CN105632983B - A kind of standard for the installation of boiler tube board quartz socket tube checks tool - Google Patents

A kind of standard for the installation of boiler tube board quartz socket tube checks tool Download PDF

Info

Publication number
CN105632983B
CN105632983B CN201610164453.7A CN201610164453A CN105632983B CN 105632983 B CN105632983 B CN 105632983B CN 201610164453 A CN201610164453 A CN 201610164453A CN 105632983 B CN105632983 B CN 105632983B
Authority
CN
China
Prior art keywords
tube
quartz socket
installation
standard
socket tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610164453.7A
Other languages
Chinese (zh)
Other versions
CN105632983A (en
Inventor
魏巍
俞玮
裴雷洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Huali Microelectronics Corp
Original Assignee
Shanghai Huali Microelectronics Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Huali Microelectronics Corp filed Critical Shanghai Huali Microelectronics Corp
Priority to CN201610164453.7A priority Critical patent/CN105632983B/en
Publication of CN105632983A publication Critical patent/CN105632983A/en
Application granted granted Critical
Publication of CN105632983B publication Critical patent/CN105632983B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L21/00Processes or apparatus adapted for the manufacture or treatment of semiconductor or solid state devices or of parts thereof
    • H01L21/67Apparatus specially adapted for handling semiconductor or electric solid state devices during manufacture or treatment thereof; Apparatus specially adapted for handling wafers during manufacture or treatment of semiconductor or electric solid state devices or components ; Apparatus not specifically provided for elsewhere
    • H01L21/67005Apparatus not specifically provided for elsewhere
    • H01L21/67011Apparatus for manufacture or treatment
    • H01L21/67098Apparatus for thermal treatment

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Condensed Matter Physics & Semiconductors (AREA)
  • General Physics & Mathematics (AREA)
  • Manufacturing & Machinery (AREA)
  • Computer Hardware Design (AREA)
  • Microelectronics & Electronic Packaging (AREA)
  • Power Engineering (AREA)
  • Devices For Use In Laboratory Experiments (AREA)
  • Re-Forming, After-Treatment, Cutting And Transporting Of Glass Products (AREA)

Abstract

The invention discloses a kind of standard for the installation of boiler tube board quartz socket tube to check tool, after two quartz socket tubes are installed in boiler tube board vacuum line, the characteristics of uniform gap being formed during using its coaxial socket, standard being checked to, the gap of tubular inspection portion to the quartz socket tube socket part of tool is parallel to stretch into, the gap whether can be freely stretched into according to it to judge whether two quartz socket tubes are in coaxial socket state, the degree of accuracy installed each time so as to Reliable guarantee quartz socket tube, and prevent the product rejection problem because caused by installation offset problem;And tubular inspection portion can be protected and be controlled built-in length during its inspection by setting maintaining part in tubular inspection portion tail end;Also it can quick and precisely judge whether the socket of two quartz socket tubes meets standard by setting watch window in maintaining part.The unified installation check standard that the present invention achievable quartz socket tube quantifies when installing, it is simple and easy to use.

