CN105673065B - A kind of projecting coal bed pressure relief gas pumping mining method of high methane - Google Patents

A kind of projecting coal bed pressure relief gas pumping mining method of high methane Download PDF

Info

Publication number
CN105673065B
CN105673065B CN201610039053.3A CN201610039053A CN105673065B CN 105673065 B CN105673065 B CN 105673065B CN 201610039053 A CN201610039053 A CN 201610039053A CN 105673065 B CN105673065 B CN 105673065B
Authority
CN
China
Prior art keywords
gas
extraction
water
drilling
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610039053.3A
Other languages
Chinese (zh)
Other versions
CN105673065A (en
Inventor
肖鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Science and Technology
Original Assignee
Xian University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Science and Technology filed Critical Xian University of Science and Technology
Priority to CN201610039053.3A priority Critical patent/CN105673065B/en
Publication of CN105673065A publication Critical patent/CN105673065A/en
Application granted granted Critical
Publication of CN105673065B publication Critical patent/CN105673065B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F7/00Methods or devices for drawing- off gases with or without subsequent use of the gas for any purpose
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Earth Drilling (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The invention discloses a kind of projecting coal bed pressure relief gas pumping mining method of high methane, comprise the following steps:At least one stone head is laid above the corresponding water-bearing stratum of high gassy and low permeability coal seam, and soil pressure cell and pore pressure gauge are installed in stone head surrounding;Constructed multiple drillings to water-bearing stratum from stone head, rapid hole sealing after pore-forming, and extraction branch pipe, the connection of extraction main pipe rail and valve are installed;Water in water-bearing stratum is replaced to clean, passage of the gas to the movement of drilling in formation high gas layer using air;So that gas is connected to the passage of the movement of drilling with drilling forms L-type gas channel;Comprehensive multiple parameters determine the extraction time, start to carry out pressure relief gas pumping mining to the high gas layer of bottom.Water in water-bearing stratum is replaced the clean rear space formed by the present invention using air, so as to increase the gas permeability of coal body, can largely be reduced borehole engineering amount, be significantly improved coal bed gas extraction effect, have wide applicability.

