optics
    • G02F1/01Devices or arrangements for the control of the intensity, colour, phase, polarisation or direction of light arriving from an independent light source, e.g. switching, gating or modulating; Non-linear optics for the control of the intensity, phase, polarisation or colour 
    • G02F1/13Devices or arrangements for the control of the intensity, colour, phase, polarisation or direction of light arriving from an independent light source, e.g. switching, gating or modulating; Non-linear optics for the control of the intensity, phase, polarisation or colour  based on liquid crystals, e.g. single liquid crystal display cells
    • G02F1/1306Details
    • G02F1/1309Repairing; Testing

Abstract

The present invention provides a kind of lighting test method and device, wherein exports time configuration information and initialization information according to test request;The time configuration information includes being in specified time in different time periods;According to time configuration information, trigger signal is generated in different specified times, constantly switches the switch state of the examining system;It stores the examining system and responds the first trigger signal and the second trigger signal total degree respectively;Judge whether total degree reaches test request, if reached, terminates the lighting test of examining system;If do not reached also, continue the lighting test of examining system.Before not reaching for the first specified time, comprising: according to initialization information, export Transistor-Transistor Logic level signal;Signal needed for Transistor-Transistor Logic level signal is converted to rear class mould group to be measured.The lighting test method and device not only meets the experiment test request of complicated periodic switch machine, also meets every function lighting experiment test request of common liquid crystal module.