Description

A kind of standard for the installation of boiler tube board quartz socket tube checks tool
Technical field
The present invention relates to semiconductor integrated circuit apparatus maintenance technology field, is used for boiler tube machine more particularly, to one kind The standard of platform quartz socket tube installation checks tool.
Background technology
For carrying out the boiler tube board of low temperature nitride processing, such as Tokyo electronics public affairs to semiconductor crystal wafer (Wafer) The boiler tube board of (TEL) Formula HCD types is taken charge of, equipped with two quartz sleeves being socketed with slotted mode in its vacuum line Manage (sleeve quartz), for collection process product.
Referring to Fig. 1, Fig. 1 is a kind of installment state structural representation of existing Formula HCD board quartz socket tubes. As shown in figure 1, two quartz socket tubes A, B are the pipe of insertion, it passes through flange end 7,4 and the pipe of one section of vacuum line 1 respectively Wall 6 is fixedly mounted using clip, can carry out cleaning maintenance to quartz socket tube A, B by dismantling this section of vacuum line.Wherein, stone The socket end of English sleeve A has one section of necking part 5, is installed with it to stretch into quartz socket tube B socket end and forms gap Coaxial parallel socket.There is spacing between quartz socket tube A, B and the tube wall 6 of this section of vacuum line, and form the space 2 of sealing, It can prevent vacuum line from revealing by being passed through nitrogen.Cladding having heaters 3 on the outside of the tube wall of this section of vacuum line, for preventing The Process Production thing collected at quartz socket tube A, B condenses.
From figure 1 it appears that because quartz socket tube A, B are only fixed by flange end 7,4, its socket end is hanging State, thus it is more difficult for realizing that quartz socket tube A, B gap are coaxially socketed.
At present during installation quartz socket tube, mainly by the installation gimmick and experience of engineer, whether it installs accurately main To rely on and visually inspect, therefore the gap being relatively difficult to ensure between two quartz socket tubes of card is coaxially socketed.Also, different engineer's peace The quartz socket tube of dress can not seek unity of standard, so as to it cannot be guaranteed that the reliability of installation quality.Once the and installation of quartz socket tube Position produces deviation, product during low temperature nitride will be caused to accumulate, so that causing particle (particle) defect that flows back.Backflow Particle is typically fall on and (falls) little particle, and main integrated distribution is at the top of cassette in crystal round fringes position Gradually successively decrease situation to bottom quantity, this can cause the serious consequence of product rejection.
Therefore, in order to prevent quartz socket tube installation skew cause boiler tube Particle caused by product rejection ask Topic, design one are used for the standard inspection fixture that quartz socket tube is coaxially socketed installation, just seemed particularly necessary.
The content of the invention
It is an object of the invention to overcome drawbacks described above existing for prior art, there is provided one kind is used for boiler tube board quartz sleeve Pipe installation standard check tool, can Reliable guarantee quartz socket tube installation when the degree of accuracy, and prevent because installation skew ask Product rejection problem caused by topic.
To achieve the above object, technical scheme is as follows:
A kind of standard for the installation of boiler tube board quartz socket tube checks tool, and the quartz socket tube is located at boiler tube board Insertion pipe in vacuum line, including first, second quartz socket tube, it is inner with the mutually inside and outside parallel socket of slotted mode, its Outer end is fixedly mounted with the tube wall of one section of vacuum line respectively, and the standard checks that tool includes:
Inspection portion, it is one section of pipe, its front end is used for after the fixed installation of first, second quartz socket tube, from the second quartz The gap of sleeve pipe outer end to first, second quartz socket tube socket part is parallel to be stretched into, whether can freely stretch into the gap according to it To judge whether first, second quartz socket tube is coaxially socketed;
Maintaining part, fixed with the pipe tail end in inspection portion, during for keeping the round tube shape in inspection portion and control its inspection Built-in length.
Preferably, between the nominal when tube wall thickness in the inspection portion and first, second quartz socket tube are coaxially socketed Gap is corresponding, and its it is parallel stretch into when formed gap coordinate.
Preferably, the pipe front end in the inspection portion, which has, helps to stretch into first, second quartz socket tube socket part gap Introduction part.
Preferably, the section of the introduction part is taper or arc.
Preferably, the maintaining part is to be perpendicularly fixed at the pedestal of inspection portion pipe tail end.
Preferably, the pedestal is flange shape.
Preferably, the maintaining part is provided with the watch window communicated with inspection portion pipe.
Preferably, the watch window is penetrated to be formed by the pipe tail end in inspection portion to maintaining part.
Preferably, the standard checks that tool is made of teflon material.
Preferably, the standard checks that tool use is integrally formed or machining is made.