Description

A kind of projecting coal bed pressure relief gas pumping mining method of high methane
Technical field
The present invention relates to gas pumping method, and in particular to a kind of projecting coal bed pressure relief gas pumping mining method of high methane.
Background technology
Roof position all preservations of many highly gassy mines in China have water-bearing layer.To prevent the generation of water inrush accident, Need to discharge water drilling to water-bearing layer construction before seam mining, then discharge water again.Find in practice by being put to water-bearing stratum Water, working face flood is not only eliminated, and the gas permeability in coal seam also significantly increases, and gas can be given off from drilling, this Illustrate to form the crack passage that coal-bed gas pours in the drilling that discharges water in rock stratum.
Through analysis, after being discharged water to roof water-bearing layer, the gas permeability in coal seam increases, and coal-bed gas is led with drilling Logical, its mechanism is similar with protective coat extracted.After protective coat extracted, due to strata movement, stress reduces, cranny development causes quilt Protective layer obtains release antireflective effect, and conducting crack is formed in interlayer rock stratum.Similarly, water-bearing stratum just looks like protective layer, is contained The process that water rock stratum discharges water is equivalent to the process that up-protective layer is exploited.Water preservation occupies certain space in rock stratum, after discharging water The space reserved in rock stratum, space is provided for the movement of bottom coal rock layer, deformation.Some water-bearing layers are very thick, can be thick up to number Ten meters.Therefore the useful space that water-bearing layer leaves after discharging water may be such that bottom coal rock layer obtains sufficient movement and deformation, stress drop The increase of low and gas permeability, foundation is provided for extraction coal seam pressure relief gas..
The content of the invention
The deficiencies in the prior art of the present invention, there is provided a kind of projecting coal bed pressure relief gas pumping mining method of high methane, add The gas permeability of coal body, shorten the gas pumping time, a large amount of borehole engineering amounts can be saved, reduce the gas emission of working face.
To achieve the above object, the technical scheme taken of the present invention is:
A kind of projecting coal bed pressure relief gas pumping mining method of high methane, comprises the following steps:
S1, lay at least one stone head above the corresponding water-bearing stratum of high gassy and low permeability coal seam, and Stone head surrounding installs soil pressure cell and pore pressure gauge;
S2, constructed multiple drillings to water-bearing stratum from stone head, rapid hole sealing after pore-forming, and pass through three-way connection will Quickly drilling is connected with extraction bye-pass, extraction bye-pass is connected with extraction main pipe rail, and total in extraction bye-pass and extraction The junction installation valve of pipeline;
S3, using air the water in water-bearing stratum replaced it is clean so that neighbouring coal rock layer produces movement and deformation, and increase contains The gas permeability of water rock stratum bottom high gas layer, while neighbouring coal rock layer is produced new crack, and formed in high gas layer Passage of the gas to the movement of drilling;
S4, cause gas is connected to the passage of the movement of drilling with drilling to form L-type gas channel;
S5, extraction main pipe rail is arranged in return airway, close to back production rib, and extraction stream is installed in extraction bye-pass Monitoring system is measured, the extraction time is determined according to the pressure value, extraction negative pressure, flow, the gas density parameter that monitor around tunnel, Start to carry out pressure relief gas pumping mining to the high gas layer of bottom.
Wherein, for bore angle to face upward 3~8 °, the spacing of wells is 3~7m, and drilling length determines according to field condition.
The invention has the advantages that:
The water in water-bearing stratum is replaced into the clean rear space formed using air, can so as to increase the gas permeability of coal body So that the coal rock layer of bottom is moved, deformation, gas permeability increase, coal seam pressure relief, produce new crack, and form coal-bed gas To the migration pathway of drilling, the present invention can largely reduce borehole engineering amount, significantly improve coal bed gas extraction effect, have extensive Practicality, and reduce the effect of face gas outburst amount, while the determination of recovery time has been considered around tunnel Pressure value, extraction negative pressure, flow and gas density parameter, improve the security of construction.
Embodiment
In order that objects and advantages of the present invention are more clearly understood, the present invention is carried out with reference to embodiments further Describe in detail.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to limit this hair It is bright.
Embodiment 1
S1, lay at least one stone head above the corresponding water-bearing stratum of high gassy and low permeability coal seam, and Stone head surrounding installs soil pressure cell and pore pressure gauge;
S2, constructed multiple drillings to water-bearing stratum from stone head, bore angle to face upward 3 °, spacing of wells 3m, Drilling length determines according to field condition;Rapid hole sealing after pore-forming, and will be quickly by drilling and extraction bye-pass by three-way connection Connection, extraction bye-pass are connected with extraction main pipe rail, and install valve in the junction of extraction bye-pass and extraction main pipe rail;
S3, using air the water in water-bearing stratum replaced it is clean so that neighbouring coal rock layer produces movement and deformation, and increase contains The gas permeability of water rock stratum bottom high gas layer, while neighbouring coal rock layer is produced new crack, and formed in high gas layer Passage of the gas to the movement of drilling;
S4, cause gas is connected to the passage of the movement of drilling with drilling to form L-type gas channel;
S5, extraction main pipe rail is arranged in return airway, close to back production rib, and extraction stream is installed in extraction bye-pass Monitoring system is measured, the extraction time is determined according to the pressure value, extraction negative pressure, flow, the gas density parameter that monitor around tunnel, Start to carry out pressure relief gas pumping mining to the high gas layer of bottom.
Embodiment 2
S1, lay at least one stone head above the corresponding water-bearing stratum of high gassy and low permeability coal seam, and Stone head surrounding installs soil pressure cell and pore pressure gauge;
S2, constructed multiple drillings to water-bearing stratum from stone head, bore angle to face upward 8 °, spacing of wells 7m, Drilling length determines according to field condition;Rapid hole sealing after pore-forming, and will be quickly by drilling and extraction bye-pass by three-way connection Connection, extraction bye-pass are connected with extraction main pipe rail, and install valve in the junction of extraction bye-pass and extraction main pipe rail;
S3, using air the water in water-bearing stratum replaced it is clean so that neighbouring coal rock layer produces movement and deformation, and increase contains The gas permeability of water rock stratum bottom high gas layer, while neighbouring coal rock layer is produced new crack, and formed in high gas layer Passage of the gas to the movement of drilling;
S4, cause gas is connected to the passage of the movement of drilling with drilling to form L-type gas channel;
S5, extraction main pipe rail is arranged in return airway, close to back production rib, and extraction stream is installed in extraction bye-pass Monitoring system is measured, the extraction time is determined according to the pressure value, extraction negative pressure, flow, the gas density parameter that monitor around tunnel, Start to carry out pressure relief gas pumping mining to the high gas layer of bottom.
Embodiment 3
S1, lay at least one stone head above the corresponding water-bearing stratum of high gassy and low permeability coal seam, and Stone head surrounding installs soil pressure cell and pore pressure gauge;
S2, constructed multiple drillings to water-bearing stratum from stone head, to face upward 5.5 °, the spacing of wells is bore angle 5m, drilling length determine according to field condition;Rapid hole sealing after pore-forming, and will be quickly by drilling and extraction branch pipe by three-way connection Road is connected, and extraction bye-pass is connected with extraction main pipe rail, and installs valve in the junction of extraction bye-pass and extraction main pipe rail;
S3, using air the water in water-bearing stratum replaced it is clean so that neighbouring coal rock layer produces movement and deformation, and increase contains The gas permeability of water rock stratum bottom high gas layer, while neighbouring coal rock layer is produced new crack, and formed in high gas layer Passage of the gas to the movement of drilling;
S4, cause gas is connected to the passage of the movement of drilling with drilling to form L-type gas channel;
S5, extraction main pipe rail is arranged in return airway, close to back production rib, and extraction stream is installed in extraction bye-pass Monitoring system is measured, the extraction time is determined according to the pressure value, extraction negative pressure, flow, the gas density parameter that monitor around tunnel, Start to carry out pressure relief gas pumping mining to the high gas layer of bottom.
Described above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications also should It is considered as protection scope of the present invention.