Description

Lighting test method and device
Technical field
The present invention relates to display field more particularly to a kind of lighting test method and devices.
Background technique
Referring to FIG. 1, Fig. 1 is the structural block diagram of available liquid crystal display screen lighting reliability test system.As shown in Figure 1, The lighting reliability test system includes microprocessor, field programmable gate array, bridge chip and mould group to be measured.Microprocessor Initializing field programmable gate array, and testing time information is sent to field programmable gate array.Field-programmable gate array Row initialization bridge chip, and Transistor-Transistor Logic level signal is transmitted to bridge chip, the bridge chip signal required to mould group to be measured output test is simultaneously Complete reliability test lighting.
Although the lighting reliability test system under the conditions of failtests, can test every function of liquid crystal module Whether meet product specification, but special failtests, such as periodic switch machine are tested, which surveys Test system is not to be able to satisfy testing requirement.
Summary of the invention
The purpose of the present invention includes providing a kind of lighting test method and device, to solve existing lighting test method And device is not able to satisfy the technical issues of periodic switch machine test experiments requirement.
Specifically, the present invention provides a kind of lighting test method, for carrying out lighting test to examining system comprising with Lower step:
Time configuration information and initialization information are exported according to test request;Wherein, the time configuration information includes place In specified time in different time periods;
According to the time configuration information, trigger signal is generated in different specified times, constantly switches the system to be measured The switch state of system;
Store the total degree that the examining system responds the first trigger signal and the second trigger signal respectively;
Judge whether the total degree reaches test request, if reached, terminates the lighting test of examining system;If Do not reach also, then continues the lighting test of examining system.
Further, when the time configuration information reach the first specified time when, generate the first trigger signal, switching to Examining system is in the open state or closed state;Then, reach the second specified time when, generate the second trigger signal, switching to Examining system is in close state or opening state.
Further, before not reaching first specified time, specifically includes the following steps:
According to initialization information, Transistor-Transistor Logic level signal is exported, and Transistor-Transistor Logic level signal is converted to needed for rear class mould group to be measured Signal to test rear class mould group to be measured.
Further, when terminating the lighting test of examining system, specifically further include: generate prompt information to remind test Member's test terminates.
The present invention also provides a kind of lighting test devices, for carrying out lighting test to examining system comprising:
Microprocessor, for exporting time configuration information and initialization information according to test request;Wherein, the time matches Confidence breath includes being in specified time in different time periods;
Field programmable gate array, for being initialized according to the initialization information;
Clock chip, for generating trigger signal in different specified times, constantly cutting according to the time configuration information Change the switch state of the examining system;
Memory module, total time for responding the first trigger signal and the second trigger signal respectively for storing the examining system Number;
When whether the total degree reaches test request, if reached, terminate the lighting test of examining system;If also Do not reach, then continues the lighting test of examining system.
Further, when the clock chip reached for the first specified time, the first trigger signal is generated, system to be measured is switched It unites in the open state or closed state;Then, when reaching for the second specified time, the clock chip generates the second triggering letter Number, switching examining system is in close state or opening state.
Further, the lighting test device further includes bridge chip and time showing module, and the bridge chip is used for Rear class mould group to be measured is driven, the time showing module is for showing testing time and test status.
Further, when the clock chip does not reach first specified time, specifically includes the following steps:
The field programmable gate array initializes bridge chip, and exports Transistor-Transistor Logic level signal to bridge chip;
Signal needed for Transistor-Transistor Logic level signal is converted to rear class mould group to be measured by the bridge chip.
Further, the lighting test device further includes prompt equipment, and the prompt equipment is for terminating examining system Lighting test when, generate prompt information so as to remind test man test terminate.
Lighting test method and device provided by the embodiment of the present invention, microprocessor can be according to test request configurable clock generators Chip, clock chip trigger the rear class electricity that examining system was closed and opened to field programmable gate array according to preset specified time Source and signal output, the number that field programmable gate array is exported according to the rear level power supply and signal for closing or opening examining system Whether test request is reached, with the experiment test purpose of execution cycle property switching on and shutting down.The lighting test method and device can expire The experiment test request of the complicated periodic switch machine of foot.
The above description is only an overview of the technical scheme of the present invention, in order to better understand the technical means of the present invention, And it can be implemented in accordance with the contents of the specification, and in order to allow above and other objects, features and advantages of the invention can It is clearer and more comprehensible, it is special below to lift preferred embodiment, and cooperate attached drawing, detailed description are as follows.
Detailed description of the invention
Fig. 1 is the structural block diagram of available liquid crystal display screen lighting reliability test system.