It can be seen from the above technical proposal that the present invention in boiler tube board vacuum line by installing two quartz socket tubes Afterwards, using its it is coaxial be socketed when form uniform gap the characteristics of, check the tubular inspection portion of tool to quartz socket tube standard The gap of socket part is parallel to be stretched into, you can judges whether two quartz socket tubes are according to whether it can freely stretch into the gap Coaxial socket state, the degree of accuracy installed each time so as to Reliable guarantee quartz socket tube, and prevent because installation skew is asked Product rejection problem caused by topic;Meanwhile the pedestal maintaining part by being set in tubular inspection portion tail end, it can be examined in standard Look into and tubular inspection portion is protected when tool is used and deposited, avoid its stress deformation, and can control stretching during its inspection Enter length;In addition, by setting watch window in pedestal maintaining part, the pipe observation caliber that can pass through inspection portion checks that tool exists Mated condition in two quartz socket tube socket gaps, so as to rapidly and accurately judge whether the socket of two quartz socket tubes accords with Standardization.The unified installation check standard quantified when being installed by the achievable quartz socket tube of the present invention, it is simple and easy to use.
Brief description of the drawings
Fig. 1 is a kind of installment state structural representation of existing Formula HCD board quartz socket tubes;
Fig. 2-Fig. 3 is that a kind of standard inspection for the installation of boiler tube board quartz socket tube of a preferred embodiment of the present invention is controlled Lamps structure schematic diagram;
Fig. 4 is that a kind of standard for the installation of boiler tube board quartz socket tube of a preferred embodiment of the present invention checks tool Use state diagram.
Embodiment
Below in conjunction with the accompanying drawings, the embodiment of the present invention is described in further detail.
It should be noted that in following embodiments, when embodiments of the present invention are described in detail, in order to clear Ground represents the structure of the present invention in order to illustrate, special that structure in accompanying drawing is not drawn according to general proportion, and has carried out part Amplification, deformation and simplified processing, therefore, should avoid being understood in this, as limitation of the invention.
In embodiment of the invention below, Fig. 2-Fig. 3 is referred to, Fig. 2-Fig. 3 is that the present invention one is preferably implemented A kind of standard for the installation of boiler tube board quartz socket tube of example checks jig structure schematic diagram.As shown in Fig. 2 the one of the present invention The standard that kind is used for the installation of boiler tube board quartz socket tube checks tool, including the 22 two primary structure portions in inspection portion 21 and maintaining part Point.Inspection portion 21 is one section of pipe with certain length, and maintaining part 22 is fixedly connected with the pipe tail end in inspection portion 21.
Referring to Fig. 4, Fig. 4 is a kind of standard for the installation of boiler tube board quartz socket tube of a preferred embodiment of the present invention Check the use state diagram of tool.As shown in figure 4, the stove with Tokyo electronics corporation (TEL) Formula HCD types Exemplified by pipe board, equipped with two quartz socket tube (sleeve being socketed with slotted mode in the vacuum line 11 of the board Quartz), respectively first, second quartz socket tube 12,15, for collection process product.First, second quartz socket tube 12, 15 pipe to penetrate, it is fixedly mounted by flange shape outer end 19,16 and one section of tube wall 18 of vacuum line respectively, such as can It is fixedly mounted, and can be sealed by sealing ring using clip.Can be by dismantling this section of vacuum line, to first, second stone English sleeve pipe carries out cleaning maintenance.The inner of first, second quartz socket tube 12,15 is socket end, wherein, the first quartz socket tube 12 The inner has one section of parallel necking part 17, to stretch into the inner of the second quartz socket tube 15, within, external square type and second quartzy Sleeve pipe is installed, and forms the coaxial parallel socket in gap.The tube wall of first, second quartz socket tube 12,15 and this section of vacuum line There is spacing between 18, and form the space 13 of sealing, can prevent vacuum line from revealing by being passed through nitrogen.This section of vacuum tube Cladding having heaters 14 on the outside of the tube wall on road, for the Process Production thing for preventing from collecting at first, second quartz socket tube 12,15 Condense.
Refer to Fig. 2 and combine and refer to Fig. 4.Standard check the front end 24 in tool pipe inspection portion 21 be used for first, the After two quartz socket tubes are fixedly mounted, gap from from the second quartz socket tube outer end to first, second quartz socket tube socket part is parallel to stretch Enter, whether can freely stretch into the gap according to it to judge whether first, second quartz socket tube is coaxially socketed.This is to make use of The characteristics of should forming a circle uniform gap in its set junction when the coaxial socket of first, second quartz socket tube composition.
As a preferred embodiment, the thickness of tube wall 23 in inspection portion 21 can be same with first, second quartz socket tube Axle be socketed when nominal clearance it is corresponding, and can pipe is parallel stretch into the gap when formed gap coordinate.