Claims (2)

1. a kind of projecting coal bed pressure relief gas pumping mining method of high methane, it is characterised in that comprise the following steps:
S1, at least one stone head is laid above the corresponding water-bearing stratum of high gassy and low permeability coal seam, and in rock Tunnel surrounding installation soil pressure cell and pore pressure gauge;
S2, constructed multiple drillings to water-bearing stratum from stone head, rapid hole sealing after pore-forming, and will be quick by three-way connection Drilling is connected with extraction bye-pass, extraction bye-pass is connected with extraction main pipe rail, and in extraction bye-pass and extraction main pipe rail Junction installation valve;
S3, using air the water in water-bearing stratum replaced it is clean so that neighbouring coal rock layer produces movement and deformation, increases water-bearing rock The gas permeability of layer bottom high gas layer, while neighbouring coal rock layer is produced new crack, and form gas in high gas layer To the passage of the movement of drilling;
S4, cause gas is connected to the passage of the movement of drilling with drilling to form L-type gas channel;
S5, extraction main pipe rail is arranged in return airway, close to back production rib, and extraction flow prison is installed in extraction bye-pass Control system, the extraction time is determined according to the pressure value, extraction negative pressure, flow, the gas density parameter that monitor around tunnel, started Pressure relief gas pumping mining is carried out to the high gas layer of bottom.
A kind of 2. projecting coal bed pressure relief gas pumping mining method of high methane according to claim 1, it is characterised in that drilling angle Spend to face upward 3~8 °, the spacing of wells is 3~7m, and drilling length determines according to field condition.
CN201610039053.3A 2016-01-12 2016-01-12 A kind of projecting coal bed pressure relief gas pumping mining method of high methane Expired - Fee Related CN105673065B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610039053.3A CN105673065B (en) 2016-01-12 2016-01-12 A kind of projecting coal bed pressure relief gas pumping mining method of high methane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610039053.3A CN105673065B (en) 2016-01-12 2016-01-12 A kind of projecting coal bed pressure relief gas pumping mining method of high methane

Publications (2)

Publication Number Publication Date
CN105673065A CN105673065A (en) 2016-06-15
CN105673065B true CN105673065B (en) 2017-12-22

Family

ID=56301730

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610039053.3A Expired - Fee Related CN105673065B (en) 2016-01-12 2016-01-12 A kind of projecting coal bed pressure relief gas pumping mining method of high methane

Country Status (1)