Fig. 2 provides a kind of lighting test method testing flow chart for the embodiment of the present invention.
Fig. 3 provides a kind of circuit module schematic diagram of lighting test device for the embodiment of the present invention.
Specific embodiment
Further to illustrate the present invention to reach the technical means and efficacy that predetermined purpose is taken, below in conjunction with attached drawing And preferred embodiment, to a kind of specific embodiment, method, the step of lighting test method and device proposed according to the present invention Suddenly, structure, feature and effect, detailed description is as follows.
For the present invention aforementioned and other technology contents, feature and effect refer to the preferable reality of schema in following cooperation Applying can clearly be presented in example detailed description.By the explanation of specific embodiment, when predetermined mesh can be reached to the present invention The technical means and efficacy taken be able to more deeply and it is specific understand, however institute's accompanying drawings are only to provide with reference to and say It is bright to be used, it is not intended to limit the present invention.
Lighting test method provided in an embodiment of the present invention can be not only used for carrying out examining system lighting test, also Rear class mould group to be measured can be tested before carrying out lighting test to examining system.Wherein, the lighting test method lighting test When examining system, the switching of the rear level power supply of examining system and the on and off of signal output is controlled.Rear class herein Mainly under the conditions of failtests, whether the every function for testing liquid crystal module meets product rule for the test of mould group to be measured Lattice.It is the specific embodiment of lighting test method of the present invention below.
Referring to FIG. 2, Fig. 2 provides a kind of lighting test method testing flow chart for the embodiment of the present invention.The lighting is surveyed Method for testing the following steps are included:
Step S1 exports time configuration information and initialization information according to test request.
Herein, the time configuration information includes being in specified time in different time periods, for example will be used for system to be measured The period of the lighting test of system is divided into continuous and recyclable the first specified time and the second specified time.Wherein, each finger Fix time is needed according to actual test come limiting time value.Initialization information herein is surveyed for test macro, lighting It when examination, needs to empty last lighting test information, then inputs current lighting test again and need test macro quasi- Standby relevant configuration information.
Step S2 judges whether to reach for the first specified time.
Step S3 generates the first trigger signal.If reaching for the first specified time, the first trigger signal is generated.
Herein, according to the time configuration information in step S1, trigger signal is generated in different specified times, constantly Switch the switch state of the examining system.Switch state herein includes the rear level power supply of examining system and beating for signal output The two states of open and close state.Periodic switch machine test experiments will complete power supply according to the performance requirement of examining system Or the "ON" and " closing " the two movements of signal output, executed within a certain period of time according to examining system "ON" and " closing " the two The total degree of movement is to examine whether examining system meets test purpose.For example, when reaching the first specified time, output first Trigger signal is exported with the rear level power supply and signal of closing examining system, this is the movement of " closing ".Certainly, tester can also be certainly Definition acts herein for "ON", i.e. when the first specified time reaches, trigger signal opens the rear level power supply and signal of examining system Output.
Step S4 judges whether to reach for the second specified time.
Herein, if having not arrived for the second specified time, in conjunction with step S3, continue to output the first trigger signal, switching to Rear level power supply and the signal output of examining system open or close.
Step S5 generates the second trigger signal.If reach the second specified time, generate the second trigger signal, switching to The state of rear level power supply and the signal output of examining system.
In conjunction with step S3 and S5, so far, examining system responds first trigger signal and the second trigger signal respectively. Such as a switch state has been completed in periodic switch machine test experiments, rear level power supply and the signal output of examining system, i.e., Complete two movements of " closing " and "ON".The first specified time and the second specified time of another circulation later are according to preceding First specified time of circulation and the switching mode of the second specified time carry out.The deadline of test is according to test request To determine.Such as need to complete examining system 1000 times switch state switching, that is, need 1000 times " closing " movement and 1000 times The cyclic switching of "ON" movement.
Step S6 stores the total degree that the examining system responds the first trigger signal and the second trigger signal respectively.
Step S7, judges whether total degree reaches test request.
Herein, if total degree reaches test request, terminate the lighting test of examining system;If do not reached also, Continue the lighting test of examining system.
Step S8 generates prompt information.
Herein, while terminating the lighting test of examining system, lighting test method of the embodiment of the present invention further includes producing The step of raw prompt information is to remind test man to test end.Wherein, which can be buzzer or loudspeaker Sound is also possible to the light of LED light.
During lighting test, according to the time configuration information, it is specified that test macro does not reach described first also Before time, and also specifically includes the following steps:
S91, output Transistor-Transistor Logic level signal.
In step S91, test macro exports Transistor-Transistor Logic level signal according to the initialization information in step S1.
S92, Transistor-Transistor Logic level signal is converted to rear class mould group to be measured needed for signal.