As above-mentioned further preferred embodiment, the pipe front end 24 in inspection portion 21, which can have, helps it to stretch into the First, the introduction part in the second quartz socket tube socket part gap.For example, the pipe front end in inspection portion can be processed into taper or The introduction part of arc section (figure omits).
Fig. 4 is referred to please continue to refer to Fig. 2 and combination.As a preferred embodiment, maintaining part 22 can be vertical solid Due to the pedestal of the pipe tail end of inspection portion 21.The maintaining part of base construction can be used for keeping the round tube shape in inspection portion and control it Built-in length during inspection.So, when standard checks that tool does not have to or deposited, inspection portion 21 is carried using pedestal 22, is kept away Exempt from it to touch hard thing and damage;Or check tool in use, pedestal 22 can play a part of handle, so as to right in standard Tubular inspection portion 21 is protected, and is avoided its stress and is deformed;The maintaining part 22 of base construction can also by its with The distance between second quartz socket tube outer end judges the depth that inspection portion 21 enters, and to control built-in length during its inspection, keeps away Exempt to be excessively entering into the necking part for touching the first quartz socket tube.
As above-mentioned further preferred embodiment, pedestal 22 can be processed into along the pipe tail end of inspection portion 21 it is parallel to The flange shape of outer setting.
Referring to Fig. 3, it is Fig. 2 left view structure.Maintaining part 22 can be set a watch window 25, watch window 25 with The pipe of inspection portion 21 communicates, and the pipe observation caliber that can pass through inspection portion checks that tool is socketed in gap in two quartz socket tubes Mated condition, so as to rapidly and accurately judge whether the socket of first, second quartz socket tube meets standard.It is preferable as one Embodiment, the tail end of watch window 25 and inspection portion pipe 21 can be penetrated and set, maximized watch window, seen with facilitating Examine.
The above-mentioned standard of the present invention checks that tool can be made of such as teflon material, and can use and be integrally formed or cut Cut and be processed into.Hardness can also be used less than quartz socket tube 12,15 and with certain wear-resisting, decay resistance material and Corresponding manufacturing process is made.
As shown in figure 4, the above-mentioned standard of the present invention checks tool 20 when in use, in first, second quartz socket tube 12,15 After in the vacuum line 11 of boiler tube board, check the tubular inspection portion 21 of tool 20 by the of diagram right side standard The outer end of two quartz socket tube 15 is stretched into the second quartz socket tube pipe, and parallel is stretched between two quartz socket tubes 12,15 socket parts Gap.The characteristics of uniform gap is necessarily formed when being coaxially socketed using first, second quartz socket tube, if the energy of tubular inspection portion 21 It is enough freely to stretch into the gap of two quartz socket tube socket parts, then it can determine whether that first, second quartz socket tube 12,15 is in coaxial sleeve Connect state;, whereas if during the installation skew of first, second quartz socket tube 12,15, its mutual gap necessarily varies, then Tubular inspection portion 21 cannot be by the small position in gap, so as to can determine whether that first, second quartz socket tube 12,15 is in non- Coaxial socket state.Standard is held when maintaining part 22 helps to check and checks that the parallel approach axis of tool 20 and control enter Dynamics.
In summary, it is coaxial using its after the present invention in boiler tube board vacuum line by installing two quartz socket tubes The characteristics of uniform gap is formed during socket, standard being checked to, the gap of tubular inspection portion to the quartz socket tube socket part of tool is put down Row stretches into, you can judge whether two quartz socket tubes are in coaxial socket state according to whether it can freely stretch into the gap, The degree of accuracy installed each time so as to Reliable guarantee quartz socket tube, and prevent the product because caused by installation offset problem Scrap problem;Meanwhile the pedestal maintaining part by being set in tubular inspection portion tail end, it can check that tool is used and deposited in standard Tubular inspection portion is protected when putting, avoids its stress deformation, and built-in length during its controllable inspection;It is in addition, logical Cross and watch window is set in pedestal maintaining part, the pipe observation caliber that can pass through inspection portion checks tool in two quartz sleeve pipe sleeves The mated condition in gap is connect, so as to rapidly and accurately judge whether the socket of two quartz socket tubes meets standard.Pass through this The unified installation check standard quantified during quartz socket tube installation can be achieved in invention, simple and easy to use.
Above-described is only the preferred embodiments of the present invention, the embodiment and the patent guarantor for being not used to the limitation present invention Scope, therefore the equivalent structure change that every specification and accompanying drawing content with the present invention is made are protected, similarly should be included in In protection scope of the present invention.