Country Link
CN (1) CN105673065B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103362540A (en) * 2013-08-07 2013-10-23 中国矿业大学 High gas coal seam pressure relief gas extraction method
CN103362541A (en) * 2013-08-07 2013-10-23 中国矿业大学 Method for locally improving coal seam air permeability in coal seam with high gas and low air permeability
CN104612644A (en) * 2014-11-18 2015-05-13 山西潞安矿业(集团)有限责任公司 Gas phase fracturing and fast gas extraction method for low permeability coal bed
CN104632272A (en) * 2015-01-29 2015-05-20 西安科技大学 'Three-soft' low-breathability work surface rib shallow hole gas extraction method
CN104863555A (en) * 2015-05-18 2015-08-26 太原理工大学 Method for improving downhole heating coal seam gas extraction amount

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103362540A (en) * 2013-08-07 2013-10-23 中国矿业大学 High gas coal seam pressure relief gas extraction method
CN103362541A (en) * 2013-08-07 2013-10-23 中国矿业大学 Method for locally improving coal seam air permeability in coal seam with high gas and low air permeability
CN104612644A (en) * 2014-11-18 2015-05-13 山西潞安矿业(集团)有限责任公司 Gas phase fracturing and fast gas extraction method for low permeability coal bed
CN104632272A (en) * 2015-01-29 2015-05-20 西安科技大学 'Three-soft' low-breathability work surface rib shallow hole gas extraction method
CN104863555A (en) * 2015-05-18 2015-08-26 太原理工大学 Method for improving downhole heating coal seam gas extraction amount

Also Published As

Publication number Publication date
CN105673065A (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN103291325B (en) The preventing control method of Coal-mining Above Confined-water floor strata gushing water
CN104514577B (en) The method of coal seam large area spontaneous combustion in goaf is hidden in a kind of efficient improvement shallow embedding
CN102797465B (en) Underground ultra-thin virtual protection layer hydraulic coal mining method
CN103362540B (en) High gas layer pressure relief gas pumping mining method
CN101581231B (en) Gas drainage method for loosening coal body through cross layer boring and hydraulic fracture
JP2021510398A (en) How to release water and coal layer gas together
CN104314610A (en) Coal road stripe region burst-preventing method
CN204782970U (en) Low permeability coal seam water conservancy slot system
CN110067592B (en) Roof gas cooperative control method based on hard roof ground fracturing
CN207073410U (en) The anti-reflection system of injection hot water and liquid nitrogen is circulated to coal seam
CN104763466B (en) Method for detecting active diffusion radius of covered rock separation grouting filling slurry
CN105804786B (en) A kind of weak seam bottom plate layer-through drilling pressure rushes anti-reflection method
CN106437823B (en) Method for eliminating outburst and standard exceeding of coal mine gas explosion
CN112253067B (en) Cross fracturing cooperative permeability increasing method for grid drilling of thick coal seam
CN103277129A (en) Technology preventing gas on upper corner of coal mining working face from exceeding limit
CN107816365A (en) A kind of quick-fried pumping integration anti-burst method of coal seam drilling
CN106014407A (en) Method for controlling disasters by utilizing roof crevice water to weaken main control coal seams and rock strata in situ
CN108301811A (en) A kind of efficient pumping method of hypotonicity coal-bed gas
CN103362541B (en) High gassy and low permeability coal seam regionality increases the method for gas permeability of coal seam
CN105673065B (en) A kind of projecting coal bed pressure relief gas pumping mining method of high methane
CN113756857B (en) Fire prevention and extinguishment extraction method for efficiently extracting coal bed gas in multi-layer old goaf on ground
CN108590737A (en) A kind of efficient method for implanting of hypotonicity spontaneous fire seam retardant
CN108661695A (en) A kind of hypotonicity coal seam efficient water injection method
CN108301861A (en) A kind of efficient method for implanting of hypotonicity coal seam dustfall agent
CN108533223A (en) A kind of underground goaf residual coal bed gas methane drainage and utilization project system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
DD01 Delivery of document by public notice

Addressee: Xiao Peng

Document name: payment instructions

DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: Xiao Peng

Document name: payment instructions

DD01 Delivery of document by public notice
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171222

Termination date: 20220112

CF01 Termination of patent right due to non-payment of annual fee