In step S92, the test of the mould group to be measured of rear class herein mainly under the conditions of failtests, tests liquid crystal Whether every function of mould group meets product specification.
In conjunction with step S91 and S92, in addition to Transistor-Transistor Logic level signal, test macro can also export other and meet data transmission association The level signal for standard of assessing a bid for tender, and can also be converted to needed for rear class mould group to be measured according to the level signal according to built-in algorithm Signal.
Therefore, lighting test method provided in an embodiment of the present invention not only can satisfy common failtests demand, And it is able to satisfy failtests demand more special in time.
On this basis, the present embodiment also provides a kind of lighting test device, referring to FIG. 3, Fig. 3 is the embodiment of the present invention A kind of circuit module schematic diagram of lighting test device is provided.As shown in figure 3, microprocessor 10 respectively with field-programmable gate array Column 20 and clock chip 30 communicate, and are believed according to test request field programmable gate array 20 and 30 input initialization of clock chip Breath, and further to clock chip 30 input time configuration information.Initializing field programmable gate array 20, on the one hand, clear Except previous test remains in the configuration information of the memory of field programmable gate array 20, on the other hand, to field-programmable gate array The configuration of column 20 related parameter with test.
Clock chip 30 is in subsequent testing procedure, according to time configuration information, generates triggering letter according to specified time Number.Herein, the time configuration information includes being in specified time in different time periods, for example will be used for point to examining system The period of lamp test is divided into continuous and recyclable the first specified time and the second specified time.Wherein, each specified time It is to be needed according to actual test come limiting time value.
Field programmable gate array 20 generates trigger signal in different specified times, constantly switches the examining system Switch state.Switch state herein includes two kinds of the rear level power supply of examining system and the on and off of signal output State.Periodic switch machine test experiments according to the performance requirement of examining system, to complete power supply or signal output "ON" and " closing " the two movements execute the total degree of "ON" and " closing " the two movements within a certain period of time according to examining system to examine Whether examining system meets test purpose.For example, the first trigger signal of output is to be measured to close when reaching the first specified time The rear level power supply and signal of system export, this is the movement of " closing ".Certainly, tester can be with customized dynamic for "ON" herein Make, i.e. when the first specified time reaches, trigger signal opens rear level power supply and the signal output of examining system.And then, it reaches When the second specified time, the second trigger signal is generated, to open rear level power supply and the signal output of examining system, this is "ON" Movement.So far, a switch state has been completed in rear level power supply and the signal output of examining system, i.e. completion " closing " and "ON" Two movements.Later another circulation first specified time and the second specified time according to preceding circulation first it is specified when Between and the switching mode of the second specified time carry out.The deadline of test is determined according to test request.For example it needs The switch state switching for completing examining system 1000 times needs 1000 times " closing " movements and the circulation of 1000 "ON" movement to cut It changes.
Memory module 40 stores the total degree that the examining system responds the first trigger signal and the second trigger signal respectively. If whether total degree reaches test request, terminate the lighting test of examining system;If do not reached also, continue system to be measured The lighting test of system.Memory module 40 can be using the memory built in field programmable gate array 20 herein, or can also be with Using the memory of peripheral hardware.
So far, the experiment test of complicated periodic switch machine is completed in lighting test device provided in an embodiment of the present invention It is required that.
While terminating the lighting test of examining system, equipment 50 is prompted to generate prompt information to remind test man to survey Examination terminates.Wherein, which can be buzzer or loudspeaker or LED light.
If clock chip 30 had not arrived for the first specified time, field programmable gate array 20 initializes bridge chip 60, and Transistor-Transistor Logic level signal is exported to bridge chip 60, Transistor-Transistor Logic level signal is converted to needed for rear class mould group 70 to be measured by bridge chip 60 Signal, for driving rear class mould group 70 to be measured.Therefore, which also meets every machine of common liquid crystal module It can lighting test requirement.
80 recording and displaying testing time of time showing module and test status, so that test man knows the testing time.
The experiment that lighting test device provided in an embodiment of the present invention can not only meet complicated periodic switch machine is surveyed Examination requires, but also meets every function lighting test requirement of common liquid crystal module.Therefore, the present invention also protects the point Application of the test device in liquid crystal display panel lighting test.
The above, only be invention preferred embodiment, be not intended to limit the present invention in any form, although The present invention has been disclosed as a preferred embodiment, and however, it is not intended to limit the invention, any person skilled in the art, Without departing from the scope of the present invention, when the technology contents using the disclosure above make a little change or are modified to With the equivalent embodiment of variation, but without departing from the technical solutions of the present invention, according to the technical essence of the invention to above Any simple modification, equivalent change and modification made by embodiment, all of which are still within the scope of the technical scheme of the invention.