Claims (10)

1. a kind of standard for the installation of boiler tube board quartz socket tube checks tool, the quartz socket tube is true located at boiler tube board Insertion pipe in blank pipe road, including first, second quartz socket tube, it is inner with the mutually inside and outside parallel socket of slotted mode, outside it End is fixedly mounted with the tube wall of one section of vacuum line respectively, it is characterised in that the standard checks that tool includes:
Inspection portion, it is one section of pipe, its front end is used for after the fixed installation of first, second quartz socket tube, from the second quartz socket tube The gap of outer end to first, second quartz socket tube socket part is parallel to be stretched into, whether can freely stretch into the gap to sentence according to it Whether disconnected first, second quartz socket tube is coaxially socketed;
Maintaining part, fixed with the pipe tail end in inspection portion, for keeping the round tube shape in inspection portion and controlling stretching during its inspection Enter length.
2. the standard according to claim 1 for the installation of boiler tube board quartz socket tube checks tool, it is characterised in that institute The nominal clearance stated when the tube wall thickness in inspection portion is coaxially socketed with first, second quartz socket tube is corresponding, and flat at it Gap is formed when row stretches into coordinate.
3. the standard according to claim 1 or 2 for the installation of boiler tube board quartz socket tube checks tool, its feature exists In the pipe front end in the inspection portion has the introduction part for helping to stretch into first, second quartz socket tube socket part gap.
4. the standard according to claim 3 for the installation of boiler tube board quartz socket tube checks tool, it is characterised in that institute The section for stating introduction part is taper or arc.
5. the standard according to claim 1 for the installation of boiler tube board quartz socket tube checks tool, it is characterised in that institute It is to be perpendicularly fixed at the pedestal of inspection portion pipe tail end to state maintaining part.
6. the standard according to claim 5 for the installation of boiler tube board quartz socket tube checks tool, it is characterised in that institute It is flange shape to state pedestal.
7. the standard for being used for the installation of boiler tube board quartz socket tube according to claim 1 or 5 checks tool, its feature exists In the maintaining part is provided with the watch window communicated with inspection portion pipe.
8. the standard according to claim 7 for the installation of boiler tube board quartz socket tube checks tool, it is characterised in that institute Watch window is stated to penetrate to be formed to maintaining part by the pipe tail end in inspection portion.
9. the standard according to claim 1 for the installation of boiler tube board quartz socket tube checks tool, it is characterised in that institute State standard and check that tool is made of teflon material.
10. the standard according to claim 9 for the installation of boiler tube board quartz socket tube checks tool, it is characterised in that The standard checks that tool use is integrally formed or machining is made.
CN201610164453.7A 2016-03-22 2016-03-22 A kind of standard for the installation of boiler tube board quartz socket tube checks tool Active CN105632983B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610164453.7A CN105632983B (en) 2016-03-22 2016-03-22 A kind of standard for the installation of boiler tube board quartz socket tube checks tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610164453.7A CN105632983B (en) 2016-03-22 2016-03-22 A kind of standard for the installation of boiler tube board quartz socket tube checks tool