Claims (9)

1. a kind of lighting test method, for carrying out lighting test to examining system, which comprises the following steps:
Time configuration information and initialization information are exported according to test request;Wherein, the time configuration information includes in not With the specified time of period;
According to the time configuration information, trigger signal is generated in different specified times, constantly switches the examining system Switch state;
Store the total degree that the examining system responds the first trigger signal and the second trigger signal respectively;
Judge whether the total degree reaches test request, if reached, terminates the lighting test of examining system;If do not had also Reach, then continues the lighting test of examining system.
2. lighting test method according to claim 1, which is characterized in that refer to when the time configuration information reaches first When fixing time, the first trigger signal is generated, examining system is in the open state or closed state for switching;Then, second is reached to refer to When fixing time, the second trigger signal is generated, switching examining system is in close state or opening state.
3. lighting test method according to claim 2, which is characterized in that before not reaching first specified time, tool Body the following steps are included:
According to initialization information, Transistor-Transistor Logic level signal is exported;
Signal needed for the Transistor-Transistor Logic level signal is converted to rear class mould group to be measured is to test rear class mould group to be measured.
4. lighting test method according to claim 1, which is characterized in that when terminating the lighting test of examining system, tool Body further include: generate prompt information to remind test man that test terminates.
5. a kind of lighting test device, for carrying out lighting test to examining system characterized by comprising
Microprocessor, for exporting time configuration information and initialization information according to test request;Wherein, the time matches confidence Breath includes being in specified time in different time periods;
Field programmable gate array, for being initialized according to the initialization information;
Clock chip, for generating trigger signal in different specified times, constantly switching institute according to the time configuration information State the switch state of examining system;
Memory module responds the total degree of the first trigger signal and the second trigger signal for storing the examining system respectively;
When whether the total degree reaches test request, if reached, terminate the lighting test of examining system;If do not reached also It arrives, then continues the lighting test of examining system.
6. lighting test device according to claim 5, which is characterized in that when clock chip arrival first is specified Between when, generate the first trigger signal, examining system is in the open state or closed state for switching;Then, when arrival second is specified Between when, the clock chip generates the second trigger signal, and switching examining system is in close state or opening state.
7. lighting test device according to claim 5, which is characterized in that the lighting test device further includes bridge chip And time showing module, the bridge chip is for driving rear class mould group to be measured, and the time showing module is for showing test Time and test status.
8. lighting test device according to claim 7, which is characterized in that the clock chip do not reach first it is specified when Between when, specifically includes the following steps:
The field programmable gate array initializes bridge chip, and exports Transistor-Transistor Logic level signal to bridge chip;
Signal needed for Transistor-Transistor Logic level signal is converted to rear class mould group to be measured by the bridge chip.
9. lighting test device according to claim 5, which is characterized in that the lighting test device further includes that prompt is set It is standby, when the prompt equipment is used to terminate the lighting test of examining system, prompt information is generated to remind test man to test knot Beam.
CN201610304688.1A 2016-05-10 2016-05-10 Lighting test method and device Active CN105807456B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610304688.1A CN105807456B (en) 2016-05-10 2016-05-10 Lighting test method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610304688.1A CN105807456B (en) 2016-05-10 2016-05-10 Lighting test method and device

Publications (2)

Publication Number Publication Date
CN105807456A CN105807456A (en) 2016-07-27
CN105807456B true CN105807456B (en) 2019-02-22

Family

ID=56455722

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610304688.1A Active CN105807456B (en) 2016-05-10 2016-05-10 Lighting test method and device

Country Status (1)

Country Link
CN (1) CN105807456B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107402460B (en) 2017-08-07 2020-03-24 京东方科技集团股份有限公司 Lighting control system board, detection method and lighting detection device
CN113053273A (en) * 2020-12-15 2021-06-29 四川长虹电器股份有限公司 Method for judging and controlling lighting of DLP micro-throw product optical machine through IIC communication

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0431822A (en) * 1990-05-28 1992-02-04 Sony Corp Liquid crystal display device
CN1233769A (en) * 1998-02-17 1999-11-03 Lg电子株式会社 Apparatus and method of displaying backlight consumption time for LCD monitor
US6014035A (en) * 1997-07-11 2000-01-11 International Business Machines Corporation Test system and test method for liquid crystal display device
JP2000111872A (en) * 1998-10-05 2000-04-21 Casio Comput Co Ltd Display device
CN1336585A (en) * 2000-07-27 2002-02-20 振玮科技股份有限公司 Electrically programmable read-only memory arbitrator and its operation method
JP2007094031A (en) * 2005-09-29 2007-04-12 Sanyo Epson Imaging Devices Corp Lighting inspection method for liquid crystal panel
CN104360509A (en) * 2014-11-21 2015-02-18 京东方科技集团股份有限公司 Light-on test method and device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070132749A1 (en) * 2005-12-12 2007-06-14 Toppoly Optoelectronics Corp. Systems for controlling brightness of displayed images

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0431822A (en) * 1990-05-28 1992-02-04 Sony Corp Liquid crystal display device
US6014035A (en) * 1997-07-11 2000-01-11 International Business Machines Corporation Test system and test method for liquid crystal display device
CN1233769A (en) * 1998-02-17 1999-11-03 Lg电子株式会社 Apparatus and method of displaying backlight consumption time for LCD monitor
JP2000111872A (en) * 1998-10-05 2000-04-21 Casio Comput Co Ltd Display device
CN1336585A (en) * 2000-07-27 2002-02-20 振玮科技股份有限公司 Electrically programmable read-only memory arbitrator and its operation method
JP2007094031A (en) * 2005-09-29 2007-04-12 Sanyo Epson Imaging Devices Corp Lighting inspection method for liquid crystal panel
CN104360509A (en) * 2014-11-21 2015-02-18 京东方科技集团股份有限公司 Light-on test method and device

Also Published As

Publication number Publication date
CN105807456A (en) 2016-07-27

Similar Documents

Publication Publication Date Title
Stevens et al. Tscope: AC library for programming cognitive experiments on the MS Windows platform
CN105807456B (en) Lighting test method and device
CN101903865B (en) A method for testing in a reconfigurable tester
CN103150274B (en) The operating method of the system and system of integrated circuit including integrated circuit
US7930162B1 (en) Accelerating hardware co-simulation using dynamic replay on first-in-first-out-driven command processor
KR20060131821A (en) Remote bist for high speed test and redundancy calculation
US20210207306A1 (en) Artificial intelligence washing machine and operation method thereof
CN103093713A (en) Chip validation method and device and system based on field programmable gate array (FPGA)
CN109272994A (en) Speech data processing method and the electronic device for supporting the speech data processing method
Janß et al. „Development of Medical Device UI-Profiles for Reliable and Safe Human-Machine-Interaction in the Integrated Operating Room of the Future “
US7240258B1 (en) Parallel test system and method
TWI591357B (en) Real-time simulation system
KR20200009670A (en) System including a plurality of display apparatus and control method thereof
CN105955918B (en) A kind of experiment general-purpose instrument system
JP2006294005A (en) Programmable controller
CN111458592A (en) Automatic detection system for car lamp driving module
CN107194258B (en) The method, apparatus and electronic equipment of monitoring code loophole, storage medium
CN109313946A (en) Human interface device
KR20230076317A (en) simulation device and control method thereof
WO2020232609A1 (en) System and method for training or testing state monitoring module
KR100583405B1 (en) Kimchi refrigerator having a fuction for testing a key input state and display state and method of the same
KR20170111873A (en) Apparatus for testing inverter
CN107305792A (en) A kind of method and apparatus for testing memory
CN103675656B (en) Switch testing supervising device
Ketsmur et al. Towards European Portuguese conversational assistants for smart homes

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 215301 No. 1, Longteng Road, Kunshan, Jiangsu

Patentee after: Kunshan Longteng Au Optronics Co

Address before: 215301 No. 1, Longteng Road, Kunshan, Jiangsu

Patentee before: Kunshan Longteng Optronics Co., Ltd.

CP01 Change in the name or title of a patent holder