Publications (2)

Publication Number Publication Date
CN105632983A CN105632983A (en) 2016-06-01
CN105632983B true CN105632983B (en) 2018-03-23

Family

ID=56047776

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610164453.7A Active CN105632983B (en) 2016-03-22 2016-03-22 A kind of standard for the installation of boiler tube board quartz socket tube checks tool

Country Status (1)

Country Link
CN (1) CN105632983B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5002503A (en) * 1989-09-08 1991-03-26 Viacom International, Inc., Cable Division Coaxial cable connector
CN101368867A (en) * 2008-07-11 2009-02-18 王颖峰 Self-locking type manual plugging apparatus
CN201656187U (en) * 2009-12-25 2010-11-24 合肥佰特微波技术有限公司 Adapter for fast plugging and unplugging test
CN201688820U (en) * 2010-05-07 2010-12-29 中国葛洲坝集团股份有限公司 Hollow circular sleeve center positional deviation measurement device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5002503A (en) * 1989-09-08 1991-03-26 Viacom International, Inc., Cable Division Coaxial cable connector
CN101368867A (en) * 2008-07-11 2009-02-18 王颖峰 Self-locking type manual plugging apparatus
CN201656187U (en) * 2009-12-25 2010-11-24 合肥佰特微波技术有限公司 Adapter for fast plugging and unplugging test
CN201688820U (en) * 2010-05-07 2010-12-29 中国葛洲坝集团股份有限公司 Hollow circular sleeve center positional deviation measurement device

Also Published As

Publication number Publication date
CN105632983A (en) 2016-06-01

Similar Documents

Publication Publication Date Title
CN111022610B (en) Process for combining left-handed inner gear ring and right-handed inner gear ring into high-precision herringbone gear
CN105632983B (en) A kind of standard for the installation of boiler tube board quartz socket tube checks tool
US20160368065A1 (en) Valve Hole and Machining Method Thereof
JP2016506621A5 (en) Mask positioning system and mask positioning method
CN205679172U (en) Pore Diameter Detection plug
CN103557905A (en) High-temperature radar sounding rod
CN206273669U (en) The screw rod bushing pipe connection of electronic strut
JP5766646B2 (en) Drift tube type linear accelerator
CN105150048B (en) With the direct-current ion beam optics burnishing device of integration in plasma bridge-type
CN105290440B (en) Large-scale shield electric machine housing tire device
CN204064197U (en) High precision triangle tapering spline detects ring gauge
CN103949904A (en) Turning clamp
CN204330238U (en) A kind of detection platform for connector welding sealing propertytest
CN103042239B (en) Mounting structure of machine tool centre and centre shaft
CN105466311A (en) Detection method for inner bore and external diameter of disc type clutch disc hub
CN105665754A (en) Ejector pin used for machining
CN205716398U (en) A kind of dish gas holder helical guideway floating guide wheel device
CN221223616U (en) Be used for cigarette equipment part hole and axle quick detection device
CN109227461A (en) The installation method and method for dismounting of positioning pin
CN209295864U (en) A kind of permanent magnetism vector motor stator piece inspection tooling
CN203282235U (en) Jacket for meter lathe
CN103350361B (en) Clamp with airtight error prevention detection for gear ring finish turning
CN218953279U (en) Metal soluble bridge plug
CN205844086U (en) A kind of fixture for woven belt extension test
CN219415987U (en) Target gauge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant